HomeMy WebLinkAbout10 - Final Amendement to CM at Risk contract with CWDCITY OF
Q �gW PORT
NEWPORT BEACH-;
City Council Staff Report
Agenda Item No.10
October 8, 2013
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: City Manager's Office
Stephen G. Badum, Assistant City Manager
949 - 644 -3002, sbadum(a).newportbeachca.gov
PREPARED BY: Stephen G. Badum, Assistant City Manager
APPROVED: A
TITLE: Close -out and Final Amendment to the Construction Manager at
Risk Contract for Civic Center & Park Project with C.W. Driver
ABSTRACT:
This item is the close -out amendment to the Construction Manager at Risk Contract for
Civic Center and Park project with C.W. Driver. The amendment addresses the
authorization for the extended General Conditions for the period of January 2013 to the
present. At its meeting on June 11, the City Council budgeted the resources for this
close -out amendment. With the project complete, this item follows -up by amending the
Driver agreement accordingly and authorizes the City Manager to file the Notice of
Completion.
RECOMMENDATIONS:
1) Authorize the Mayor to sign the final close -out amendment to the Construction
Manager at Risk Contract for Civic Center and Park project with C.W. Driver.
2) Delegate the authority to file a Notice of Completion for the Civic Center & Park
project to the City Manager upon his determination that the project is fully
complete.
Close -out and Final Amendment to the Construction Manager at Risk Contract for Civic Center & Park Project with
October 8, 2013
Page 2
FUNDING REQUIREMENTS:
At the June 11, 2013 City Council Meeting, a budget amendment was approved to
cover the cost of project changes and extended general conditions for the project
(approximately $1.4M).
DISCUSSION:
Following the design process, the original construction contract envisioned a 24 -month
construction period from start to finish. While the project was substantially finished in
January 2013, the final completion date was extended to June 2013. This is due to
various factors including material delays, scheduling conflicts, weather, and the overall
complexity of the project. The additional time required resulted in increased costs to the
contractor, C.W. Driver (CWD), for general conditions. Since June, the construction
team has been reduced substantially and has been working on various "punchlist" items
(ongoing corrections and minor construction changes).
Construction General Conditions
As previously noted, CWD has continued to provide "general conditions" for the project
on a time and materials basis. General conditions typically include the fixed costs for the
construction field office (including construction trailers, office equipment, portable
restrooms, copiers, computers, telephone and equipment), personnel to staff the project
(including superintendent, inspection and support staff), and the coordination with the
architect team, subcontractors, and City representatives. To help reduce these costs,
CWD's construction management staff was downsized in early 2013 and the
construction trailers and fencing were removed. CWD's project office was temporarily
located in the new Training Room / Command Center until July 2013. The estimated
additional cost for the extended general condition period and any residual work past
July was established to be $1,400,000, and C.W. Driver has agreed to limit their request
for extended general conditions to this amount. With the approval of this amendment,
the contract total will be $107,904,125.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this action is not subject to the California
Environmental Quality Act ( "CEQA ") pursuant to Sections 15060(c)(2) (the activity will
not result in a direct or reasonably foreseeable indirect physical change in the
environment) and 15060(c)(3) (the activity is not a project as defined in Section 15378)
of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it
has no potential for resulting in physical change to the environment, directly or
indirectly.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
4
Close -out and Final Amendment to the Construction Manager at Risk Contract for Civic Center & Park Project with
October 8, 2013
Page 3
Submitted by:
City Manager
ent: CM @R Contract Amendment
AMENDMENT NO. SIX TO CONSTRUCTION MANAGER AT RISK
CONTRACT WITH C.W. DRIVER, INC. FOR
NEWPORT BEACH CIVIC CENTER AND PARK GMP PHASE THREE
(EXTENDED GENERAL CONDITIONS)
THIS AMENDMENT NO. SIX TO CONSTRUCTION MANAGER AT RISK
CONTRACT ( "Amendment No. Six'), is entered into as of this 9th day of October, 2013,
by and between the CITY OF NEWPORT BEACH, a California municipal corporation
and charter city ( "City "), and C.W. DRIVER, INC., a California Corporation whose
address is 15615 Alton Parkway, Suite 150, Irvine, California 92618 ( "CM "), and is
made with reference to the following:
RECITALS:
A. On June 7, 2010, City and CM entered into a Construction Manager at Risk
Contract ( "CM Contract ") for the Newport Beach Civic Center and Park Project
( "Project ").
