HomeMy WebLinkAboutExhibit 1EXHIBIT NO. 1
Draft Resolution for project approval
A
RESOLUTION NO.
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
NEWPORT BEACH RESCINDING PLANNING COMMISSION
RESOLUTIONS 1723 AND 1751 AND RECOMMENDING THAT THE
CITY COUNCIL ADOPT MITIGATED NEGATIVE DECLARATION (SCH
NO. 2008051082) AND APPROVE GENERAL PLAN AMENDMENT NO.
2005 -006, COASTAL LAND USE PLAN AMENDMENT NO. 2005 -002,
CODE AMENDMENT NO. 2005 -009, NEWPORT TRACT MAP NO. 2005-
004 (TTM 16882), MODIFICATION PERMIT NO. 2005 -087 AND
COASTAL RESIDENTIAL DEVELOPMENT PERMIT NO. 2005 -002 FOR
PROPERTY LOCATED AT 201 -205, 207 CARNATION AVENUE 101
BAYSIDE PLACE (PA 2005 -196).
WHEREAS, an application was filed by Advanced Real Estate Services, Inc. with
respect to property located at 201 -205, 207 Carnation Avenue, and 101 Bayside Place
to construct a 8 -unit residential condominium development on a 1.4 acre site. The
application includes:
1. General Plan Amendment No. 2005 -006 to change the land use designation of a 584
square -foot portion of a parcel identified as 101 Bayside Place from RT (Two -Unit
Residential) to RM (Multiple -Unit Residential, 20 dwelling units per acre).
2. Coastal Land Use Plan Amendment No. 2005 -002 to change the Coastal Land Use
Plan designation of the same 584 square -foot portion of a parcel identified as 101
Bayside Place from RH -D (High Density Residential - 50.1 to 60 dwelling units per
acre) to RM -A (Medium Density Residential - 6.1 to 10 dwelling units per acre).
3. Zone Change No. 2005 -009 to change the zoning designation of the 584 square -foot
portion of a parcel identified as 101 Bayside Place from R -2 (Two - Family Residential)
to MFR (Multifamily Residential, 2178 square feet per unit).
4. Newport Tentative Tract Map No. 2005 -004 (TTM16882) to combine the 584 square -
foot portion of a parcel identified as 101 Bayside Place with parcels identified as 201-
205 Carnation Avenue and 207 Carnation Avenue, and to subdivide the air space for
8 residential condominium units.
5. Modification Permit No. 2005 -087 to permit a 5 -foot subterranean building
encroachment and 42 -inch high protective guardrails within the required 10 -foot front
setback along Carnation Avenue; subterranean and above grade building
encroachments of 3' -1" and 5' -7" into a required 10' -7° side yard setback between the
project and 215 Carnation including four deck/balcony features with protective guard
rails that exceed the maximum 6 -foot height above natural grade; and three balconies
and one at grade landing each with protective guard rails that exceed the maximum
height of 6 feet from natural grade within the required 10' -7" side yard abutting
Bayside Place.
0
City of Newport Beach
Planning Commission Resolution No.
Page 2 of 37
6. Coastal Residential Development Permit No. 2005 -002 to allow demolition of the
existing dwelling units within the Coastal Zone pursuant to Chapter 20.86 of the
Municipal Code.
WHEREAS, on February 22, 2007, April 5, 2007, May 17, 2007, February 21,
2008, and June 19, 2008, the Planning Commission held a noticed public hearing in the
City Hall Council Chambers, 3300 Newport Boulevard, Newport Beach, California, at
which time the applications, project and a draft Mitigated Negative Declaration were
considered. Notice of time, place and purpose of the public hearing was given in
accordance with law and testimony was presented to and considered by the Planning
Commission at the hearing.
WHEREAS, the project site has two separate land use designations assigned by
the Land Use Element of the General Plan (584 square -feet is designated RT (Two -Unit
Residential) and the remaining portion of the site, 60,700 square -feet, is designated RM
(Mufti -Unit Residential, 20 dwelling units per acre). The proposed amendment changing
the land use designation of the 584 square -foot portion of the site to match the
remainder of the site will numerically allow 1 additional unit; however, the density
limitation as dictated by the Zoning Ordinance is more restrictive as it excludes
submerged lands and slopes in excess of 50% from the calculation. The density of the
proposed project is below the resulting maximum density permitted by the General Plan
(28 dwellings) and is consistent with the maximum density allowed by the existing MFR
zone (9 units). The residential condominium project is consistent with the proposed
Multi - Family Residential land use designation and is consistent with residential
developments within the area.
WHEREAS, Charter Section 423 requires that all proposed General Plan
Amendments be reviewed to determine if the square footage (for non - residential
projects), peak hour vehicle trip, or dwelling units thresholds would be exceeded as the
means to determine whether a vote by the electorate would be required to approve the
General Plan Amendment. Pursuant to Council Policy A -18, voter approval is not
required as the proposed General Plan Amendment represents an increase of 1
dwelling unit and an increase of 1 A.M. and 1 P.M. peak hour trip. Additionally, no prior
amendments have been approved within Statistical Area F3 and, therefore, the project
and prior amendments do not cumulatively exceed Charter Section 423 thresholds as to
require a vote of the electorate.
WHEREAS, the proposed project subject to conditions of approval is consistent
with General Plan Policy LU5.1.9 inasmuch as building elevations that face public
streets need to be treated to achieve the highest level of urban design and
neighborhood quality. Architectural treatment of building elevations and the modulation
of mass are to convey the character of separate living units or clusters of living units,
avoiding the appearance of a singular building volume. Street elevations are to be
provided with high quality materials and finishes to convey quality. Roof profiles are
.�O
City of Newport Beach
Planning Commission Resolution No.
Page 3 of 37
modulated to reduce the apparent scale of large structures and to provide visual interest
and variety. Parking areas are designed to be integral with the architecture of the
development. Usable and functional private open space for each unit are incorporated
as each unit has an outdoor deck or patio that may include a fire pit and spa. Common
open space that creates a pleasant living environment with opportunities for recreation
is also included. Private storage areas for each unit are also provided. The project
design incorporates building articulation, roof modulation and a diverse architectural
style. Although specific exterior finishes or building materials are not identified at this
time, the applicant and architect are committed to providing the highest quality project
commensurate with the expense of the project and appropriate to their target buyer.
WHEREAS, the proposed project subject to conditions of approval is consistent
with General Plan Policy LU 5.1.8 that requires adequate enclosed parking considering
the number of bedrooms. One unit has 2 bedrooms, five units have 3 bedrooms, one
unit has 4 bedrooms and one unit has 5 bedrooms. Five of the units have other rooms
that could be modified and used as bedrooms and the unit sizes range from 2,689 to
4,990 square feet. The project provides two spaces for each of 2 units without vehicle
lifts, and three spaces for each of 6 units with vehicle lifts. Seven guest parking spaces,
one service vehicle space and 2 golf cart spaces are provided for a total of 32 covered,
vehicle spaces. An area for motorcycle or bicycle parking is also included. Provided
parking is in excess of the minimum required pursuant to the Zoning Code (2.5 parking
spaces per unit for total of 20 spaces).
WHEREAS, the proposed project is consistent with General Plan Policy CE7.1.8
and Policy CE7.1.1 as well as Coastal Land Use Policy 2.9.3 -1 that require new
development to avoid the use of parking configurations or parking management
programs that are difficult to maintain and enforce and that new development is required
to provide adequate, convenient parking for residents. All parking is enclosed on site
with access to lower parking levels taken from two vehicle elevators. Five of the seven
guest parking spaces and parking for one unit is located at street level where access to
the vehicle elevators is not necessary. No gates are planned that could possibly inhibit
to the street -level parking. Only seven of the eight units and two guest parking spaces
will required the use of the vehicle elevators. The below -grade parking configuration
accessed by elevators is sufficiently convenient in that two vehicle elevators to access
the garage are proposed, which will reduce vehicle wait times to avoid significant
conflicts entering or exiting the elevators. Emergency power generators are required so
that vehicle access is maintained if electrical power is lost. The vehicle maneuvering
areas within the parking areas meet or will be modified prior to the issuance of a
building permit consistent with applicable standards required by the City Traffic
Engineer.
WHEREAS, the Land Use and Natural Resources Elements of the General Plan
contain general policies regarding the protection of public views, visual resources,
coastal bluffs and other natural resources and the Coastal Land Use Plan (CLUP)
reflects these same policies and includes additional policies that expand upon the topics
City of Newport Beach
Planning Commission Resolution No.
Page 4 of 37
addressed in the Land Use and Natural Resources Elements of the General Plan and
are applicable only within the Coastal Zone such that a finding of consistency with the
CLUP is an implicit finding of consistency with the Land Use Element of the General
Plan. Accordingly, based upon facts in support of findings that the project's consistency
with the relevant CLUP policies as indicated below, the project is determined to be
consistent with all resource protection policies within the Land Use and Natural
Resources Elements.
WHEREAS, the Coastal Land Use Plan (CLUP) designates the majority of the
site RM -A (Medium Density Residential - 6.1 to 10 dwelling units per acre) and a 584
square -foot portion of the site is designated RH -D High Density Residential - 50.1 to 60
dwelling units per acre. The proposed amendment of the land use designation for the
584 square -foot portion of the site will result in a land use designation the same as the
larger portion of the site and will numerically increase the maximum permissible project
density by 1 unit, from 13 to 14, but not the maximum permissible density pursuant to
the RM -A Zoning for the site.
WHEREAS, the proposed project is consistent with applicable policies within Chapter 2
(Land Use and Development) of the Coastal Land Use Plan based upon the following:
1. Policy 2.7 -1. Continue to maintain appropriate setbacks and density, floor area, and
height limits for residential development to protect the character of established
neighborhoods and to protect coastal access and coastal resources.
