HomeMy WebLinkAbout16 - C.W. Driver - Claims SettlementTO: FROM: PREPARED BY: PHONE: TITLE: ABSTRACT: CITY OF Agenda Item No. 16. HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL Dave Kiff, City Manager— (949) 644 -3002, dkiff @newportbeachca.gov Stephen Badum 949 - 644 -3002 Claims Settlement - C.W. Driver, Bohlin Cywinski Jackson, and City The proposed Settlement Agreement and General Release resolves in final form all outstanding claims made by certain sub - contractors to C.W. Driver for the Civic Center and Park Project. RECOMMENDATION: Approve the Settlement Agreement and General Release, in substantially the same form as that staff report attachment, with C.W. Driver, in the amount of $2,399,430 (net new cost to City of $2.19M). FUNDING REQUIREMENTS: If approved, the expenditure will be drawn from the General Liability Fund. DISCUSSION: The Civic Center and Park project was substantially completed in April 2013 by C.W. Driver. Bohlin Cywinski Jackson (BCJ) has been the lead project architect, with several subcontractors working under BCJ. The City has been largely satisfied with the completed project, which included a city hall, parking structure, 14 -acre park, dog park, pedestrian bridge, stormwater detention facility, and expansion of the Central Library. The project has won honors for its energy efficiency and advanced design. The partnership between CW Driver, BCJ, and the City has been a strong one, with cooperation all throughout the over five years (2008 to 2013) of the project's design, construction, and completion. Since completion, several sub - contractors to C.W. Driver submitted claims requesting payment for change orders that were previously rejected by the City and for extended general conditions due to alleged delays. The total claims submitted to C. W. Driver totaled over $9M. Stop payment notices were also filed in the amount of $8.2 million. The City is currently holding the project retention of $4,548,429.85 from CW Driver. C.W. Driver has been negotiating with the various sub - contractors to reduce or eliminate the various claims. Recognizing that the project was contracted as a Construction Manager at Risk contract, C.W. Driver has proposed absorbing a major portion of the cost to settle these claims. They are proposing that the City provide a portion of the claims settlement cost. A breakdown of the proposed City share of the claim settlement is shown as Attachment A. The City Attorney's office and project staff have reviewed the various claims and feel that many of the claims are unwarranted. However, further litigation on these matters would likely balloon the claims costs further and cost significant resources as the claims are administered to fully review and analyze responsibility. Including legal expenses, the cost of an unfavorable judgment or arbitration action could expose the City to up to $8 million in expenses. With that potential risk in mind, Staff reluctantly recommends that the attached settlement agreement (Attachment B) be executed by City Council. Unfortunately, having claims at the end of a large construction project such as this one is fairly typical. Resolving these types of claims through a settlement agreement is always challenging to swallow, but the alternative legal actions can take years to resolve and will ultimately cost the City more in lost staff time and legal costs. The City is fortunate that we elected to construct the Civic Center and Park utilizing a Construction Manager at Risk delivery method, so much of the claims settlement expense falls on C.W. Driver. The final settlement amount represents about 2% of the overall construction amount ($112,833,339) and a smaller percentage of the "all -in" costs of the project if costs are included from 2008 -09 onward ($139,939,969). Therefore, while distasteful, the proposed settlement is likely to be a sound business decision. Proposed Settlement The execution of the agreement settles all claims and protects the City from any future claims associated with the construction contract. In general the agreement includes: • Payment of $2,399,430 to C. W. Driver representing the City's share to settle all outstanding claims (net new cost to City = $2,199,430); • C.W. Driver will secure all Stop Payment notice releases so that the City may immediately release the project retention to C. W. Driver; • Acceptance of the project as it currently exists with the City assuming responsibility to secure the final certificate of occupancy (several small issues remain to be resolved and will be completed within the next few weeks by staff); and • Assignment of any rights to pursue the manufacturer of NaturalPAVE relating to park walkways. More about the 'Natural PAVE' material issue The paving material, NaturalPAVE, for the Park and some of the Civic Center walkways is a flexible paving product that is suitable for ADA compliant walkways with the appearance of decomposed granite. It was specified by our Landscape Architect, Peter Walker Partners. The material is manufactured by Soil Stabilization Product Co and it was installed by Park West's subcontractor, Blacktop Paving, who was the manufacturer certified installer for the NaturalPAVE product. Near the completion of the walkway installation, we observed cracking issues on some of the walkway areas within the park. Subsequent investigation indicated a potential material failure, but the manufacturer insisted that their product met the product specifications and claimed improper installation. Staff has observed that the cracking of the park walkways has not degraded further and no new areas of concern have appeared. As a part of their portion of the settlement, Park West has agreed to repair some of the walkways at their cost and their rights to pursue the manufacturer we be assigned to the City. ENVIRONMENTAL REVIEW: Staff recommends the City Council find this action is not subject to the California Environmental Quality Act ( "CEQA ") pursuant to Sections 15060(c)(2) (the activity will not result in a direct or reasonably foreseeable indirect physical change in the environment) and 15060(c)(3) (the activity is not a project as defined in Section 15378) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential for resulting in physical change to the environment, directly or indirectly. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Name: Description: D 14 -02 -19 Attachment A - Chart.odf Summary of Claims D CW Driver Inc. Settlement Aareement.odf Proposed Settlement Agreement w/3 Exhibits Attachment A - Summary of Claims Subcontractor & Associated Work Scope /Claim HPnourft City Hall and Literary Addition Critchfield Mechanical - HVAC $250,000 Montbleau & Associates - Finish Carpentry $125,400 Preferred Ceilings - Ceiling Finishes $115,1140 SME Steel - Structural Steel & Misc. metals $1,350,000 Superior Wall Systems - Interior wall framing and drywall $84,004 Subtotal Cit r Hall and Library Addition $1,920,000 Detention Basin and Grounds Park West - Detention Basin and Landscape $561,572 Subtotal Detention Basin and Grounds $561,572 Total Claims Settlement Amount $2,461,572 Less allocated project contingency ($82,142) Final Settlement Amount $2,399,430 Contribution from BCJ Feel M00,400p fet New Cast to City 1 $2,199,430 SETTLEMENT AGREEMENT AND GENERAL RELEASE WITH C.W. DRIVER, INC. THIS SETTLEMENT AGREEMENT AND GENERAL RELEASE ( "Settlement Agreement "), is entered into as of this day of February, 2014 ( "Effective Date "), by and between the CITY OF NEWPORT BEACH, a California municipal corporation and charter city ( "City'), and C.W. DRIVER, INC., a California Corporation whose address is 15615 Alton Parkway, Suite 150, Irvine, California 92618 ( "CM "), and is made with reference to the following: RECITALS: A. On June 7, 2010, City and CM entered into a Construction Manager at Risk Contract ( "CM Contract ") for the Newport Beach Civic Center and Park Project ('Project "). B. On September 3, 2010, City and CM entered into Amendment No. One to the CM Contract ( "Amendment No. One "), as contemplated in the CM Contract, Article Six, Section 6.1.9(e), to add the Design Build 450 stall parking garage and to increase the Guaranteed Maximum Price ( "GMP "). C. On February 22, 2011, City and CM entered into Amendment No. Two to the CM Contract ( "Amendment No. Two ") for additional services not included in the CM Contract or Amendment No. One, to add the construction of the City Hall Office Building, Central Library Expansion, Parks and miscellaneous items of work for the Newport Beach Civic Center, to increase the GMP by $82,374,384 for a total GMP of $104,306,931; and to update the insurance provisions consistent with the City's election to implement an Owner Controlled Insurance Program ( "OCI P "). D. On November 29, 2011, City and CM entered into Amendment No. Three to the CM Contract ( "Amendment No. Three "), to reflect the City's option to construct the San Miguel Pedestrian Bridge as part of Phase Three as originally contemplated in the CM Contract, Article One, Section 1.3, and increase the GMP to $105,306,931 utilizing $1,000,000 of the Owner's Contingency along with $1,000,000 of the Construction Contingency to fund the costs of construction. E. On April 24, 2012, City and CM entered into Amendment No. Four to the CM Contract ( "Amendment No. Four") for additional services not included in the CM Contract or prior amendments to add the fabrication and installation of Project signing and the installation of dry utilities modifications to increase the GMP by $476,281 for a total GMP of $105,783,212. On October 23, 2012, City and CM entered into Amendment No. Five to the CM Contract ( "Amendment No. Five ") for additional services not included in the CM Contract or prior amendments for Library Clerestory repair to increase the GMP by $720,913 for a total GMP of $106,504,125. G. On October 9, 2013 City and CM entered in Amendment No. Six to the CM Contract ( "Amendment No. Six') for additional services not included in the CM Contract, or prior amendments for extended general conditions and to increase the GMP by $1,400,000 for a total GMP of $107,904,125. H. CM has submitted a claim for $8,203,965 for, among other things, alleged extra work performed by CM's contractors, subcontractors and suppliers, on the Project, as well as delays which impacted CM's contractors, subcontractors, and suppliers on the Project ( "Claims "). A detailed list of the Claims is set forth in Exhibit A hereto and incorporated herein by this reference. For purposes of avoiding legal proceedings related to the Claims, City and CM desire to enter into this Settlement Agreement for additional services not included in the CM Contract, or prior amendments, to provide a release of all claims associated in any way with the Project, and to increase the GMP by $2,399,430 for a total GMP of $110,303,555. . NOW, THEREFORE, it is mutually agreed by and between the undersigned parties as follows: SCOPE OF WORK City and CM acknowledge that the above Recitals are true and correct and are hereby incorporated herein by reference. Article Two of the CM Contract shall be supplemented to include this Settlement Agreement. 2. GUARANTEED MAXIMUM PRICE Section 6.1.1 of the CM Contract shall be amended to increase the GMP to One Hundred and Ten Million Three Hundred Three Thousand Five Hundred Fifty -Five Dollars and 00/100 ($110,303,555) ( "Final. Contract Amount'), an increase in the GMP by Two Million Three Hundred Ninety -Nine Thousand Four Hundred Thirty Dollars and No /100 ($2,399,430), within three (3) business days of the execution of this Settlement Agreement by the City and CM. The Final Completion Contract Date shall be the Effective Date of this Settlement Agreement 3. FINAL PAYMENT & RELEASE A. Notwithstanding the potential additional future work provided in Subsection, 3(F), the GMP provided in this Settlement Agreement shall be the final payment by City for the Project and shall satisfy all past, current and future claims for compensation, damages, costs, expense, interest or demand for any type of payment C.W. DRIVER, INC. Page 2 by CM, its subcontractors, suppliers, as well as any other person or entity that relates in any way to the Claims, CM Contract, as amended, and /or the Project. The City authorizes its City Manager to execute all assignment, waiver and other agreements reasonably necessary to close out this Project, including, but not limited to, the assignment agreement for the installation of the NaturalPAVE material attached hereto as Exhibit B, and incorporated herein by reference. B. CM, for themselves and all of their predecessors, successors, assigns, representatives, attorneys, employees, officers, subcontractors, suppliers or agents (collectively, "CM "), do hereby fully and forever release and discharge City and all of its predecessors, successors, assigns, representatives, attorneys, employees, officers, contractors, subcontractors, suppliers or agents of and from any and all actions, claims, demands, rights, damages, costs, expenses, attorneys fees, expert fees, consultant fees, other fees, interest, and compensation of any nature whatsoever, which CM has or may hereafter accrue, including without limitation, any and all known and unknown, foreseen and unforeseen claims, damage and injury, relating to, or in any way, directly or indirectly, involving or arising out of any facts or circumstances related in any way to the Claims, CM Contract, as amended, and /or the Project. C. CM shall cause all stop notices and other claims filed against the Project to be released within fifteen (15) calendar days of the signing of this Settlement Agreement. CM and the City acknowledge and agree that money that is the subject of stop notice claims filed with the City that relate in any way to the Claims, CM Contract, as amended, and /or the Project shall be released in accordance with California law and after lawsuits filed by any contractor, subcontractor, supplier, or other person or entity, if any, that relates in any way to the Claims, CM Contract, as amended, and /or the Project have been dismissed with prejudice. D. CM shall defend, indemnify, release and hold harmless the City from and against any and all claims, demands, obligations, damages, actions, causes of action, suits, losses, judgments, fines, penalties, liabilities, costs and expenses (including without limitation, attorneys' fees, disbursements and court costs) of every kind and nature brought by any contractor, subcontractor, supplier, stop notice claimant, or employee, person, entity, agent, and/ or success or assign thereof, which may arise from or in any manner relate (directly or indirectly) to the Claims, CM Contract, as amended, and /or the Project. This indemnification shall include, but not be limited to, damages awarded against the City, if any, costs of suit, attorneys' fees, and other expenses incurred in connection with such claim, action, or proceeding whether incurred by CM, the City, and /or the parties initiating or bringing such proceeding. E. It is the intention and understanding of CM, in executing this Settlement Agreement that it shall be effective as a full and final accord and satisfaction and compromise and release, of each and every settled or released matter related to the Claims, the CM Contract, as amended, and /or the Project. In furtherance of this C.W. DRIVER, INC. Page 3 intention, CM acknowledges that it is familiar with California Civil Code Section 1542 which provides as follows: "A general release does not extend to claims which the creditor does not know or suspects to exist in his favor at the time of executing the release, which, if known by him, must have materially affected his settlement with the debtor." CM hereby expressly waives and /or relinquishes any right or benefit which it has, or might have, under California Civil Code Section 1542 and all other similar provisions of law of other jurisdictions to the fullest extent allowed by law. In connection with such compromise, waiver and relinquishment, CM acknowledges that it is aware that it may hereafter discover facts in addition to or different from those which it may now know or believe to be true with respect to the Claims, the CM Contract, as amended, and /or the Project and this Settlement Agreement, but that, except as is otherwise provided herein, it is Ms intention hereby to fully, finally and forever settle and release all matters, disputes and differences, known or unknown, suspected or unsuspected, which do now exist, may exist, or heretofore have existed, and that in furtherance of such intention, the release actually given herein shall be and remain in effect as a full and complete general release, notwithstanding the discovery or existence of any such additional or different facts. F. As part of this Settlement Agreement, the parties agree as follows: I. The City accepts all of the work installed by CM as identified in the CM Contract, including all items identified on the Project's punch list; ii. CM is not responsible for any on -going California Building Code issues (e.g., building roof trellis/canopy approval) or correctional work that is related to the final certificate of occupancy; !it. Following execution of this Settlement Agreement, if the City requests, in writing, any additional services related to building or system maintenance investigation /issues /training, the costs of said requests shall be reimbursed to CM on an hourly basis in accordance with CM's current 2014 hourly rate schedule and pursuant to a valid contract; iv. Following execution of this Settlement Agreement, if the City requests, in writing, any additional services related to mechanical, electrical, plumbing, building controls or security systems, the costs for said requests shall be reimbursed to CM on an hourly basis in accordance with CM's current 2014 hourly rate schedule and related subcontractor's current 2014 hourly rate schedule and pursuant to a valid contract; V. Following execution of this Settlement Agreement, if the City requests, in writing, any additional services related to schedule analysis, documentation research, review and assembly as related to the City pursuing potential claims against C.W. DRIVER, INC. Page 4 parties that performed services on the Project, the costs for said requests shall be reimbursed to CM on an hourly basis in accordance with CM's current 2014 hourly rate schedule and pursuant to a valid contract; and vi. All current CM Contract warranties, subcontract warranties and manufacturers warranties shall remain in full force and effect in accordance with the CM Contract. 