B. On September 3, 2010, City and CM entered into Amendment No. One to the
CM Contract ( "Amendment No. One "), as contemplated in the CM Contract,
Article Six, Section 6.1.9(e), to add the Design Build 450 stall parking garage and
to increase the Guaranteed Maximum Price ( "GMP ").
C. On February 22, 2011, City and CM entered into Amendment No. Two to the CM
Contract ( "Amendment No. Two ") for additional services not included in the CM
contract or Amendment No. One, to add the construction of the City Hall Office
Building, Central Library Expansion, Parks and miscellaneous items of work for
the Newport Beach Civic Center; to increase the CMP by $82,374,384.00 for a
total GMP of $104,306,931.00; and to update the insurance provisions consistent
with the City's election to implement an Owner Controlled Insurance Program
( "OCIP ").
D. On November 29, 2011, City and CM entered into Amendment No. Three to the
CM Contract ( "Amendment No. Three "), to reflect the City's option to construct
the San Miguel Pedestrian Bridge as part of Phase Three as originally
contemplated in the CM Contract, Article One, Section 1.3, and increase the
GMP to $105,306,931.00 utilizing $1,000,000.00 of the Owner's Contingency
along with $1,000,000.00 of the Construction Contingency to fund the costs of
construction.
E. On April 24, 2012, City and CM entered into Amendment No. Four to the CM
Contract ( "Amendment No. Four") for additional services not included in the CM
Contract or prior amendments to add the fabrication and installation of project
signing and the installation of dry utilities modifications to increase the GMP by
$476,281.00 for a total GMP of $105,783,212.00.
4
F. On October 23, 2012, City and CM entered into Amendment No. Five to the CM
Contract ( "Amendment No. Five ") for additional services not included in the CM
Contract or prior amendments for Library Clerestory repair to increase the GMP
by $720,913.00 for a total GMP of $106,504,125.00. .
G. City desires to enter into this Amendment No. Six for additional services not
included in the CM Contract, or prior Amendments for extended general
conditions and to increase the GMP by $1,400,000.00 for a total GMP of
$107,904,125.00.
H. City and Consultant mutually desire to amend the Contract, as provided below.
NOW, THEREFORE, it is mutually agreed by and between the undersigned
parties as follows:
1. GUARANTEED MAXIMUM PRICE
Section 6.1.1 of the CM Contract shall be amended to increase the GMP to One
Hundred and Seven Million Nine Hundred Four Thousand Three Hundred Twenty -
Five Dollars and 001100 ($107,904.125.00).
2. INTEGRATED CONTRACT
Except as expressly modified herein, all other provisions, terms, and covenants set forth
in the CM Contract as amended shall remain unchanged and shall be in full force and
effect.
[SIGNATURES ON NEXT PAGE]
C.W. DRIVER, INC. Page 2
5
IN WITNESS WHEREOF, the parties hereto have executed this Amendment No.
Six on the dates written below.
APPROVED AS TO FORM:
CITY ATTORNEY'S OFFICE
Date: to 12 l 13
Aaron C. Harp
City Attorney 111Y
ATTEST:
Bv:
Leilani I. Brown
City Clerk
CITY OF NEWPORT BEACH,
A California municipal corporation
Date:
Bv:
Keith D. Curry
Mayor
CONSULTANT: C.W. DRIVER, INC., a
California Corporation
Date:
By:
Dana Roberts
President
Date:
By:
Bessie Kouvara
Chief Financial Officer
[END OF SIGNATURES]
C.W. DRIVER, INC. Page 3
y
Agenda Item No. 10
October 8, 2013
ATTACHMENT 1
I 1 ,
AMENDMENT NO. SIX TO CONSTRUCTION MANAGER AT RISK
CONTRACT WITH C.W. DRIVER, INC. FOR
NEWPORT BEACH CIVIC CENTER AND PARK GMP PHASE THREE
(EXTENDED GENERAL CONDITIONS)
THIS AMENDMENT NO. SIX TO CONSTRUCTION MANAGER AT RISK
CONTRACT ( "Amendment No. Six "), is entered into as of this 9th day of October, 2013,
by and between the CITY OF NEWPORT BEACH, a California municipal corporation
and charter city ( "City "), and C.W. DRIVER, INC., a California Corporation whose
address is 15615 Alton Parkway, Suite 150, Irvine, California 92618 ( "CM "), and is
made with reference to the following:
RECITALS:
A. On June 7, 2010, City and CM entered into a Construction Manager at Risk
Contract ( "CM Contract ") for the Newport Beach Civic Center and Park Project
( "Project ").
