Agenda Item No. 9
June 11, 2013
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
David A. Webb, Public Works Director
949 - 644 -3311, dawebb @newportbeachca.gov
PREPARED BY: Alfred Castanon, Associate Civil Engineer
949 - 644 -3314, acastanon @newportbeachca.gov
APPROVED:
TITLE: 2012 -2013 Sidewalk, Curb & Gutter Replacement Project - Notice
of Completion and Acceptance of Contract No. 5204
ABSTRACT:
On November 13, 2012, City Council awarded Contract No. 5204, 2012 -2013 Sidewalk,
Curb & Gutter Replacement Project to Grigolla & Sons Construction Company, for a total
contract cost of $491,400 plus $49,000.00 allowance for contingencies. The required work
is now complete and staff requests City Council acceptance and close out of the contract.
RECOMMENDATIONS:
1. Accept the completed work and authorize the City Clerk to file a Notice of Completion for
the project.
2. Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of the
Civil Code.
3. Release the Faithful Performance Bond one year after acceptance by the City Council.
FUNDING REQUIREMENTS:
Funds for the construction contract were expended from the following accounts
Account Description
Account Number
Amount
General Fund
7013- C2001009
$141,444.35
CDBG
7161- C2001009
$75,880.00
Measure M Turnback
7281- C2001009
$206,600.00
City Hall Reuse
7011- CIO02040
$21,355.00
Total:
$510,664.60
I of 5
2012 -2013 Sidewalk, Curb & Gutter Replacement Project - Notice of Completion and
Acceptance of Contract No. 5204
June 11, 2013
Page 2
DISCUSSION:
Overall Contract Cost/Time Summary
The work necessary to complete this contract included replacement of existing sidewalk,
curb and gutter, curb access ramps, driveways, and pruning tree roots in the Balboa
Peninsula, West Newport, Newport Shores and Lido Isle communities. The contract was
completed to the satisfaction of the Public Works Department. A summary of the contract
cost is as follows:
Original bid amount:
Actual cost of bid items constructed
Total change orders:
Final contract cost:
$491,400.00
$448,310.60
$62,354.00
$510,664.60
The actual cost of bid items constructed was $43,089.40 less than the original bid amount
due to less concrete replacement required than originally estimated. The final contract cost
was approximately 3.9 percent above the original bid amount with two change orders
totaling $62,354.00. The change orders included additional concrete replacement at China
Cove and Balboa Pier; along with decommissioning work at the old City Hall site involving
installation of fencing, removal of stairway & access ladders, permanently securing windows
and doors as well as modification to parking lot striping and signage.
A summary of the project schedule is as follows:
Estimated Completion Date per 2012 Baseline Schedule March 29, 2013
Project Awarded for Construction November 11, 2012
Contract Completion Date with Approved Extensions May 31, 2013
Actual Substantial Construction Completion Date April 26, 2013
2 of
Actual
% Due to
% Due. to
Final Cost at
Contingency
Contract
Directed
Unforeseen
7LContract
Completion
Allowance
Change
Change
Change
$510,664.60
10% or less
+3,9%
100%
0%
Allowed Contract Time (days)
85
Actual Time
Under ( -) or Over ( +)
-24
The work necessary to complete this contract included replacement of existing sidewalk,
curb and gutter, curb access ramps, driveways, and pruning tree roots in the Balboa
Peninsula, West Newport, Newport Shores and Lido Isle communities. The contract was
completed to the satisfaction of the Public Works Department. A summary of the contract
cost is as follows:
Original bid amount:
Actual cost of bid items constructed
Total change orders:
Final contract cost:
$491,400.00
$448,310.60
$62,354.00
$510,664.60
The actual cost of bid items constructed was $43,089.40 less than the original bid amount
due to less concrete replacement required than originally estimated. The final contract cost
was approximately 3.9 percent above the original bid amount with two change orders
totaling $62,354.00. The change orders included additional concrete replacement at China
Cove and Balboa Pier; along with decommissioning work at the old City Hall site involving
installation of fencing, removal of stairway & access ladders, permanently securing windows
and doors as well as modification to parking lot striping and signage.
A summary of the project schedule is as follows:
Estimated Completion Date per 2012 Baseline Schedule March 29, 2013
Project Awarded for Construction November 11, 2012
Contract Completion Date with Approved Extensions May 31, 2013
Actual Substantial Construction Completion Date April 26, 2013
2 of
2012 -2013 Sidewalk, Curb & Gutter Replacement Project - Notice of Completion and
Acceptance of Contract No. 5204
June 11, 2013
Page 3
ENVIRONMENTAL REVIEW:
City Council found this project exempt from the California Environmental Quality Act
( "CEQX) pursuant to Section 15301(c). This exemption covers the minor alteration of
existing public facilities with negligible expansion of the facilities in areas that are not
environmentally sensitive.