4. ASSIGNMENT OF RIGHTS CM warrants and agrees that CM will assign to the City, and that CM will obtain assignments to the City from its contractors, subcontractors, suppliers, as well as any other person or entity that provided supplies, services, and /or work on the Project, an assignment of all rights that each of them have, may have, or may hereafter accrue, including without limitation, any and all known and unknown, foreseen and unforeseen claims, damage and injury, relating to, or in any way, directly or indirectly, involving or arising out of any facts or circumstances related in any way to the Claims, CM Contract, as amended, and /or the Project including, but not limited to, demands, obligations, damages, actions, causes of action, suits, losses, judgments, fines, penalties, costs and expenses (including without limitation, attorneys' fees, disbursements and court costs) of every kind and nature for alleged extra work, delays, or otherwise, that relate to work, services and /or supplies provided to the Project that are associated in any way with the work or services performed by Architect, Bohiin Cywinski Jackson, a Pennsylvania corporation ( "BCJ"), BCJ's contractors, subcontractors, or anyone performing work on BCJ's behalf. All assignments required under this section shall be delivered to City within sixty (60) calendar days of the execution of this Settlement Agreement, in a form substantially similar to that form attached as Exhibit "C" hereto and incorporated herein by reference. 5. CONSTRUCTION This Settlement Agreement shall not be construed against the party preparing it, but shall be construed as if all parties jointly prepared this Settlement Agreement. Any uncertainty and ambiguity shall not be interpreted against any one party. This Settlement Agreement is to be performed in California and it is to be interpreted, enforced, and governed by and under the laws of the State of California. Language in all parts of this Settlement Agreement shall be in all cases construed as a. whole according to its very meaning. 6. ATTORNEYS' FEES Should suit be brought to enforce or interpret any part of this Settlement Agreement or the CM Contract, as amended, the prevailing party shall not be entitled to recover attorneys' fees. C.W. DRIVER, INC. Page 5 7. AUTHORITY Each of the parties is authorized to enter into this Settlement Agreement and has taken all actions to authorize its officers to enter into it and bind the parties, as evidenced by their signatures below. 8. INTEGRATED CONTRACT Except as expressly modified herein, all other provisions, terms and covenants set forth in the CM Contract, as amended, shall remain unchanged and shall be in full force and effect. 9. NO ADMISSION OF LIABILITY This Settlement Agreement and the releases contained herein and the consideration referred to herein are done to save litigation expense and to effect the compromise and settlement of claims and defenses which are denied, disputed, and contested. Nothing contained herein shall be construed as an admission by any party of any liability of any kind to any other party, person or entity. 10. INVALID CLAUSE MAYBE SEVERED. If any provision, clause, or part of the Settlement Agreement is adjudged illegal, invalid or unenforceable, the balance of this Settlement Agreement shall remain in full force and effect. [SIGNATURES ON NEXT PAGE] C.W. DRIVER, INC. Page 6 IN WITNESS WHEREOF, the parties hereto have executed this Settlement Agreement on the dates written below. APPROVED AS TO FORM: CITY ATTORNEY'S OFFICE Date: 2 ✓ o By: Aaron C. Harp City Attorney ATTEST: Date: CITY OF NEWPORT BEACH, A California municipal corporation By: Rush N. Hill, II Mayor CM: C.W. DRIVER, INC., a California Corporation Date: By: By: Leilani I. Brown Dana Roberts City Clerk President Date: Bessie Kouvara Chief Financial Officer [END OF SIGNATURES] Attachments: Exhibit A: Claims List Exhibit B: NaturalPAVE Assignment Agreement Exhibit C: Sample Assignment Form C.W. DRIVER, INC. Page 7 EXHIBIT A CLAIMS LIST C.W. Driver, Inc. Page A -1 Civic Center & Park Claims List 01/13/2014 ICIalms Original Claim I Negotiated I by Sub - Contractor amount Amount Critchfield Mechanical - HVAC Claim for extended General Conditions $ 507,647 $ 250,000 Subtotal = $ 507,647 $ 250,000 Montbleau - Finish Carpentry Claim for extended General Conditions $ 473,059 $ 125,000 Subtotal = $ 473,059 $ 125,000 Park West - Landscapine Rejected Change Order - Detention Basin Soil $ 230,664 Rejected Change Order - Detention Basin Grading (Stice Cc) $ 183,342 Claim for extended General Conditions $ 385,883 Claim for extended Maintenance $ 49,324 Rejected change Order- Additional Natural PAVE costs $ 235,346 Rejected Change Order - Substitute walkway concrete $ 165,763 Subtotal = $ 1,250,322 $ 561,572 Prefered - Ceiling Finishes Rejected Change Order - Revisions to overhead linear grilles $ 122,236 Rejected Change Order - Linear wood over presentation wall $ 13,312 Subtotal = $ 135,548 $ 115,000 SME - Structural Steel and Misc. Metals Claim for extended General Conditions $ 1,083,101 Claim for Design Assist costs $ 718,359 Rejected Change Order - additional deck supports $ 76,018 Rejected Change Order - additional plating and tabs $ 80,911 Rejected Change Order - Revisions to conduit hole sizes $ 39,549 Rejected Change Order - Revised skylight supports $ 42,433 Subtotal = $ 2,040,371 $ 1,350,000 Superior Wall Systems - Framing & Drywall Claim for loss of production due to schedule changes $ 477,877 $ 80,000 Subtotal= $ 477,877 $ 80,000 Tower Glass- Exterior Curtain Wall Claim for extended General Conditions $ 3,139,769 Rejected Change Order - Clerestory window operator covers $ 81,921 Rejected Change Order - Custom mounting bolts $ 97,451 Subtotal = $ 3,319,141 $ - Total = $ 8,203,965 $ 2,481,572 Credit for construction contingency balance = $ 82,142 Total = $ 2,399,430 EXHIBIT B NATURALPAVE ASSIGNMENT AGREEMENT C.W. Driver, Inc. Page B -1 ASSIGNMENT AGREEMENT This Assignment Agreement ( "Assignment') is made as of February _, 2014 ( "Effective Date "), by and between Park West Landscape Inc., a California corporation, C.W. Driver, Inc., a California corporation (collectively "Assignors ") and the City of Newport Beach, a California municipal corporation and charter city ( "Assignee "). Assignors and Assignee are sometimes hereinafter individually referred to as a 'Party' and collectively as the "Parties ". RECITALS. A. As part of the work performed pursuant to its agreement with C.W. Driver, Inc., Park West entered into a contract with Blacktop Paving, Inc., to install NaturalPave material, manufactured by Soil Stabilization Products Company, Inc. ("SSPCo"), in walking paths at Assignee's Newport Beach Civic Center and Park Project. B. A. number of the NaturalPave walking paths are experiencing premature cracking and deterioration. C. Assignors desires to assign to Assignee any and all of their rights, title and interests that they have, or may have, which is related in any way to the NaturalPave material or installation thereof including, but not limited to, any contractual or other claims Assignors may have against SSPCo, Blacktop Paving, Inc., and any other person or entity that is connected in any way to the manufacture, production. or installation of the NaturalPave material at the Newport Beach Civic Center and Park Project. NOW, THEREFORE, for good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the Parties agree as follows: 1.0 The Recitals set forth above are incorporated into and made part of this Assignment. 2.0 Upon the Effective Date of this Assignment, Assignors assign to Assignee all of their rights, title and interests they have, or may have, that is related in any way to the NaturalPave material or installation thereof including, but not limited to, any contractual or other claims Assignors may have against SSPCo, Blacktop Paving, Inc., and any other person or entity that is connected in any to the manufacture, production or installation of the NaturalPave at the Newport Beach Civic Center and Park Project. Assignors also agree to cooperate with Assignee in the use or enforcement of this assignment and to take all steps necessary, including, but not limited to, the execution of future documents to effectuate this assignment and assist Assignee in the use or enforcement of the rights, title and interests. assigned herein. Assignors represent and warrant that they have not assigned, released or otherwise diminished the rights, title and interests they are assigning to Assignee in this Assignment. 3.0 Assignee hereby accepts the assignment of Assignors' rights, title and interests as set forth in Section 2.0 above. Assignee also releases Assignors from any claims it may have against them related to the NaturalPave material or installation. 4.0 This Assignment shall inure to the benefit of and be binding upon Assignors and Assignee and their respective heirs, executors, legal representatives, successors and assigns. If any provision of this Assignment or the application thereof to any person or circumstance shall be invalid or unenforceable to any extent, the remainder of this Assignment and the application of such provisions to other persons or circumstances shall not be affected and shall be enforced to the greatest extent by law. This Assignment shall be interpreted, construed, and enforced according to the laws of the State of California. This Assignment may be executed in any number of counterparts all of which taken together shall constitute one and the same instrument. 5.0 Each of the Parties is authorized to enter into this Assignment, and has taken all actions to authorize its officers to enter into it, as evidenced by their signatures below. [SIGNATURES ON FOLLOWING PAGES] Assignors and Assignee have executed this Assignment the day and year first above written. ASSIGNORS: Park West Landscape Inc., a California corporation By: Its: By: Its: C.W. Driver, Inc., a California corporation By: Its: By: Its: ASSIGNEE: City of Newport Beach, a California municipal corporation and charter city By: Name: Title: 3 ATTEST: Leilani I. Brown City Clerk APPROVED AS TO FORM: Aaron C. Harp City Attorney [END OF SIGNATURES] IH EXHIBIT C SAMPLE ASSIGNMENT AGREEMENT This Assignment Agreement ( "Assignment') is made as of , 2014 ( "Effective Date "), by and between ( "Assignors ") and the City of Newport Beach, a California municipal corporation and charter city ( "Assignee "). Assignors and Assignee are sometimes hereinafter individually referred to as a "Party" and collectively as the "Parties ". RECITALS. A. As part of the work performed pursuant to its agreement with C.W. Driver, Inc., performed the following work at Assignee's Newport Beach Civic Center and Park Project ( 'Project') B. As part of the work performed on the Project, may have experienced delays or extra costs attributable to C.W. Driver, Inc., Bohlin Cywinski Jackson ( "BCJ ") and /or the Assignee (collectively, "Project Parties "). C. Assignors desires to assign to Assignee any and all of their rights, title and interests that they have, or may have against the Project Parties, which is related in any way to the Project. NOW, THEREFORE, for good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the Parties agree as follows: 1.0 The Recitals set forth above are incorporated into and made part of this Assignment. 2.0 Upon the Effective Date of this Assignment, Assignors assign to Assignee all of their rights, title and interests they have, or may have, that is related in any way to the Project including, but not limited to, any contractual or other claims Assignors may have against the Project Parties, and any other person or entity that is connected in any way to the Project. Assignors also agree to cooperate with Assignee in the use or enforcement of this assignment and to take all steps necessary, including, but not limited to, the execution of future documents to effectuate this assignment and assist Assignee in the use or enforcement of the rights, title and interests assigned herein. Assignors represent and warrant that they have not assigned, released or otherwise diminished the rights, title and interests they are assigning to Assignee in this Assignment. 3.0 Assignee hereby accepts the assignment of Assignors' rights, title and interests as set forth in Section 2.0 above. 4.0 This Assignment shall inure to the benefit of and be binding upon Assignors and Assignee and their respective heirs, executors, legal representatives, successors and assigns. If any provision of this Assignment or the application thereof C.W. DRIVER, INC. Page 2 to any person or circumstance shall be invalid or unenforceable to any extent, the remainder of this Assignment and the application of such provisions to other persons or circumstances shall not be affected and shall be enforced to the greatest extent by law. This Assignment shall be interpreted, construed, and enforced according to the laws of the State of California. This Assignment may be executed in any number of counterparts all of which taken together shall constitute one and the same instrument. 5.0 Each of the Parties is authorized to enter into this Assignment, and has taken all actions to authorize its officers to enter into it, as evidenced by their signatures below. Assignors and Assignee have executed this Assignment the day and year first above written. ASSIGNORS: By: Its: By: Its: ASSIGNEE: Dave Kiff City Manager ATTEST: Leilani I. Brown City Clerk APPROVED AS TO FORM: Aaron C. Harp City Attorney [END OF SIGNATURES] C.W. DRIVER, INC. Page 3 AMENDMENT NO. TWO FOR GMP PHASE THREE (CIVIC CENTER BUILDING, CENTRAL LIBRARY EXPANSION & PARK) C.W. DRIVER FOR FOR NEWPORT BEACH CIVIC CENTER AND PARK THIS AMENDMENT NO. TWO FOR CONSTRUCTION MANAGER AT RISK CONTRACT ( "Amendment No. Two), is entered into as of this day of , 2011, by and between the CITY OF NEWPORT BEACH, a California Municipal Corporation ( "City "), and C.W. Driver, Inc., a California Corporation whose address is 15615 Alton Parkway, Suite 150, Irvine, California 92618 ( "CM "), and is made with reference to the following: RECITALS: A. On June 7, 2010, City and CM entered into a Construction Manager at Risk Contract ( "CM Contract ") for the Newport Beach Civic Center and Park Project ( "Project "). B. On September 3, 2010, City and CM entered into Change Order No. One to the CM Contract, as contemplated in the CM Contract, Article Six, Section 6.1.9(e), to add the Design Build 450 stall parking garage and to increase the Guaranteed Maximum Price ( °GMP "). C. City desires to enter into this Amendment No. Two to reflect additional services not included in the CM Contract or Change Order No. One, to add the construction of the City Hall Office Building, Central Library Expansion, Parks and miscellaneous items of work for the Newport Beach Civic Center and to increase the Guaranteed Maximum Price ( "GMP ") and to update the insurance provisions consistent with the City's election to implement an Owner Controlled Insurance Program ( "OCIP "). D. City and CM mutually desire to amend the agreement, as provided below. NOW, THEREFORE, it is mutually agreed by and between the undersigned parties as follows: 1. SCOPE OF WORK Article Two of the CM Contract shall be supplemented to include the Scope of Work dated February 16, 2011, which is attached hereto as Exhibit `1' and incorporated herein by referenced. The City may elect to delete certain tasks of the Scope of Services at its sole discretion. 2. COMPENSATION Article Six, Section 6.1.1 of the CM Contract shall be amended to increase the GMP to Eighty -Two Million, Three Hundred Seventy -Four Thousand, Three Hundred Eighty - Four Dollars and no /100 ($82,374,384.00). 3. INSURANCE Section 7.1 of the CM Contract shall be amended to include subpart (a) to read: (a) On February 22, 2011, the City Council elected to implement an OCIP consistent with this Section 7.1. The terms and obligations imposed on the City and CM as a result of this election are set forth in Exhibit 2, attached hereto and fully incorporated by this reference. 