The project conforms to the height limit of the MFR zone and no deviation is proposed.
The project proposes 62,231 gross square -feet, below the maximum 75,868 allowed by
the existing MFR zone standard. The proposed 8 -unit project is below the maximum
permissible density established by the RM -A (Medium Density Residential - 6.1 to 10
dwelling units per acre). Setback encroachments are primarily subterranean and would
not impact the character of the area. The above - ground encroachments are minor in
nature. The project provides between 5 to 10 feet of setback area to the north abutting
215 Carnation Avenue where no public view presently exists due to current site
conditions. The setback proposed will provide adequate separation from the building to
the north and the encroachments will not impact fragile resources as the
encroachments are located on the opposite side of the building away from the bluff and
bay.
2. Policy 2.7 -2. Continue the administration of provisions of State law relative to the
demolition, conversion and construction of low and moderate- income dwelling units
within the coastal zone.
Government Code Section 65590 (Mello Act) regulates the demolition or conversion of
low and moderate income units within the Coastal Zone. All units were vacated in
December of 2001 and only a caretaker and the applicant's family reside in the
la
City of Newport Beach
Planning Commission Resolution No.
Page 5 of 37
apartment. No low or moderate income residents currently reside within the project and,
therefore, Government Code Section 65590 is not applicable.
3. Policy 2.8.1 -1. Review all applications for new development to determine potential
threats from coastal and other hazards.
Policy 2.8.1 -2. Design and site new development to avoid hazardous areas and
minimize fisks to life and property from coastal and other hazards.
Policy 2.8.1 -3. Design land divisions, including lot line adjustments, to avoid
hazardous areas and minimize risks to life and property from coastal and other
hazards.
A coastal hazards study has been prepared by GeoSoils Inc., dated October, 5, 2006.
Given the location, topography and development proposed, potential hazards are
seismic ground shaking, coastal bluff retreat due to erosional forces and tsunamis.
Seismic issues are mitigated with the implementation of the Building Code and coastal
bluff retreat is not expected to impact the project during the 75 year economic life of the
building. Inundation by wave action or tsunami is considered very remote and the
proposed residential improvements are well above wave action.
4. Policy 2.8.1 -4. Require new development to assure stability and structural integrity,
and neither create nor contribute significantly to erosion, geologic instability, or
destruction of the site or surrounding area or in any way require the construction of
protective devices that would substantially alter natural landforms along bluffs and
Cliffs.
Policy 2.8.3 -1. Require all coastal development permit applications for new
development on a beach or on a coastal bluff property subject to wave action to
assess the potential for flooding or damage from waves, storm surge, or seiches,
through a wave uprush and impact reports prepared by a licensed civil engineer with
expertise in coastal processes. The conditions that shall be considered in a wave
uprush study are: a seasonally eroded beach combined with long -term (75 years)
erosion; high tide conditions, combined with long -term (75 year) projections for sea
level rise, storm waves from a 100 -year event or a storm that compares to the
1982183 El Nino event.
Policy 2.8.6 -10. Site and design new structures to avoid the need for shoreline and
bluff protective devices during the economic life of the structure (75 years).
Policy 2.8.7 -3. Require applications for new development, where applicable [i.e., in
areas of known or potential geologic or seismic hazards], to include a
geologic/soils/geotechnical study that identifies any geologic hazards affecting the
proposed project site, any necessary mitigation measures, and contains a statement
that the project site is suitable for the proposed development and that the
13
City of Newport Beach
Planning Commission Resolution No.
Page 6 of 37
development will be safe from geologic hazard. Require such reports to be signed by
a licensed Certified Engineering Geologist or Geotechnical Engineer and subject to
review and approval by the City.
A Grading Plan Review Report prepared by Neblett & Associates, August 2005, the
Coastal Hazard Study prepared by GeoSoils Inc., dated October 2006, a Stormwater
Pollution Prevention Plan prepared by Hunsaker and Associates dated March 27, 2005
collectively indicate that the project will not be subject to nor contribute to erosion,
geologic instability, geologic hazard nor require shoreline protective devices during the
economic life of the structure (75 years).
5. Policy 2.8.6 -9. Require property owners to record a waiver of future shoreline
protection for new development during the economic life of the structure (75 years)
as a condition of approval of a coastal development permit for new development on
a beach, shoreline, or bluff that is subject to wave action, erosion, flooding,
landslides, or other hazards associated with development on a beach or bluff.
Shoreline protection may be permitted to protect existing structures that were legally
constructed prior to the certification of the LCP, unless a waiver of future shoreline
protection was required by a previous coastal development permit.
A waiver of future shoreline protective devices is included as a condition of approval.
6. Policy 2.9.3 -10 Require new development to minimize curb cuts to protect on- street
parking spaces and close curb cuts to create new public parking wherever feasible. The
project will reduce the width of existing curb cuts creating 3 additional street spaces.
WHEREAS, the proposed project is consistent with Chapter 3 (Public Access) of the
Coastal Land Use Plan based upon the following:
Policy 3.1.1 -1. Protect, and where feasible, expand and enhance public access to and
along the shoreline and to beaches, coastal waters, tidelands, coastal parks, and trails.
Policy 3.1.2 -1. Protect, and where feasible, expand and enhance public access to and
along coastal bluffs.
Policy 3.1.2 -2. Site, design, and maintain public access improvements in a manner to
avoid or minimize impacts to coastal bluffs.
Policy 3.1.1 -11. Require new development to minimize impacts to public access to and
along the shoreline.
Policy 3.1.1 -9. Protect, expand, and enhance a system of public coastal access that
achieves the following.
• Maximizes public access to and along the shoreline,
�q
City of Newport Beach
Planning Commission Resolution No.
Page 7 of 37
• Includes pedestrian, hiking, bicycle, and equestrian trails,
• Provides connections to beaches, parks, and recreational facilities;
• Provides connections with trail systems of adjacent jurisdictions;
• Provides access to coastal view corridors;
• Facilitates alternative modes of transportation,
• Minimizes alterations to natural landforms,
• Protects environmentally sensitive habitat areas,
• Does not violate private property rights.
Policy 3.1.1 -24. Encourage the creation of new public vertical accessways where
feasible, including Corona del Mar and other areas of limited public accessibility.
Policy 3.1.1 -13. Require a direct dedication or an Offer to Dedicate (OTD) an easement
for lateral public access for all new shorefront development causing or contributing to
adverse public access impacts. Such dedication or easement shall extend from the
limits of public ownership (e.g. mean high tide line) landward to a fixed point seaward of
the primary extent of development (e.g. intersection of sand with toe or top of
revetment, vertical face of seawall, dripline of deck, or toe of bluff).
Policy 3.1.1 -14. Require a direct dedication or an Offer to Dedicate (0 TD) an easement
for vertical access in all new development projects causing or contributing to adverse
public access impacts, unless adequate access is available nearby. Vertical
accessways shall be a sufficient size to accommodate two -way pedestrian passage and
landscape buffer and should be sited along the border or side property line of the
project site or away from existing or proposed development to the maximum feasible
extent.
Policy 3.1.1 -24. Encourage the creation of new public vertical accessways where
feasible, including Corona del Mar and other areas of limited public accessibility.
Policy 3.1.1 -26. Consistent with the policies above, provide maximum public access
from the nearest public roadway to the shoreline and along the shoreline with new
development except where (1) it is inconsistent with public safety, military security
needs, or the protection of fragile coastal resources or (2) adequate access exists
nearby.
Policy 3.1.1 -27. Implement public access policies in a manner that takes into account
the need to regulate the time, place, and manner of public access depending on the
facts and circumstances in each case including, but not limited to, the following:
• Topographic and geologic site characteristics;
• Capacity of the site to sustain use and at what level of intensity;
• Fragility of natural resource areas;
• Proximity to residential uses;
• Public safety services, including lifeguards, fire, and police access;
k'D
City of Newport Beach
Planning Commission Resolution No.
Page 8 of 37
• Support facilities, including parking and restrooms;
• Management and maintenance of the access;
• The need to balance constitutional rights of individual property owners and the
public's constitutional rights of access.
The project site has no dedicated public access easements or physical access to the
coastal bluff or bay. No abutting vertical or lateral public access presently exists that
would connect to any access that might be considered within the development. The
steep topography of the site makes vertical access a safety concern and access for the
disabled could not be accommodated. Support facilities presently do not exist nor are
they planned, and parking in the area is constrained. Lastly, access through the site
would be in close proximity to residential uses.
The lower portion of the bluff face (below 50.7 feet MSL), submerged lands and
tidelands will remain in their existing condition, with the exception of the construction of
a new dock system to replace the existing one. Public access to the tidelands from the
water will not be affected as the development will be well above the tidelands. Access to
the designated view point at the end of Carnation Avenue will also remain unaffected
and the public view from that point and Ocean Boulevard will be enhanced with project
approval with the installation of a bench and /or other public amenity at the corner to
improve the experience. The project will create 3 new parking spaces along Carnation
Avenue with the reduction in the width of the existing driveway approaches. These new
public parking spaces will enhance access to the area. With the reduction in residential
density and the fact that no access rights or proscriptive access rights exist, the project
will not impact or impede public access.
Public access to the bay is currently provided in the vicinity at China Cove, Lookout
Point and at a street -end located in the 2300 block of Bayside Drive. These access
points are located approximately 450 feet to the east, 1,125 feet to the east and
approximately 480 feet to the northwest, respectively. Based upon the forgoing,
requiring public access easements or outright dedication of land for public access is not
necessary.
WHEREAS, the proposed project is consistent with Policy 4.1.3 -1 of the Coastal
Land Use Plan that states "Utilize the following mitigation measures to reduce the
potential for adverse impacts to ESA natural habitats from sources including, but not
limited to, those identified in Table 4.1.1." Only Subsections E, F, G, and N are
applicable to the proposed project as the other subsections are clearly inapplicable as
they relate to different physical and operational aspects of Newport Bay.
