CASE NO.:
❑ REQUEST FOR MODIFICATION TO PROVISIONS
OF TITLE 9 (FIRE CODE) OR TITLE 15 (BUILDING CODE)
OF THE NEWPORT BEACH MUNICIPAL CODE
(See Reverse for Basis for Approval) (Fee $316)
® REQUEST FOR ALTERNATE MATERIAL
OR METHOD OF CONSTRUCTION
(See Reverse for Basis for Approval) (Fee $316)
For above requests, complete Sections 1, 2 & 3
below by printing in ink or typing.
M
RECEIVED BY
COMMUNITY
DEVELOPMENT
MAY 0 8 2025
CITY OF
NEWPORT BEACH
III FOR STAFF USE ONLY III
Plan Check # W 9 ,! — OYM of Stories 2
Occupancy Classification
Az3 a
Use of Building SFD
# of Units /
Project Status Pf�a
[.w
Construction Type V43
r!5?r
Verified by
No. of Items ..
Fee due q 3/IV
DISTRIBUTION:
Owner
FPlan Check 0' A'
Petitioner
r I Inspector
Fire
❑ Other
1 I JOB ADDRESS: PETITIONER:
SITE ADDRESS: 1927 Port Bristol Circle Petitioner Denise Xagorarakis
Owner Fredy Catota (Petitioner to be architect or engineer)
1441 W 244th St. Address 17900 Skypark Cir. Ste. 102
Address Harbor City Zip 90710 Irvine, CA Zip 92614
Daytime Phone ( 323 ) 617-0742 Daytime Phone (949) 422-4364
Email: denisenxagdesigns.com
2 REQUEST: Submit plans if necessary to illustrate request. Additional sheets or data may be attached.
To rovitle less than the code required clear distance from the 1 exterior finish grade to the underside of the wood sill plate of the new exterior walls
and r71 externr finished arade or finished surface to the weep screed.
TION/FINDINGS OF EQUIVALENCY:
2022 CRC R317.1, R703.7.2.1
The continuous bituthene and copper or stainless steel flashing provides equivalent protection form penetration of moisture to the building as the
minimum vertical separation between the too of the building concrete and the exterior surface prescribed in the building code.
Position Architect
Petitioner's 05/06/2025
Siqnature CA Professional Lic. # C37154 Date:
III FOR STAFF USE ONLY III
DEPARTMENT ACTION: In accordance with: `gCBC 104.11/CFC 104.9 ❑ CBC 104.10/CFC 104.8
(Alternate materials & methods) (CBC Modification)
❑ Concurrence from Fire Code Official is required. ❑ Approved ❑ Disapproved ❑ Written Comments Attached
By:
Request (DOES),(DOES NOT) lessen any fire protection requirements.
bequest (DOE (DOES NOT) lessen the structural integrity
Date
I The Request is: ranted ❑ Denied (See reverse for appeal information) I
Granted (Ratification required)
Conditions of
Position CHIEF BUILDING OFFICIAL Date
Print Name
APPEAL OF DIVISION ACTION TO THE BUILDING BOARD OF APPEALS (See Reverse)
(Signature, statement of owner or applicant, statement of reasons for appeal and filing fees are required.)
CASHIER RECEIPT NUMBER: RED -00S644 7015 Forms\mod[f 07/29/24
Guidelines for Approval of Alternate Materials, Design and Methods of Construction
Basis For Approval
For the Chief Building Official and Fire Code Official or their designated agent to approve a request for modification
or a request for alternate material or method of construction, he/she must determine that special, individual reasons
exist that make compliance with the strict letter of the Code impractical and that equivalency is provided. The
resulting condition must be in conformance with the spirit and purpose of the Code provisions involved and that such
modification does not lessen fire protection, structural integrity or occupant safety. The applicant must provide
sufficient information with this application to allow the above evaluation to be made.
Requirements for Submittals
The applicant design professional shall prepare a Written Report that describes the alternate proposal along with the
applicable data listed below:
• State specific code provisions for which alternative is requested and why request is being submitted.
• Describe by code section those provisions for which alternative is desired.
• Compare the proposed alternative versus the code requirements in terms of structural strength, suitability,
effectiveness, fire resistance, safety and health impacts affecting the building or user of the building.
• Demonstrate that the proposed alternative is compatible with balance of code requirements.
• When applicable, specify how authoritative consensus document(s) are used to substantiate proposal.
(Reference draft ]CC Building Performance Code Commentary Section 1.4.2.3 for background information).
• Provide assumptions, references, and documentation of evaluation methods utilized. This includes intended
use, input data, anticipated outputs, and limitations of computer models and other analytical tools or methods.
• Specify when and where special inspection and testing are required and the standards of acceptance for
demonstrating compliance. Show how the proposed alternate, if accepted, will be identified on the job site.
• Where land use restrictions and building setbacks are required, deed restrictions may be an appropriate method
to ensure continued compliance.
• State how and where alternate proposal is incorporated within construction plans and prepare plan amendments
as necessary. The design professional has the responsibility to coordinate all construction documents and
ensure compatibility between documents.
• The report and design documents shall be dated, signed and stamped by the design professional according to
the plan submittal procedure.
• For alternate methods of design requests, the applicant shall set performance criteria for his design.
Performance criteria shall be reviewed, amended and approved by the Building or Fire Code Official prior to
start of design.
Alternative Design Review/Verif!cation
The Chief Building Official or Fire Code Official has the responsibility to review design submittals for compliance to
the adopted codes and procedures. If the Building or Fire Code Official does not have the expertise on staff to
make a thorough and competent review, the Building or Fire Code Official shall select a consultant that possesses
the necessary qualifications to perform a third -party or peer review. Cost of peer review shall be paid by applicant to
the Building Division prior to commencing the review.
