HomeMy WebLinkAbout07 - Anchor QEA Amend 1Agenda Item No. 7
July 9, 2013
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
David A. Webb, Public Works Director
949 - 644 - 3311, dawebb @newportbeachca.gov
PREPARED BY: Chris Miller, Harbor Resources Manager
949 - 644 - 3043, cmiller @newportbeachca.gov
APPROVED:
TITLE: Amendment No. 1 with Anchor QEA, L.P., for Consultant Services
to Provide Necessary Water Quality and Field Management
Services for the Lower Bay Dredging Project
ABSTRACT:
As Anchor QEA, L.P. ( "Anchor QEA") was already under contract to provide the
necessary water quality monitoring and sediment sampling for Phase I of the Lower
Harbor Dredging, Anchor QEA was requested and provided necessary services for
water quality monitoring and sediment sampling for Phase II of the Lower Bay Dredging
Project. The attached Amendment No. 1 memorializes the extra services provided by
Anchor QEA for the Phase II Project.
RECOMMENDATION:
Approve and execute Amendment No. 1 with Anchor QEA for required water quality and
field management services for Phase II of the Lower Bay Dredging Project.
FUNDING REQUIREMENTS:
Anchor QEA has performed the requested additional services for a not -to- exceed cost
of $142,198.00. Funds are available in the Capital Improvement Projects budget,
account No. 7241- C4402003.
DISCUSSION:
Anchor QEA assisted the City with necessary water quality and permit compliance
services for Phase I of the Project. Midway through Phase I, the City decided to dredge
additional areas as Phase II of the Project to take advantage of the Army Corps of
Engineers presence in the harbor with their dredge equipment. Because of the federal
government's budget shortfall in funding the Project, the City was forced to intervene
and contribute funds for the water quality and sediment sampling efforts. This included
1 of 12
Amendment No. 1 with Anchor QEA, L.P., for Consultant Services to Provide Necessary
Water Quality and Field Management Services for the Lower Bay Dredging Project
July 09, 2013
Page 2
assisting in the negotiation and execution of a Santa Ana Regional Water Board
"Monitoring and Report Plan" for Phase II to monitor for adverse impacts associated
with dredging. As the Project was in full construction mode at the time, City staff
requested and Anchor QEA agreed to provide the same level of necessary monitoring
and sampling services at the same billing rates for Phase II as they have contracted for
under Phase I. Anchor QEA's efforts also included water quality monitoring and
chemical analysis, as well as conformational sediment analysis at the end of the
Project. The attached Amendment No. 1 memorializes the additional work provided by
Anchor QEA on the Project to keep it on schedule and on budget.
Scope of Services
Task 1: Phase II — Necessary Water Quality and Sediment Sampling. (Please see
the attached Scope of Services for a detailed description of the Work).
ENVIRONMENTAL REVIEW:
This federal project has been evaluated by the Army Corps of Engineers, South Pacific
Division, Los Angeles District under the National Environmental Policy Act as an
Environmental Assessment which concluded that the project will not have a significant
adverse impact upon the existing environment or the quality of the human environment.
NOTICING:
This agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers this item).
Submitted by:
David A. We b
Public Works Director
Attachments: A. Vicinity Map of Lower Bay Dredging Project
B. Amendment No. 1
2of12
')
`'° �.°' a 1. u -. Y �{G �S'� l\� «y° \'eF— }•�ra'�'±'.. iJ
A
-
z 7 Y
{ 3
;} X0413 0411
-
4-17 0-1 -10 s4-8
SOl1BCE: Aeria�hom Birg man. LOdineslmm Glv of Newport Beam. LEGEND:
NOBQOMALMTNM: GlNpmu 6tite plane, Zane 6, NAM.
WE ALOANM: mean 1pw<r bwwattr(MLLM Oeo Sampling lmna r5 Area la Area Aa
Area lb Area ab d
Area 2 Area 5
o1e m o—
Area 3
ATTACHMENT A
3of12
ATTACHMENT B
AMENDMENT NO. ONE TO
PROFESSIONAL SERVICES AGREEMENT
WITH ANCHOR QEA FOR
WATER QUALITY AND FIELD MANAGEMENT SERVICES FOR THE LOWER
NEWPORT BAY DREDGING
THIS AMENDMENT NO. ONE TO PROFESSIONAL SERVICES AGREEMENT
( "Agreement ") is made and entered into as of this 29th day of May, 2013 ( "Effective
Date ") by and between the CITY OF NEWPORT BEACH, a California Municipal
Corporation and charter City ( "City "), and Anchor QEA, a California corporation
( "Consultant "), whose address is 26300 La Alameda, Suite 240, Mission Viejo, CA
92691, and is made with reference to the following:
IA*411 r_1m
A. On May 8, 2013, City and Consultant entered into a Professional Services
Agreement ( "Agreement ") for water quality and field management services for the
Lower Newport Bay dredging project ( "Project ").