4. INTEGRATED CONTRACT Except as expressly modified herein, all other provisions, terms, and covenants set forth in the CM Contract and Change Order No. One shall remain unchanged and shall be in full force and effect. IN WITNESS WHEREOF, the parties hereto have executed this Amendment No. Two on the dates written below. APPROVED AS TO FORM: OFFICE OF THE CITY ATTORNEY Da By- Le Mulvihill Assistant City Attorney ATTEST: Date: By: Leilani I. Brown City Clerk CITY OF NEWPORT BEACH, A California municipal corporation By: Michael F. Henn Mayor CM: C.W. DRIVER, INC., a California Corporation Date: By: Dana Roberts President and Chief Executive Officer Date: By: Bessie Kouvara Chief Financial Officer Attachments: Exhibit 1 - Additional Services to be Performed Exhibit 2 - Owner Controlled Insurance Program Exhibit 1 C.W. Driver BUILDERS SINCE 1919 February 16, 2011 Mr. Stephen G. Badum City of Newport Beach 3300 Newport Blvd. Newport Beach, CA 92658 Re: Newport Beach Civic Center and Park Project Project Phase III GMP Dear Stephen, 15615 Alton Parkway Suite 150 Irvine, CA 92618 Fax 949.261.5167 Telephone 949.261.5100 C.W. Driver is pleased to submit our Guaranteed Maximum Price Proposal (GMP) for the Newport Civic Center and Park Project — Phase III. For clarification of our proposed services, please see the attached documents. The total proposal for these services is as follows: Item Description To al I Project Phase Ill GMP Scope of Work* $79,097,902 II Credit for Scope Reduction of Previous Phase I and II ($373,000) III Revised Subtotal $78,724,902 IV - Off -site Liability and Auto — (0.712%) $558,947 V Construction Management Fee (3.25%) $2,558,559 A Direct Expenses Allowance for Project Bond (0.65%) $531,975 TOTAL $82,374,384 "incmaes �onstrucnon tonungency PROJECT SCOPE: Phase III of the Newport Civic Center and Park Project consists of a certified LEED Silver 95,000sf two story office structure, a I7,000sf two story addition onto the existing Newport Beach Public Library, new dog park and associated improvements at the North Park (North of San Miguel), (3) pedestrian bridges, plantings, walk paths and gathering areas of various pavement types, benches and appurtenances at the Central Park, and various site improvements and landscaping surrounding the building structures at the South Park area. The GMP for this work is based upon the initial design identified in the 100% CD Set of Documents and Specification provided by Bohlin, Cywinski, Jackson (BCJ) dated November 4, 2010, subsequent issued Addendum #1, dated November 18, 2010 and Addendum #2, dated December 10, 2010 including pre -bid RFI responses #Prebid -0001 through #Prebid -0162 and Bulletin I dated January 20, 201 I. However, Prebid -RFI # -0137 is excluded from the GMP. Any changes made to the plans and specifications issued after these dates are specifically excluded from the project GMP. (Please see attached Exhibit A) In addition to the above scope of work, there are two alternates identified in the Phase III Design Documents: 1) Pedestrian Bridge over San Miguel .. ............................Add $ 2,000,000 2) Photovoltaic System for Civic Center Building ................Add $ 750,000 Los Angeles Irvine Ontario San Diego License No. 102 Both Alternates #1 and #2 are specifically excluded from the Phase III Project Scope of work and excluded from the GMP amount. Should the City of Newport Beach choose to add either of these alternates to the project, the Project GMP would increase by the amounts shown above. A list of Value Engineering (VE) suggestions that were approved by the City of Newport Beach for the Phase III scope of work has been attached for your reference. Those VE items already approved by the City (totaling have been identified ( "YES' in Accepted Column) in the attached `Value Engineering Log" and the costs are reflected in the final Phase III GMP proposal. As part of the Phase III GMP, CWD has included a list of Project Allowances for your reference. As stipulated in our Agreement, 100% of any allowance amount not used in the project will be returned to the Owner in its entirety. The allowances are identified in the attached "Scope and Pricing Sheets ". CWD will provide the Owner with a full accounting of the usage of these monies on a monthly, basis. As previously agreed to, the City has elected to use an Owner Controlled Insurance Program (OCIP) for both the Phase II and Phase III portion of the Project. The Phase III GMP proposal accounts for the use of this program on the project for all requirements as identified in the project draft OCIP Manual dated November 2, 2010 and the OCIP project safety manual dated December 7, 2010. Project Phase III Scope Qualifications and Exclusions: General Qualifications: a. Bg1ARUP to provide all CAD file backgrounds and 3D models necessary for this work. b. CWD to issue the City of Newport Beach (CNB) a completed 3D Revit model at project closeout as produced by CWD and their subcontractors during the construction coordination process. Training how to use the model is included. c. City of Newport Beach to contract with all artists providing work for the project including the Willow Structures identified on the Landscape Drawings. CWD has included an allowance of $100,000 in the GMP for this work as a place holder for the City that can be transferred out at a later date. d. CNB to pay for all Building Permits and inspections under City of Newport Beach jurisdiction. Individual trade permits as required in the specifications are included by CWD and their subcontractors. e. CNB to pay for all construction utility usage charges for project. CWD has not included any money in the GMP for these charges. f. CWD excludes all hazardous material removal including subsurface conditions not identified in the project soils report. g. In the case of conflicts between the floor plans and finish schedule, the finishes shown on the project finish schedule shall supersede and Is included in the GMP. h. CWD excludes temporary office or swing space for library staff during construction. Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 Page 2of9 i. rct. $r nu. iUz I, All labor and work hours for this work are based upon regular project working hours, Monday thru Friday and exclude overtime and shift work with the exception of after hours utility shut downs as required for the existing library. CWD_ includes- all - required_ recycling and_ recycling._ documentation -of construction waste in _ accordance with project LEED requirements. k. The Civic Center's target to obtain a LEED Silver rating is based upon the design prepared by the Project Architect, Bohlin, Cywinski, Jackson. CWD is reliant upon the project design to achieve this Silver LEED rating target. 1. CWD excludes demo, relocation and any work associated with relocating the City's existing ATM machine to the new City Hall project site. m. CWD includes all site dewatering and State required water quality provisions as defined in the project documents, SWPPP and erosion control, etc. for the project as part of this proposal for normal seasonal weather conditions. CWD has not included this scope for provisions for above average! normal rain fall or force majeure conditions as stated in our agreement. n. CWD excludes all project design and engineering for project except for those trades where it is specifically required by the project documents as defined as deferred approvals listed in item #6 of Sheet CS2. o. CWD includes coordination of work with the CNB's project consultants and General Services Department. p. CWD includes a project mock -up of the north park fence at the dog park. q. CWD has not included any project scope of work, costs or fees for attaining LEED certification for the existing library or library addition. Therefore, any additional work or fees associated with attaining any type of LEED certification for these areas is specifically excluded from this Phase III GMP Proposal. - r. CWD excludes all retro- commissioning scope of work beyond what is currently shown in the contract documents for the existing library and library addition. s. The Owner has selected an OCIP to be used on this project with AON being the OCIP Administrator. CWD will fill out and have our subcontractors fill out and submit the AON -f insurance form provided in the draft OCIP project manual dated November 2, 2010 as required to enroll in the program, however, AON will be responsible for verification of final enrollment in the program by the subcontractors on the project. CWD will help coordinate any efforts necessary with the CNB and AON. t. This Phase III GMP has taken into account the selected OCIP insurance program for this project and this proposal includes all of the total costs and final credits associated with this insurance program. Therefore, CWD and their subcontractors exclude any final cost adjustments to the project under this proposal at the closeout of the project as related to this type of insurance program. Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 _A r Page 3of9 LICU,N5LL N� 102 u. CWD will provide all specified work as shown including all required labor and equipment warranties, but does not guarantee or warranty the Engineer of Record's expected level of energy efficiency of the building or the expected functionality of any of the building systems. This is the responsibility of the project Engineer of Record. v. CNB to provide a separate Commissioning Agent to commission the project. w. CWD specifically excludes removal, protection, transportation and installation of all wall pictures, picture hangers, etc. as identified as OFCI items in the contract documents. x. CWD will provide the City with all required warranties and guarantees as required by the Contract Documents unless otherwise qualified in this letter, however, please be informed that since the library addition and Civic Center will have separate completion and project turn over dates, that the warrantees and guarantees for each part of the project will start at the project Owner Occupancy date for each individual project structure respectively. y. In addition to the Scope of Work in the Phase III GMP, CWD is also performing the utility relocation scope of work for the chilled water lines at the backside of the existing library as follows. This work is being paid for out of Phase I contingency and therefore, not reflected in the Project Phase III GMP costs: (I) Relocation of the existing two (2) inch gas line that services the hot water boiler system. This line will be re- routed through the existing library space, down to the basement level to the existing airway where the new high efficient boiler will be located. (2) Furnish and install a new 96% high efficiency boiler (1.7MBTU /H) complete with all required housekeeping pads, vent flues, piping, and new electrical power to new boiler location. (3) Cut and cap of existing hot and cold water lines. (Removal of lines by Phase III Grading / Demo Subcontractor) (4) Cut and cap of existing gas service to library building. (Removal of lines by Phase III Grading / Demo Subcontractor) (5) Cutting and temporary patching of existing AC paving (hot patch) between library and existing utility yard. (6) Safe -off and removal of two (2) existing exterior light poles to be turned over to Owner for storage. (7) Flushing, testing and commissioning of the systems modified by this work. (8) Owner's manuals and as -built documents to be turned over to the Owner at project completion for this scope of work. (9) (1) year Contractor's warranty in addition to equipment manufacturer's warranty for new equipment. II. Trade Specific Qualifications 002.1 — Site Utilities a. CWD includes an allowance of $17,000 for slope anchors not shown in the specifications, but typically required by code. Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 Page 4 of 9 r LICFNSP: No. 1.2 002.2 — Demolition a. CWD includes all temporary safety barricades and associated signage for public safety. 002.3 — Site Concrete a. CWD has the water specified in_ contract documents for any horizontal surfaces or curbs. The architect informed CWD that this scope was not required in these areas. 002.4 — Landscape and Irrigation a. CWD excludes the Willow Structures as shown on the contract documents and all associated labor and equipment related to the building of these structures by the chosen artist. (see allowances) b. Bq /PWP to locate and source all specimen trees for project to verify their availability in the market for the quantities shown on the project documents including Torrey Pines and Magnolia trees. 002.6 — Finish Grading a. Finish grade of landscaped areas will be within +/- 0.10' of indicated grade vs. the tolerances identified per the specifications. 003.1 — Structural Concrete / Rebar a. Exposed elements of structural concrete that are required to be integrally colored concrete will be formed and poured separately to minimize the amount of colored concrete required. This may require the addition of concrete construction joints not shown by the plans. 003.2 — Soil Anchors a. There is no specification or design performance criteria provided for drilled caissons at the landscape bridges. All caissons are assumed to be 24" diameter x 20' depth, with reinforcing as indicated in detail I O/S6.35. Concrete mix is assumed to be Type A per Concrete plan note 3 on sheet S0.2 004.2 — Stone Veneer / Stone Pavers a. Stone veneer on the face of radiused walls is assumed to be straight and segmented. GMP does not include curved stone. b. GMP pricing is based upon specified stone material and not necessarily from the named supplier. c. Cast stone steps at the library central stairway are assumed to be selected from manufacturer's standard product line. 005.1 — Structural Steel / Misc. Metals a. CWD excludes costs for any required out of state welding inspection b. Elevator pit ladders are excluded from the GMP, there are none shown on the documents and we have been informed that they are not required. 006.2 — Finish Carpentry and Millwork a. Premium corian surface material included, selection still to be made by project architect b. 9Wood material at council chambers to be segmented panels, not curved at radius wall. Material specified in documents cannot be made curved. c Lentech privacy panels will be mounted to the structural slab, not to the access floor as indicated. Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 Page 5 of 9 (]W) L. ICFN5L. N.,101 007.1 — Waterproofing a. The GMP includes scope of work to re- waterproof the North elevation of the existing library basement wall as identified in the contract documents. However, since the contract documents do require exposing and re- waterproofing ALL of the basement walls, CWD does not guarantee against water intrusion into the library existing basement area b. The GMP excludes damp proofing along stone walls and precast stair treads directly in contact with soil or aggregate mulch. 007.2 — Roofing a. According to the manufacturer, Deter roof leak detection system can only be installed within roof assemblies that are directly adhered to a concrete roof slab, therefore, CWD can only provide the Detec roof leak detection system under these conditions. b. CWD includes a standard two (2) year installation labor warranty and a twenty (20) year standard manufacturer's limited warranty against material defects in lieu of the specified ten (10) year comprehensive warranty for the specified roofing system. c. The GMP includes use a value engineering alternate to utilize polyisocyanurate roofing insulation in lieu of the specified extruded polystyrene 008.3 — Storefront / Glass & Glazing a.. The GMP includes supply the specified Shuco operable window operators, to be installed in the approved curtain wall system. b. The GMP includes supply and installation of Shuco exterior curtain wall and storefront components, with engineering and fabrication by Tower Glass. c. It is assumed that the building structure, as indicated by the structural plans and details, has been designed to withstand imposed loads from the exterior curtain wall. Curtain wall indicated to attach to the underside of the metal roof decking will be through - bolted to the decking and backed with plate washers. No other deck reinforcement has been included. d. CWD to protect in place top row of windows along North elevation of existing library where new addition is to be constructed. e. The GMP includes an allowance of $134,000 for removal and reinstallation of glazing at library curtain wall at North elevation as indicated in the contract documents. 009.1 — Drywall, Lath & Plaster a. CWD to provide a Level V finish at all walls to receive paint finish in the Civic Center Building in lieu of the specified Level IV finish shown in the contract documents. 009.3 — Ceramic Tile a. Specified Floor Tile CT — 2, "Porcealto" is no longer available in 8'x8" size. CWD including same tile in a 12"x 12" size. b. Specified Floor Tile CT — 3 & CT — 4 shown in the library bathrooms is not specified in the finish schedule or specifications. CWD has included a $3.00 /sf material allowance for tile in these areas. c. CWD includes standard cementitious grouts and setting beds. All epoxy and latex products have been excluded unless specifically shown on documents. d. Y -0" wainscot of 2x8" specified tile at Civic Center Rooms 1505, 1506. I50B, and 2258 will be provided. e. The contract documents do not define a specific tile pattern /layout. Therefore, the GMP assumes all the is installed in a square grid at 90 degrees to wall/floor lines. Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 Page 6 of 9 .f L ICX NSM Nn. I U 2 009.6 — Floor Coverings a. Section 096816 — Tile Carpeting: CPT — 4 & CPT -5 are not specified, so CPT -I is assumed at these areas. b. Standard carpet tile to be used to replace all carpet removed during construction of library remodel. Only carpet removed in library as shown on demo plan of library drawings. c. Only Static Control Resilient Flooring per specification section 09 65 36 will be factory installed on access floor panels. All other floor coverings on access flooring will be installed at the jobsite after installation of access floor system. d. CWD excludes special moisture testing beyond what is identified in the contract documents or any special concrete sealers required to mitigate excessive moisture in the building slab on grade. 010.3 — Signage & Graphics a. There is currently no signage shown on the contract documents. Per our discussions with Bq, there will be a project signage package developed later in the project. Therefore all signage and graphics are currently excluded from the GMP. - 012.1 — Roller Shades b. In the event of conflict between Architectural details and the Electrical shade plans on E2.12 and E2.13 regarding quantities of motorized vs. manual shades, the electrical shade plans shall take precedence. c. Roller shades are excluded in the clearstory windows of the Civic Center as per the contract documents. d. GMP price includes standard quality blackout fabric only for the blackout shades. 