HomeMy WebLinkAbout06 - Award Contract No. 3449- Sunset Ridge Park� t�FW POR T O d NEWPORT BEACH CA�lFORNP City Council Staff Report Agenda Item No. 6 December 10, 2013 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department David A. Webb, Public Works Director 949 - 644 -3330, dawebb @newportbeachca.gov PREPARED BY: Andy Tran, Senior Civil Engineer 949 - 644 -3315, atran @newportbeachca.gov APPROVED: TITLE: Sunset Ridge Park - Award of Contract No. 3449 ARSTRACT- Staff has received favorable bids for the construction of Sunset Ridge Park (SRP) and is requesting City Council's approval to award the construction contract to Environmental Construction, Inc. of Woodland Hills California. RECOMMENDATION: 1. Approve the final park design and the project plans and specifications. 2. Award Contract No. 3449 to Environmental Construction, Inc., for the total bid amount of $5,214,820.00, and authorize the Mayor and the City Clerk to execute the contract. 3. Establish a contingency of $520,000.00 (approximately 10 %) to cover the cost of unforeseen work. 4. Terminate the Access Agreement between the City of Newport Beach and Newport Banning Ranch, LLC regarding Sunset Ridge Park approved by City Council on March 23, 2010. FUNDING REQUIREMENTS: The current adopted budget includes sufficient funding for the award of this contract. The following fund will be expensed: Account Description Account Number Amount Major Facilities Master Plan 7412- C5100515 $ 5,734,820.00 Total: $ 5,734,820.00 1 of 6 Sunset Ridge Park - Award of Contract No. 3449 December 10, 2013 Page 2 Staff recommends establishing a ten (10) percent contingency for unforeseen conditions associated with construction. Proposed uses are as follows: Vendor Purpose Amount Environmental Construction Construction Contract $ 5,214,820.00 Environmental Construction Construction Contingency $ 520,000.00 Total: $ 5,734,820.00 DISCUSSION: The City Council approved the original SRP design concept in June 2008, and the project Environmental Impact Report in March 2010. After approximately 3 -1/2 years of working with the California Coastal Commission to obtain a coastal development permit, Coastal Development Permit 5 -11 -302 for SRP was issued on November 7, 2013. As part of this permit process, the original park concept was modified to remove the in -park parking lot and the proposed park assess road across the adjacent Banning Ranch Property. In addition, the majority of the park's landscape palette (other than the field areas) was modified to a California Coastal Sage Scrub palette. Due to these required changes to the park plans, staff is recommending City Council officially approve the final park design (Attachment B) and the project plans and specifications. During the development on the original SRP design, the City and Newport Banning Ranch LLC (NBR) negotiated and entered into an access agreement dated March 23, 2010 that would have provided for a 28 foot wide public access road to cross over NBR property to allow access to the park from West Coast Highway. This original park access road design was withdrawn during the coastal permitting process due to concerns raised on how it would fit into the future NBR development. As a result, the City modified the park design to be served from the existing parking lot on the northeast corner of West Coast Highway and Superior Avenue. The City and NBR also developed and recorded a replacement easement on June 4, 2013 providing for the necessary maintenance and emergency access to the park within the existing 16 foot wide service road. The original access agreement with NBR is no longer needed and staff is now requesting termination of that agreement. At 10:00 a.m. on November 27, 2013, the City Clerk opened and read the following bids for this project: 2 of Sunset Ridge Park - Award of Contract No. 3449 December 10, 2013 Page 3 BIDDER AS -BID AMOUNT Low Environmental Construction $ 5,215,476.00 2 Horizons Construction Co. $ 5,492,800.00 3 Kasa Construction $ 5,656,100.00 4 RC Graves Construction $ 5,769,524.00 5 Ohno Construction Co. $ 6,499,000.00 6 Los Angeles Engineering $ 6,791,625.00 7 Yakar $ 6,669,700.00 8 Mallcraft $ 7,095,900.00 9 Palp $ 7,264,375.00 10 Toby B. Hayward $ 7,553,853.01 CORRECTED AMOUNT $ 5,214,820.00 $ 5,492,799.00 $ 5,772,768.00 $ 6,934,700.00 The total low bid amount is 21% below the Engineer's Estimate of $6,600,000.00. The low bidder, Environmental Construction, Inc., possesses both California State Contractors License Classifications "A" and "C -27" as required by the project specifications. A check of the Contractor's references indicates they have satisfactorily completed similar projects for other municipalities. This contract involves constructing a new active park on a 13.7 acre undeveloped site at the northwest corner of West Coast Highway and Superior Avenue. Proposed improvements include the following: • Pony League Baseball Field • Two (2) Soccer Fields • Warm -up Field • Children's Play Area • Picnic Area • Restrooms • Memorial Butterfly Garden • Overlook Area with Trellis Structure • Meandering Walkways Pursuant to the Contract Specifications, the Contractor will have 180 consecutive working days to complete the project. ENVIRONMENTAL REVIEW: The Final Environmental Impact Report for the Sunset Ridge Park project was certified by City Council on March 10, 2010. 3 of Sunset Ridge Park - Award of Contract No. 3449 December 10, 2013 Page 4 NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). This project as undergone extensive public review and comments through the regulatory review and permitting process. Submitted by: '1910. 1114 avid A. Webb Public Works Director Attachments: A. Location Map B. Final Park Design 4 of s� 9 C� 2� s �1 VVE51 Attachment A PROJECT LOCATION it 4j INN Ti FT7 fT fTTr7 f f 1 I i H, 1 11 L iiiiii�ljLU� 1=1 TM-711 19TIT7 F17TTl SUNSET RIDGE PARK W�CO \. ►l T CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -3449 1 12/10/2013 5 of I • s� �e r e c 'Vest Coast Highway SUNSET RIDGE PARK FINAL PARK DESIGN Attachment B S S _ •a as d Prd`�o S�Pe`so� Mu CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -3449 12/10/2013 6 of