E. Limit encroachments into wetlands to development that is consistent with Section
30233 of the Coastal Act and Policy 4.2.3 -1 of the Coastal Land Use Plan.
The residential portion of the project will not encroach into wetlands or open coastal
waters. The expanded boating facility (replacement docks) is a permitted encroachment
[(�p
City of Newport Beach
Planning Commission Resolution No.
Page 9 of 37
within open coastal waters pursuant to Section 30233 of the Coastal Act and Policy
4.2.3 -1 as construction must be conducted in accordance with all mitigation measures
contained within the Mitigated Negative Declaration.
F. Regulate landscaping or revegetation of blufftop areas to control erosion and invasive
plant species and provide a transition area between developed areas and natural
habitats.
A condition of approval requires all non - native plantings on the bluff to be removed and
revegetation of the bluff face is regulated to only allow native and non - invasive plantings
indigenous to the California coastal bluff environment.
G. Require irrigation practices on blufftops that minimize erosion of bluffs.
An irrigation plan is required pursuant to conditions of approval for the project and
temporary irrigation on the bluff face may only be to be used to establish vegetation.
N. Prohibit invasive species and require removal in new development.
A condition of approval requires all non - native plantings on the bluff to be removed and
revegetation of the bluff face is regulated to allow only native and non - invasive plantings
indigenous to the California coastal bluff environment.
WHEREAS, the proposed project is consistent with the following policies of
Chapter 4 (Coastal Resource Protection) based upon the following:
Policy 4.3.1 -5. Require development on steep slopes or steep slopes with erosive soils
to implement structural best management practices (BMPs) to prevent or minimize
erosion consistent with any load allocation of the TMDLs adopted for Newport Bay.
Policy 4.3.1 -6. Require grading/erosion control plans to include soil stabilization on
graded or disturbed areas.
Policy 4.3.1 -7. Require measures be taken during construction to limit land disturbance
activities such as clearing and grading, limiting cut -and fill to reduce erosion and
sediment loss, and avoiding steep slopes, unstable areas, and erosive soils. Require
construction to minimize disturbance of natural vegetation, including significant trees,
native vegetation, root structures, and other physical or biological features important for
preventing erosion or sedimentation.
Policy 4.3.2 -22. Require beachfront and waterfront development to incorporate BMPs
designed to prevent or minimize polluted runoff to beach and coastal waters.
Policy 4.3.2 -23. Require new development applications to include a Water Quality
Management Plan (WQMP). The WQMP's purpose is to minimize to the maximum
11
City of Newport Beach
Planning Commission Resolution No.
Page 10 of 37
extent practicable dry weather runoff, runoff from small storms (less than 314" of rain
falling over a 24 -hour period) and the concentration of pollutants in such runoff during
construction and post- construction from the property.
An Erosion and Sediment Control Plan, Stormwater Pollution Prevention plan and a
Water Quality Management Plan are required by conditions of approval and they must
include best management practices to ensure that erosion is controlled to the maximum
extent feasible.
WHEREAS, the proposed project is consistent with Policy 4.4.3 -4. of the Coastal
Land Use Plan that states "On bluffs subject to marine erosion, require new accessory
structures such as decks, patios and walkways that do not require structural foundations
to be sited in accordance with the predominant line of existing development in the
subject area, but not less than 10 feet from the bluff edge. Require accessory structures
to be removed or relocated landward when threatened by erosion, instability or other
hazards."
No new accessory structures are proposed. The policy also requires that accessory
structures be removed or relocated landward when threatened by erosion, instability or
other hazards. A condition of approval is included such that the existing accessory
structures (concrete pad, staircase and walkway) will be removed if threatened by
erosional processes in the future.
WHEREAS, the proposed project is consistent with Policy 4.4.3 -11 of the Coastal
Land Use Plan that states "Require applications for new development to include slope
stability analyses and erosion rate estimates provided by a licensed Certfed
Engineering Geologist or Geotechnical Engineer."
A Grading Plan Review Report prepared by Neblett & Associates, August 2005, the
Coastal Hazard Study prepared by GeoSoils Inc., dated October 2006, a Stormwater
Pollution Prevention Plan prepared by Hunsaker and Associates dated March 27, 2005,
collectively indicate that the project will not be subject to nor contribute to erosion,
geologic instability, geologic hazard nor require shoreline protective devices during the
economic life of the structure (75 years).
WHEREAS, the proposed project is consistent with the following policies of
Chapter 4 (Coastal Resource Protection) that regulate the protection of public views
based upon the following:
Policy 4.4.1 -1. Protect and, where feasible, enhance the scenic and visual qualities of
the coastal zone, including public views to and along the ocean, bay, and harbor and to
coastal bluffs and other scenic coastal areas.
Policy 4.4.1 -2. Design and site new development, including landscaping, so as to
minimize impacts to public coastal views.
I
City of Newport Beach
Planning Commission Resolution No.
Page 11 of 37
Policy 4.4.1 -4. Where appropriate, require new development to provide view
easements or corridors designed to protect public coastal views or to restore public
coastal views in developed areas.
Policy 4.4.1 -6. Protect public coastal views from the following roadway
segments... Ocean Boulevard (Figure 4 -3 of the CLUP identifies the intersection of
Camation Avenue and Ocean Boulevard as a "view point. ")
Policy 4.4.1 -7. Design and site new development, including landscaping, on the edges
of public coastal view corridors, including those down public streets, to frame and
accent public coastal views.
Policy 4.4.2 -2. Continue to regulate the visual and physical mass of structures
consistent with the unique character and visual scale of Newport Beach.
Policy 4.4.2 -3. implement the regulation of the building envelope to preserve public
views through the height, setback, floor area, lot coverage, and building bulk regulation
of the Zoning Code in effect as of October 13, 2005 that limit the building profile and
maximize public view opportunities.
A public view presently exists over the southeastern portion of the site from Ocean
Boulevard and Carnation Avenue to the south and southwest between the existing 14-
unit apartment building and improvements on the adjoining property to the southeast.
The siting of the proposed building would provide a greater separation between these
buildings than exists today. Presently, the horizontal view window measures 25 degrees
and with the project, the view window will increase to 44 degrees. Based upon the
visual simulation prepared by the project architect, the public view from Ocean
Boulevard to the west will also be improved due to the position of the proposed building.
Although the proposed building is taller than the existing building, there is no public view
over the buildings; therefore, the taller building proposed will not impact a public view.
The project is consistent with the 28 -foot building height limit as demonstrated by the
project plans and verified by staff, and with other building envelope restrictions with the
exception of setback encroachments as proposed. Since the visible portion of the
building will not extend below 50.7 feet MSL and is consistent with the predominant line
of existing development as identified by the City Council on August 14, 2007, impacts to
public views of the site from the south, west and from Begonia Park are not significantly
impacted so as to be inconsistent with CLUP policy. The above -grade encroachments
of the building into the side yard setback adjacent to 215 Carnation Avenue will not
impact a public view as public view from Carnation Avenue or Ocean Boulevard to
Newport Bay or Pacific Ocean presently does not exist in that location. Other setback
encroachments are below the grade of the street and would not impact a public view.
Project encroachments into the required side yard setback abutting Bayside Place do
impact public views from Begonia Park or other vantage points from the northwest as
the balconies and walkway do not project beyond the silhouette of the remainder of the
M
City of Newport Beach
Planning Commission Resolution No.
Page 12 of 37
building that conforms to setback regulations. No other public views exist from the street
through the site due to the position of the current buildings. Therefore, the proposed
project will not have an impact upon existing public views through the site to the south
and west. The recordation of a public view easement to protect the public view over the
site from Ocean Boulevard and Carnation Avenue is required as a condition of approval.
WHEREAS, the proposed project is consistent with the following policies of
Chapter 4 (Coastal Resource Protection) as they related to the scenic and visual
qualities of the coastal zone and to minimizing the alteration of the coastal bluff based
upon the following:
Policy 4.4.1 -1. Protect and, where feasible, enhance the scenic and visual qualities of
the coastal zone, including public views to and along the ocean, bay, and harbor and to
coastal bluffs and other scenic coastal areas.
Policy 4.4.1 -2. Design and site new development, including landscaping, so as to
minimize impacts to public coastal views.
Policy 4.4.1 -3 Design and site new development to minimize alterations to significant
natural landforms, including bluffs, cliffs and canyons.
Policy 4.4.3 4 Prohibit development on bluff faces, except private development on
coastal bluff faces along Ocean Boulevard, Carnation Avenue and Pacific Drive in
Corona del Mar determined to be consistent with the predominant line of existing
development or public improvements providing public access, protecting coastal
resources, or providing for public safety. Permit such improvements only when no
feasible altemative exists and when designed and constructed to minimize alteration of
the bluff face, to not contribute to further erosion of the bluff face, and to be visually
compatible with the surrounding area to the maximum extent feasible.
Policy 4.4.3 -9. Where principal structures exist on coastal bluff faces along Ocean
Boulevard, Carnation Avenue and Pacific Drive in Corona del Mar, require all new
development to be sited in accordance with the predominant line of existing
development in order to protect public coastal views. Establish a predominant line of
development for both principle structures and accessory improvements. The setback
shall be increased where necessary to ensure safety and stability of the development.
Policy 4.4.3 -12. Employ site design and construction techniques to minimize alteration
of coastal bluffs to the maximum extent feasible, such as:
A. Siting new development on the flattest area of the site, except when an
alternative location is more protective of coastal resources.
B. Utilizing existing driveways and building pads to the maximum extent
feasible.
C. Clustering building sites.
h0
City of Newport Beach
Planning Commission Resolution No.
Page 13 of 37
D. Shared use of driveways.
E. Designing buildings to conform to the natural contours of the site, and
arranging driveways and patio areas to be compatible with the slopes and
building design.