012.2 — Theatrical Seating a. The City and the Architect have indicated a desire that the fixed audience seating in the council chamber be provided with a premium upholstery material in order to assure longevity and wearablity over the life of the facility, however the final material selection was not available prior to completion of the GMP. CWD has therefore included an allowance of $50,000 in the Project Phase III GMP proposal for this material upgrade. 013.1 — Tensioned Fabric Structures a. The GMP includes cost for a double layer of the specified fabric material, with offset radio welded seams in order to mitigate visual seams. 014.1 — Elevators a. GMP includes cost to supply Otis Gen2L elevators. 0 15. 1 — Fire Protection a. The GMP price excludes a rapid reaction fire sprinkler system for IDF, Computer Rooms, Command Center, etc. b. The GMP price excludes fire sprinklers under all raised floor areas c. The GMP price excludes fire sprinklers at sail feature d. Copper pipe is only included on the second floor of the Civic Center where the pipe is curved to match the radius of the building ceiling and in ceiling areas open'to public view. e. Every attempt to match the sprinkler head placement as shown on the architectural plans will be made, however, final sprinkler head count, placement and spacing to be determined by the fire department and local jurisdictional governing entities. Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 - Page 7 of 9 L IC P: NS P: No. 102 015.3 — HVAC a. The blowdown tank indicated in detail 3/MS.04 is assumed to be an old detail that is no longer applicable for this project and therefore, this work is excluded in the GMP. b. The GMP includes minor rework of existing HVAC system in the library ONLY where the ducts and mechanical equipment in the ceiling conflicts with the temporary . construction . safety barrier... _. The drawings do not clearly show how the controls are relocated or connected during construction and therefore, this scope (if required) has been excluded from the GMP. c. The GMP specifically excludes all air testing and balance of both the existing library building and new addition. This work will be re- evaluated, and if necessary, priced once the City receives the retro- commissioning report from their Project Commissioning Agent. 016.1 — Electrical a. The GMP includes all specified low voltage scope of work and manufacturers as indicated in the contract documents. b. The GMP excludes utility relocation scope of work at library for existing library main power and for the Civic Center Building. c. The project documents do not show any type of book security system in the new library addition. The GMP includes an allowance of $10,000 in the Project Phase III GMP for this scope of work. Phase III GMP Proposal Standard Exclusions: I. Monthly site and office utility usage costs 2. Project night watchman 3. Materials, soils testing and inspection 4. Out of State / Area inspection and premium costs 5. Shuttle services for trades and temporary parking costs 6. Unknown subsurface conditions 7. Building permit and plan check fees 8. All utility company, connection fees and usage costs 9. Subsequent construction phases or added scope of work not addressed in this proposal 10. Independent Labor Compliance Consultant 11. Relocation of low voltage fiber optic line along Avocado Avenue 12. Scope changes requested by others 13. Temporary access roads for emergency use vehicles 14. Construction of exterior conduit and piping utility chases not specifically shown on the contract documents. 15. Installation of electrical lines under the slab of the existing library. (Item 927c. of CWD's Phase III GMP Proposal excepted where an allowance has been provided) 16. Temporary Emergency generators, associated infrastructure and appurtenances Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 - Page 8 of 9 LICENSE No. 102 17. Cost of providing a Builder's Risk Insurance policy to cover 100% of all work being performed. The City shall obtain, pay for and maintain a policy until CWD has been fully paid including retention. The plicy shall also have an insurance deductible not to exceed $25,000 per occurrence. - Please note that we are committed to the total success of this project and look forward to continuing our relationship with the City of Newport Beach and the Design Team. Please feel free to call, should you have any questions. Sincerely, Bruce Curry Project Executive cc: William Hahn, CWD Robert Shafer, CWD Andy Feth, CWD David Edwards, CWD Rimma Gumik, CWD Attachments Include: • Phase III GMP Summary • Phase III GMP Scope and Pricing Sheets • Phase III GMP Value Engineering Log • Summary of Allowances • List of Phase III — Exhibit "A" Contract Document Listing • Trade Package Summary — Scope Analysis • Summary Project Schedule • Subcontractor Bid Day Submissions (Separate Binder) Newport Beach Civic Center and Park Project Phase III Guaranteed Maximum Price (GMP) February 4, 2011 Page 9 of 9 LICEN�1: Na i0' C W* Driver SOLDERS SINCE 1919 PHASE 3 GMP C. W. DRIVER OV16111 Printed: I&Fe111 Dare Prepared: 16- Feb -II Estimate No.: #87101 Square Feet 122,295 Months On -Site: 25.0 Includes Addenda: N/A Estimato, am, ay lirva Bid package * No. Description Seq Description Notes Phase III * I Project Statistics 2 Allowances 678,475 3 Sustainable Design Requirements In Soft Costs _ 4 General Commissioning Requirements By owner 5 Hazardous Materials Mitigation In Soft Costs 6 Survey hrn 305,230 7 Site Specific Requirements 327,096 8 Temp. Barricades & Chain link Fencing 202,681 9 Security In Soft Casts 10 Temp Facilities and Controls 93,110 11 Construction & Final Clean -Up 326,395 12 Tests and Inspection In Soft Costs - 13 Demonstration and training with allowances 002.2 Demolition - 14 Selective Structure Demolition 263,725 IS Construction Waste Management and Disposal 39,124 002.6 Finish Grading 16 Site Clearing/Site and Fine Grading 1,349,825 17 Temp Dewatering 51,097 18 Temp Earth Support 81,081 003.2 sell Anchors 19 Ground Anchors 554,800 20 Erosion Control 161,321 002.5 Ac Paving 21 Asphalt Concrete Pavement 226,227 22 Striping and Pavement Markings with AC paving 004.2 Stone veneer and Pavers 23 Sand -set Stone Paving With Stone veneer and pavers 24 Mortar -set Precast Concrete Unit Slab Pavers With Stone 25 FRP Structural Shapes /fencing for phase 114 with wades 002.3 site concrete 26 Concrete Paving 2,972,443 002.1 site utilities 27 Underground Utilities 903,998 28 Natural Gas Distribution with site utilities 29 Storm Drainage Piping phase I and for phase III with site utilities 30 Landscape Sub- drainage with landscape 31 Sub. drainage With Underground utilities 32 Willow Sculptures With Allowances 33 Site Furnishings 531,826 002.4 Landscape & Irrigation 34 Landscape and Irrigation 4,816,892 35 Concrete Reinforcement - Structural with Cast in place concrete - Structural 36 Concrete Reinforcing- Civil with Site concrete 003.1 structural concrete 37 Cast -in -place Concrete - .Structural 4,280,568 TBD 38 Landscape Cast -in -place Concrete Site Walls PACE 1 CWa Driver Newport Beach Civic Center d P k BUILDERS SINCE 1019 PHASE 3 GMP C. W. DRIVER ESTIMATE SUMMARY 02/16/11 Printed: 16- Feb -II Date Prepared: I6- Feb -I I Estimate No.: #87101 Square Feet 122,295 Months On -Site: 25.0 Includes Addenda: N/A Estirsul eoa,ay Tr,vx * No. Bid package Description Seq Description Notes Phase 111 41 Mortar -Set Precast Concrete Units with Stone Veneer and paving 000.1 Masonry and brick pavers 42 Site Concrete Unit Masonry Walls- Landscape, Brick Pavers, Brick Floors 1,236,938 000.2 stone Veneer and pavers 43 Exterior Stone Cladding and Paving 3,626,717 44 Stone Tiling with exterior stone 006.1 Structural Steel 45 Structural Steel 8,414,696 0052 Metal Deck 46 Metal Decking 588,456 005.3 Miscellaneous &Ornamental Metals 47 Metal Fabrications 2,131,648 48 Decorative Metal and Glass Railings 49 Flagpoles with muc metals 006.1 Rough Carpentry 50 Rough Carpentry 678,407 008.1 Reugh,carpentry 51 Interior Architectural Woodwork doors paneling privacy ,artitinn5 1,984,450 52 Mockup 75,000 007.1 waterproofing 53 Water proofing Site Damp proofing/ 881,373 007.4 evading mseleuon - 54 Thermal Insulation under slab building insulation is moved to concrete 271,086 ' 009.1 Drywall. Lech Sr Plaster 55 Fireproofing with drywall 56 Penetration Firestopping 38,589 007.3 Sheet Metal 57 Architectural Metal Fladock Panels with sheet metal 008.3 Curtain Wall 58 Architectural Metal Panels with curtain wall 59 Concrete Sealer 124,019 007.2 Roofing 60 Polyvinyl- chloride(PVC) Roofing 1,298,305 0073 Sheet Metal 61 Sheet Metal Flashing and Trim 1,173,627 62 Roof Accessories 63 Expansion Control 62,998 008.5 skylights 64 Sloped Glazing Assemblies IIS,I85 65 Joint Sealants 180,871 008.1 Doors, Frames & Hardware 66 Hollow Metal Doors and Frames Card entry; fire doors 608,295 67 Sound Control Door Assemblies with doors 006.1 Rough Carpentry 68 Sliding Aluminum -Gamed Glass Doors - with aluminum curtain wall 008.2 overhead coning Doors 69 Overhead Coiling Grilles 82,654 70 Smoke Guards with allowances 008.3 curtain wan 71 Aluminum- framed Entrances and Storefronts/ Glazed Aluminum Curtain Walls 7,310,000 72 Aluminum Windows with curtain wall 009.1 Drywall, Lath &Plaster 73 Gypsum Board 2,784,963 PAGE 2 G*W. Driver BUILDERS SI>CiE 1919 PHASE 3 (SHIP C. W. DRIVER 02/16/11 Printed: 16- Feb -II Dale Prepared: 16- Feb -11 Estimate No.: #87101 Square Feel 122,295 Months On -Site: 25.0 Includes Addenda: N/A EsGmatc, POS. M. Tr.VB * No. Bid package Description Seq Description Notes Phase III 74 Access Doors & Frames 43,548 009.2 Ceramic Tile 75 Ceramic Tiling 219,340 009.3 Acoustical ceilings 76 Acoustical Panel Ceilings and Wood ceilings 2,253,796 009.4 Acoustical wall a ceiling Panels 77 Stretched Fabric Ceiling Systems 409,669 009.5 Floor coverings 78 Flooring 376,851 009.9 Terra— 79 Resinous Matrix Terrazzo Flooring 13,200 009.6 Access Flooring 80 Access Floor 1,201,823 009.7 Painting 81 Painting 675,165 010.1 Tenet Partidonsa Accessories 82 Toilet Compartments 85,130 Buy-out 83 Louvers & Vents with sheet metal _ 84 Wall and Door Protection 8,587 85 Visual Display Surfaces 18,542 86 Signage with allowances ........ ...._........ 87 ............. 88 Metal Lockers _.. _.... _.. Fire Extinguishers ._........ 14,510 .. __ 7,299 _. _.. .. ............. ............ 89 Projection Screens and Projector Mounts 38,425 90 FF & E with sof, costs 011.1' Food service equipment 91 Food Service Equipment 121,970 92 Residential Appliances 21,425 012.1 wmdew treatments 93 94 Artwork Roller Window Shades soft costs and allowances 181,000 95 Entrance Floor Mats and Frames 28,198 012.2 Theater Scaling 96 Fixed Audience Seating 214,360 013.1 Tensioned Fabric strecrures 97 Tensioned Fabric Structures -Sail 314,831 98 Photovoltaic System alternate 99 Material Handling Carts 50,690 014.1 Ele.arors 100 Electric Traction Elevators 246,444 015.1 Fire Promedon 101 Fire Protection 672,397 015.2 Plumbing 102 Plumbing 1,066,253 015.3 HVAC 103 HVAC 7,026,176 016.1 Electrical 104 Electrical '9,626,197 105 Audiovisual Systems with electrical 106 IT with Electrical 107 Electronic Safety And Security with electrical 108 Alternates 109 Photographic Documentation 24,062 # # 110 End Cal Listing �^-ed of imxmn. oo w� ode..• SUBTOTAL 76,794,080 PAGE 3 C.WDriver N,,p,ft Beach C*a*, Ceturtsibir and Park 11CILDERS SINCE 1919 PHASE 3 GNP C. W. DRIVER ESTIMATE SUMMARY OVI&I I Printed: I 6-Feb. I I Dam Prepared: 16-Fe" I Estimate No, 987101 Square Feet 122,295 Months Off-Sim, 2S.0 Includes Addenda: N/A Estimator, .., po ri'Xit No. Bid peatkage, Description Seq Description Notes Phase III III Construction Contingenq 3.00% 2,303,822 # # 112 Design confrgand, # # 113 Escalation- market condixfors # # 114 Credit for phase (373.000) at # 115 Sub Bonds # # 116 Preconstruction Pi # 117 General Conditions (7,169,255) # ft JIB 119 Permits & Special Insur, ...... ... .. . .................... ......... ............ ... ... ... Data Protesting .. ...... ....... ... - ........ 4 # 120 Off site Liability and Auto insurance 0.71% 558,947 # # 121 On Site Liability miammes, 0.20% by Owner # # 122 O.erhoad & Fee 3.25% 2,558,559 123 PHorne Bond 0,65% 531,976 1 Total Estimate 82,374,384 PAGE 4 Ca Driver Newport Beach Center and Park Newport Beach. GA BLILDERS .SINCE, 1919 nl ". LI uu IuxrP or�m, 16- Feb-11 kW 101 PAGE 1 02116/11 16- Febrll Budget# Description /Scope of Work Quantity Unit CosdUnit Total 01 ,�x0 00 213,112 100% CDdrawings issued on November4, 2010, Addendal,2 and bulletin I Exclusions and qualifications -under separate cover City Hall Lower level 11,653.0 sgft First floor 39.234.0 sgft Second floor 38.776.0 sqh Balcony 960.0 sqh Bridge 152.0 sqh Roof 66,285.0 sqh Total hall area including I/2 area of balcony and bridge Community room First floor 4,860.0 sqh Second floor 2,317.0 sqh Roof 16,437.0 sqh Chambers First floor 5,816.0 sqh Slanted roof 6.201.0 sqh Library Lower level 3,494.0 sqh Frst floor 9,198.0 sqh Second floor 9,118.0 sqh Lower Roof 5.605.0 sqh Upper roof 6.862.0 sqh South Park 232,961.0 sqk Central Park 244,008.0 sqh - Indudingwedands 74,020.0 sqh North Park 142,109.0 sqh Subtotal for parks 619,078.0 sqk Alternates t ' Grand Total Project Statistics MIMOI ..,..._..d_3. ✓�� : p'- 71I."E.I ��""'I iii.M W n::Ii liUNN PAGE 1 ���� 111MIDRRS SINCE: 1959 Newnurt Beach civ' 03116111 r Center and Park Newport Beach. CA SCOPE AND PRICING SHEETS 75.000 .nwi v ew: u,". I. I&Feb -II M7101 16- Feb-II 25,00000 25.000 Library windows- degine, -re -glaze 1.0 Isum 134.000.00 134.000 Budgeal 1.0 Isum Description/Scope oFWerk Quantity Unit CosdUnit Total Owner specified Doan 1.0 each 110,000.00 110,000 ' Owner specified Doors 2.0 each 75,000.00 150,000 Owner spcalled Steel Beam penetrations 30.0 each 1,20D.00 36,000 Owner specified Touch up paint 1.0 Isum 10,000.00 10,000 017900 Facilitator !Training company 1.0 Isum 25,000.00 25,000 01 7900 Instructor by trades 017900 Professional Videographer 240.0 mnhr 100.00 24,000 31680 Adverse conditions / rock drilling for tie 225.0 Ink 9100 20,475 Willow sculpture designed and installed by Patrick Dougherty.7 pieces in each sculpture 1.0 allow 75,000.00 75.000 CWD support for the willow, art installation 1.0 allow 25,00000 25.000 Library windows- degine, -re -glaze 1.0 Isum 134.000.00 134.000 Premium Upholstery 1.0 Isum 50.000.00 50000 Library Secutlry Sensors 1.0 allow 10,000.00 10,000 678.475 ' Grand Total Allowances 678,475 I In soh costs In soft costs I Alternates Grand Total Sustainable Desien Reauirements cows Grand Total General Commissionine Reauirements PAGE 2 \.rle l lW TirlV�r Newen —rt -Beach Civic Center and Park nisi. ...111.. Newport Beach CA n,' 16 -Febd I 8t11LDPA88INCE 1519 W7101 PAGE 3 OU16111 16 -Feb�I I BudgeUl DescrfptiosdScope of Work Quantity Unit Cost/Unit Total in soft costs, if required • Aleem °egs Grand Total Hazardous Materials Mitigation Phase 111 Layout for foundations 30.0 cwhr 215.00 6,450 Layout building utilities connections to site utilities 10.0 cwhr 215.00 2,150 Provide vertical and horizontal control of building structure 40.0 cwhr 215.00 8,600 Provide as -built drawings 1.0 Isum 5,000 5.000 Community room Layout for foundations 8.0 cwhr 215.00 1,720 Layout budding utilities connections to site utilitiu 2.0 cwhr 215.00 430 Provide vertical and horizontal control of building structure 8.0 cwhr 215.00 1,720 Provide as -built drawings 1.0 Isum 1,000 1,000 Chambers Layout for foundations 8.0 cwhr 215.00 1,720 Layout building utilities connections to site utilities 2.0 cwhr 215.00 430 Pronde venial and horizontal control of building structure ' 8.0 cwhr 215.00 1,720 Provide as -built drawings 1.0 [sum 1,000 1,000 Library Layout for demolition 20.0 cwhr 21 SAO 4,300 Layout for foundations 40.0 cwhr 215.00 8,600 Layout building utilities connections to site utdmiss 16.0 cwhr 21100 3,440 Provide vertical and horizontal control of building structure 4.0 cwhr 215.00 860 Provide as -built drawings 1.0 Isum 3,500.00 3,500 South Park Layout limits of work 40.0 cwhr 215.00 8.600 PAGE 3 �� NeMod Heath Chit Center and Park - �¢i Lldll lnuh Newport Beach CA 16- Feb -11 Bn11.138RS SINCE 1919 ka1101 02/16/11 bFeb 1l PAGE 4 Budget# UescripdoNScope of Work Quantity Unit Cost/Unit Total Layout demolidon 20.0 cwhr 215.00 4,300 Rough grade staking 80.0 cwhr 215.00 17,200 Layout over exavation I engineered fill limits 20.0 cwhr 215.00 4,300 Site utilities staking 120.0 cwhr 215.00 25,800 Layout fine grading 40.0 cwhr 215.00 8,600 Layout site concrete 20.0 cwhr 215.00 4,300 Layout AC paving 20.0 cwhr 215.00 4,300 Layout landscaping 20.0 cwhr 215.00 4,300 Layout site walls and fencing 40.0 cwhr 215.00 8.600 Provide as -built drawings LO ]sum 4,500.00 4,500 Central Park Layout limits of work 40.0 cwhr 215.00 8,600 Layout demolition 8.0 cwhr 215.00 1.720 Rough Grade staking 40.0 twhr 215.00 8,600 Site utilities staking 20.0 cwhr 215.00 4,300 Layout fine grading 80.0 cwhr 215.00 17,200 Layoutsitewalks 30.0 cwhr 215.00 6,450 Layout landscaping 40.0 cwhr .215.00 8,600 Layout site walls and fencing / bridges/ piles 120.0 cwhr 215.00 25,800 Provide as -built drawings 1.0 Isum 3,000.0 3,000 North Park Layout limits ofwork 20.0 cwhr 215.00 4,300 Layout demolition 8.0 cwhr 215.00 1,720 Rough grade staWng 80.0 cwhr 215.00 17,200 Site utilities staking 4.0 cwhr 215.00 660 Layout fine grading 80.0 cwhr 215.00 17,200 Layout site concrete 16.0 cwhr 215.00 3.490 Layout landscaping 40.0 cwhr 215.00 8.600 Layout site walls and fencing! bridge 80.0 cwhr 215.00 17.200 - Prance as -built drawings 1.0 Isum 3.000.00 3,000 305,230 Aft. on. Grand Total Survey 305,230 01 s0 00 a -C n. Phase 111 Protect openings 22.0 month 1.340]4 29.496 Forkiik 22.0 moth 2.700.00 59,400 Skip loader 22.0 moth 2.400.00 52,800 Rental squiphnols 1.0 ]sum 8.50000 8,500 Equipment repair LO Isum 5.500.00 51500 Gasoline and oil 22.0 