B. City desires to enter into this Amendment No. One to reflect additional services
not included in the Agreement, to extend the term of the Agreement and to
increase the total compensation and to update insurance requirements.
C. City and Consultant mutually desire to amend the Agreement, as provided below
NOW, THEREFORE, it is mutually agreed by and between the undersigned
parties as follows:
1. TERM
Section 1 of the Agreement is amended in its entirety and replaced with the
following: "The term of this Agreement shall commence on May 8, 2012, and shall
terminate on June 30, 2015 unless terminated earlier as set forth herein."
2. SERVICES TO BE PERFORMED
Exhibit A to the Agreement shall be supplemented to include the Scope of
Services dated May 9, 2013, attached hereto and incorporated herein by reference
( "Services" or "Work "). The City may elect to delete certain Services within the Scope of
Services at its sole discretion.
3. COMPENSATION TO CONSULTANT
Section 4.1 of the Agreement is amended in its entirety and replaced with the
following: "City shall pay Consultant for the Services on a time and expense not-to-
exceed basis in accordance with the provisions of this Section, the Schedule of Billing
Rates attached to the Agreement as Exhibit B and the Proposal attached hereto as
Exhibit B -1 and incorporated herein by reference. Consultant's compensation for all
Work performed in accordance with this Agreement, including all reimbursable items
and subconsultant fees, shall not exceed Five Hundred Forty Five Thousand Two
4of12
Hundred Fifteen Dollars and 00/100 ($545,215.00) without prior written authorization
from City. No billing rate changes shall be made during the term of this Agreement
without the prior written approval of City."
4. INTEGRATED CONTRACT
Except as expressly modified herein, all other provisions, terms, and covenants
set forth in the Agreement shall remain unchanged and shall be In full force and effect.
IN WITNESS WHEREOF, the parties have caused this Amendment No. One to
be executed on the dates written below.
APPROVED AS TO FORM:
CITY ATTORN Y'S OFFICE
Date: zo / 13
i�
Aaron C. Harp
City Attorney
F-111 a 1 *1111
lI ( �o r
CITY OF NEWPORT BEACH,
A California municipal corporation
By:
Keith D. Curry
Mayor
CONSULTANT: Anchor QEA, a California
limited partnership
BY:
Leilani I. Brown Steve Cappellino
City Clerk Senior Partner
[END OF SIGNATURES]
Attachments: Exhibit A - Scope of Services dated May 9, 2013
Exhibit B -1 - Proposal
Anchor QEA Page 2
5of12
EXHIBIT A
SCOPE OF SERVICES DATED MAY 9, 2013
Anchor QEA Page A -1 6 or 12
ANCHOR
QEA
26300 La Alameda, Suite 240
Mission Viejo, California 92691
Phone 949.347:2780
fax 949.334.9646
May 9, 2013
Mr. Chris Miller
City of Newport Beach, Harbor Resources Division
829 Harbor Island Drive
Newport Beach, California 92660
Re: Revised Scope of Work for Phase II Lower Newport Bay Dredging Support
Dear Mr, Miller:
Anchor QEA, L.P., is pleased to have supported the City of Newport Beach (City) with water
quality and permit compliance services related to the Lower Newport Bay Federal Dredging
Program, Phase I dredging activities have been completed and the contractor (RE Stnite)
recently completed Phase II operations, which included additional dredging within multiple
areas throughout Lower Newport Bay (LNB).
As with the Phase I program, Phase 11 of the LNB dredging effort was a federally sponsored
program to restore navigation depths to the federal channels throughout the Bay. Because of
a budget shortfall with federal funding for the project, the City was forced to intervene and
contribute funds to the program: This included assisting in the negotiation and execution'of
a Santa Ana Regional Water Board water quality and-sediment monitoring program to
monitor for adverse impacts associated with the dredging effort.
In addition to assisting the City in the development and implementation of a water quality
monitoring program for the federal areas, Anchor-QEA also assisted with permitting and
design: activities for dredging the backside of Linda Isle, which lies on joint City and County
of Orange (County) tidelands. Although permitted separately, construction of this project
was included as part of die Phase Ii federal dredging project.
7of12
Mr. Chris Miller
May 9.2013
To continue supporting the dredging program for LNB, two additional tasks were required, as
outlined below:
• Task 1 — Phase 11 Water Quality and Sediment Sampling
• Task 2 — Linda Isle City /County Permit Support (Task 2 costs and project details are
described under separate cover)
This Scope of Work details work elements for Task 1 only. A separate letter has been
submitted to cover Task 2 changes.