F. Utilizing special foundations, such as stepped, split level, or cantilever
designs.
G. Detaching parts of the development, such as a garage from a dwelling
unit.
H. Requiring any altered slopes to blend into the natural contours of the site.
The City Council has interpreted Policies 4.4.3 -8 and 4.4.3 -9 to mean that development
on bluff faces is prohibited, except private development on coastal bluff faces along Ocean
Boulevard, Carnation Avenue and Pacific Drive in Corona del Mar determined to be
consistent with the predominant line of existing development. Additionally, public
improvements on coastal bluff faces that are allowable are those that provide public access,
protect coastal resources, or provide for public safety when no feasible alternative exists
and when they are designed and constructed to minimize alteration or further erosion of the
bluff face and are visually compatible with the surrounding area to the maximum extent
feasible. In all cases where the predominant line of existing development is used to
establish a development limit, it shall not be the only criteria used for this purpose. All
coastal land use policies shall be considered in determining the appropriate extent of new
development and size of new structures. The City Council made these clarifications by
adopting Coastal Land Use Plan Amendment No. 2007 -003, which has not yet been
considered by the California Coastal Commission.
Existing development of the site is located on the face of a coastal bluff. Identification of
the project site as a coastal bluff is based upon the professional opinion of Sidney
Neblett, a Certified Engineering Geologist. The coastal bluff transitions from north - facing
to west - facing roughly northwest of the intersection of Ocean Boulevard and Carnation
Avenue in the center of the project. This transition point extends down to the northwest
to the western extent of a small pocket beach unofficially known as Carnation Cove.
North of the transition point of this coastal bluff, is a series of residential structures
developed between 42 and 58 feet above mean sea level. East of the transition point
along Ocean Boulevard is a series of projects that were developed much farther down
the bluff face with several at the waters edge. The City Council reviewed this existing
development pattern at a noticed public hearing on August 14, 2007, and determined
that the predominant line of existing development is 50.7 feet MSL. The visible portion
of the project does not extend below this elevation except where it connects with an
existing access staircase leading to the Bay. The project minimizes alteration of the
coastal bluff and protects public views of the coastal bluff by not altering the bluff face
below the predominant line of existing development and preserving the majority of the
visible bluff. The project is required to blend any altered slopes outside of the building
footprint to the natural contours, native rocks or soils of the site. For these reasons, the
project protects the scenic and visual qualities of the coastal zone, minimizes alteration
of the bluff and is consistent with CLUP Policies 4.4.1 -1, 4.4.1 -2, 4.4.1 -3, 4.4.3 -8, 4.4.3-
9, 4.4.3 -12 and Coastal Land Use Plan Amendment No. 2007 -003.
City of Newport Beach
Planning Commission Resolution No.
Page 14 of 37
WHEREAS, the granting of the Modification Permit allowing above grade and
below grade encroachments into the front and side yard setbacks is necessary due to
practical difficulties associated with the property and that the strict application of the
Zoning Code results in physical hardships that are inconsistent with the purpose and
intent of the Zoning Code for the following reasons:
The site is irregular in shape, has steep topography and has submerged lands which
make it difficult to design a project at the density proposed while providing required
parking. Approximately 65% of the site is submerged or has slopes in excess of 50 %.
The need to provide on -site parking requires that a significant portion of the building
area be allocated for the parking garage, thereby reducing available area for residential
units. The required side yard setback is also larger than the required front yard setback
and the application of this standard represents a practical difficulty given the relatively
small buildable area available on the entire site.
WHEREAS, the granting of the Modification Permit allowing above grade and
below grade encroachments into the front and side yard setbacks will be compatible
with the existing development in the neighborhood and the granting of the permit
application will not adversely affect the health or safety of persons residing or working in
the neighborhood of the property and will not be detrimental to the general welfare or
injurious to property or improvements in the neighborhood for the following reasons:
The requested encroachments within the front yard, with the exception of the 42 -inch
high protective guardrail, will be entirely subterranean and will not be visible. The
proposed guardrail will have an open design allowing visibility through while providing
adequate protection to pedestrians on the public sidewalk from falling over the proposed
retaining wall located within the required front yard. Building encroachments within the
required front and side yard setback on levels below the street will not be visible. Side
yard setback encroachments (Balconies, stairways, stair landing and building areas)
that are above -grade that are proposed between the project and 215 Carnation Avenue
will leave between a 5' to 7'-6" setback on the street level and 10 feet of setback area
on levels above. The provided setbacks exceed typical 4 -foot setbacks along Carnation
Avenue. The decks are of limited size and consequently of limited use and, therefore,
the privacy of the abutting resident should not be negatively effected. This area between
the proposed building and the property line will provide sufficient separation between
the project and the abutting residence to the north and the setbacks provided will
provide for private views between the buildings from upper levels of residences across
Carnation Avenue. The varying distances also provides some building articulation as
suggested by General Plan policy. The encroachments of balconies, including
protective guard railings, within the side setback abutting Bayside Place should not
impact these residents given the change in topography, the separation provided by
Bayside Place, a private roadway, and the fact that these residences are oriented
toward Newport Bay and not project. The encroachments within the side setback
abutting Bayside Place also do not encroach within a public view from Begonia Park or
�d-
City of Newport Beach
Planning Commission Resolution No.
Page 15 of 37
other vantage points from the west any more than the proposed building does which is
compliant with the setback. The encroaching balconies and guard railings will encroach
into private views of residents to the north on Carnation Avenue, but the majority of the
view to the west and southwest will remain unchanged.
WHEREAS, Newport Tract No. 2005 -004 (TTM16882) can be approved based
upon the following findings:
The modified project is consistent with the current land use designation including the
proposed amendment. The project is consistent with Land Use Element Policy
LU5.1.9 regarding the character and quality of multi - family residential development.
The project is consistent with Land Use Element and Natural Resources Element
policies related to the protection of public views, visual resources, coastal bluffs and
other natural resources based upon the project's consistency with the Coastal Land
Use Plan. The site is not subject to a specific plan. Minimum lot sizes established by
the Zoning Ordinance are also maintained as required by the City Subdivision Code.
The tentative tract map, pursuant to the conditions of approval, is consistent with the
Newport Beach Subdivision Code (Title 19) and applicable requirements of the
Subdivision Map.
2. The buildable area of the site is relatively small compared to the entire 1.4 acre site.
The site is not likely to be subject to coastal erosional processes or hazards during
the 75 -year economic life of the project. No earthquake faults were found on -site and
there is not likely to be an incidence of landslide, lateral spreading, subsidence,
liquefaction, or collapse on -site or near the site given on -site soils conditions. These
factors indicate that the site is suitable for development.
3. The design of the subdivision and proposed improvements subject to conditions of
approval will not cause substantial environmental damage nor substantially and
avoidably injure fish or wildlife or their habitat based upon the Mitigated Negative
Declaration (SCH# 2008051082) and the adoption of mitigation measures as
conditions of project approval.
4. The tract map would subdivide airspace for residential condominium purposes and is
not expected to cause serious public health problems given the use of typical
construction materials and practices. No evidence is known to exist that would
indicate that the proposed subdivision will generate any serious public health
problems. All mitigation measures as outlined in the Mitigated Negative Declaration
and the Building, Grading and Fire codes will be implemented to ensure the
protection of public health.
5. The proposed subdivision will not conflict with easements, acquired by the public at
large, because a utility and sewer easement that affects the site is presently not in
use and can be abandoned. The design of the proposed subdivision will not impact
an existing storm drain easement and storm drain as proposed improvements will not
�3
City of Newport Beach
Planning Commission Resolution No.
Page 16 of 37
encroach upon the existing easement. The storm drain easement will appear on the
final map. Public utility easements for utility connections that serve the project site are
present and will be modified, if necessary, to serve the proposed project.
6. The site is not subject to a Williamson Act contract.
7. The property is not located within the boundaries of a specific plan;
8. The subdivision is subject to Title 24 of the California Building Code that requires new
construction to meet minimum heating and cooling efficiency standards depending on
location and climate. The Newport Beach Building Department enforces Title 24
compliance through the plan check and field inspection processes. The site has a
western exposure and incorporates curved roof elements that will provide some
shading of windows and passive solar cooling. Significant exterior wall segments are
below grade which will benefit from passive cooling.
9. The subdivision is consistent with Section 66412.3 of the Subdivision Map Act and
Section 65584 of the California Government Code regarding the City's share of the
regional housing needs although the proposed subdivision will have the effect of
reducing the residential density on the site from 15 units to 8 units. The reduction is
insignificant given the City's current housing supply. Although the reduction in units
does not assist the City in reaching its production goals, no affordable housing units
are being eliminated based upon the fact that the project was not occupied by low or
moderate income households. The reduction in density is consistent with existing
density limitations of the Municipal Code.
10.Wastewater discharge into the existing sewer system will be consistent with existing
residential use of the property, which does not violate Regional Water Quality
Control Board (RWQCB) requirements.
11.The proposed subdivision is entirely within the coastal zone and the site is not
presently developed with coastal - related uses, coastal- dependent uses or water
oriented recreational uses that would be displaced by a non - priority use. The project
site is constrained by topography and public access exists nearby making on -site
vertical and lateral access unnecessary. Public access to the area is enhanced as a
result of increasing public parking opportunities on Carnation Avenue afforded by 3
on street parking spaces to be added with closure of existing driveway curb cuts.
The position of the proposed building enhances public views from Ocean Boulevard
and Carnation Avenue by increasing the view angle between the development on
the project site and adjacent development. The modified project developed in
accordance with the conditions of approval will minimize alteration of the coastal
bluff and preserve the scenic and visual quality of the coast by preserving the bluff
below 50.7 feet MSL. Lastly, the project will not impact sensitive marine resources
with the implementation of the conditions of approval.