moth I,IOD.00 24,200 PAGE 4 Newoort fle,rh Civic Cenmr and Park GWDrivef AV st, I I'D K RS SINCE 1419 DVI6III n—m .1.11 rucerl 16- Feb-II M7101 16- Feb-II PAGE 5 Budget# Description/Scope of Work Quantity Unit Co$Wnit Total Rumble planes 1.0 hus. 145,000.00 145,OW Remove, own store and Install owner existing loans follows - City Seal 1.0 Isom 1,000.00 1,00 City plaques 1.0 loun 1.200.00 1.200 Im Santa for trees 1.0 moth with landscape Arouk, services 9.0 moth with landscape 327.096 Aftesaetet Grand Total Site Specific Requirements 327.096 Phase III Relocate/ niunciam as needed to., them link with 'Co. 6,68E0 Infit 2.00 13,360 Library follows Temporary barricades - metal studs firaming. Upbeard both sides, paint ( 2 ai 480.0 Inft 165.00 79,200 Temp barricades outside 24.0 week 3.11 LEE 74,6" Dust partitions at the librea, 2.000.0 sqft 4.0 I'M Temp wood fencing 300.0 kft 3100 9.900 Instill remove temp filters at the HVAC 1.0 Nam EOWLM 8.000 Protect new boilers 1.0 Is.. 765.00 765 South Park Relocate/ maintain as needed temp chain link with scrips 1.600.0 Inift 1.12 1792 Central Park Relocate/ maintain as needed temp chain link with scrim I.250.0 Init 1.12 1,400 Additional protection at sensitive areas 350.0 Ink 12.00 4,200 North Park Relocate/ maintain as needed temp chain link with scrim 1.250.0 Iaft 1.12 1.400 202,681 Alternates Grand Total Temp. Barricades & Chain link Fencing 202.681 01 SID 00 by Owner In soft costs PAGE 5 hl�oapodr Reach Civic Center and Park Maiver Ninall Reach CA Bt HIDERS SINCB 1919 MveR .1.11 imi e, 16-FeW 1 #6101 PAGE 6 Budgetg Desearlptick./St.p. of W.rk, Quantity Unit CoWUnpt Tend Aftr.Pt, Grand Total Security Phase III Mat/equip protection 1.0 lsum 12,500.00 12,500 Temp utilities hook up 1.0 Isom 40,000.00 40,000 Library Maintain HVACm operations dud, the 2.0 moth remodeling 12,555.00 25,110 Tenn,unifitiesh..k.p.tthelibmary 1.0 Isum 3,500.00 3,500 Vermin control services LO Isum 12,000.00 12000 93.110 AltSmatst Ems= Grand Total Temp Facilities and Controls 93,110 moral �'Mffw- Phase II Continuous clean up and support 22.0 monk 7,398.73 162.772 Final clean up -city hall, 80,0 mnhr 62.15 49.717 Fiml clean up- community room. Nab runt, 6115 12.429 Final clean up- Chambers 7000 mnhr 62.15 12,429 Final clean up at the library 10 Is.. 28,830.00 28,830 Glass dean up 400.0 ..h, 62.15 24,859 South Park Final clean up 102.0 mnhr 62.13 6,339 Central Park Final clean up 80.0 mnhr 62.13 4.9]2 North Park Final clean up 120.0 mnhr 62,15 7,458 Parking garage clean up Periodically 6.0 month 1455 00 8.730 Parking garage final clean up 1.0 month 7,860.00 7,860 PAGE 6 Nwnrc ll ah Civic Center and Park LI41. l].I J W �� NMpaq Beach CA � I: I&Feb -II BUILDERS SINCE 1919 %111101 OW16111 1641,II PAGE 7 PAGE 8 a1 M1.Vl�V1l1 801i.DRRS SINCE MO Newport Beach OW16111 Civic Center and Path Newport Beach CA SCOPE AND PRICING SHEETS eimM: emxA: - vim Iiln Tl 16 -FeGll 487101 16- Feb -II Budget# Description/Scope of Work Quantity Unit CosdUnit Total Imentery and Remove furniture by owner Transport to the owner selected location and Store 40.0 mnhr 62.15 2,486 Transport back, clean reinstall 40.0 mnhr 62.15 2,486 Waste management 40.0 each 475.00 19,000 Scaffold at stairs 8.0 month 425.00 3,400 Temporary, doors at the 2nd floor for the exit - head Iremove 2.0 each 1,455.00 2.910 Site Clearing Clear and dispose of site vegetation at library : Clear and dispose of concrete at library area Remove A.C. paving at library Remove utilities to be relocated Protect existing utilities and trees as noted I.0 Isum 7,500.00 7,500 Demo of electrical vaulta 3.0 each 3,501 10,500 Additional Moves in 4.0 each 2,777.00 11,108 263,T15 Ahemae ' Grand Total Selective Structure Demolition 263,725 01 74'19 Phase III Extra labor to sort through duration of the Project 1,6480 mnhr 23.74 39,124 39,124 Aftivinams Grand Total Construction Waste Management. and D 39.124 31 0000 0241 13 Selective Site Demo 015639 Tree protection Phase 111 - Sub contractor proposal 1.0 Isum 1,286,000.00 1.286.000 Mobiliadon Fine grade Wall trim as needed for walls at basement level at Phase III Backfill exterior walls only with onsita footing spoils Concrete spoils haul o0 PAGE 8 GW. Driver Beach CIA, Center and Park a Y Y Newport Beuh. CA BUILDERS "NCH 1019 03116111 Iwo-. vimliamm om1 16 -111 AB71ol 16- Feb-II PAGE Budget# DescriptioNScope of Work Quantity Unit CostlUnit Total Street sweeper Library Site Clearing Clear and dispose of site vegetation at Of.,,: with demo Clear and dispose of concrete at library area with demo Remove A.C. paving at library with demo Remove utilities to be reloated with demo Protect existing utilities and trees as noted with demo Demo of electrical vaults with demo Moves in - withdemo Place and compact (2) topsoil over landscape areas Cut back for retaining walls Backfill for the temporary retaining basin 11.750.0 sgft 3.00 35,250 Backfill exterior walls only with onsite footing spoils 364.8 cuyd 16.0 5.837 Concrete spoils haul off Street sweeper South Park Grading Grade for curbs, gutters and flow lines associated with vehicle paving Grading for walkway paths Grading of landsape areas with 2 it of topsoil Cut curb grade for "A" curb along proposed walks Rough Bade to + / -.I 'for pavement and hardsape areas fine grade at swales Street sweeper Backfill landscape areas with of topsoil from designated onsite piles Re-gade landscape areas after topsoil - phci mend Allow for (5) mobilinations Central Park Grading of slopes. Backfill landscape areas with of topsoil from designated onsite piles Re -grade landsape areas after topsoil placement Import from onsite topsoil stockpiles to fast Middle park Place and compact (2) from onsite topsoil over BnnefWast Middle Park Areas Rough grading of slopes and landscape areas to allow underground contractor w install storm drain PAGE C.W. Driver Newport Beach Civic Center and Park Newport eaa._n. co RVILt1RRS S"CR 1919 OW16111 R�d�i�k>ea, areaw: I&Feb -I I 07101 16- Feb-II PAGE 10 Budget# Description /Scope of Work Quantity Unit Cost/Unit Total Cut curb grade for "A" curb along proposed walks Rough grade for swales after sand drains have been installed by others Original ground processing. provide construction water meter for own work Rough grading of walkway paths +! -.I' after curbs are installed Ro-Grading of landscape areas and slopes after underground has been installed. Recompect 3' below bottom of footings for pedestrian bridges Import from onsite topsoil stockpiles to Fast Middle park Street sweeper North Park + I Rough grade for paved areas along Avocado Dr. Rough grade for swales after sand drains have been installed by others Original ground processing. Cut curb grade for "A" curb along proposed landscape walks Cutback for retaining walls (upper two walls) Backfill retaining walls with rock per de tail "B" walls "B'TC" 1,199.0 Infc 16.00 19,184 Re -grade all areas after backfill of retaining walls are backfilled /utility been installed Rough grade for walks after curbs installed Backfill landscape areas with 6" of topsoil ham designated onsite piles Re -grade landscape areas after topsoil placement Street sweeper Touch up grade after backfill of retaining walls are backfilled and installed Move in 2.0 each 1,777.00 3,554 1,349,825 a B1S4m9teF SO Grand Total Site CiearinglSite and Fine Grading 1,349,825 hsaih F NEIN ft''NORNIMMOIN"ININN, x MR. . Phase III Rend We pumps and hoses to dewater during rainy season 88.0 locations 580.65 51,097 . PAGE 10 Sleveata Reach C.WDriver BVILDERS SINCE 1019 OW16111 Chilc Center and Park Men SCOPE AND PRICING SHEETS v1.11 a.. 16-Feb- I I 467101 16- Feb-II Budget# Description /Scope of Work Quantity Unit costlunit Total 51,097 Aftimust lx Grand Total Temp Dewatering 51.097 AIM34,10,1B Phase III Ramps/ Temporary earth support at the 3.0010 sqft basement at the library 27.00 81,081 81,081 Alternates Grand Total Tennis Earth Support 81.081 31.68 00 t Phase III Subcontractor proposal 1.0 Isum 531,000o0 531.000 Footing tie down per 13115/53.02 secterr,we testing - install about 61 it, included Spoils re.mt.t by grading Additional move for library 1.0 1'.. 3.500.00 3.500 Prepare the sin for the equipment 1.0 [so. 4.800.W 4.800 Romediever of the grade after the tie back 1.0 lsu. .pem,,.n 11.00.00 11,000 Central park 24" diameter drilled piers. 20-0 at bridges in above Spoils remml 1.0 1'.. 4,500.00 4,500 554.800 Afternad, Grand Total Ground Anchors 354.800 #31 2 5 00 ScU OK W OR 9 PAGE 11 ti�1e 11e Lll�vilr `ort (leach Civic Center and Park Newport Beach. C4 BtIILI)RR$ SINCE 1919 OU16111 ra.ea: mau anon rro— 16- Feb-11 487101 16-Feb-11 PAGE 12 Budget# Description /Scope cii Quantity Unit Cost/Unit Total Phase 111 Maintain and remove gravel bags around penmerer fence 7,700.0 each 3.00 23,IO0 Trash and debris guards 12.0 each 1,287.75 15,453 Run offcuntrol 12.0 month 3,777.00 45,324 Monthly visits 18.0 month 228.11 4,106 Library Maintain and remove gravel bags around perimeter fence 1.200.0 each 100 300 Run off conrrol 9.0 month 1,259.00 11,331 Trash and debris guards 3.0 each 1.287.75 3,863 Monthly visits 9.0 month 228.11 2,053 South Park Maintain and remove gavel bags around perimeter. fence 200.0 each 3.00 600 Run off control 9.0 month 1.259.00 1,331 Monthly visits 3.0 month 228.11 684 Protect sensitive area 21.0 month 664.04 13.945 Central Park Maintain and remove gravel bag around perimeter fence 500.0 each 3.00 1,500 Run off control 9.0 month 1.259.00 11,331 Monthly visits 3.0 month 228.11 684 North Park Mainmin and remove gravel bags around perimeter fence 200.0 each 2.00 400 Run off control 9.0 month 1.259.00 11.331 Monthly Ann, 3.0 month 228.11 684 161,321 Alternates Grand Total Erosion Control 161,321 o-NF' ,x132 12 16 Phase III Subcontractor proposal 1.0 (sum 199,919.00 199,919 Vehicular asphalt paving Base Tack coat PAGE 12 Newport Beach Civic Center and Park GWDriver Newpert Beach. CA I'VILDERS SINCU 1019 P,u.: .1.11 I..n1 n,nae 16-Feb-11 Ali PAGE 13 03/16111 16- Feb -II Budget# Description /Scope of Work Quantity Unit Costiunit Total Recycled Traffic control at Awacodo and McArthur 2.0 weeks 1,11M.00 2,200 Patch at the utilities 3.444.0 sqk 7.00 24,108 226.227 N Grand Total Asphalt Concrete Paver 226,227 321723 ' Garage striping is educed in garage pricing Phase III With AC paving 10- Wide pedestrian croularig 3' -2- x 18' White pedestrian ban, 6-4- on center 4" White bash striping for walkways and ADA parking- assumed 6" White lane stripe Lane arrows Parking Im striping Red curb- Sig. - no 'topping fire lane 12" solid white striping 4' blue striping at 36" cc and perimeter outline for walkways & ADA parking 4" double yellow swiping 8" solid white ]an. strip. Crosswalk Strip (IT'x 8') Handicap "Parking Only' and "Van Accessible" sign Hari pwarner, ..M.g Special Accessible Passenger Loading Zone Alveot, F- Grand Total Striping and Pavement XW=32 14 10 i I M 1 1101 PSO 5 q 1, 0 1 N 11 ON 32 14 3.16 Mortar -set Precast Concrete Unit Slab Pay.n PAGE 13 G W �TIV T Newport Beach Civic Center and Park q .1.11 r r, NEVII, Beazh. GA IWroe 16 -FeWI Rt, IADEgg SINCE, Into M7101 SCOPE AND PRICING SHEETS 02116/11 16- Feb -II Budgoal DescriptioniScope of Work Quantity Unit Cost/Unit Total Afternoon ffilimm Grand Total Sand -set Stone Paving with Scene Total Mortar -set Precast 0330 of Cut- In-place Concrete - Civil az applies 03 31 00 Concrete Formwork 321123 Aggregate Base 033001 Concrete Reinforcing - Civil Phase 111 2,957.130.00 2.957,130 South Park Fine grade Install / remove rumble plates Mist pads -, site furnishings. tanclotmers Fiber secondary reinforcement At scene cobble paving 9" concrete sub slab of 4 112" thick aggregate base o1 sub grade soil 4 IJr thick aggregate base I6" thick x 1'4" tall curb Smooch dowels at 18" OC at curb 2 and trench drain Trench drain encasement At brick paving: concrete sub slab 4 1W thick aggregate base Depress concrete sub slab along planting area for FRP retention angle As basalt stone pavers: 5" concrete sub slab 4 Jr 1 thick aggregate base Slip sheet Paver concrete sub slab saw cut control joints PAGE 14 NweiBeachC'v'c Center and Park, Q• Y Di1V�C NNNwoort Beach CA BVILDERS SINCE 1919 OLIOlI Pcn. LINn.1.n, P,.1 16- Feb-II W101 16- Feb-11 PAGE 15 Budget! Description /Scope of Work Quantity Unit CosdUnit Total Paver concrete sub slab expansion joint smwth dowels Expansion joint fill material per 31L 13.02 Expansion joint sealant and bond breaker per Pedestrian concrete paving 4 1a' Nick aggregate base Overex and moisture condition 8" below aggregate base Pedestrian concrete paYing - ramps near library entrance S" thick reinforced conorme with #3 rebar 18" OCEW poured on top of 6" thick compacted agg base 24" thick concrete sub slab for stone seat will 18" Nick concrete root barrier wall, 6' -0" high Concrete curb gutter Concrete curb I' -6° high battered concrete header at flexible paving Concrete stepped sub slab beneath precast treads at Monumental Stairs per LI0.01 - Concrete stair treads at Park Stairs #5, 46. W. 48; cooled grooves to be stained with LM Scofield Liahochreme Chemstain CS -I Black per 3/L09.03 Handrail post footings Concrete handicap curb nmp Detectable warning tiles at handicap ramp Concrete maintenance strip Protect finished product 1.0 Isum 2.757.00 2,757 Footings for light poles bollard light Bollard pipe Trench drains 03 33 13 Pedestrian concrete paving mockup 03 33 13 Mockup of Stair #2 concrete stair and check .11 03 33 13 Concrete landscape wall 04 22 23 Concrete steps for Monumental stair mockup 044213 Footings for 8 -0 long wall end mockup 8.0 Ink, 337.00 2,696 05 70 00 F.. ings for decorative metal mockups (TED) 1.0 Isum 760.35 760 05730 Footings for mockups for each form and finish of decorative metal railing 1.0 Isum 2,281.05 2,281 06 15 35 Footings for 10 x 10 bridge mockup 1.0 Isum 5.069.00 5.069 Demo mock LO Isum 1.750.00 1.750 Reba, Central park Misr pads -, sire furnishings transformers PAGE 15 �� T Driver Newport Beach Civic Center and Park �l� NYESdi_,SAoort Beach CA MAII13EHB SIECR 1919 02116111 Rm,tl. L141112)B FM Rerne4 16- Feb -II M7101 16 -Feb -II Budget# DescriptioNScope of Work Quantity Unit CosdUnit Total Pedestrian concrete paving Concrete stair treads at Park Stairs #3, #4; tooled grooves to be mined with LM Scofield Lithochrome Chemstain CS -1 Black per 31L09.03 Handrail post footings Retaining wall at sensitive area -per L9.03a and L2.02 -with handrails- 2 sides 1' -6" high buttered concrete header at flexible Paving Bollards North Park Fine grade Install I remove rumble plates Miss pads - site furnishings, transformers Pedestran concrete paving 4 IIX duckaggregatebase Overex and moisture condition 0" below aggregate base Expansion joint fill materi.l Expansion joint sealant and bond breaker Expansion joint smooth dowels Saw cut joint I'-6" high battered concrete header at flexible paving Concrete stair treads at Park Stairs # I, #2; tooled grooves to be stained with LM Scofield Lithochrome Chearstain CS -1 Black Handrail post footings Bollards Pedestrian paving smooth dowels a I" exposed pedestrian paving edge along plandng areas Detectable warning tiles at handicap ramp Concrete curb Detectable warning tiles at handicap ramp Undmpe concrete - site walls South Park Park Stair 45 Access ramp walls Petting, 6" wall, assume avg height is I' -6" from top of footing to top of wall 2' -0' x I' -6" CMU wall footing Backfll Seawalls ( under Stone-hriek-veneer ) Footing I'-B- thick concrete wall Park Suit #6 Footings PAGE 16 G � 1'. Drive. P,•t ae.rn c.ie Center and c..a Newonrt Beach CA BUILDERS SINCE 1419 SCOPE AND PRICING SHEETS 0V16111 Mmd: vl Nll lxYM 16- Feb-11 X87101 16- Feb -II Budget# Description /Scope of Work Quantity Unit CestlUnit Total Wall. assume avg height is 2' -0" from top of footing to top of wall Park Stair #7 (west side of Phase III) Footings Park Stair #8 (west side of Phase III) Footings Central Park Park Sour #3 Park Seair #4 North Park Subcontractor proposal was in mass ex -to be 140,265.00 Credited Dog park fence footing Seat well adjacent to Willow Sculpture #I, 16" h x 8' wide per Clarification 4.010 Park Stair #1 Park Stair #2 Solid rod FEE bars spaced' apart and set in a continuous footing Concrete footing i Crain channels Reba, Fiber secondary reinforcement in walls Fiber secondary reinforcement in slabs 2,9]2,443 * Aftvmaees IMMUAM Grand Total Concrete Paving 2.912,443 oar3�.ls r Site Retaining walls with concret Formwork Material at Exposed Surfaces: Smooth metal, resin - coated Plywood, or high- density overlay plywood which will provide ulna smooth surface ketaming Walls Winter Beige Medium sand- blast Stairs & Cheek wags Winter Beige Medium sand -blase Pedestrian Paving Winter Beige Medium sand- blast Headers Winter Beige Medium sand -blast Footings No Color Form finish & light broom top Bridge Antmenn Winter Beige Medium sand blast Cason Garden Path Charcoal Grey Acid etch finish PAGE 17 Ve r rt i"IVeI Newport heath CiWe Cvvbr and Park, NNgnore Beach. CA BtIIODERS SINCE 1919 Evei11 Pm-1: >, en lcxm r,.v,na: 16-Feb -II M7101 16 -Feb II Budget# Description /Scope of Work Quantity Unit Cost/Unit Total Dog Park Fence Footing Winter Beige Medium sand -blast Stairs with site concrete Retaining wall, type A (mxt of surface parking lot) Footing 12" thick .11, assume avg height is 10' -0" hom top of footing to top of wall Finish on exposed side color / sandblast Repining walls at new retention basin at the library at gabions Footings at retaining walls at new retention basin at the library Site wall south of Council Chambers Footing Wall, assume avg height is S -0" from top of footing to top of wall Finish on exposed side color / sandblast Repining wall, type A (east of surface parking structure) Footing 12" thick wall, assume avg height is 10' -0" from top of footing to top of wall Finish on exposed side color /sandblast Repining wall west of loading dock Footing Wall, assume avg height is 15' -0" from top of footing to top of wall eackfll Finish on exposed side color l sandblast Repining wall east of loading dock Footing Wall, assume avg height is IS' -0" from mp of footing to top of wall Backfll at walls Finish on exposed side culcr /sandblast Central Park Bening wall at sensitive arm North Park Repining wall, type A (cm, of pcdcur an walk and west of dog park) Footing Wall. assume avg height is V O-0 from cop of footing to top of wall Finish on exposed side sandblast / color Altcoomm a "4 yi a, `s PAGE 18 .1M1YriyVr NNwoort peach Chad Center and Park Newport Beach. CA SWIAOBRS SINCE 1949 SCOPE AND PRICING SNEETS DWI Mt1 owmi .11. 