NOTICING:
This agenda item has been noticed according to the Brown Act (72 hours in advance of the
meeting at which the City Council considers the item). In addition, the City Clerk will be filing
a Notice of Completion for the project as a result of this action.
The Notice Inviting Bids was advertised in the City's official publication and in construction
industry publications.
Submitted by:
David A. Webb
Public Works Director
Attachment: A. Project Location Maps
3 of
L
c , G \R 161H
a
I —.
� L� � PRODUC ➢ON PLACE
SFgSHORS oQ vys SG.J( /�O
STREET i
J/� l GP 1E) ISTH STREET 1'IEST
Z, 0 °Q,v Pyti > ^Hi °Hr !/�) 51REE15 PR1VA pp
9�A1 OE,�URV�LE Vf, GOOSE
COURT MEDICAL
2 s.S P2 y
9
SUMMERWND °\° HA(YARD � 0, PVT)
Nf
R
2T'
" O° ODYSSEY
002 1 PV) P ftUNOP yy,, � �4'9 �cTf'fF [ 9 A
v (T
coil o o 0 p Q
1 yN
CO�COq> 50� +� RG�F'`P�`F'n`V GPO v°id u�
O4. QUO Oy h� \ SE- COAST ei`a- Rr 444" T °r�FSC hJa (PV
Qoy °N2 yi. y'` \ "S`ipR �03e HrOlilVq OpL(( Sl,,, Cllr QS�
yew`¢ (al'TjT(AVj� $. O'�, 3 Nr
F
4,0 i�.'yc'J
q�E a S r -S �R 24, �sa �4e Cp
y° y° y� \ \r•F co",
NIVER A HIC""y iHOAG
BALBOA IN
h
C""
CHgNNE(o
J as y1 ° 99 9
O
0 y
O
z
I&
3y� Zt
'Sa��O ZS S ✓��
Z
y'V20 yS �'Y�
S
Z
10
.�f
NEWPORT SHORES, BALBOA PENINSULA, & WEST NEWPORT
FY 2012 -2013 SIDEWALK, CURB CITY OF NEWPORT BEACH
& GUTTER REPLACEMENT PROJECT I PUBLIC WORKS DEPARTMENT
LOCATDON MAP
C -5204 I SHEET 1
4 of
°N6 tlonc r° - 00
'I'S,J Q9
ON
\Y P J�
SANSA CLIFF DR _S" 1J`'�J .2P 0l P2 /S�' r/PFEJ
AVON ST e Q h,
PVT o
NESTR
(PVT) 0 5W w IV
(PVT) COAST 2�.AV4V o,.e liy� BF,yO� J Q� 0 011E ( C °P eFJ S'l. JAMES ROpD Q2
V O
ST C= CLEF VS Pq(
�fI PLACE o �°- e h /CH /V,�l" �FF.J�Sr4, p(A0f �n o° i K oe Qv 53.4, III i,
��
YJ b° c s I� o o ?c,'O oc KINGS DRIVE
AVE z VIA MALAGA F ( /D ^O N c Q o ° °op °S g°� COggT ROAD I
V 9J 32ND ° ST hA /I00\ �D sti?oe $ ?� c� ""HIV HVIY
\ yeReo oe'o 4N e4, AY \VEST COAST
m_3�� ST W / �SeES �\ \�Seyeo `Qoe�eS�ci yPCRE5TV1E1'/ �R (PVT)
30TH ST a 00 .fP P ��SeSP e °OP�PQ; C g ue 24' 9?o VISTA VIPVERLY
2
Yov
OR
28TH ST 0 1, \ (/0 g�q T ° 4pSSJti 7%Z �P
0r
ST O vP IgADq , \ \SyeQ pJ =oe 24n, c�"4�2
o`T'P
0 S1SS2 0y �� ti9 OVJ F 0g0P.c ¢e bA LIDO
161 SZt;�o2 �`a .�090 A FPO J( 95 oCSOSJ Se OUD ^�"`^ \\ - \ \Sc
ryA1 ry,�, °SOS Yq�' S�,042U
tid T" I (f W R /Ch
1 e Bq( I G(f
y%
2' Op F I 1 1 BAY
° B 1
?J 10 D BlVO I AVENUE,
h II'EST / I /I HEST
e- BACBO ll l U yS
h �' y BLVD ll / °
y FRONT '--5Z
^ ry y {ffST i NEST — f
y
PALO
Dq
y
O e
N y
O
H
0
O
Z
WEST NEWPORT, BALBOA PENINSULA & LIDO ISLE
FY 2012 -2013 SIDEWALK, CURB CITY OF NEWPORT BEACH
& GUTTER REPLACEMENT PROJECT PUBLIC WORKS DEPARTMENT
LOCATION MAP C -5204 SHEET 2
5 of