City of Newport Beach
Planning Commission Resolution No.
Page 17 of 37
WHEREAS, the project includes the demolition of 15 dwelling units within the
Coastal Zone within 2 buildings and pursuant to Chapter 20.86 of the Zoning Code,
units proposed for demolition and occupied by low or moderate income households
must be replaced if such replacement is determined to be feasible. The 15 units are not
occupied by low or moderate income households and, therefore, no replacement units
are required. Households potentially meeting the low or moderate income limits were
not evicted for the purpose of avoiding a replacement requirement within the previous
12 months.
WHEREAS, an Initial Study and Mitigated Negative Declaration (MND) (SCH No.
2008051082) have been prepared pursuant to the Environmental Quality Act (CEQA),
the State CEQA Guidelines, and City Council Policy K -3. Several previous drafts of the
MND were circulated for public comment. Ultimately, the City Council determined that
the predominant line of existing development was 50.7 feet MSL and required the
applicant to revise the project. Based upon the revised project, which also includes
replacement docks, a final draft MND was prepared and circulated for public review
between May 19, 2008, and June 17, 2008.
WHEREAS, on the basis of the entire environmental review record, the proposed
project will have a less than significant impact upon the environment and there are no
known substantial adverse affects on human beings that would be caused. Additionally,
there are no long -term environmental goals that would be compromised by the project,
nor cumulative impacts anticipated in connection with the project. The mitigation
measures identified are feasible and reduce potential environmental impacts to a less
than significant level. The mitigation measures are applied to the project and are
incorporated as conditions of approval.
WHEREAS, the Planning Commission finds that judicial challenges to the City's
CEQA determinations and approvals of land use projects are costly and time
consuming. In addition, project opponents often seek an award of attorneys' fees in
such challenges. As project applicants are the primary beneficiaries of such approvals,
it is appropriate that such applicants should bear the expense of defending against any
such judicial challenge, and bear the responsibility for any costs, attorneys' fees, and
damages which may be awarded to a successful challenger.
NOW, THEREFORE, BE IT RESOLVED:
Section 1. The Planning Commission of the City of Newport Beach does hereby
find, on the basis of the whole record, that there is no substantial evidence that the
project will have a significant effect on the environment and that the Mitigated Negative
Declaration reflects the Planning Commission's independent judgment and analysis.
The Planning Commission hereby recommends that the City Council adopt Mitigated
Negative Declaration SCH No. 2008051082 and the attached Mitigation Monitoring and
Reporting Program. The document and all material which constitute the record upon
Planning Commission
City of Newport Beach
Resolution No.
Page 18 of 37
which this decision was based are on file with the Planning Department, City Hall, 3300
Newport Boulevard, Newport Beach, California.
Section 2. Based on the aforementioned findings, the Planning Commission
hereby recommends that the City Council approve General Plan Amendment No. 2005-
006 per Exhibit "A", Coastal Land Use Plan Amendment No. 2005 -002 per Exhibit "B °,
Code Amendment No. 2005 -009 per Exhibit "C; and approve Newport Tentative Tract
Map No. 2005 -004 (TTM 16882), Modification Permit No. 2005 -087 and Coastal
Residential Development Permit No. 2005 -002 (PA 2005 -196) subject to conditions of
approval attached as Exhibit "D °.
Section 3. Planning Commission Resolution Nos. 1723 and 1751 are hereby
rescinded.
PASSED, APPROVED AND ADOPTED THIS 19th DAY JUNE, 2008.
W
IM
AYES:
NOES:
Robert Hawkins, Chairman
Bradley Hillgren, Secretary
City of Newport Beach
Planning Commission Resolution No.
Page 20 of 37
Exhibit "113"
k !l
City of Newport Beach
Planning Commission Resolution No.
Page 21 of 37
Exhibit "C"
A
City of Newport Beach
Planning Commission Resolution No.
Page 22 of 37
Exhibit "D"
CONDITIONS OF APPROVAL
Newport Tract No. 2005 -004 (Tentative Tract Map No. 16882)
Modification Permit No. 2005 -087
(Project - specific conditions are in italics)
Planning Department
The applicant shall comply with all federal, state, and local laws. Material violation
of any of those laws in connection with the use will be cause for revocation of this
permit. The project is subject to all applicable City ordinances, policies, and
standards, unless specifically waived or modified by the conditions of approval.
2. This approval was based on the particulars of the individual case and does not in
and of itself or in combination with other approvals in the vicinity or Citywide
constitute a precedent for future approvals or decisions.
3. Should the property be sold or otherwise come under different ownership, any
future owners or assignees shall be notified of the conditions of this approval by
either the current business owner, property owner or the leasing agent.
4. The development shall be in substantial conformance with the approved plans
stamped and dated June 19, 2008, except as modified by the conditions of approval.
5. Project approvals except the Tentative Tract Map shall expire unless exercised
within 24 months from the effective date of approval as specified in Section
20.91.050A of the Newport Beach Municipal Code. Reasonable extensions may be
granted by the Planning Director in accordance with applicable regulations. The
Tentative Tract Map shall expire within 36 months from the date of final approval
unless extensions are granted prior to expiration in accordance with the
Subdivision Ordinance and Subdivision Map Act.
6. The applicant shall obtain a Coastal Development Permit from the California
Coastal Commission prior to the issuance of any building, grading or demolition
permit for the project.
The Covenants, Conditions, and Restrictions (CC &Rs) for the proposed
condominium association shall provide for the long term maintenance of the project
and shall be reviewed and approved by the Newport Beach City Attorney prior to
their recordation. The CC &Rs shall include a provision that residents shall park
only operable vehicles within the parking garage that are in active use (i.e. no long
term storage of vehicles).
k�6
City of Newport Beach
Planning Commission Resolution No.
Page 23 of 37
8. Prior to the issuance of a grading or building permit, the applicant shall provide the
City with a performance bond or its equivalent to ensure timely completion of all
improvements represented on plans and drawings submitted for permit approval in
the event construction of improvements consistent with project approval is
abandoned. The performance bond or its equivalent shall be in 100% of the cost of
the building shell and shall be issued with the City as benerrciary by an insurance
company currently authorized by the insurance Commissioner to transact business of
insurance in the State of California and shall have an assigned policyholders' Rating
of A (or higheo and Financial Size Category Class Vil (or larger) in accordance with
the latest edition of Bests Key Rating Guide unless otherwise approved by the City
Risk Manager. The bond or equivalent shall be released in 25% increments upon
completion of each quarter of construction of the building shell.
9. Prior to the issuance of a grading or building permit for new construction, the
applicant shall execute a waiver of all claims against the City for future liability or
damage resulting from the approval to build the project. The form and content of
the waiver shall be in a form acceptable to the office of the City Attorney and the
waiver shall be recorded against the property in question.
10. Prior to the issuance of a building permit, the applicant shall prepare a photometric
study in conjunction with a final lighting plan for approval by the Planning Director.
The site shall not be excessively illuminated as excessive illumination may be
determined consistent with the luminance recommendations of the Illuminating
Engineering Society of North America or by the Planning Director in the event the
illumination creates an unacceptable negative impact on surrounding land uses or
environmental resources.
11. Prior to the issuance of a building permit, a landscape and irrigation plan prepared
by a licensed landscape architect shall be submitted for review and approval by the
Planning Director. The plans shall incorporate native drought tolerant plantings and
water efficient irrigation practices. All planting areas, with the exception of bluff
areas, shall be provided with a permanent underground automatic sprinkler
irrigation system of a design suitable for the type and arrangement of the plant
materials selected. The irrigation system shall be adjustable based upon either a
signal from a satellite or an on -site moisture- sensor. Planting areas adjacent to
vehicular activity shall be protected by a continuous concrete curb or similar
permanent barrier. Landscaping shall be located so as not to impede vehicular
sight distance to the satisfaction of the Traffic Engineer. The proposed landscaping
adjacent to the back of sidewalk shall be designed with provisions that will prevent
irrigation and /or other runoff from spilling onto the sidewalk.
12. Boat slips may be developed, maintained and operated in tidelands adjacent to the
residential condominium development provided all necessary permits are first
obtained. The maximum number of boat slips shall be no greater than the total
number of residential units developed. Use of the boat slips shall be limited to
�t
City of Newport Beach
Planning Commission Resolution No.
Page 24 of 37
residents and their guests and the slips shall not be leased, subleased or allowed to
come into the control of non - residents of the condominium development.
13. Prior to the issuance of a building or grading perm it. a waiver of future shoreline
protection during the economic life of the structure (75 years) shall be recorded
against the property. The waiver shall be binding upon all future owners and
assignees. The waiver shall be reviewed and approved by the City Attomey prior to
recordation.
14. Prior to issuance of the certificate of occupancy or final of building permits, the
applicant shall schedule an evening inspection by the Code Enforcement Division
to confirm control of light and glare. The Planning Director may order the dimming
of light sources or other remediation upon finding that the site is excessively
illuminated.
15. Prior to issuance of a certificate occupancy for the project, the applicant shall
install a public bench within the public right -of -way as depicted on the site plan.
The specific design and location of the bench shall be approved by the Public
Works, Planning and General Services Departments prior to installation.
16. Prior to the issuance of a certificate of occupancy, the applicant shall schedule an
inspection by the Code and Water Quality Enforcement Division to confirm that all
landscaping materials and irrigation systems have been installed in accordance
with the approved plans.
17. All landscape materials and landscaped areas shall be installed and maintained in
accordance with the approved landscape plan. All landscaped areas shall be
maintained in a healthy and growing condition and shall receive regular pruning,
fertilizing, watering, mowing and trimming. All landscaped areas shall be kept free
of weeds and debris. All irrigation systems shall be kept operable, including
adjustments, replacements, repairs, and cleaning as part of regular maintenance.