Task 1: Phase II Water Quality and Sediment Sampling
During the end of the Phase I operations, Anchor QEA assisted the City in negotiating a
revised Monitoring and Reporting Plan (MRP) to cover Phase II dredging operations. The
revised MRP for LNB is attached, which details the specific requirements of the'program.
Work elements for Phase II were'modi£ied .fr. orii those required for Phase I. Water quality
monitoring and chemical analyses were required in three dredge areas; water quality was
conducted once per week during dredging and water samples were collected fox chemical
analyses once in each of the three dredge areas. In addition, confirmational sediment
sampling was required at two of the dredge areas where corrtantinated sediments occurred at
depths below the planned dredge prism. At the conclusion of the program, a detailed
summary report is required to comply with the Santa Ana Regional Water Board permit.
The original budget estimated for this task was $62,374 and was based on the following Ivey
assumptions:
RE Staite would continue dredging, as in Phase I, utilising tcvo dredges operating.
simultaneously.
o Each dredge area would be completed before moving to a new area. This is important
because the Water Board monitoring plan dictated the frequency of monitoring based
on the number of starts and stops for each dredge area on a weekly basis.
• Based on the rate 6t which sediment was removed for Phase I (with two dredges), the
total number of field days to meet the requirements of the monitoring program.
during dredging was calculated to be 15 days.
• No post- dredge sediment toxicity woti.kl be required.
8of12
Mr. Chrls 14iller
May 9, 2013
Page 3
These assumptions were largely not met during constriction for the following reasons:
• RE Staite moved their larger capacity dredge out of INB for use on a different project
about half way through the program. Instead., they used two smaller dredges for part
of Phase If dredging and then relied on just one dredge for the remainder of Phase II
dredging. This resulted in a slower dredge rate than was originally anticipated, and
consequently the slower operation resulted inadditional field.days.
• In the City /County dredge area, dredging was performed intermittently to coincide'
with the tides and for very limited hours each day. Prior to completion of this area,
the dredge was moved out of this area and into a different dredge area for a few
weeks. This resulted in additional field days, because mo;uitoring was required each
time a different area was dredged,
• The actual-number of field days. to comply with the permit was 24 clays (nice
additional days),
a There was frequent communication problems with the dredge contractor regarding
planned activities that resulted in numerous field events that resulted in no samples
collected because the dredge was operating in an area different than what was
communicated previously.'
a The permit required toxicity testing of post- dredge sediments in two dredge areas,
which increased the analytical cost of the project significantly. '
Basel( on the above deviations from the original assumptions, the estimated cost to complete
this task is approximately $142,000. Of this amount, approximately $134,000 has been
expended and approximately $8,000 remains for completion of the project closure reports to
the various regulatory agencies and final .lab fees. The attached detailed cost sheet presents
the labor and direct cost assumptions estimated to complete the required field and reporting
effort. Monitoring and reporting for the federal and City /County dredge areas are both
included in this task.
SUMMARY OF COSTS
The following table summarizes the costs for the.above tasks. A detailed cost breakdown is
attached to this scope of work to provide supporting information and assumptions
9of12
Mr. Chris Miller
May 9, 2013
Page 1
(Attachment A). The attached table includes costs for both Tusks 1 and 2 for reference only.
The current Scope of Worlc is for Taslc 1.. These costs represen.tnot.-to- exceed time and
materials estimates.
Table 1
Summary Budget Estimate by Task
Item
Estimate Level of Effort
Task 1, Phase II Water Quality and Sediment Sampling
$142,198
` Task 2. Linda Isle Permit Suppori*
.Total
$142,198
" Task 2 costs-and protect details are described. under separate cover.
We appreciate the opportunity to continue supporting the City with the LNB Federal
Dredging Program. If there are any questions about this scope of work, please do not
hesitate to contact us at (949) 347 -2760.
Sincerely,
Steve Cappellino
Anchor QEA, L.P.
10 of 12
EXHIBIT B -1
PROPOSAL
Anchor QEA Page B -1 11 of 12
ANCHOR O'A, LC.
2013 PROJECT COST ESTIMATING FORM
'PMPDWVPMi -c,. Name: City or Newpar. Bead,
04rz(13 I! NB Pivse it and Citp!CoLSy
Task t -°hass 0w- ar OwW.d sedunam SeO --9
TasY.2 -! ilea Isle �sJJCv1s11 Prmi Svppert
Copy ofAIlES CM �'OCt EsSmae? -tsl: Taal ter.)
Nambc.-
Prepated: CappeEno
12 of 12
3mn9
—
—
—
—
— .