1.. ",va: 16-Feb -II M17101 6 -Feb 1 I PAGE 19 Budget# Descriptiom1impe of Work Quantity Unit CostlUnit Total - Grand Total Landscape Cast- in•place 33 11 00 az applies 31 33 33 Trenching and Backfilling 333100 Sanitary Utility Sewerage Piping 3339 ❑ Sanitary Utility Sewerage Manholes, Frames and Covers Phase 111 Subcontractor proposal 1.0 lavm 850.551.00 850.551 Saw cut. remove replace AC at the sweet Traffic control - Street crossing Water Domestic water 3" Domestic water backllpw provender Domestic water mCler Domestic, fire and condenser water POC 3" Domestic water meter 4" Domestic water back low preventer, Thrust blocks Twang, chIcni iza mn Preast culvert and deveaor check 1.0 Isum 53,447.00 53,447 Fire Water B" Fire water double check backfl. prevention Hydrant 8' Fire water - connect to garage Fire water POC Fire water - 8" 8" Water servicelAvocedo Avenue Thrust blocks Testing. chlurinivasio t Sewer Connect to existing cleanom San!., chore., Sanitary sewer Connect to existing SS manhole SS manhole 6" Sewer at Avocado Drop SSMH to grade Connect to existing SMH at Avocado SS POC Saddle existing sewer 4" Sanitary sewer POC Testing Upsize the pipe to handle the run off from the detention basin ( avocado) not included PAGE 19 Newport Stash Civic Center and Peril, QW. Drivier Ngolipmrt Beach, CA at1 ILDERs SINCE 1919 ".1 WF6-1 1 487101 PAGE 20 02116111 16 -Feb -II Budgets Description /Scope of Work Quantity Unit CostUnit Total 903,998 • Aftermeam; Emu= Grand Total Underground Utilities 903.998 az Ppli.a 313333 Trenching and Stucirfilling with site utilities 4 'Gax line Gas MC 'Gas meter and regulated seismic valve Connect to building Connect to existing gas line Aitermat F- Grand Total Natural Gas Distribintio 213 41 00 as applies 03 30 01 Cast-m-plat. Concrete -Civil as applies 31 23 33 Trenching and Backfilling 314419 Utility Sax,trn Water Treatment 33 49 13 Storm Don.... hNah.les, F,.ma, and Covers with site utilities South Park 24" Storm drain I S' Storm drain 12' Storm drain 8" Storm tire. 6' Storm drain ,r Storm Drain Storm drain man hole Catch %'i. Headwall Rainwater leader Storm junction structure (STD- 3 I O-L) Stnm drain man We & vveir Commort to existing trench drain W x 24" Concrete box culvert PAGE 20 �r�1 t{�T Driver NNNN�eioart Bach Club; Center and Park QR �/� NNN�oort Beach. CO SOLDERS SINCE 1919 eL I6 /1I Fn¢f: Lu.rl I. PM �r�: 16Feb -II tl8 >IIII 16- Feb-11 Budget# Description(Scope of Work Quantity unit Costiunit Total Connect to existing storm drain man hole - adimn as needed Area drain in paving S" diameter, Josam 5A series satin bronze fin I /C09.05 Connect SD inlet to (E) SD Connect to (E) SD SD clean out SD curb inlet 6" Storm drain - connect to garage Storm drain - 4" connect SD vertical bend and cleanout Thrust blocks Connect on new 18" SD Connect to Existing Curb Inlet Central Park 18" Storm drain 12- Storm drain 8" Storm drain 6" Storm drain 4" Storm drain Area drain inlet Curb cut SD point of connection to (E) SD clean out SD vertical bend and cleanout Trench drain type A Headwall outlet Sorm curb inlet STD-30S-L) Catch basin in planting, 2' min cover typ. North Park 12"Starm drain 8" Storm drain 6" Storm drain Storm drain me Curb cut Storm drain man hole 6 weir structure Headwall outlet Connect to existing SDMH SD can out SD venial bend and cleanout SD inlet Area drain Catch basin in planting, T min cover typ. 4" Storm Drain Storm drain manhole 02 Storm curb Inlet (STD- 30S -L) Swale atrium drain Storm junction structure (STD - 310 -L) PACE 21 CNewport Rmuh .ArDriver "VILDERS SINCE 1919 02116111 rivis Cart .... d End, SCOPE AND PRICING SHEETS Is. al.l. s.. P, ; 16 -Feb -II M87101 16- Feb-II Budgetill Description/Scope of Work Quantity Unit Cost/Unit Total Afternates Grand Total Storm Drainage Piping 33 41 P9 With landscape package 2.5 with landscape South Park, 6" perforated PVC pipe 4" Per$omted sub train I' Wide gravel sub drain Gravel Detention basins Central Park V Perforated PVC pipe Drain clear-cut Area drain Tie into civil storm dram Treatment Swale 4" Perforated sub drain at swals, I' Wide gravel sub train Swales North Park 6• Perforated PVC pipe Drain clear-cut Area drain Tie into civil storm drain Swale 8" Perforated sub train at ovale I' Wide gravel sub drain Gavel sub train Detention basin After non Grand Total Landscape Sub- drainag PAGE; 22 M. Driver Newport Beach Center and Park Pri ... 11aaaM Newport Beach. CA Pam 16 -Fall Rt`:1LU EES SINGE 1919 M7101 SCOPE AND PRICING SHEETS 01/16/11 16-Fab II • Budget# Description /Scope of Work Quantity Unit CosUUnit Total ARernotes - Grand Total Sub- drainage site concrete Grand Total FRP Structural Shapes/ Willow sculpwre designed and installed by 1.0 allowance Patrick Douzhei 7 Pieces in each sculomre Grand Total Willow Phase III Cafe tables with landscape Cafe chairs with landscape 12.977.0 Picnic tables and benches: custom himcated table and bench Ipe 1.0 Isum 12.977.00 12,977 13.977.0 Accessible Round Ipe Picnic table and bench 1.0 Isum 13.977.00 13.977 10.665.0 Steel structure at Picnic tables and benches: custom fabricated table and bench re 3.0 Isum 3.555.00 10.665 Trash receptacles: Ironsites series model S42 with standard lid, powder coated finish, VS bronze in color, and with 3 In -line anchor hole mount. From Victor Stanley 15.0 each 873.90 13,108 PAGE 23 C.W. Driver NewponBeachCivc Center and Park Newport Beazh. GA BUILDER$ SINCE 1939 OL16111 ncvl. .1.1. Ise. nw,"a', 16- Feb-II 07101 16 -Feb I I PAGE 24 Budget# Description /Scope of Work Quantity Unit CostfUnit Total Recycling receptacles: Ironsices series model 5.0 each 1,068.55 5,343 $42 with recycle package lid, powder Geared Wit VS bronze in color, and with 3 imime anchor hole mount. From Victor Stanley Add for freight trash and recycling receptacles 1.0 Isom 1,013.80 1,014 Installation 15.0 chrw 248 3,726 Delivery to the job site ham port 1.0 Isum 3,345.54 3,346 Tree grate 3.0 each with mist metals Large Concrete rabbit sculpture here each landscape Cemrock 8' nil, integral color white concrete with glared7peinted eyes and nose Boulder circle - salvaged from site with landscape Central Park Picnic tables: custom fabricated table Ipe 5.0 [sum 12,97200 64,885 Steel for Picnic cables : custom fabricated 5.0 Isum 3,555.00 17,775 cable Ipe Back co back bench,lpe seat board in l 112" 1.0 each 9.750 9,750 wide spacing Concrete cotton tailed rabbit custom Isom with landscape designed 5' long x 3' wide x 17' call rabbits, 5 different sculptured forms, 3 of each form and I each 8' rabbit, as available from Cemrock Landscapes, Inc Tucson, AZ (520) 571 -1888, www cemrock.com Trash receptacles: Ironsices series model 542 87190 with standard lid, powder coated finish, VS bronze in color, and with 3 in -line anchor hole mount. From Victor Stanley Recycling receptacles: Ironsices series model 10.0 each 1.068.55 10,685 542 with recycle package lid, powder coated finish VS bronze in color, and with 3 in -line anchor hole mount. From Victor Stanley Delivery to the job site from port LO Isom 3345.54 3,346 Single bench 12.0 each 4,185.00 50,220 Serpentine Custom Cut Ipe Picnic Table 05 - t02.0 Inft 842.77 85.963 3' wide table, V 4" wide benches on each side. W' joint between boards Accessible Round Ipe Picnic table and bench 1.0 each 13,977.00 13.977 Birdblind Bridge benches 2.0 each 3,555.00 7.110 North Park Picnic cables and benches: Ipe 5.0 each 13,977.00 69,885 Single bench -Ipe 3.0 each 4.185.00 12.555 Trash receptacles: Ironies series model S42 3.0 each 873.90 2,622 with standard lid, powder coated finish, VS bronze in colo% and with 3 in -line anchor hole mount. From Victor Stanley Recycling receptacles: Ironsices series model 3.0 each 1,068.55 3,206 542 with recycle package lid, powder coated finish VS bronze in color, and with 3 in -line anchor hole mount. From Victor Stanley Delivery to the job site from port 1,0 Isum 3,345.54 3346 Inuallation 200 mnhr 248.38 4,968 Tree grate 30 each with steel PAGE 24 IYiI Newport Beach C v'c Center and Path Newport Beach CA et12LDERS SINCIR 1939 owl Owl 1 aaw Winn swan nw•pa: 16 -Feb -II "7101 16- Felt-II PAGE 25 Budget# Description/Sc pe of Work Quantity Unit CostfUnit Total Dog park cash receptade 2.0 to 873.90 1.748 Back- to4ack benches - Ipe 7.0 ea 634018 44,382 Accessible Round line Picnic table and bench per U0.03 1.0 ea Instillanon of benches and rabies 1.0 ea 61,250.00 61,250 1 , IPI= i�w ._ 531,826 Afternoons :. ,: ,. Grand Total Site Furnishings 531,826 Subcontractor proposal 1.0 Isum 4,747,829.00 4,747,829 32 01 90 Landscape Maintenance Period 32 1500 Aggregate Surfacing 329113 Planting Soil Preparation 329119 Planting Soil Preparation and Planting Soil Mix Designs 329119.13 Topsoil 3291 19. 23 Structural Pleating Soil Mix 329210 Contract Growing and Maim, 329221 Meadpw5eeding 329222 Wildflower and Grant; Seeding 329223 Lawn Sodding 32 84 00 Irrigation Soils Soil testing by Wallace lab Fine grade within 0.04 Eucluded Mobilisation Rip, till, amend in- place, and fine grade topsoil installed as apart of MX package Imported soil in lieu of top soil 36" Imported loamy sand wood 12" Imported loamy sand copsoil stabilized " Existing soil amended in place 24" Imported cactus topsoil mix Topsoil in rip rap pockets Geo(zbnc in rip rap Flexible paving walk., - 3" flexible paving 4" aggregate base o/ 6" moisture - conditioned excavated and replaced subgrade soil c/ subgmde - at flexible paving Aggregate Mulch Retention angle at entry walls- 4" x 4" x 1/4" FRP 360.0 Ink 22.00 7,920 Rip rap at bio detention basin- 5 locations 50 each 2,424.00 12,120 Irrigation Irrigation meter and back0ow prevencer Irrigation controller PAGE 25 Mart Reach CNIk Centerand Park C W. Driver Newnnrt Beach. Gn ]VI6DRR8 SINCE 1939 03/16/11 Winrcf. nuinI.. Fn ry v-: 16 -Fel lI #87101 16- Feb -II PAGE 26 Budget# Description /Scope of Work Quantity Unit CostlUnit Total Tree irrigation bubbler Controller assembly provide 120 VAC Planting per plans FFeisting city palms and ands to be transplanted temporarily containerized and replanted in proposed landscape Equipment, cranes Plastic Root barrier Magnolia trees subject co awilbiliry Torrey pine -15 gal container subject to awilbiliry Torrey pine - 36' box subject m awilbiliry Sodded lawn Aggregate Mulch Aggregate mulch not adjacent to landscaping( at parking garage 3.150.0 sgft with landscape Aggregate mulch not adjacent o landscaping( at stone walls) drain channels 4.165.5 sgft 5.50 22,910 Biobarner 7,315.5 sqk 2.03 14,833 Wood chip mulch 3" thick wood chip mulch at tree wells Steel header at wood chip mulch Stabilized aggregate paving mockup, 30-0. II- 0 x 3" depth, including concrete I wood headers Mock -up areas of backfill mix at the specified depths and apply irrigation to induce settlement Mock -up areas of soil mixes at the specified depths and apply irrigation to induce settlement Structural planting soil mix mockup, (2) 10 -0 x I5 -0 x 6' lifts Tree staking mockup Root ball anchor system mockup Boulders Gravel mulch at planting areas T' depth over dobarrier K9 grass - artificial turf by Forever Lawn; Albuquerque, NM (505) 217 -0177 www.foreverlawn.com Crew of people to do fine grade per spec 240.0 mnhr 47.00 11,280 1 -Year maintenance 4,816,892 x Bftef06to m _. M 3 Grand Total Landscape and Irrigatio 4.816,892 .. 03 20 00. rash r PAGE 26 1 f Driver Newport B...h G V [ Ganmr znd Park qty N�weore eeah A BGILVEES SINCE 1919 mr. viu111xum By.rttl. 16 -Feb -I1 M7101 OVIVI I 16 -Feb -I I PAGE 27 (}W�i1VeI NewoortReachC'v ' cCenterandPark YV Nw+port Rauch CA I'MIA)ER3 SINCE 1919 OW16111 nvvea. LINII IIIDPM waP..os: 16 -FebII pa]IOI IbFeb -II PAGE 28 Budget# Description/Scope of Work Quantity Unit Cost/Unit Total Curbs at restrooms Restroom slab depressions 2" Topping slab at remps for stone Concrete steps o n metal deck Equipment pad Curb ac piping per plumbing details 25.0 each 225.00 5,625 Embeds for CIP Mockup Mist trenching for mechanical work Mockup to demonstrate typical formwork, joints, and proposed surface finish, texture, and color Mockups to demonstrate typical joints, surface finish, texture, tolerances. and standard of workmanship. Footings for mockup of AESS assemblies 1.0 each 3,649.68 3,650 100 Sqh wall for waterproofing mockup 100.0 sqh 12.17 1,217 fooung for metal faced composite water- spay test assembly LO each 1,824.84 1.825 Footing for glazing mockups 4.0 each 50000 2000 Demo the mock ups 1.0 Isom 750.00 750 Community Room See scope above Concrete roppmg at ruhamr floor for brick food, steel mesh at concrete at double slab 4,000.0 sqh 4.00 16.000 Chambers See scope above Suspended slab under seating Concrete walls under suspended slab Library See scope above Grout at seismic joint WeNand bridge Abutment wall footing Add to form abutment structure Add to form abutment seat Foam fill in abutment structure 5" slab above foam fill 2" grout between steel and concrete abutment Deck bridge Abutment seat Add to form abutment structure Add to form abutment seat Bird blind Bridge Abutment structure Add to form abutment structure Add to form abutment seat Foam 011 in abutment structure 5" Slab above foam mfill PAGE 28 C W. Driver Beach C'v i Center and Park Newport Beach. GA SUILDER.S SINCE 3919 mMm: viaii izmm B.-Ir I6- Feb-II M7101 OW16111 1&F6-I I PAGE 29 CVU���� NewoertBeach Center and Park �t x Newport Beazh. CA BUIWa EES SINCE 1019 0L16111 ii J: .1is"... nwrto, 16- Feb -II M7101 16 -hvtr I I PAGE 30 Budget# DescriptionlScops of Work Quantity Unit CoodUnk Total Cast stone tread, risers, and landings on setting bed on 3116" meal pans (bottom IS treads and risers on (E) concrete stepped slab, not metal pan) per R6.01 767 sqk South Park Monumental stairs - precast concrete with anchor pins, stone inlay, sealant & backer rod, and expansion joint fill material at each tread. over mortar setting bed with mesh fabric reinforcement and drain mat all over concrete sub slab and compacted mi Monumental stair mockup per 04 22 23 • Alternates Grand Total Mortar -Set Precast Con 44.22 4B Fives. # 32 1400 Sand -set Brick Paving Phase III Subcontractor proposal 1.0 Isum 1,190,330.00 1,190,330 Tile I brick flooring - Belden Brick Company "Tumbleweed ". 4" x T x 2 114" 321400 8- 0x8 -0 brick paving mockup 64.0 sqk 65.00 4,160 Prepare substrate 2,337.0 sqk 2.53 5,923 Mockup of brick flooring 1.0 a11w included Protect with lumber until final completion 2,400.0 sqk 1,00 2,400 Chamber South Park CMU sign wall I - 3' all with control joint at 18.5 Cl sign wall 2 - T -6' all with control forms every 20' Brick paving sand set brick pavers laid on edge over I" cement sabilized sand setting bed over 5" reinforced concrete sub slab on top of 12" thick compacted agg base. Edge of . paver areas restrained by 6" x 6" x 31T FRP angle bolted to sub slab at all ad Add for FRP angles as all locations 2,363.0 Infr 12.00 28.356 Geotech barrier 23,076.0 sgft 0.25 5.769 1.236.938 I� IN, IBM fl. r �i PAGE 30 G.xX, iver NNwoort Beach Civic Center and Park �/y Newport Beach CG Bt!11,01igs SINCE 1939 OV16111 .a-! ."in iavm o9nrta: 16- Feb-11 48)101 16 -Febl I PACE 31 Budget# DescriptioNSCOpe of Work Quantity Unit CusdUnit Total Grand Total Site Concrete Unit Masu 1,236,938 OA A2 00 0442 13 Site Stone Veneer Walls Phase III Community room Subcontractor proposal 1.0 bum 3,603,490.00 3,603,490 Stone veneer Stone veneer at stair F Stone to be sealed Stone coping at the stone wall 8 -0 long wall end modal, per 0442 13 Independent testing her hollow stones I.0 Isum 12,000.00 12,000 protect with lumber until final completion 1.0 Isum 7,500.00 7,500 Stone file I in elevators 96.0 sqR 38.82 3,727 Chambers Stone veneer Reuters Stone veneer coping Site wall Add for one mock up per specs Add foranthor testing Flexural strength test (3) Add for structural stone calculations Add for samples per spedfication: -attic stock (6) 24" x 48" x 2" (3) 12" x 36- x 36" Stone to be Sealed Add forsaHolding Stone coping at the stone wall Library Cast stone treads, risers, and landings on setting bed on 3116" metal pans (bottom 18 treads and risers on (E) concrete stepped slab, not metal pan) South Park French limestone seat wall veneer (bench) over 2" mortar type M of I' thicit concrete sub slab with drain base of subgrade soil Scone veneer at Sign Wall I Stone veneer at Sign Wall 2 Cap stones at sign walls Stone to be sealed Scone veneer at Council Chambers wall Supply and install cast stone stair beads Cast stone landing PACE 31 Nadi Beach Cimic Center and Park C.WDriver N=p,ft likesuch- CA RVIIA)ERS SHINCH 1919 r,o—a 16-Feb-II Noun PACE 32 OV16111 16- Feb -II Budget! Description/Scope, of Work Quantity Unit Conflunit Total 3,626,717 Afternoon, Grand Total gatericur Stone Cl.dtl 3.626,717 Phase III with stone Tile I - Stone pattern I - 12!'x 30" x 3W - AG&M Chinese Basalt Tli, I - Stone pattern 2 - V . 12" . 19132- - AG&M Chinese Basalt Tile I - Stone pattern 2 - 4' x 12" x 19132- - AG&M Chinese Basalt stairs @ Phase III stairs Anti fracture membrane Prepare substrate Mockup of stone floor the Library Tile I - Stone patmers, 2 - IF' x 12- x 19132!' - AG&M Chinese Basalt Tile I - Stone pattern 2. 