Project Description:COMM - RELOCATE (2) TEMP MODULAR TRAILERS 960 SF EACH, PRE-
FAB METAL WALK-WAYS & STAIRS
Project Address:1 HOAG DR Permit Number:XC2025-5159
Permit App. Date:Permit Expires:
Use:Occupancy:Const. Type:
No. Stories:Permit Valuation:
Applicant/Contact:Liebke, Steven Phone:(949) 400-5462
Plan Check Engineer:Oliver Daluz
ODaluz@NewportBeachCA.gov
Phone:(949) 644-3271
1st Review: 6.30.25 2nd Review:3rd Review:X
Italic comments By Appointment
The project plans were reviewed for compliance with the following codes and standards:
2022 CBC; 2022 CPC; 2022 CEC; 2022 CMC; 2022 Building Energy Efficiency Standards (BEES);
2022 California Green Building Standards Code (CAL Green); & Chapter 15 of the Newport Beach
Municipal Code (NBMC).
The code section references are from the 2022 CBC, unless otherwise stated.
•TO EXPEDITE PROJECT APPROVAL: Please provide a written response indicating how and where
each comment was resolved on the plans.
•Resubmit all previously reviewed plans, updated plans and supporting documents with each subsequent
review.
•AFTER 2nd PLAN REVIEW: Please call the plan check engineer listed above to schedule a plan review
appointment, to expedite project approval.
•For clarification of any plan review comment, please call the plan check engineer listed above.
•Plan check status: www.newportbeachca.gov/civic. Under ‘Search’ tab, type in plan check number
above.
2
ELECTRICAL
1. All plans and electrical calculations are to be designed by a CA Registered Electrical Engineer, or
Licensed Architect, or Licensed Electrical Contractor (C-10); provide stamp with signature and date.
This comment will remain up to and include at the time of permit issuance.
2. Indicate the scope of electrical work with a brief description of the equipment being installed. Clarify
what is new and existing on plans.
3. Show grounding electrode system for all electrical service equipment / transformers / panels at each
detached trailer.
4. Clarify Panel ‘DPM’ main OCPD and bus rating.
MECHANICAL
No comments
PLUMBING
5. All plans and plumbing calculations are to be designed by a CA Registered Mechanical Engineer,
or Licensed Architect, or Licensed Plumbing Contractor (C-36); provide stamp with signature and
date. This comment will remain up to and include at the time of permit issuance.
6. Provide plumbing plans showing water and sewer connections to trailers. Additional comments may
apply based on new information.