Agenda Item No. SS2
May 14, 2013
.o \
•
L, 1:0 t;
REVISED CONCEPTUAL LANDSCAPE PLAN
Project Background
Neighborhood Revitalization Committee
One of five CAP's formed by Council action
Corona del Mar Entry Improvements
\IFOa%
Gateway /Beautification /Pedestrian Enhancement
Traffic Study Conducted Summer /Fall 2012
Council Reviewed Project on January 8, 2013
CONCEMAL LANDSCAPE PLAN
CITY OF NEWPORT BEACH
CORONA DEL MAR ENTRY
SE
.vim. �i. ...... -...
Y'
I1
l
Concept Presented Prior to Traffic Study
View from MacArthur Blvd Looking South
�Fw
a
.�S
1 � e
View from MacArthur Blvd Looking South
(With Proposed Landscape)
i
Meetings with Corona del Mar
BID and Residents Association
New conceptual plans with Carnation Avenue
Two -Way traffic
Support plans for additional landscaping and
increased sidewalk width
Concerned with loss of 8 parking spaces on Coast Hwy
Alternative with Carnation Avenue One -Way
southbound traffic
Replaces 6 parking spaces. Some concerns with
Carnation Avenue plan impacting truck deliveries
i
i
i
CONCEPT3
TWO WAY CARNATION
CORONA DEL MAR ENTRY
CONCEPTUAL LANDSCAPE ALTERNATIVES
^1 CONC + yasb \\O�C-C -
_ — — ASPH
S
i(
�o
11) � I • 0'0 I
r ce.c
VICINITY MAP Ip�'
ONE WAY CARNATION - CONCEPT 3
CORONA DEL MAR ENTRY
CONCEPTUAL LANDSCAPE ALTERNATIVES
1 '
TCIA6x.
C / O / a
O
O � /
�
f a �
A
1
4 fly/
.rNr
Changing Carnation Ave to One -Way
Between Coast Highway and 4th Ave
(Southbound Only)
New concepts include changing Carnation Avenue to One -
Way southbound between Coast Highway and 4th Ave.
Reasons for "One -Way" alternative:
Low volume of northbound traffic
Eliminates sight distance requirement for northbound traffic
c Creates possibility for 6 additional parking spaces on Carnation
Avenue
Provides increased landscaping and intersection treatment at
Carnation Ave and Coast Highway
Reduces distance for pedestrians to cross Carnation Avenue
Alternatives for Replacement of 8 lost
Parking Spaces on Coast Highway
Change Carnation Avenue to One -Way traffic
(addition of up to 5 parking spaces)
Consider modification of Old School Park to
create additional parking (up to 10 spaces)
Include replacement of 8 lost parking spaces
in upcoming Corona del Mar parking study
(prepared in partnership with CdM BID)
Preliminary Cost Estimate
Complete Design
Construction
(One Way Option)
Construction
(Two Way Option)
$50,000
$350,000
$250,000
ON
Additional Annual
Maintenance $20,000
r
wocoHCt o
CORD RY
Pi NA Dp CPPF kRTSArurvss
1
I \
6
I • t� I
Recommendations
Direct Staff to:
— Proceed with Concept 3
— Proceed with alternative for changing Carnation
Ave to One -Way southbound between Coast Hwy
and Wh Ave
Work with BID representatives regarding
replacement of lost parking spaces on Carnation
Avenue and arrangements for truck deliveries
Include replacement of any lost parking spaces in
CdM pending Parking Study
Recommendations
Provide Direction to staff regarding:
— Funding for design of Corona Del Mar Entry
Improvements in FY 2013 -14 CIP Budget (estimate
cost $50,000)
Funding for construction of Corona Del Mar Entry
Improvements in future CIP Budget (estimated
cost $350,000)