B. On September 3, 2010, City and CM entered into Amendment No. One to the
CM Contract ( "Amendment No. One "), as contemplated in the CM Contract,
Article Six, Section 6.1.9(e), to add the Design Build 450 stall parking garage and
to increase the Guaranteed Maximum Price ( "GMP ").
C. On February 22, 2011, City and CM entered into Amendment No. Two to the CM
Contract ( "Amendment No. Two ") for additional services not included in the CM
contract or Amendment No. One, to add the construction of the City Hall Office
Building, Central Library Expansion, Parks and miscellaneous items of work for
the Newport Beach Civic Center; to increase the GGMP by $82,374,384.00 for a
total GMP of $104,306,931.00; and to update the insurance provisions consistent
with the City's election to implement an Owner Controlled Insurance Program
( "OCI P ").
D. On November 29, 2011, City and CM entered into Amendment No. Three to the
CM Contract ( "Amendment No. Three "), to reflect the City's option to construct
the San Miguel Pedestrian Bridge as part of Phase Three as originally
contemplated in the CM Contract, Article One, Section 1.3, and increase the
GMP to $105,306,931.00 utilizing $1,000,000.00 of the Owner's Contingency
along with $1,000,000.00 of the Construction Contingency to fund the costs of
construction.
E. On April 24, 2012, City and CM entered into Amendment No. Four to the CM
Contract ( "Amendment No. Four') for additional services not included in the CM
Contract or prior amendments to add the fabrication and installation of project
signing and the installation of dry utilities modifications to increase the GMP by
$476,281.00 for a total GMP of $105,783,212.00.
F. On October 23, 2012, City and CM entered into Amendment No. Five to the CM
Contract ( "Amendment No. Five') for additional services not included in the CM
Contract or prior amendments for Library Clerestory repair to increase the GMP
by $720,913.00 for a total GMP of $106,504,125.00.
G. City desires to enter into this Amendment No. Six for additional services not
included in the CM Contract, or prior Amendments for extended general
conditions and to increase the GMP by $1,400,000.00 for a total GMP of
$107,904,125.00.
H. City and CMonsultant mutually desire to amend the Contract, as provided below.
NOW, THEREFORE, it is mutually agreed by and between the undersigned
parties as follows:
1. GUARANTEED MAXIMUM PRICE
Section 6.1.1 of the CM Contract shall be amended to increase the GMP to One
Hundred and Seven Million Nine Hundred Four Thousand Three Hundred Twenty -
Five Dollars and 00 /100 ($107,904.125.00). Payment by City to CM shall not be a
waiver of anv of Citv's riahts to recover damaaes or anv other tvoe of monetary or non
monetary relief including reimbursement of any amounts paid by City to CM.
2. INTEGRATED CONTRACT
Except as expressly modified herein, all other provisions, terms, and covenants set forth
in the CM Contract as amended shall remain unchanged and shall be in full force and
effect.
[SIGNATURES ON NEXT PAGE]
C.W. DRIVER, INC. Page 2
IN WITNESS WHEREOF, the parties hereto have executed this Amendment No.
Six on the dates written below.
APPROVED AS TO FORM:
CITY ATTORNEY'S OFFICE
Date:
By:
Aaron C. Harp
City Attorney
ATTEST:
Date:
By:
Leilani I. Brown
City Clerk
CITY OF NEWPORT BEACH,
A California municipal corporation
Keith D. Curry
Mayor
CONSUL-T- ANT: -C.W. DRIVER, INC., a
California Corporation
Dana Roberts
President
By:
Bessie Kouvara
Chief Financial Officer
[END OF SIGNATURES]
C.W. DRIVER, INC. Page 3