18. Lighting shall be in compliance with applicable standards of the Zoning Code.
Exterior on -site lighting shall be shielded and confined within site boundaries. No
direct rays or glare are permitted to shine onto public streets or adjacent sites or
create a public nuisance.
19. All mechanical equipment shall be screened from view of adjacent properties and
adjacent public streets within the limits authorized by this permit, and shall be
sound attenuated in accordance with Chapter 10.26 of the Newport Beach
Municipal Code, Community Noise Control.
20. Water leaving the project site due to over - irrigation of landscape shall be
minimized. If an incident such as this is reported, a representative from the Code
and Water Quality Enforcement Division of the City Manager's Office shall visit the
1
City of Newport Beach
Planning Commission Resolution No.
Page 25 of 37
location, investigate, inform resident if possible, leave a note and in some cases
shut -off the water.
21. Watering should be done during the early morning or evening hours to minimize
evaporation (between 4:00 p.m. and 9:00 a.m., the following morning).
22. All irrigation system leaks shall be investigated by a representative from the Code
and Water Quality Enforcement Division of the City Manager's Office and the
applicant or future owners shall complete all required repairs.
23. The applicant shall be responsible for the payment of all administrative costs
identified by the Planning Department within 30 days of receiving a final notification of
costs or prior to the issuance of a Building Permit.
24. All altered slopes that are outside of the building envelope shall be contoured to
resemble the existing natural terrain.
25. To the fullest extent permitted by law, applicant shall indemnify, defend and hold
harmless City, its City Council, its boards and commissions, officials, officers,
employees, and agents from and against any and all claims, demands, obligations,
damages, actions, causes of action, suits, losses, judgments, fines, penalties,
liabilities, costs and expenses (including without limitation, attorney's fees,
disbursements and court costs) of every kind and nature whatsoever which may
arise from or in any manner relate (directly or indirectly) to City's approval of the
AERIE Project including, but not limited to, the approval of General Plan
Amendment No. 2005 -006, Coastal Land Use Plan Amendment No. 2005 -002,
Code Amendment No. 2005 -009, Tentative Tract Map No. 2005 -004 (Tract 16882),
Modification Permit No. 2005 -087 and Coastal Residential Development Permit
No. 2005 -002 collectively referred to as PA 2005 -196; and /or the City's related
California Environmental Quality Act determinations, the adoption of a Mitigated
Negative Declaration and a Mitigation Monitoring Program for the AERIE Project.
This indemnification shall include, but not be limited to, damages awarded against
the City, if any, costs of suit, attorneys' fees, and other expenses incurred in
connection with such claim, action, causes of action, suit or proceeding whether
incurred by applicant, City, and/or the parties initiating or bringing such proceeding.
The applicant shall indemnify the City for all of City's costs, attorneys' fees, and
damages which City incurs in enforcing the indemnification provisions set forth in
this condition. The applicant shall pay to the City upon demand any amount owed
to the City pursuant to the indemnification requirements prescribed in this
condition.
26. The project shall incorporate and implement an emergency power backup system so
the vehicle lifts will operate during a power outage. The location of the generator shall
be sound attenuated and screened from public view and subject to the review and
approval of the Planning Director.
City of Newport Beach
Planning Commission Resolution No.
Page 26 of 37
27. Remote control operators for the vehicle elevators, in quantities equal to the number
of parking spaces assigned to each dwelling unit, shall be provided to occupants of
the respective units. The project shall incorporate an external indicating system to
alert drivers which vehicle elevator will be available for immediate use. The vehicle
elevator system shag be designed and maintained to return the elevator cars to the
street level when not in use. The vehicle elevator system shall be maintained for
efficient use throughout the life of the project.
28. Vehicle parking and maneuvering areas shall be restricted to the operation,
maneuvering and parking of operable vehicles and shag not be used for storage of
any kind including the long -term storage of vehicles not in regular use.
29. Construction activities shall be confined to the hours of 7:00 a.m. and 6:30 p.m. on
weekdays and on Saturdays between the hours of 8:00 a.m. and 6:00 p.m.
30. No idling of construction vehicles or equipment shall be allowed. Construction
vehicles and equipment shall be property operated and maintained and shall be
turned off immediately. Construction workers, equipment operators or truck drivers
shall not employ any form of audible signaling system during any phase of
construction.
31. Reclaimed water shall be used wherever available, assuming it is economically
feasible.
Fire Department
32. One gumey - accommodating elevator shall be provided in accordance with Chapter
30 of the Califomia Building Code within the project that must access each level.
33. A Class 111 standpipe system shall be provided at the private dock in accordance with
Newport Beach Fire Department guidelines.
34. A public fire hydrant shall be provided at the comer of Carnation Avenue and Ocean
Boulevard. The hydrant shall be installed and tested prior to occupancy of the project,
unless required earlier by the Fire Department.
35. A fire alarm system with fire control room shall be provided within the project.
Monitored Automatic fire sprinklers shall be required for the entire structure to meet
NFA13, #MEOW and in accordance with Newport Beach Fire Department
requirements. Shut -off valves and a waterflow device shall be provided for each unit.
A Class 1 standpipe shall be provided at every level at all stairs. Standpipe and
sprinklers may be a combination system.
36. The project shall provide pressurized exit enclosures and vestibules in accordance
with the Building Code. Enclosures shall be a minimum two -hour fire rated
construction.
City of Newport Beach
Planning Commission Resolution No.
Page 27 of 37
37. Approved numbers or addresses shall be placed on all new and existing buildings
in such a position that is plainly visible and legible from the street or road fronting
the property. Said numbers shall be of made of non - combustible materials, shall
contrast with their background, and shall be either internally or externally
illuminated to be visible at night. Number shall be no less than six inches in height
with a one -inch stroke.
Public Works
38. All parking stall dimensions shall comply with City's Standard Drawings STD -805-
L-A.
39. Driveway /drive aisle slopes shall comply with City Standard STD - 160 -L -C, which
accommodate a 15 percent maximum slope and a maximum change in grade of 11
percent. The building plans shall show detailed profile of each of the proposed
driveways.
40. Project driveways must conform to the City's sight distance standard 110 -L. The
design shall be reviewed and approved by the City Traffic Engineer.
41. All work conducted within the public right -of -way shall be approved under an
encroachment permit issued by the Public Works Department.
42. Construction surety in a form acceptable to the City, guaranteeing the completion
of the various required public improvements and repairs, shall be submitted to the
Public Works Department for City Council approval prior to the issuance of Public
Works Department encroachment permit.
43. All improvements shall be constructed as required by Ordinance and the Public
Works Department.
44. A water demand, a storm drain system capacity, and a sanitary sewer system
capacity study shall be submitted to the Public Works Department along with the
first building plan check submittal. The recommendations of these studies shall be
incorporated as a part of the submitted plans.
45. Street, drainage and utility improvements within the public right -of -way shall be
submitted on City standard improvement plan formats. All of the plan sheets shall
be wet sealed, dated, and signed by the California registered professionals
responsible for the designs shown on said plans.
46. All new landscaping within the public right -of -way shall be approved by the General
Services Department and the Public Works Department.
47. The applicant shall submit detailed plans for the on -site drainage system(s) to
demonstrate that it will prevent the underground garage from being flooded during
storm events.
35
City of Newport Beach
Planning Commission Resolution No.
Page 28 of 37
48. The Developer shall file one (1) Final Tract Map (Map).
49. The roadway cross section shown on the Map with a 110 -foot light-of-way width
should be labeled as "Ocean Boulevard ".
50. The Map shall be prepared on the California coordinate system (NAD88). Prior to
Map recordation, the surveyor /engineer preparing the Map shall submit to the
County Surveyor and the City of Newport Beach a digital- graphic file of said map in
a manner described in the Orange County Subdivision Code and Orange County
Subdivision Manual. The Map to be submitted to the City of Newport Beach shall
comply with the City's CADD Standards. Scanned images will not be accepted.
51. Prior to recordation, the Map boundary shall be tied onto the Horizontal Control
System established by the County Surveyor in a manner described in Sections 7-
9 -330 and 7 -9 -337 of the Orange County Subdivision Code and Orange County
Subdivision Manual, Subarticle 18. Monuments (one inch iron pipe with tag) shall
be set On Each Lot Corner unless otherwise approved by the City Engineer.
Monuments shall be protected in place if installed prior to completion of
construction project.
52. The applicant's request to vacate the existing sewer /utilities easement shall be
approved by the City Utilities Department prior to the issuance of a building permit
or the recordation of the final tract map. The existing private ingress/egress
easement with the same width, length, and alignment as the existing sewer /utilities
easement shall be vacated or permission from the beneficiaries of the private
easement shag be documented prior to the issuance of a building permit or the
recordation of the final tract map.
53. A 5 -foot wide public sewer and utilities easement as measured from the centerline
of the existing sewer main fronting the development site shall be recorded against
the property. The applicant shall prepare and submit the legal description for said
easement for City review and approval.
54. All easements of record shall be recorded as a part of the Final Map.
55. All improvements shall be designed and constructed in accordance with the current
edition of the City Design Criteria, Standard Special Provisions, and Standard
Drawings.
56. The sidewalk portion of the proposed new driveway approach shall be constructed
with 2% cross -fall per City Standards.
57. Temporary construction sheet piles shall be installed to protect all existing storm
drain and sanitary sewer mains within and adjacent to the development site.
��o
City of Newport Beach
Planning Commission Resolution No.
Page 29 of 37
58. No structures or construction tie -backs shall be constructed within the limits of any
easements or public right -of -way without the approval of an Encroachment
Agreement and Permit.
59. Full -width concrete sidewalk and curb and gutter shall be constructed along the
length of the Carnation Avenue and Ocean Boulevard frontages. The new sidewalk
shall join the existing sidewalk in front of 2501 Ocean Boulevard.