4!'x 12" x 19132- - AG&M Chin. Basalt stain @ Jib., van. And fracture membrane Afternarto Grand Total Stone Tiling 051200 � ¢r -t '36wdfflwmpfiw= 05 1250 Buckling Restrained Braces 055100 Metal stairs Subcontractor proposal 1.0 lsum 8.142.731 8.142.731 a. time for come 1.0 Isum 27,000.0 27.000 Phase III Shop drawao calculations/ coordination, BIM 1.0 Isu. 69,952.20 69.952 Buckling restrained lances (DRB) Field Deviling ofAESS 1,200.0 mnhr 87.00 104.400 BRB Connections Columns - tapered Bruce frames Column anchor bolts and templates for them PACE 32 �i1V� Newport BeachCivcCenter and Park Y Y Newport Beach. CA RO1LI)ERSSI,l'CR 1419 OV16111 P: d: man riven na•Fd: 16 -Feb 11 487101 16- Feb -II PAGE 33 Budget# Description /Scope of Work Quantity Unit Cost/Unit Total Curved roof Verendeel crosses Added cost for roof architectural exposed structural Steel (AESS) Stairs Stairs 2B, 2C, 2D, 2E SS Handrail & Cable Rail System Grate Landing Stairs 2B, 2C, 2D, 2E SS handrail SS Guardrail: Handrail Trellis Canopies with outriggers Survey of column anchor bobs 1.0 Isom 5,969.25 5.969 Reinforcing plates at pipe penetrations at beam web - quantity assumed -assume Geld.,hore, lift 50.0 each 1,250.00 62,500 Safety rails- install/ remove - 32.0 mnhr 67.00 2.144 Mockup of AESS assemblies Community room Same scope as above Brace frames Bridge Low roof collector line Curved roof Verendeel cruses Added cost for ronf AESS Stair F SS Guardrail IS' SS Handrail @ Stair F & Bridge Add for Metal Pan for Cast Stone @ Stair F Add for risers Chambers Buckling restrained braces Colum n Roof Addedcostfor r.mfAHS Low wdll support Library MF ( Moment Frames) MF Connections 1.5" SS Handrail @ Stair, in library Patent fees for the connection Central Park wetland bridge deck bridge PAGE 33 C.WDriver atill,I)RIts SFNVIE 1919 Nw,,t Beach OV16111 Cish, Cemormad Park Mass Beazh. CA SCOPE AND PRICING SHEETS eoal v onAz me" I. 1� 16 -Feb -II 887101 16- Feb -I1 Budgetill DescripticurdScops, ol'Work Quantity Unit Cost/Unit Total Birdblind Bridge 8,414,696 Grand Total Structural Steel 8,414,696 95 30 Q0, Subcontractor proposal 1.0 Isum 580,956.00 580.956 Phase 111 Metal decking Edge forms included Support angles at columns included Deformed bar angles included Home, Is. included with stru star add f.,.ddili.n.1 openings 20.0 each 375.00 7.500 588,456 Alwrub, F- Grand Total Metal Decking 588.456 tiff=, 05, so 00 Subcontractor Proposal 1.0 Isum 2,110,348 2.110.348 055300 Metal Gratings 056000 Site Metal Fabrications Mass Ex Fencing at the ravening wall with fencing 'horived site rails Phase III Aluminum /Steel Angle Guardrail System @ Balcony Fronts 55 Cable Fail System A Cut C-Channel @ Balcony Sides Galvnaod Metal Grating @ Mechanical Well Galvanized Metal G.dmZ @ Mechanical Wall PAGE 34 C.W. Driver Newport Beach Civic Center and Park Y e...rtnrt Beach. CA BUILDERS SINCE 1939 OW16 /11 Nmn1 YIn111kL VM Bo.rcE: IbFeb -I I W7101 16 -Feb -II Budget# Description /Scope of Work Quantity Unit Cost/Unit Total MEP Screens at the roof supports only - louvers are separately Railings at the stairs on the south side Ramps railings Ramps metal plates Elevator it ladders Roof access ladders- ship ladder Elevator sump pitand grate Nosings Fall arrest safety anchors per 2/AS.20 - 0550DD Support for coiling grills Sur bar embedded nosing strip Misr supports. angles ( at skyiighu. elevators. countemps) Stainless steel wall panels at elemors Self Serve kiosk From TW" AL trellis @ I P' o.c. wd end caps Mockups for each form and finish of decorative metal ailing Community room Misc suppors Handrail @ building Exterior 12" Cut Channel @ Bridge w/ HP coating welded to SS shoe for glass guardrail support Chambers Bullet protective place Handrails at ramps Mist support for none Misc supports Recessed alum gating at conference at Zink wall Floor gating with supports Prefin 2 "x8" AL trellis @ I OP o.c. w/ end raps Library Stair Misc supports Aluminum Grating w/ Removable Section for Access Add for Metal Pan for Cast Scone @ Library Stairs Add for 12 risers Mem1 guardrail at line N 1 Support for coiling grills Steel Plates @ CW & Floor Slab - (1) 1'& (1) 8" steel plate at tine intersection of ma....to wall and floor slab: welded and painted 20 ga. closure panel between vertical mullions additional support for misr equipment LO ]sum 16.800.00 16.800 South Park Trench drains covers Trench drain type B PAGE 35 *� r a y�4 Newport Beach C'v'c Center and Park �ly D li Newport BeacF CA 9011,UER881NCE 1019 m.w: viuu liven n,serta: I6 -Febl i p61101 PACE 36 OV16111 16- Feb -II Budget# Description /Scope of Work Quantity Unit CosdUnit Total Trench drain at north of parking garage, south of Chambers, & library playa Trench drain and grate at precast concrete stair at entry court 4" trench drain at south of Chambers - no details lust shown on legend 1 I/4' x 1 114" with IIF radius, solid square carbon steel bar handrail painted Bollards 20.0 each 225.00 4,500 Central Park 1 114" x 1 1/4" with 118" radius, sold square carbon steel bar handrail, painted wetland bridge 3'-6" High guardrail with l' square steel picket at 5" o.c. and 4- x 3" steel tabs welded to bridge beam deck bridge T -6 "high guardrail Birdblind Bridge B' High g xvdni! with I" square stsel picket at 5' o.c. and 4" x 3" steel tabs welded to bridge beam North Park 1 1 /4" x 1 114" with IN radius, solid square carbon steel bar handrail, painted 2,131,648 * Alternate: Grand Total Metal Fabrications 2.13 1,648 0573 00 W,„ With misc metals Ahern Grand Total Decorative Metal and G QJ 35 00 5 ": r:w; 4s F° G.i� , ri( Phase HI Expansion joint cover at the bridge 8.0 Inft 145.99 1.168 Community room Library Expansion joint cover homental 264.0 Ink 134.84 35.597 Expansion joint cover at the roof 132.0 Ink 13484 17.298 Expansion joint cover vertical 128.0 Ink 65.90 8.435 PACE 36 blid"aud Beach Chdr and Park Me Driver Newport BUILDERS SINCE 1919 OW16111 L'.0 l2iaP 16- Feb -11 487101 16- Feb-II PAGE 37 Budgetalt DescriptiondScopeofWorlh, Quantity Unit CosdUnit Total 62,998 Alto ate. Grand Total Expansion Control 62.998 Subcontractor Proposal 1.0 Int. 663,607.00 663.607 061500 Wood Deckin,, 06 IS 35 Site Carpentry 061600 Sheathing all eachad to be fire treated FSC certified Phase III Wood nallin, as required at all roof edge and Sutter conditions Mist plywood / blocking Fire - treated word blocking at top of metal stud pampers Forming and blocking for mirror attachment Rooftop equipment bases and support curbs IPE decking at the balconies 3/9" MDF soffit Store/ prep IPE wood 1.0 1'.. 10,000.00 10,000 Community mom Wood milers as required at all roof edge and gutter conditions Mist plywood / blocking Chambers Wood milers as required at all roof edge and 't., condition, Met plywood I blocking Platform at dais Library Wood rollers as required at all roof edge and gutter conditions Miss, plywood I blocking wetland bridge 1 112' IPE decking wetland bridge 4x4 " Tfiri " nailer attached to steel I beams with 5/8 welded and threaded studs at 24" on center wstitrid bul, 514 x 6 FSC ourtiffied IPE attached to rollers with stainless steel screws per specs. di bid,. 1 112- IPE decking di bridge 4x4 " TimberSil " rattlers attached to steel I be.., with 518 welded and threaded studs at 24- on center PAGE 37 C.W. Driver Newport Beach Or , Center and Park Newport BeacM1- CA 861L1>F.RS S"C8 1919 0211611 I - I&Feb - II M7101 16 -Feb I PAGE 38 Budget# Descripthudsc.pe of Work Quantity Unit CcstlUnit Total deck bridge 5/4 x 6 FSC certified IPE attached to milers with stainless steel screws per specs. isolated Bridge 11/2 "IPE decking BirdlAmil Bridge - 4x4 "TimberSil" nailer, attached m steel beams with 518 welded and threaded studs at 24" on tenter Birdblind Bridge 514 x 6 FSC certified IPE attached to milers with stainless steel screws per specs. Protect wood with protective board 3,200.0 sq(t 1.50 4,800 678,407 x Altern0tes ,. Grand Total Rough Carpentry 678.407 44 40 23 Interior Architectural Woodwork 066400 Plastic Paneling Phase III Subcontractor proposal 1.0 Isum 1.963.550.00 1.963,550 Architectural Woodwork Plastic Laminate Cabinets /Casework Countertops Metal Supports for open area tables Conan / Solid Surfaces SS Poles a, millwork Open wall cabinets Brochure holders Wood Paneling Wood Wiling, Wood Wall Tile Marker boards on Doors at Command Cancer Fabric .11 panels Privacy Panels Aluminum Framing structural support for panels structural support for panels Fastening / anchors / support Compliance with trade associations - WI- Woodwork Institute FSC - Forest Stewardship Council TEED PAGE 38 /`I�x] l�ii NewnortBeachChdr Center and Park �...+ �Y��ll NealicatBeach CA 8@ILDRR8SINCE 1419 07/16/11 vane: .ion itmsn "uv: 16 -Feb -II "7101 16 -Few 1 PAGE 39 Budgetl DescriptionlScope ofWark Quantity Unit C.Et Unit Total Wood and MDF Wall Base Supply Room Shelving Benches Coat hooks Glass & Glazing within Millwork Cut Ours - with Grommets Computer Equipment Plumbing coordination - Electrical coordination Protection of solid surface wunters Wood substructure for all solid surface counters Non - Typical Materials Apple My Formics Color Core 9 Wood Specific Areas Shelf Check Station at Ultra, Casework and Trim at Credit Union lantech FRP Cafe Food Service plans Library Stairwell Panels MDF Marquee above the cafe Command Center Restkooms Kitchen I Kitchenettes IT Supply Room Podiums Council Chamber Wall Paneling (?Wood) Council Chamber table NBTV Clerk Counter Cashiering Revenue Counter Work Stations One Stop Shop Desk One Stop Shop Tables One Stop Shop Lora, and shelving Mother's Rpom Plot Room I Active Vault File Vault Hallway Displays Wood Jambs (See door scope) Conkrence Room Doors Design and engineering of ceiling attachment 1.0 [sum 7,500.00 7,500 Deoiling at site 200.0 mnhr 67.00 13,400 Mockup 1,984,450 AltC[Bffifi PAGE 39 G W, Driver Newport Reach Civic Center and Park mun I.. Ne.eprsrt Reach. CA "pi—s 16 -Feb -I I BCILVER3 SINCE 1919 H02101 SCOPE AND PRICING SHEETS owl 6111 l61 I * Budget# Description /Scope of Work Quantity Unit Costli Total Grand Total Interior Architectural V Phase III Misc. Mock ups, including for the root 1.0 lot 75,000.00 75,000 structure ]5,000 t] 11 I6 Damproofing 021336 Self Adhering Sheet Waterproofing 01 1322 Pre - applied Sheet Waterproofing 0313 SS Thermoplastic Sheet WP with Ache. Polymercora 021200 Bentonite Geoteatile WP 021923 Site Water and Grand ReoeHeins phase III Subconuactor proposal 1.0 bum 881.373.00 881.323 Under slab waterproofing Waterproofing at basement walls Waterproofing at trenches Elevator pits Waterproofing at 18 "" pods steps Drain pipe with gravel Water stop VE Under slab insulation l" notincluded Community room Under slab waterproofing Retaining wall along 22 line per VA4.05 with insulation Drain pipe with gavel Water stop Under slab insulation 2" Chambers Under slab waterproofing VE Under slab insulation l" not included PAGE 40 �} 1VeI N,,,ft Beach Chic, Center and Park Isle I Newport BeacM1 CA BUILDERS SINCE 1919 SCOPE AND PRICING SHEETS OL 16111 >.m•rta: 16 -freMII pW 101 16- Feb-II PAGP 41 Budget# DescriptioNSrope of Work Quantity Unit Cost/Unit Total Library Under slab waterproofing Waterproofing at library existing basement walls not included Waterproofing at library below grade walls 100 zqk wall mockup Waterproofing at the site retaining walls Sub drainage perforated pipe surrounded by drain rock and wrapped in peonage fabric Central Park Waterproofing at the site abutment wall - at bridges Waterproofing at stair cheek walls Dampproofing on Backfilled Side of Retaining Walls. Dampproofing Along Stone Walls and Precast Stair Treads Directly in Conan with Soil or Aggregate Mukh, excluded 881,3]3 Ass Grand Total Water proofing Site Da 881.373 Subcontractor proposal 1.0 [sum 260.000.00 260.000 Phase III R -19 (FS -25) foiled faced fiberglass Batts at exterior wall framing R -11 unfaced fiberglass Batts at interior acoustical partitions 3" Foiled faced curtain wall insulation at curtain wall 2" Black -laced insulation Acoustical insulation at Chiller room with drywall Isolators with drywall Sizing and shop drawings for Fell with drywall 5/8" plywood 1.0 Isum 76600 ]66 Additional furring channels., clips with drywall Batt insulation with drywall Additional drywall with drywall PAGP 41 �� NNwonrt Beach Civi< Center and Park Q.W. NewA ort eeufls_pstLjS3{B,�,,. C 9 BUILDERS SINCE 1919 - 02116111 ninroG LIN1112'IB PM 16- Feb -11 M7101 16- Feb-II PAGE 42 * Budget# DescriptiodScope of Work Quantity Unit Ctstil Total Insulation at airway section 13 a5.01 3.000.0 sqk 144 10,320 Communitymom R- 19(FS -25) foiled faced fiberglass setts at exterior wall framing R -11 unfaced fiberglass bats at interior acoustical partitions 3" Foiled faced curtain wall insulation at curtain wall 2" Black -freed insulation Chambers R- 19(FS- 25)foiled faced fiberglass bats at emenor wall framing R -11 unlaced fberglass bans at interior acuusticel partitions 3" Foiled heed curtain wall insulation at curtain wall 2" Black -faced insulation Library R.19 (FS- 25) foiled faced fiberglass bans at exterior wall framing R -11 unfaced fiberglass bares at interior acoustical pardtions 3" Foiled heed curtain wellinsulation at curtain wall - 2" Black -heed insulation 271,086 AftsfIl92fS Grand Total Thermal Insulation 271 ,086 Phase III with drywall, s Aft eren ', e ; M6 . i . Grand Total Fireproofing d� %*LH,k07 84 13 c�2�....t`�'± � � �'£ 'R, WIN'l iidbii r— .1:.ka. •� f � �t ,�. :..em3 PAGE 42 h.1. 1 M1 1.'riuVr SOLVERS SINCE 1919 N^etuad Reach OW16111 Orr Center ad Park m.�a. Newport BeacM1. CA ny..a: SCOPE AND PRICING SHEETS au", ru a R1 16-Feb -I I rrenm 16 -Feb lI Budget# DescriptioNScope of Work Quantity Unit Cost/Unit Total 078446 Fire-resistive Joint Systems Phase 111 Are stopping and safing 120.484.0 sgft 0.30 36,145 SaOngwith smoke seal at perimeter Boor slab incl as indicated Saengwith smoke seal at head of rated iad gypsum board wall assemblies 078446 Mockup for each fire resistive joint condition 1.0 a11w 2,444.00 2.444 38,589 Afita mrt Grand Total Penetration Firestoppin 38,589 07 42 13 0731 16 Architectural Metal Shingles with sheet met 074213 Architectural Metal Flat Lock Plate Panels Alternate[ Grand Total Architectural Metal Flal =V7 074219 074219 - Architectural Metal Plate Panels withcurtainwall Phase 111 E:tenor metal soffit 07 42 19A Metal panel wall system Mackup Mockup for each form of construction Construction water-spray test mockup of metal faced composite wall panel assembly, include typical wall and corner panel Alternates Grand Total Architectural Metal Pan PACE 43 lA. ♦ I� Driver Neel Beach Civic Center and Park New¢oH B¢acM1. [D 8VILDERS SINCE 1919 Mnul: LIb111 YiaM I>m.2a: 16- Feb-11 #87101 PAGE 44 OLI6111 16- Feb-II Budget# DescriptioNScope of Work Quantity Unit Cost/Unit Total Illy Qi2706 ., Phase 111 Concrete seal per finish schedule 7,806.0 sqh 2.99 23.340 Seal concrete foraccess floor applicsfc. 71,005.0 sqh 121 85,916 Seal pad concrete at generators 100.0 sqh 4.02 402 Community room Concrete sea11 treamentat mechanics 2,552.0 sqh rooms 2.99 7,630 Chambers Concrete seal 691.0 sqh 2.99 2,066 Library Concrete seal 1,560.0 sqft 2.99 4,664 124,019 Afermot Grand Total Concrete Sealer 124.019 SOMA? 54 19 Phase 111 Subcontractor proposal 1.0 Isum 1.281,160.00 1,281,160 VE Use Poly Iiso insulation in lieu of Rigid Polystyrene in above VE Use Anchors in lieu ofadhesive in above Rent Roof walkway allavvance Temp roof N/A Chambers Roofing membrane over 6" non rigid insulation over sloped deck Temp roof 6.000.0 sqh 1.27 7.620 Library - semproof 7,500.0 sqh 1.27 9.525 1,298,305 1� r. Grand Total Polyvinyl- chloride (PVC - 1,298305 %pwm r 07 62 00 Subcontractor proposal LO Isum 1,173.627.00 1.173.627 Phase III Sill flashing at clerestory windows PAGE 44 Q.W. Newport Beach Cv'c Center and Park Qe Nyp� rt Reach, y poort SCA &1i111DERS SIFfCK 1919 owl 6/11 vlau lzMm e,.—k 16- Feb-11 }07101 16 -Feb-1 I' Budget# Description/Scope of Work Quantity Unit CoadUnit Total Soft panels IIA5.02 Prefin metal flashing @ trans to metal roof Prefinished metal drip edge at metal roof Prefinished metal soft at metal roof edge Prefin metal flashing at roof transition from 2A to IA Flashing at mechanical penthouse perimeter Flashing vim piece at metal shingle & curtain .11 Prefinished Art coping Metal pan Stainless steel custom gutter Methanical pad covers Misc flashing Mockup of 10 -0 long roof eve, bulk -in gutter, fascia, fascia trim, apron flashing. including supporting construction cleats, seams, attachments, underfeyment. and accessories Community room Sill flashing at clerestory windows Misc flashing Prefin metal flashing @ tans to metal roof Prefinished moral drip edge at metal roof Prefinished metal soft at metal roof edge - Prefin metal flashing atroof tarsition from 2A to IA Flashing at mechanical penthouse perimeter Stainless steel custom gutter 8 a5.22 Mechanical pad cover Chambers Misc flashing Library Zinc shingles Misc flashing SS flashing at Cafe & Credit Union roofs Stepped hashing at membrane roof & curtain wall SS flashing and fascia at high roof 1,173,627 9Bemates Grand Total Sheet Metal Flashing an 1.173,627 PAGE 45 G.W,Driver RUIi.ISERS SINCE 1919 blgw- ortDeathClAtCenrer 02/16/11 end Park Newport Brach CA SCOPE AND PRICING SHEETS N,wd awv e: Wiwi IIIMPn I&Febll X87101 16- Feb -II Budget# Descrtpthmiscope of Work Quantity Unit CesUUnit Total With sheet metal Phase 111 Kopf hatches Community room Roof haches Chambers Roof hatches OWNAlt¢rnaS4S Grand Total Roof Accessories 084433 Phase III Skylights 5.0 each 1,750.00 8,750 Polycarbonate rectangular 6.0 each 1,750.00 10,500 Community room Chambers Skylight solar fritted glass 176.0 soft 355.00 62.480 Add for STC 36 included Library Skylight(doms) 1.0 Isum 33.455.40 33,455 Add for STC 36 io above 115,185 = Alto-on, s re Grand Total Sloped Glazing Assemb 115.185 .. .Y 079200' KNEE— °' .,gin.? 079214 Site Joint Sealants with wade Phase III PAGE 46 CW Driver sq Hauout Beach Civic Center and Park . RUJIIDRRS SINCE 1919 IFT-EWMITIM all I" li: M: 14 4 v OV16111 un,uu .111111.. J6-Feb4 I WIN 16 -Feb -II PAGE 47 Budget# Description /Scope of Work Quantity unit Cientlunit Total Extensive sealants and caulking due to HVAC requirements 103,212.0 sqft 1.75 180,621 Mockup of joint sealum anannables 1.0 Isom 250.00 250 180.871 Grand Total joint Sealants 0871 00 Door Nerd—re Subcontractor proposal 1.0 Isma, 607,170.00 607,170 Phase III aterhar single leaf doors cst42 Single door assemblies, non rated. Single door assemblies, 57C 43. Paired dmor.s..lifies, ... rated. Singe door assemblies. STC 43 4dectric hardware. Paired door assemblies, STC 43. Paired door assemblies, non rated w1clecuric hardware. Paired door assemblies, STC 50. Single door assemblies, STC 37. Single door assemblies, 60 min. mined. STC 50. Single door assemblies, 60 min. rated, STC 43. Assume additional Fire rated Single door assemblies. 