HomeMy WebLinkAbout11 - Balboa Peninsula Water Main Replacement, East Irvine Terrace Water Main Replacement & Shorecliff Community Water System Improvements - Phase 2 - Award of Contract No. 9835-1 (26W12)Q �EwPpRT
CITY OF
s NEWPORT BEACH
`q44:09 City Council Staff Report
September 9, 2025
Agenda Item No. 11
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Michael J. Sinacori, Assistant City Engineer - 949-644-3342z
msinacori@newportbeachca.gov
TITLE: Balboa Peninsula Water Main Replacement, East Irvine Terrace
Water Main Replacement & Shorecliff Community Water System
Improvements — Phase 2— Award of Contract No. 9835-1 (26W12)
The City of Newport Beach received construction bids for the Balboa Peninsula Water
Main Replacement, East Irvine Terrace Water Main Replacement & Shorecliff Community
Water System Improvements — Phase 2 project and requests City Council approval to
award the construction contract to T.E. Roberts, Inc. of Irvine. This project will replace
deteriorated water mains located in the central Balboa Peninsula, East Irvine Terrace and
Shorecliff communities.
RECOMMENDATIONS:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15302(c), Class 2 (reconstruction of existing facility involving
negligible or no expansion of capacity) of the CEQA Guidelines, because this project
has no potential to have a significant effect on the environment;
b) Approve the project plans and specifications;
c) Award Contract No. 9835-1 to T.E. Roberts, Inc. for the total bid price of $6,741,473
for the Balboa Peninsula Water Main Replacement, East Irvine Terrace Water Main
Replacement & Shorecliff Community Water System Improvements — Phase 2 project,
and authorize the Mayor and City Clerk to execute the contract; and
d) Establish a contingency of $1,350,000 (approximately 20% of total bid) to cover the
cost of unforeseen work not included in the original contract.
DISCUSSION:
The existing Balboa Peninsula water mains (14 and 16 inches in size) included in the
project are older deteriorated cast-iron water mains, installed in 1926, that have outlived
their design life and are now due to be replaced.
Balboa Peninsula Water Main Replacement, East Irvine Terrace Water Main
Replacement & Shorecliff Community Water System Improvements —
Phase 2— Award of Contract No. 9835-1 (26W12)
September 9, 2025
Page 2
These water mains are large diameter pipes located in alleys north of Balboa Boulevard
between 6t" Street and Cypress Street. A large diameter water transmission main was
installed in Balboa Boulevard about a decade ago, allowing for the downsizing of the older
water mains in the alleys. These older mains in the alleys will be replaced with standard
8-inch piping, to maintain distribution and reduce risk to homes during potential water
main breaks. The East Irvine Terrace Community water mains are asbestos cement water
mains installed in 1956 and are located between El Paseo Drive and Avocado Avenue,
and Bayside Drive and East Coast Highway. The Shorecliff community water main
package picks up the remaining asbestos cement water mains that were not replaced in
last year's phase 1 project. These water mains are located on Seaward Road, Driftwood
Road, Morning Canyon Road and Evening Canyon Road between Seaward Road and
Morning Canyon Road.
At 10 a.m. on August 12, 2025 , the City Clerk opened and read the following bids for this
project:
BIDDER
TOTAL BID AMOUNT
Low
T.E. Roberts, Inc.
$ 6,741,473.00
2nd
Dominguez General Engineering, Inc.
$ 9,824,750.00
3rd
Big Ben, Inc.
$ 10,012,407.00
4th
Nationwide Contracting Services, Inc.
$ 12,025,650.00
5th
Toro Enterprises, Inc.
$ 13,709,180.00
6th
MMC, Inc.
$ 13,804,000.00
The low bidder, T.E. Roberts, Inc., possesses a California State Contractor's License
Classification "A", as required by the project specifications. A review of references for
T.E. Roberts, Inc. shows satisfactory completion of similar contracts for the City and other
municipalities. T.E. Roberts successfully completed the Balboa Island Water Main
Replacement (Phase 1, Phase 2 and Phase 3) projects, including the West Irvine Terrace
Water Main Replacement and Shorecliff Community Water System Improvements —
Phase 1 projects.
The low bid was 29% below the engineer's estimate of $9,500,000. The difference
between the low bid and engineer's estimate appears to be due to favorable bids for water
main and water service construction, trench dewatering, and street pavement restoration.
The proposed projects include construction of new, 8-inch PVC water mains, water
services, fire hydrants, and the removal and abandonment of existing 14-inch and 16-
inch water mains for the Balboa Peninsula community at the Balboa Fire Station and
Library development.