60. New concrete curbs shall be dowelled into sound concrete roadway pavement.
61. Trees shall not be installed at locations where mature tree roots could damage the
existing City sewer main.
62. The plans suggested there will be a 16 -foot drop from the top of proposed
perimeter /retaining walls along the Carnation Avenue property line to the garden
below. The proposed top of wall is shown on the Plans as 15" above the sidewalk
finish surface. Adequate safety provisions for pedestrians and W/B Ocean
Boulevard vehicle traffic shall be shown on building plans along the length of said
walls and shall be implemented throughout the life of the project.
63. Each dwelling unit shall be served by its individual water service and sewer lateral
connection and cleanout.
64. All utility connections shall be placed underground in accordance with the
Subdivision Code.
65. The on -site parking, vehicular circulation and pedestrian circulation systems shall
be subject to further review and approval by the Traffic Engineer and any
corrections/modifications shall be made to the satisfaction of the Traffic Engineer.
66. All non - standard improvements within the public right -of -way would require an
Encroachment Agreement and Encroachment Permit.
67. Curb cuts within the public right -of -way leading to the pedestrian walkways shall
not be permitted. Standard curb, gutter and sidewalk shall be installed.
68. Gates shall not be designed to open out into the public right -of -way.
69. Raised planters shall not be permitted within the Public right -of -way. Planting
adjacent to the curb shall accommodate a vehicle car door opening. Project
landscape plans shall provide details of the planters and shall be reviewed and
approved by the Public Works Department prior to the issuance of a building
permit.
70. The driveway approaches within the public right -of -way shall be shall be narrowed
to the width of garage openings they serve. Six -inch curbs shall have a 3 foot flare.
Drive approaches shall be modified to comply with ADA requirements.
-31
City of Newport Beach
Planning Commission Resolution No.
Page 30 of 37
71. Planters adjacent to the freight elevators shall be pulled back from the Carnation
Avenue property line two feet to improve vehicle maneuvering. Planters in the front
yard shall not encroach into the projection of the garage door edge.
72. No structural support column shall be located in the middle of the driveway leading
to the parking area located on the Second Level.
73. The loading area adjacent to the ADA accessible stall shall be 8 -foot wide.
74. Prior to the issuance of a building permit, the applicant shall prepare a study of the
existing drainage area and catch basin in Carnation Avenue to determine the
appropriate size of catch basin. The developer shall enlarge the existing catch
basin accordingly.
75. Prior to the issuance of the building permit, Public Works Department plan check
and inspection fee shall be paid.
76. Prior to the issuance of a grading or building permit, the applicant shall prepare a
construction phasing plan and construction delivery plan that includes routing of
large vehicles. The plan shall include a haul route plan for review and approval of
the Public Works Department. Said plan shall specify the routes to be traveled,
times of travel, total number of trucks, number of trucks per hour, time of operation,
and safety /congestion precautions (e.g., signage, flagmen). Large construction
vehicles shall not be permitted to travel narrow streets and alleys as determined by
the Public Works Department. Traffic control and transportation of equipment and
materials shall be conducted in accordance with state and local requirements. The
plans shall include a provision that maintains the public right -of -way open to
vehicular and pedestrian traffic after working hours daily.
77. Where vehicles leave the construction site and enter adjacent public streets, any
visible track -out extending for more than fifty (50) feet from the access point shall
be swept within thirty (30) minutes of deposition.
78. Prior to commencement of demolition and aradina, the applicant shall submit to the
City calculations showing the proposed travel route for haul trucks, the distance
traveled, and how many daily truck trips that can be accommodated to ensure that
the daily cumulative miles traveled is below the assumed total vehicle miles
traveled in the quantitative air quality assessment of the Mitigated negative
declaration.
Building Department
79. The applicant is required to obtain all applicable permits from the City of Newport
Beach. The construction plans must comply with the most recent, City- adopted
version of the California Building Code. The facility shall be designed to meet fire
City of Newport Beach
Planning Commission Resolution No.
Page 31 of 37
protection requirements and shall be subject to review and approval by the
Newport Beach Building and Fire Departments.
80. The proposed project shall conform to the requirements of the Uniform Building
Code, any local amendments to the UBC, and State Disabled Access
requirements, unless otherwise approved by the Building Department.
81. County Sanitation District fees shall be paid prior to issuance of any building
permits.
82. Prior to the issuance of the grading permit, a Stormwater Pollution Prevention Plan
( SWPPP) shall be prepared and approved by the City of Newport Beach as the
local permitting agency in accordance with the requirements of the Regional Water
Quality Control Board (RWQCB). The SWPPP shall include BMPs to eliminate
and/or minimize stormwater pollution prior to, and during construction. The
SWPPP shall require construction to occur in stages and stabilized prior to
disturbing other areas and require the use of temporary diversion dikes and basins to
trap sediment from run -off and allow clarification prior to discharge.
83. Prior to the issuance of the grading permit, the applicant shall prepare a Water
Quality Management Plan (WQMP) specifically identifying the Best Management
Practices (BMP's) that will be used on site to control predictable pollutant runoff.
The plan shall identify the types of structural and non - structural measures to be
used. The plan shall comply with the Orange County Drainage Area Management
Plan (DAMP). Particular attention should be addressed to the appendix section
"Best Management Practices for New Development." The WQMP shall clearly
show the locations of structural BMP's, and assignment of long term maintenance
responsibilities (which shall also be included in the Maintenance Agreement). The
plan shall be prepared to the format of the DAMP title "Water Quality Management
Plan Outline" and be subject to the approval of the City.
84. Prior to the issuance of the grading or building permit, the applicant shall obtain a
NPDES permit. The applicant shall incorporate storm water pollutant control into
erosion control plans using BMPs to the maximum extent possible. Evidence that
proper clearances have been obtained through the State Water Resources Control
Board shall be given to the Building Department prior to issuance of grading
permits.
85. Prior to the issuance of the grading permit, the applicant shall submit evidence to
the City Building Official that the applicant has obtained coverage under the
NPDES statewide General Construction Activity Stormwater Permit from the State
Water Resources Control Board.
86. Prior to the issuance of a grading or building permit, the applicant shall submit an
Erosion and Sediment Control Plan (ESCP) in a manner meeting approval of the
City Building Official, to demonstrate compliance with local and state water quality
�A
City of Newport Beach
Planning Commission Resolution No.
Page 32 of 37
regulations for grading and construction activities. The ESCP shall identify how all
construction materials, wastes, grading or demolition debris, and stockpiles of soil,
aggregates, soil amendments, etc. shall be properly covered, stored, and secured
to prevent transport into local drainages or coastal waters by wind, rain, tracking,
tidal erosion, or dispersion. The ESCP shall also describe how the applicant will
ensure that all Best Management Practices (BMPs) will be maintained during
construction of any future public right -of -ways. A copy of the current ESCP shall
be kept at the project site and be available for City of Newport Beach review on
request. The ESCP shall include and require the use of soil stabilization measures
for all disturbed areas.
87. Prior to issuance of the grading permit, the project applicant shall document to the
City of Newport Beach Building Department that all facilities will be designed and
constructed to comply with current seismic safety standards and the current City -
adopted version of the Uniform Building Code.
88. Prior to issuance of the grading permit, a geotechnical report shall be submitted
with construction drawings for plan check. The Building Department shall ensure
that the project complies with the geotechnical recommendations included in the
preliminary geologic investigation as well as additional requirements, if any,
imposed by the Newport Beach Building Department.
89. Prior to issuance of the building permit, school impacts fees will be paid to the
Building Department to assist in funding school facility expansion and educational
services to area residents.
Mitigation Measures from the Mitigated Negative Declaration
90. Mitigation Measure III -1: During grading activities, any exposed soil areas shall be
watered at least four times per day. Stockpiles of crushed cement, debris, dirt or
other dusty materials shall be covered or watered twice daily. On windy days or
when fugitive dust can be observed leaving the proposed project site, additional
applications of water shall be applied to maintain a minimum 12 percent moisture
content as defined by SCAQMD Rule 403. Soil disturbance shall be terminated
whenever windy conditions exceed 25 miles per hour.
91. Mitigation Measure III -2: Truck loads carrying soil and debris material shall be
wetted or covered prior to leaving the site. Where vehicles leave the construction
site and enter adjacent public streets, the streets shall be swept daily.
92. Mitigation Measure III -3: All diesel- powered machinery exceeding 100 horsepower
shall be equipped with soot traps, unless the Contractor demonstrates to the
satisfaction of the City Building Official that it is infeasible.
93. Mitigation Measure III-4: The construction contractor shall time the construction
activities, including the transportation of construction equipment vehicles and
q0
City of Newport Beach
Planning Commission Resolution No.
Page 33 of 37
equipment to the site, and delivery of materials, so as not to interfere with peak
hour traffic. To minimize obstruction of through traffic lanes adjacent to the site, a
flag person shall be retained to maintain safety adjacent to existing roadways, if
deemed necessary by the City.
94. Mitigation Measure III -5: The construction contractor shall encourage ridesharing
and transit incentives for the construction workers.
95. Mitigation Measure III -6: To the extent feasible, pre- coated /natural colored building
materials shall be used. Water -based or low VOC coatings shall be used that
comply with SCAQMD Rule 1113 limits. Spray equipment with high transfer
efficiency, or manual coatings application such as paint brush, hand roller, trowel,
etc. shall be used to reduce VOC emissions, where practical. Paint application
shall use lower volatility paint not exceeding 100 grams of ROG per liter.
96. Mitigation Measure IVA: An updated pre- construction eelgrass and invasive algae
survey shall be completed within 30 days of the initiation of the proposed
dock/gangway construction. The results of this survey will be used to update the
results of the March 2007 eelgrass survey and to identify, if any, potential project -
related eelgrass losses and the presence or absence of the invasive algae
(Caulerpa taxifolia) in accordance with NMFS requirements.