• Verify that all applicable information and justifications listed above as requirements for submittals is received and
verify that evaluation and design methods used by designer are appropriate to the alternative proposed.
• Verify products are being used in accordance with their listing conditions as required by recognized listing
agencies. If not available, require documentation and/or testing to demonstrate compliance with intent of code
and intended use.
• Evaluate performance of material and possible flaws that could affect performance of material in its installed
state.
• The reviewer shall document that the submittal has been reviewed and accepted as meeting the alternative
materials, design and methods of construction provisions of the code. If the Building or Fire Code Official is not
satisfied that the applicant has met the conditions, the request should be denied in writing with the applicable
reason(s).
Inspection/Field Verification
The alternate proposal as approved in the construction documents must be verified by inspection, and, where
necessary, testing as follows:
• To verify that alternate materials, systems and fabricated products comply with accepted design criteria and the
manufacturer's and engineer's installation procedures, inspectors should check product labeling, certification,
quality assurance processes, and testing, as applicable.
• When appropriate, an approved third party quality assurance inspection and testing service may be required for
continuous and complex inspection and testing activities. This is intended to verify that construction complies
with the code and the approved plans.
Appeal from the determination or action of the Chief Building Official or Fire Code Official or their designated agent
may be made to the Building and Fire Board of Appeals. To appeal, the applicant must provide special individual
reasons that make compliance with the strict letter of the Code impractical. Appeals or ratifications pertaining to
State Disabled Access Standards require complete evidence to substantiate that the proposed design is equivalent
to that prescribed by that standards or that due to legal or physical constraints, compliance with the standards or
providing equivalency would create an unreasonable hardship.
Appeals must be submitted on the Appeal Form available at Permit Counter accompanied by the proper fee. You
will be notified in writing of the appeal hearing's time and date.
STUCCO WITH CORROSION
RESISTANT METAL LATH
CORR. RESIT. LATH 0/ BLDG. PAPER.
PROVIDE POSITIVE LAP 0/ FOUNDATION
EDGE AT BOTTOM
VERTICAL SIDING
PRESERV. TREATED SILL PLATE —
<8" ABV GRADE. (CRCR317.1)
BUILDING PAPER 0/ CORR. RESIST.
METAL FLASHING 0/ METAL BASE
SCREED WITH WEEP HOLES PER
CODE REQUIREMENTS N
CV
M
CONCRETE
WALK SL 1/4:12
CONTINUOUS S.S. OR COPPER FLASHING OVER
BITUTHENE MOISTURE BARRIER. BOTH EXTEND 6"
BELOW TOP OF CONCRETE STEM WALL. EXTEND
MOISTURE BARRIER 18" ABV. FLOOR SHEATHING
AND FLASHING 6" ABV. FLOOR SHEATHING.
FLEXIBLE SEALANT
2X FRAMING
W�-110110
J
W
m
ce
Z
LL
T.O.C.
0
In n °n
VERIFY AL,t MIN. ° 3
CLEAR. DIM WI FIN.
° ATANU6. REQ. AT SLAB Zo v
OR 1" MIN. ° ° a
° z
°
ALT. METHOD OF SCREED - STUCCO / SIDING
SCALE: N.T.S.
I-
x a c DESIGNS m ;gym PORT BRISTOL RESIDENCE
`MSKYP PARK CIR, STE 1@ 1927 PORT BRISTOL CIRCLE
DNTKY P
IRVINE, CALIFORNIA OW14
9.mgd l NEWPORT BEACH_ CA 9266n
LESS THAN 718" MIN. EXT.
2"VEN E�_R 314",MIN.INT.
2X BUILDING PAPER 01 CORROSION
RESISTANT METAL FLASHING 01 C.R.
METAL BASE SCREED
NATURAL STONE VENEER TO BE ADHERED
TO WALL PER CRC R703.12 & IN ACCORD. W/
MANUF'S INSTRUCTIONS. REFER TO TABLE
R703.8(2) FOR MAX WEIGHT & VENEER
WEIGHT.
2X BACKING
PRESERV. TREATED SILL PLATE
<8" ABV GRADE. (CRCR317.1)
1/8" CORR. RESIST. STEEL, LSHAPE, W/
WEEP HOLES PER CODE REQ. - CONT.
W/ LAG SCREWS @ 16" O.C.
CONCRETE
WALK SL 114:12
CONTINUOUS S.S. OR COPPER FLASHING OVER
BITUTHENE MOISTURE BARRIER. BOTH EXTEND 6"
BELOW TOP OF CONCRETE STEM WALL. EXTEND
MOISTURE BARRIER 18" ABV. FLOOR SHEATHING
AND FLASHING 6" ABV. FLOOR SHEATHING.
FLEXIBLE SEALANT
/*zcu -
C37154
5-3'1
2X FRAMING
0
SHEATHING PER z
STRUCT.DWGS
x
m
z VERIFY ALL MIN.
a
CLEARANCE
z_
z_ DIMENSIONS Wl
=n SIDINGo
m
> MANUFACTURER'S
REQUIREMENTSAT z
d
2"
I
SLAB OR 1"MIN.
q
J
m
° UO
io
n
a ° 4
o
° d Z
m a o
° °
z
o
° US,° m
o
a ° z
°°
ALT. METHOD OF SCREED - STONE VENEER
SCALE: N.T.S.
XAG DESIGNS �� a m PORT BRISTOL RESIDENCE
°900SKYNF°' 1927 PORT BRISTOL CIRCLE
CONTS PARK CIR 5>E 104
IRVINF, CAUFORNK92614
s 2a �.�m NEWPORT BEACH_ CA 92660