Work necessary to complete this contract also includes installation of new water valves,
installation of fittings and connections to existing water mains, pavement restoration,
restriping, traffic control, and other appurtenant work as required by the contract.
This water main construction will require alley and street closures and traffic detours. The
contractor will be required to keep cross traffic flowing at all times.
11-2
Balboa Peninsula Water Main Replacement, East Irvine Terrace Water Main
Replacement & Shorecliff Community Water System Improvements —
Phase 2— Award of Contract No. 9835-1 (26W12)
September 9, 2025
Page 3
A detailed schedule will be prepared by the contractor following project award, which can
be adjusted to address the concerns of area businesses and residents. Project phasing
has been developed to minimize impacts to the community. For example, no work will be
allowed on the Balboa Peninsula during the summer season to minimize traffic
disruptions. Work on the Peninsula will begin in October and have a target completion of
May 15, 2026.
Pursuant to the contract specifications, the contractor will have 400 consecutive working
days to complete the work, following the Notice to Proceed. Work is scheduled to start in
October 2025 on the Balboa Peninsula, followed by work in the Shorecliff community and
then East Irvine Terrace.
The project plans and specifications will be available for review at the September 9, 2025
City Council meeting or upon request.
FISCAL IMPACT:
The adopted Capital Improvement Program budget includes sufficient funding for the
award of this contract. The following funds will be expended:
Account Description Account Number Amount
Water Capital Distribution & Piping
Proposed fund uses are as follows:
Vendor
T.E. Roberts, Inc.
T.E. Roberts, Inc.
Geocon, Inc.
Various
70201931-980000-26W12 $ 8,238,323.00
Purpose
Amount
Construction Contract
$
6,741,473.00
Construction Contingency
$
1,350,000.00
Materials Testing
$
144,850.00
Printing & Incidentals
$
2,000.00
Total:
$
8,238,323.00
Water Capital Distribution & Piping Funds generate revenue primarily through water rates
collected from service users.
Staff recommends establishing $1,350,000 (approximately 20% of total bid) for
contingency purposes and unforeseen conditions associated with construction.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(c), Class 2 (reconstruction
of existing facility involving negligible or no expansion of capacity) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because this project has
no potential to have a significant effect on the environment.
11-3
Balboa Peninsula Water Main Replacement, East Irvine Terrace Water Main
Replacement & Shorecliff Community Water System Improvements —
Phase 2— Award of Contract No. 9835-1 (26W12)
September 9, 2025
Page 4
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Maps
11-4
ATTACHMENT A
JO
�0
'14OOP
WEST BAY AVENUE
ALLEY 245E
w WEST BALBOA BOULEVARD
co
iz-
co
OCEAN FRONT WEST
Q Q
a �
Q
o Z oo
ti
� tiq
o O
o �u
o
U c
O
2
I
2
7rA7,4
co
& Y ALLEY24$M
U
OCEAN FRONT Fgst
BALBOA PENINSULA
FAST BAY AVENUE
ALLFY2450 ��.
V
FAST
Bq�BOA BC Vo
PROPOSED WATER MAIN REPLACEMENT
BALBOA PENINSULA WATER MAIN REPLACEMENT CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
LOCATION MAP C-9835-1 I 26W12 1 09/06/25
11-5
ATTACHMENT A
ePsI-o O�
SEgORIF7 D VF �J�P c�G99s F9
O
MgRgpqT Bch'
q DRIVE
03
r
O
F
a -9lT �GG9�cc� ��P
2 T9�G�9 G�o�/G o�/GF
F �
6 T�� GAT
sq �i�9 �, ,Q9cF J� O y9L
Tyzp'O
G
9,91-SRO �F,S,� �pGQO Jac°
Fo
Q ��/� 6k-
OOti
� , P�tc
c�
EAST IRVINE TERRACE
PROPOSED WATER MAIN REPLACEMENT
EAST IRVINE TERRACE WATER MAIN REPLACEMENT CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
LOCATION MAP C-9835-1 I 26W12 1 09/06/25
11-6
ATTACHMENT A
0
0
U
CD
2
4
4Q
gNORCL/pp
SHORECLIFF COMMUNITY
PROPOSED WATER MAIN REPLACEMENT
SHORECLIFF COMMUNITY
WATER SYSTEM IMPROVEMENTS PHASE 2
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
LOCATION MAP
C-9835-1
09/06/25
11-7