97. Mitigation Measure IV -2: A post - construction project eelgrass survey shall be
completed within 30 days of the completion of project construction in accordance
with the Southern California Eelgrass Mitigation Policy (NMFS 1991 as amended,
Revision 11). The report will be presented to the resources agencies and the
Executive Director of the California Coastal Commission within 30 days after
completion of the survey. If any eelgrass has been impacted in excess of that
determined in the pre- construction survey, any additional impacted eelgrass will be
mitigated at a ratio of 1.2:1 (mitigation to impact).
98. Mitigation Measure IV -3: Eelgrass shall be mitigated based on two annual
monitoring surveys that document the changes in bed (i.e., area extent and
density) in the vicinity of the footprint of the boat dock, moored vessel(s), and /or
related structures during the active- growth period for eelgrass (typically March
through October). Mitigation shall be implemented pursuant to the requirements of
the Southern California Eelgrass Mitigation Policy (NMFS 1991 as amended,
Revision 11). A statement from the applicant indicating their understanding of the
potential mitigation obligation that may follow the initial two year monitoring is
required. If losses are identified, a final eelgrass mitigation plan shall be submitted
to the City of Newport Beach and resources agencies for review and acceptance.
99. Mitigation Measure IV-4: The project marine biologist shall mark the positions of
eelgrass beds in the vicinity of the dock and gangway construction area with buoys
prior to the initiation of any construction activities.
Planning Commission
City of Newport Beach
Resolution No.
Page 34 of 37
100. Mitigation Measure IV -5: The project marine biologist shall meet with the
construction crew prior to initiation of construction to orient them to specific areas
where eelgrass occurs.
101. Mitigation Measure IV -6: Support vessels and barges shall maneuver and work
over eelgrass beds only during tides of +2 feet mean lower low water (MLLW) or
higher to prevent grounding within eelgrass beds, damage to eelgrass from
propellers, and to limit water turbidity.
102. Mitigation Measure IV -7: Anchors and anchor chains shall not impinge upon
eelgrass habitat.
103. Mitigation Measure IV -8: Construction activities associated with the elevated
walkway leading to the gangway, and construction personnel shall avoid impacts to
rocky intertidal habitat and to eelgrass beds and sand dollar habitat within the
Carnation Cove.
104. Mitigation Measure IV -9: Residents shall be informed of the sensitivity of the cove
as a unique marine biological habitat to assist in ensuring the long -term protection
of the cove's marine biological resources.
105. Mitigation Measure IV -10: If vegetation clearing is to take place between March 15
and July 31, a pre - construction nesting survey for migratory birds will be conducted
as required by the California Department of Fish and Game and U.S. Fish and
Wildlife Service. Pre - construction surveys are to be conducted no more than 30
days prior to ground disturbance. Some restrictions on construction activities may
be required in the vicinity of the nests until the site is no longer active, as
determined by a qualified biologist.
106. Mitigation Measure V -1: A qualified paleontologist shall be retained by the project
applicant to develop a Paleontological Resource Impact Mitigation Program
(PRIMP) consistent with the guidance of the Society of Vertebrate Paleontology
(SVP). In the event that fossils are encountered during construction activities,
ground- disturbing excavations in the vicinity of the discovery shall be redirected or
halted by the monitor until the find has been salvaged. Any fossils discovered
during project construction shall be prepared to a point of identification and
stabilized for long -term storage. Any discovery, along with supporting
documentation and an itemized catalogue, shall be accessioned into the
collections of a suitable repository. Curation costs to accession any collections
shall be the responsibility of the project applicant.
107. Mitigation Measure VI -1: During periods when boats would be exposed to
excessive wave - induced motions, boats should be sheltered at locations inside
Newport Harbor to avoid damage.
City of Newport Beach
Planning Commission Resolution No.
Page 35 of 37
108. Mitigation Measure VI -2: The dock design shall be based on the extreme wave
conditions identified in the coastal engineering study (Noble Consultants, Inc.,
2008). One percent height of impinging random waves shall be used, which
translates to a minimum design wave height of about 1.7 times the significant wave
height (i.e., four to 4.5 feet).
109. Mitigation Measure VII -1: Any repairs, renovations, removal or demolition activities
that will impact the Asbestos Containing Materials (ACM) or inaccessible ACM
shall be performed by a licensed asbestos contractor. Inaccessible suspect ACM
shall be tested prior to demolition or renovation. Air emissions of asbestos fibers
and leaded dust would be reduced to below a level of significance through
compliance with existing federal, state, and local regulatory requirements. Proper
safety procedures for the handling of suspect ACM shall always be followed in
order to protect the occupants of the building and the asbestos workers.
110. Mitigation Measure VII -2: The property owner shall maintain all Lead Based Paint
(LBP) in good condition at all times. Any LBP in poor condition must be stabilized
by removal of all loose and flaking paint chips under controlled conditions and
application of a primer /encapsulant (seal -coat) over the remaining intact paint.
111. Mitigation Measure VII -3: A contractor performing paint removal work shall follow
the OSHA lead standard for the construction industry. The lead content of the
paint should be considered when choosing a method to remove the pain, as proper
waste disposal requirements and worker protection measure shall be taken.
112. Mitigation Measure VIII -1: The developer shall be responsible for
replacement/upsizing of the 10 -foot wide catch basin located in Carnation Avenue
storm drain, which is currently deficient. The new catch basin will be sized to
provide sufficient capacity for the runoff generated by this project, as well as
existing runoff from the rest of the tributary area to this facility. It shall satisfy the
appropriate storm -year design criteria established by the City Engineer. This storm
drain reconstruction shall include appropriate urban runoff filtration elements, to
reduce potential water pollution impacts into Newport Harbor. Reconstruction of
this storm drain shall occur outside of the rainy season.
113. Mitigation Measure VIII -2: All debris and trash shall be disposed in suitable trash
containers on land or on the work barge at the end of each construction day.
114. Mitigation Measure VIII -3: Discharge of any hazardous materials into Newport Bay
is prohibited.
115. Mitigation Measure VIII -4: Silt curtains shall be deployed around work barges and
around the pile sleeving or drilling operations where feasible to minimize the
spread of turbid waters into adjacent eelgrass beds within and outside the project
area.
Li)
City of Newport Beach
Planning Commission Resolution No.
Page 36 of 37
116. Mitigation Measure IX -1: The property owner(s) shall execute and record a waiver
of future shoreline protection for the project prior to the issuance of a building
permit. Said waiver shall be subject to the review and approval of the City Attorney.
117. Mitigation Measure IX -2: The applicant shall dedicate a view easement as depicted
on the exhibit below; however, it will only affect the project site. Structures and
landscaping within the easement area shall not be permitted to block public views.
The easement shall be recorded prior to the issuance of a building permit for new
construction and shall be reflected on the final tract map.
MUUNEOFMSTINGWLS - -- _
PREVKM% PROPOSED DEVELOPNFNf
F#(
PREVIOUS PROPOSED DEOK
PROPOSEDNNR31)1 K
PROPOSEDUNRS
I
I
�
I
P1Q
I I
,
m�-am
i
Y
I
--- - -- --
-7_71
DS,NI PLtR
i-
/
CARNATION AVE.
s
/
/
rouiruxwRRreucueL
//
IvEwuorDOyNr
_____
118. Mitigation Measure IX -3: Accessory structures shall be relocated or removed if
threatened by coastal erosion. Accessory structures shall not be expanded and
routine maintenance of accessory structures is permitted.
119. Mitigation Measure IX-4: Bluff landscaping shall consist of native, drought tolerant
plant species determined to be consistent with the California coastal buff
environment. Invasive and non - native species shall be removed. Irrigation of bluff
faces to establish re- vegetated areas shall be temporary and used only to establish
the plants. Upon establishment of the plantings, the temporary irrigation system
shall be removed.
120. Mitigation Measure XI -1: All construction equipment, stationary and mobile, shall
be equipped with properly operating and maintained muffling devices.
0
City of Newport Beach
Planning Commission Resolution No.
Page 37 of 37
121. Mitigation Measure XI -2: A construction schedule shall be developed that
minimizes potential cumulative construction noise levels.
122. Mitigation Measure XI -3: The construction contractor shall notify the residents of
the construction schedule for the proposed project, including construction of the
dock, and shall keep them informed on any changes to the schedule. The
notification shall also identify the name and phone number of a contact person in
case of complaints. The contact person shall take all reasonable steps to resolve
the complaint.
123. Mitigation Measure XV -1: Prior to commencement of each major phase of
construction, the Contractor shall submit a construction staging, parking and traffic
control plan for approval by the Public Works Department, which shall address
issues pertaining to potential traffic conflicts during peak traffic periods, potential
displacement of on- street parking, and safety.
• This plan shall identify the proposed construction staging area(s), construction
crew parking area(s), estimated number and types of vehicles that will occur
during that phase, the proposed arrival /departure routes and operational
safeguards (e.g. flagmen, barricades, shuttle services, etc.) and hourly
restrictions, if necessary, to avoid traffic conflicts during peak traffic periods,
displacement of on- street parking and to ensure safety.
• The construction staging, parking and traffic control plan shall provide for an off -
site parking lot for construction crews which will be shuttled to and from the
project site at the beginning and end of each day until such time that the project
site can accommodate off - street construction vehicle parking. Until that time,
construction crews shall be prohibited from parking in the adjacent residential
neighborhood.
• The plan shall identify all construction traffic routes, which shall avoid narrow
residential streets unless there is no alternative, and the plan shall not include
any streets where some form of construction is underway within or adjacent to
the street that would impact the efficacy of the proposed route.
Dirt hauling shall not be scheduled during weekday peak hour traffic periods or
during the summer season (Memorial Day holiday weekend through and
including the Labor Day holiday weekend).
The approved construction staging, parking traffic control plan shall be
implemented throughout each major construction phase.
�5