—
—
—
Total
TOL?I
Lahor Cat odes
Rate
Task,
Tsk2
Haurs
➢altars
Pri[tcpal CL'JEnarPJVPL Sci
S 219
42
6
0
0
0
0
0
0
a
0
48
s 10 ,612
Sr V.=amn A, -4,al l -n, W' PleNs6
$. 199
24
8
0
0
0
0
a )
0
0
0
32
5 6.368
mia iirc Anaks['GY,F^gf^ -F: rfarG.^_'
s 180
0
(
24
0
0
0
0
0 [
0
0
0
2A
3 4,320
Seniac 0. -zIyr: I'}4JOL.LFaetSd
s 150
24
47
0
0
0
0
9
0
9
0'
71
5 11,360
Stz, _�cAvP- Y,L=c'Sci
S 145
120
]!f
0
0
0
0
0
0
-0
192
5 22,710
StsT 2 A� vWCI.NEngHLYFla'S
s 120
520 I
0
0
0
0
0
0
0
0
0
520
5 67,200
Sff : Atr_;ystlCFNEr.91P,F.PIaNSd
S i i0
0
0
0
0
0
0
0
0
0
0
0
5 -
Se,de CAO➢eslyner
s 115
0
0
0
0
0
0
0
0
0
0
0
$ -
CA ueslena
S Se
23
0
0
0
0
0
0
0
0
a
20
s ? ,
(y.dmml)
�chriain aaamr
2
1$
S2
0
�
-
\aSa =[ E[cetl Cvu-YL� t
0
0
0
0.
0
0
- 0
0
0
0
S
t
0
0-
U
0
0
0
0
0
9�
1 Totel�Labar
5 111,980,5
26.055
S -
s -
3 -
s -
s -�s
-
s
- -
s 1se,03e
!!!! A r Rare
3 140
Nt:lpse L.d3rce1
s 14.=
S -
S -
s -
s -.
3 _
5 -
s -
s -
s
5 15.000
�Chemfml
Ldlt
Toiis^j TSd g {1Ja�.11us)
$ <.000
5 -
s -
s -
5 -
s -
5
Y -
s -
? _I
s 4.090
GN.00. =.nEa�xNSwrey -:g-
5 -
s -
s -
s -
s -
5 -
.-
s -
S -
s -
S .-
IS -
'+p'aq".��1Slivers
S. -
s 13.000
s -
5 -
s -
s -
s -
s -
s
S -
s t;em
5 -
$ -
s -
s -
s -
S -
$ -
$ -
s -
s -
s -
Is
-
5 -
5 -
s -
5 -
s -
s -
s -Is
Total Cost
,
$ 19,000
5 13,000
5 -
$ -
s -
s' -
5 -
$
-is,
tmrkup an suSmn:W[srRS
SJM
- 95 0
s 6se
3
s -
$ _,I
S ,-
I Si•.600
Reimbursable^,
CAWCe nput.r [Jhr)
smoc
5 -
s -
S -
s -
s -
S -
5 -
s -
s -
s -
-
Il
MSeaOe (Venue)
1 511.500
s -
S
s -
s -
s -
3 -
s -
s -
$ -
5
-
Cc- ies (S2epy)
50.10
3 -
s -
S -
5 -
s -
s -
5 -
s -
S -
s
-
Anchor 1,=(S ay)
4300
s 4,650
5 -
$ -'$
-
$ -
3 -
$ -
5 -
S
s -
5 <650
Faxes (SFss)
$160
s -
s -
5 -
5 -
s -
3 -
s -
-
5 -
5 -
s -
Ou, da EVensee
s -
5 -
5
luck Renal -
S Zane
3 -
S -
s -
S -
s -
3 -
s -
s -
s -
I s 2,000
P.epmJAldNaq
3 -
s -
$ -
s -
s -
$ -
5 -
5 -
s -
s -
[daVFadesJCmsier
s 1,500
S -
S -
$ -
3 -
s -
3 -
s -
s -
s
$ 1,500
CSrtce,Ea51 srP Rental
4 -
$ -
5 -
3 -
s -
3 -
3 -
3 -
s
s -
Fiur� Sa linq EgafP.—t
s 1.350
$ -
,
s
5 -
S -
3 -
$
3 -
5 -
5 :,250
kticYG:�o3
i s 5661
3 -
s -
s -
$ -
$
-
s -
S -
S
3 ma
[czy
T. mCOZy
10.0�I3
X0256
6farbrPmomiaa
SAs.'v
Is
-
$ -
s -
5 -
s -
s -
3 -
5 -IS
-I
Is
SuPuree
S
S
nfiNtl�supP�P= rius�l
56%
S
-
s -
s -
s -Is
TOTAL COSTS
S 142,198
5 39,706
S -
S -
5 -
s 7s
-
I S -
5 -
S -
S 181,su
12 of 12