HomeMy WebLinkAbout21 - Temporary Fire Station No. 1 Project — Award of Contract No. 8865-3 (23F12)Q �EwPpRT
c
9C/FOR
TO:
FROM:
CITY OF
NEWPORT BEACH
City Council Staff Report
August 26, 2025
Agenda Item No. 21
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer - 949-644-3321,
tandefur@newportbeachca.gov
TITLE: Temporary Fire Station No. 1 Project — Award of Contract No. 8865-
3 (23F12)
ABSTRACT:
The City of Newport Beach received construction bids for the Temporary Fire Station No.
1 Project. Staff requests City Council approval to award the construction contract to
Premo Construction, Inc. of Irvine. The project involves preparing the site to receive and
install a temporary fire station trailer; furnish and install an equipment storage box; install
an Americans with Disabilities Act (ADA) compliant ramp, outdoor safety lighting, chain
link security fencing with footings, privacy screens, and gates; make dry and wet utility
connections; provide monthly inspections and as needed repairs; restore site to pre -trailer
condition at the end of the project; and other improvements to make the temporary facility
functional and operable for the contract term of 18 months with the option to extend the
contract term on a monthly basis for no more than a total of 12 additional months.
RECOMMENDATIONS:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15303 under Class 3 (New Construction or conversion of small
structures), Section 15304 under Class 4 (Minor Alterations to Land), and Section
15311 under Class 11 (Accessory Structures) of the CEQA Guidelines, California
Code of Regulations, Title 14, Division 6, Chapter 3 because this project has no
potential to have a significant effect on the environment and the exceptions to these
categorical exemptions under Section 15300.2 are not applicable;
b) Approve the project plans and specifications;
c) Find the bid submitted by VSI Technologies to be non -responsive;
d) Award Contract No. 8865-3, including the additive bid item for potential lease
extension to Premo Construction, Inc. for the total bid price of $295,800 for the
Temporary Fire Station No.1 Temporary Trailer Project, and authorize the Mayor and
City Clerk to execute the contract; and
e) Establish a contingency of $29,500 (approximately 10% of total bid) to cover the cost
of unforeseen work not included in the original contract.
21-1
Temporary Fire Station No. 1 Project — Award of Contract No. 8865-3 (23F12)
August 26, 2025
Page 2
DISCUSSION:
The Temporary Fire Station No. 1 Project (Project) will support the upcoming Balboa
Branch Library and Fire Station No. 1 Project. To maintain operation of Fire Station No.
1 during demolition and the construction of the new station, a temporary fire station will
be required for approximately 18 months from Fall 2025 to Spring 2027.
The East Ocean Front Parking Lot has nearby utilities along Palm Street, allowing
connection to the City's water and sewer mains, as well as access to connect to
Southern California Edison's electrical vault. The installation of the wet and dry utilities
will be performed through a separate contract.
A limited term permit with a duration of greater than 90 days was approved by the City to
allow the installation and operation of a temporary fire station. A public hearing was held
on May 15, 2025. A notice of the time, place and purpose of the hearing was made public
in accordance with the Newport Beach Municipal Code. Evidence, both written and oral,
was presented to and considered by the zoning administrator at the hearing. The zoning
administrator of the City -approved Limited Term Permit PA2025-0031, subject to the
conditions outlined in Resolution No. ZA2025-027.
At 1 p.m. on July 3, 2025, the City Clerk opened and read the following bids for this
project:
BIDDER
TOTAL BID AMOUNT
Low
VSI Technologies*
$138,500
2nd
Premo Construction, Inc.
$247,800
3rd
TRA, Inc.
$289,802
4t"
YMC
$329,000
5t"
Elegant Construction, Inc.
$458,000
6t"
MLC Constructors
$671,742
*Non -responsive bid
The City received six bids. The apparent low bidder, VSI Technologies, was deemed non-
responsive since its bid contained irregularities and did not conform to the Instructions to
Bidders. These deficiencies included not having the required Department of Industrial
Relations (DIR) registration and not having a valid Contractor's License. The second
lowest bidder, Premo Construction Inc., is registered with the DIR and possesses a
California State Contractor's License Classification "B", as required by the project
specifications. A review of references for Premo Construction, Inc. shows satisfactory
completion of contracts for other public agencies including the City of La Palma,
City of Santa Ana, and the Anaheim Elementary School District.
Premo Construction's total bid amount was approximately 24% above the Engineer's Bid
Estimate of $200,000. The difference between the low bid and the Engineer's Estimate
was primarily due to the cost of furnishing and installing the temporary trailer for the
18-month contract term.
21-2
Temporary Fire Station No. 1 Project — Award of Contract No. 8865-3 (23F12)
August 26, 2025
Page 3
If the temporary fire station is needed beyond the 18-month contract term, the cost to
extend the use of the temporary fire station will be on a monthly basis and this is captured
as an Additive Bid item. If the temporary fire station is not needed beyond the 18-month
contract term, then no compensation for this item shall be provided to the contractor.
Pursuant to the contract specifications, the contractor shall adhere to the performance
milestones as time is of the essence in this contract. It is recommended that Council
award the additive bid item to potentially extend the lease for an additional 12 months for
a cost of $48,000. This brings the total cost of the contract award to $295,800.
The project plans and specifications will be available for review at the August 26, 2025,
City Council meeting or upon request.
FISCAL IMPACT:
The adopted Capital Improvement Program budget includes sufficient funding for the
award of this contract. The following funds will be expended:
Account Description
Facilities Financial Plan (FFP)
Proposed fund uses are as follows:
Vendor
Premo Construction, Inc.
Premo Construction, Inc.
Premo Construction, Inc.
Account Number Amount
53201-980000-23F12 $ 325,300
Purpose
Construction Contract
Additional 12 months usage
Construction Contingency
Total:
Amount
$ 247,800
$ 48,000
$ 29,500
$ 325,300
The City's FFP is a comprehensive master facilities replacement schedule that projects
the timing of construction of facility projects; projects the schedule of any planned debt
issuance; includes all relevant revenue sources and expenditures on a yearly,
project -by -project basis; and determines the long-term "level funding" annual budget
commitment that is required to support the program.
Staff recommends establishing $29,500 (approximately 10% of total bid) for contingency
purposes and unforeseen conditions associated with construction.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15303 under Class 3 (New
Construction or conversion of small structures), Section 15304 under Class 4 (Minor
Alterations to Land), and Section 15311 under Class 11 (Accessory Structures) of the
CEQA Guidelines, California Code of Regulations, Title 14, Division 6, Chapter 3 because
this project has no potential to have a significant effect on the environment and the
exceptions to these categorical exemptions under Section 15300.2 are not applicable.
21-3
Temporary Fire Station No. 1 Project — Award of Contract No. 8865-3 (23F12)
August 26, 2025
Page 4
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
21-4
Attachment A
Location Map
21-5
ATTACHMENT A
0
a
F
eq�e0q
PROJECT
LOCATION
TEMPORARY FIRE STATION NO. 1 PROJECT CITY OF NEWPORT BEACH
LOCATION MAP PUBLIC WORKS DEPARTMENT
C-8865-3 23F12 08/26/25