60 min. rated. Assume additional fire rated paired assembly. 90 ner. rated. Single do., assemblies, 60 min. rated. Paired assembly. 90 min, rated. Closet/stomge double doom - marker board applied to full door 8! height Closednomp double doors 8' height - meoll m" Closedstorage double doors - storage only V height Closedscorage double doom Theight - not on schedule Singe door assembly. STC 43 w1mao closer and elearomic hardware Single assemblies, firancelo,, w /,rvots. non .,ad. Paired assemblies, mmelcss, w1poor, non rated. Single door assemblies non raced, wiside Igh. Door mockup PAGE 47 •hrl, i 1 � Y N ownort ARILDRN651NC£ 1919 03116111 Beach CV'c Cancer and Park Newport Beach CA SCOPE AND PRICING SHEETS PM¢C: ".ox: LIYII ITNPM 16- Feb -1I M7101 16- Feb-II Budget# Description /Scope of Work Quantity Unit CostlUnit Total Card entry - All Phase III perimeter doors Interior at critical areas, HR, HK files room. several in basement One ourside and inside elevator that goes to basement - Community room Exterior double doors Exterior single leaf doors Single door assemblies, STC 37 Single door assemblies, non rated. Paired door assemblies, non rated. Card entry- allow Knox box 3.0 each 375.00 1,125 Chambers Bi folding pair. non rated. Single door assemblies. non rated. Card entry Library Single door assemblies, non raced Single door assemblies, STC 43. Paired door assemblies, STC 41 Single deorassemblies, STC 50 w /vision lit.. Card entry 608,295 Alternatea oe Grand Total Hollow Metal Doors ant 608.295 oa3473' p as applicable 09 H 00 Door Hardware With doors • - Itemates Grand Total Sound Control Door As i Phase HI access doors- with glass insert and lighting 1.0 Isum per HVAC 26,764 26,764 Community room PAGE 48 �!1VCl NewaortBeachC'v'c Cantor and Par �l �! N l Ya poft loft Bpyr,YZcja_CA HVIL DERS SINN 1919 1Nnree: v1411 i1m vn a.a•�.d: 16 -Feb 11 NW101 0116111 164e ] I PAGE 49 iA11 a� .YAiy1/r Newport Reach Civic Cnntorand Park GWD NV. Beach. CA EUII.IIBRS SINCE 1919 03116/11 nN¢!: .1.111..xx In —ii: 16-feb 11 Wn01 16- Fab-II PAGE 50 Budget# Description /Scope of Work Quantity Unit CostfUnit Total Ahern Grand Total Smoke Guards b54113':i': main wens as applicable 08 80 00 Glazing a sapplicable087100 Door Hardware 08 44 13 Glazed Aluminum Curtain Walls Phase III Subcontractor proposal 1.0 Isum 6,839.00.00 6,839,000 Add for Shuco windows 1.0 Isum 344,000.0 344,000 Addfor Shucasystem'+ 1.0 Isum 112,000.00 112,000 Exterior I" dear low -E insulated glazing unit, butt glazed, Exterior "clear low -E insulated glazing unit fully tempered, I" Spandrel pattern I Insulated glazing unit Operable motorized awning aluminum windows - W06A - exterior Phase III south elevation Exterior small operable casement wndw-@I" clear Low -E insulated glazing unit Exterior aluminum operable casement window Exterior W09 fixed window sliver at stone .11 Exterior insulated aluminum closure, glazel alum curtain wall, with 18" deep extruded alum CW end caps at east side of each opera ble window Extruded aluminum fins supported by &to match CW mullions Add for 10" extruded aluminum mullion cap at vertical mullions _ Add for 18" extruded aluminum cap at each operable clearstory window 10"x3.25" Aluminum channel & prefnished aluminum 0062 liner panel Alum storefront dooml leak with electrified panic hardware All glass doors - 1 W clear tempered glazing top and bottom full nil - Floor mounted auto opentom and panic hardware Glazingabove stain Additional testing on site Inmrer 1" clear law -E insulated glazing unit Interior glazing in sidelights 318" tempered glazing PAGE 50 1V�1 Newport BeachCieic Cen[erandPrrX waX Ntn, Beare CA BUILDERS SINCE 1919 _ OLI6111 .ea sn", l,za rs nrwr,a'' 16- Feb-II M7101 16 -Febl1 Budget# DescriptioniSrope of Work Quantity Unit Crebunit Total Interior 1/2" laminated glass fin acall son, ramps Interior glass guardrail Glass guardrail at bridge Architectural Metal Shelf for Projector (A7.05) Mock up Mockup for each form of construction for sliding aluminum - framed glass doors Mockup for each form of construction and finish for aluminumdamed entrances and storefronts Mockup for each form of construction and finish for glazed aluminum certain wells Mockup for each form of construction and finish for sloped glazing assemblies Mockup for each form of construction and finish for aluminum windows Site water testing 1.0 each 15,000.00 15,000 Add for acoustical requirements Community room Fxteriorl" clear IOW -E insulated glazing unit butt glazed Exterior insulated aluminum closure, glazed alum curtain.11, with 18- deep extruded alum CW end caps at eras, side of each operable window Operable motorized awning aluminum window Exterior glared aluminum curtain walls at north entrance with I set of entrance doors SW x 10.0" each lea[ Panic hardware and power assisted. swings 180 degrees Extruded AL Fins supported by & to match CW mullions Add for 6 single doors; 6 double doors: Add for acoustical requirements STC 35-per sketch Add for 10" extruded AL mullion cap at venial mlliona Add for IB" extruded AL cap at each operable clearstory window Prefinished alum perimeter channel Testing Chambers Type 11 curtain wall framing system, butt glazed Add for zoixa ical requirements at glazed - curtamwall STC40 Interior 111" laminated glass wl 1 1/2" x I la" alum extruded channels installed flush with fabric wall panels and floor PAGE 51 Nrw,nt 6... Civic C aprk exJ uzu, xvM Q V i P Newoort Beach cA 16-letsd I dPi1.DERS SINC9 1939 #87101 02116111 16- Feb -II PACE 52 Budget# Description/Scope of Woric Quantity unit Cosb'unit Total Interior type 11 curtain wall framing system, butt glazed at venibule w I set of double doors Alum hi-field doors w/ glass panels STC 40 Nana wall owner Alownace Doer leave Testing Library Exterior I" dear low -E insulated glazing unit bum glazed with I set of double doors Exterior I" chair low -E insulated glazing unit fully tempered. with I set of aluminum sliding entrance doors, I set of double doors Exterior 1 "spandrel pattern insulating glazing unit Extruded horizontal aluminum fins Extruded vertical alum fins supported by venial cw mullion Extruded CW W /10" alum fins at vertical mullion caps above T AFF Operable motorized awning aluminum window - A - I" clear low -E insulated glass Interior 318" tempered storefront glazing w/ 4 single leaf glass doors Interior glass guardrail above stairs Automatic sliding doors - Door leaves Add for 10" extruded AL mullion ap at vertical mullions Add for 10"x3.25" AL channel It prefinished liner panel Add for acoustical requirements Testing ],310.000 4 Attempt, s M. Grand Total Aluminum-framed Enter 1,310,000 t 085113 MCA:, A,11" 2aY jnfor 1!;" Pgoinglalp Piz s applicable 08 80 00 with Alum curtain wall ARcructe i a4. Grand Total Aluminum Windows PACE 52 Newport Bead C c Center and Park Wgiver N snort Beach. CA BVILDERS SINCE 1919 02116111 lxx¢ . VI&II IazaPM o�.2a: 16-Feb l l X87101 16-Feb -II PAGE 53 Budget# DescriptionlSimpe of Work Quantity Unit CostfUnit Total 09 29 00 `: 54000 Cold formed metal Gaming 61600 Sheathing (at cold formed metal framing). not in spea 72500 Weather barrier (at plaster). 92117 Gypsum shaft wall assemblies 92216 Non - structural metal framing 92350 Acoustical plaster ceilings 92400 Portland cement plaster 92900 Gypsum board Subcontractor proposal 1.0 Isum 2,627,000.00 2,627,000 Phase III Wall I hour Wall I shaft 180& 168 Wall Drywall only extra Wall NR Wall not rated, full height A4c A4d Wall not rated, full height dwx3 A4f Wall not rated, full height dwx4 A41b Wall chase With chase A4a, 04 Wall studs only Man stretch wall HM tames install Gypboard railings Resiliently suspended ceiling per A&31- 518" plywood between 2layers of 5/8" gyp with 2" acoustical treatment Gyp & Insulated builders plenum above finish ceiling Gypboard at ceiling at stretched fabric Gypboard soot break Exterior curb sill window 4/A5.I 1Tint Exterior curb Iamb window 41111 exterior & imonor Exterior wall zinc. exterior & interior Fire proofing separation Ihour A to B Wall furring at perimeter plywood at panels Membrane at panels Misc dens shield Misc backing Frame VAC units - double GB layer Frame mechanial doghouse Sound isolated ceiling hangers Double layer of vapor barrier 120,484.0 sift 0J5 90,363 Mockup of 100 soft for each type of finish Mockup of 100 sgft for each level cf gyp bd finish PAGE 53 1MY/AIY Vr Newport 6earl,CAd Centerand Park NewnaK Beach CA RUI Lllggfi SINCE 1919 SCOPE AND PRICING SHEETS 02116111 emm: Wien Ixvm h va` 16- Feb -II YBnol I6 Feb -I I Budget# Description /Scope of Work Quantity Unit Cost/Unit Total Mockup smoke damper installation complete 40.0 mnhr 65.00 2,600 with wall framing wallboard, wall opening filler pieces. perimeter mounting angles, sleeve, breakaway, duct connections, and duct smoke detector access door Community room Wall I shaft Wall not rated, hill height Mc, A4d Wall chase Ma. C4 Wall furring at perimeter Wall studs only Min stretch wall HM tames install Gypboard ceilings Gypboard soffit cove Framing of exterior wall for stone exterior only 2hr wall Framing for exterior wall framing at zinc shingles. Includes fire- created plywood at zinc wall panel assemblies Membrane at panels Exterior curb sill window interior Exterior curb jamb window exterior & interior Misr dens shield Misc backing Chambers Wall I hour Wall not rated, full height dwx3 A4f Wall not rated, full height dwx4 A4h Wall chase A4a, C4 Wall furring at perimeter Gypboard ceilings Gypbmrd soffit break Gypboard soffit cove Wall furring at window heed interior Exterior wall stone exterior only Exterior wall framing at zinc shingles. Includes fire - treated plywood at zinc wall panel assemblies (2/A5.02 and 5,1 IIA5.21)) Membrane at panels Misr dens shield Protective wrap Library Wall chase Wall I shah Wall not rated, full height Mr, A4d Wall not rated, full height dwx4 A4h PAGE 54 1 M1 iJl yl�/r Neweart Beach Civic Can and Fart big,, Beach CA Rni1.DA63 SINCE 1919 OV16111 n,'w: viols lz FH P�— 16 -Feb -II %87101 16 -Feb -II PACE 55 Budget# Description/5cope of Work Quantity Unit Cose'Unit Total Wall furring at perimeter HM frames install Gypbwrd ceilings 1,844.0 Gypbwrd at ceiling at stretched fabric Acoustic plaster ceiling 5/8" Vertical gyp soft at ceiling perimeter Gypboard soffit cove Eaterior wall dear story roof interior also Exterior curb sill window 4/A5.11 3' interior Extender curb sill window roof closure slab edge Exterior wall zinc. exterior & interior Includes fire - treated plywood at zinc wall panel assemblies (2/A5.02 and 5, I VA5.21)) Membrane at panels Eaterior plaster soft Acoustical plaster treatment at the skylight Plywood at sound wall Mist dens shield BY CWD Protealve wrap 1.0 Isum 65.000.00 65,000 Mist backing In all buildings Caulking of through penetrations- additional caulking required due to HVAC requirements , Sheet metal sleeves at through penetrations Sheet pads and caulking at wall box penetrations - Primer for drywall finishes Framing for wood ceilings. Engineering and shop dawings for the exterior metal stud Gaming. Scaffolding level Finish. 2,784.963 VE Grand Total Gypsum Board 2,784,963 093013 WEN-H P. 1OW LMAN,:aar ' –..ah. i Sub Proposal 1.0 Issue 181,635.00 181,635 Phase III PACE 55 Iex, ��� Newport Beach Civic Centar and Park �lw No Beach. CA BUILDERS SINCE 1919 02116111 Mn.t mm1 labs Pn hwnd, 16- Feb-II M7101 16 -Feb II PACE 56 Budget# Description /Scope at Work Quantity Unit CostlUnit Total Ceramic the flooring OCT) Ceramic rile flooring (CT 2) Ceramic die walls Ceramic tile base Crack protection membrane 1,936.0 sqh 1.01 1.963 Mockup of floor and wall file 1.0 a11w 650.00 650 Acoustic at 696.0 sqft 2.00 1,392 Community room Ceramic tile flooring Ceramic the walls Ceramic ti1e base - Crack protection membrane 813.0 sqh 1.01 824 Chambers Ceramic file flooring Ceramic file walls Ceramic tile base Crack protection membrane 111.0 sqk 1.01 113 Library Ceramic tile flooring Ceramic tile floonng(Tile 1) Ceramic die walls Ceramic tile base Crack protection membrane 3,387.0 sqk 1.01 3,434 Acoustic at 3,387.0 sqk 2.00 6,774 Undefined floor finish per clarification 10, assuming tile 937:0 sqh 18.25 17.100 Undefined base per clariflcadon 10. assuming die 248.01nh 22.09 5,456 219.340 Alt,. tes Grand Total Ceramic Tiling 219,340 OM,1109,511 '13 Subcontractor Proposal 1.0 Isum 2,180,000.00 2,180.000 09 54 26 Linear Wood Ceilings 09 54 30 Tile Wood Ceilings Phase III Acoustical panels for acoustical panel ceiling - ACPI Interior linear wood ceiling by 9 wood with aromcdc backing Exterior linear wood ceiling by 9 wood Protective mesh at Exterior linear wood ceiling by 9 wood PACE 56 Q.W. Driver Nawoart Beach CiAc Ceareraad Park �/Nnwpnrt Beach CA BGILDP-BS SINCE 1919 OU16111 ,rr. viol rloiipm rKwraa: 16- Feb-11 M7101 16- Feb-II PAGE 57 Budget# Description /Scope of Work Quantity Unit Cost/Unit Total 4-ft-by-,I-ft Mock -up of the sound absorptive finish system replicating relative details and conditions - Suspended acoustical at stairs Ceiling in basement - Mockup linear wood ceiling assembly and anchorage system Treatment of the line between ceiling and due verticai wood 875.0 Inh 35.00 30,625 Community room Acoustical panels for acoustical panel ailing - ACP I - washable in kitchen Interior linear wood ceiling by 9 wood with acoustic backing Exterior linear wood ceiling by 9 wood Protective mesh at Exterior linear wood ceiling by 9 wood Metal detail at wood ceilings 1.0 Isum 12,555.00 12,555 Chambers Acoustical ceiling file type 2 with recessed Fluorocentfixture, - Sloped woad ceiling d recessed light troughs Acoustic backing at sloped wood ceiling Interior linear wood ceiling by 9 mod with acoustic backing Acoustic backing at linear wood ceiling Metal panel ceiling on 3 -5/8" studs with insulation at Vestibule 175.0 sqk 22.00 3,850 Library Acousticalpanelsforacousticalpanelceiling - ACPI ACP2 Cafl ceiling 632.0 sqh 27.00 17,064 Metal panel ceiling on 3 -5 /8" studs with insulation per 21115.05 M1.0 sqh 22.00 9,702 2.253.796 Allotmetet Grand Total Acoustical Panel Ceiling 2,253,796 . s4 43 09 54 40 Stretched PVC ceiling Systems 0917 13 Stretched Fabric Wall Systems Phase 111 Stretched fabric ceiling 3.300.0 sqh 2531 83,516 Stretched fabric wall panel 9,927.0 sqh 15.00 148,905 PAGE 57 Nei Newport Beach Civic Center and Park 1�1 �( Neil Beach CA N tYILfl N.R3 SINCE 1919 02116/11 Mnxf: .lull ixlaM 16- Feb-II #07101 16- Feb-II PAGE 58 Budget# Description/Scope of Work Quantity unit Costfunit Total Vinyl ceiling 2,400.0 sqk 42.00 100,800 Mockup of 3 -0 x3 -0 assembled ceiling system 1.0 allw 2.000.00 2,000 Wall mockup of typical wall area, including intersection of wall and ceiling corners, and perimeters 1.0 2,500.00 2,500 Community room Fabric wall panels 603.0 sqft 18.00 10,854 Tackable fabric panels 1,934.0 calk 7.00 13,538 Fabric panel on operable wall assembly 097723 with owner allowance Chambers Stretched fabric wall (FAB) 2,642.0 sqft E.W 47,556 Library sqk Stretched fabric wall (FAB) sqft 409,669 Alt ans, Grand Total Stretched Fabric Ceilinf 409,669 99,te5 19 096513 Resilient ease and Accessories 096536 With access floor 0965 16 Resilient Sheet Flooring 096519 Resilient Tile Flooring 096813 Tile Carpeting 096816 Sheet Carpeting Subcontractor Proposal 1.0 loan 326,425.00 - 326,425 Phase 111 CPT type I - carpet tile w/ attic stock and mock up Attic stock and mock up Rubber sheet flooring type 2 w attic stock and mock up Rubber floor tiles type I w attic stock and mockup Moisture test and remediation 49,8310 sqft 0.35 17,441 Mockup 100 sq. R for each type, color and pattern of resiliem sheet flouring 100.0 sqft 5.07 507 Mockup I sal. ft. for each type, color and pattern of resilient tile flooring 100.0 sqft 5.07 507 Tile carpet mockup 100.0 sgft 507 507 Sheet carpet mockup 100.0 sgft SW 507 Resilient base Ink 100 PAGE 58 GYY. L11 �V Naw nsewn C..,,.a.d P.. "1.: .1.11 ixxm + Newport Heach. CG 16 -Feb l l RUILOENS SINCH 1919 47101 O1II6111 16- Feb -II PAGE 59 [xJ �� Noi Beach Civic CanMrand Park �(� NNNnort Beach. CO RIi1LDKRS SINCE 1919 OL1611I Rln¢i L1411123B FT1 ir,o.e: 16- Feb -11 NB71o1 16- Feb -II PAGE 60 BodgetN Descri ptioNRupe of Work Quantity Unit CosNUnk Total "factory¢pplied" rile . SDT static dissipative lubber as shown on Sheet A3.01 and Section 096536 Anchors for extra once Uwe load at second floor 36,000.0 sgft 1.25 45,000 Protect the flooraher installation - tape and cover with masonite - by GC ?- uncover 8,000.0 sqh 1.00 8,000 Coordination with nades -by GC? 693.3 mnhr 49.00 33,973 Seismic arid, 72,000.0 sqh 0.20 14,400 Equipment tie downs 200.0 each 121.66 24,331 09 69 00 Mockup of 3 floor panels in length by 3 floor ,mal, in width. Include condition around column and at slab edge all. inlcuded Independent Testing of Access Floor Plenum inlcuded - Community room Chambers added `: Bare fnish access floor with factory applied die Library 1,201,823 Ahsm¢tea - - - Grand Total Access Floor 1201.823 1 _ _ 09 91 �p0' 099600 Nigh Performance Coatings 099713.33 site Paines Phase 111 Subcontractor proposal 10 Isum 630,894.00 630,894 add for LEED paint from the specified 1.0 Isum 15,000.00 15,000 phase III Exterior steel paint - high performance Exterior - sail steel - high performance I.01mm 750.00 750 Interior steel paint - high performance Mist flashing, not stainless steel Doors Gyp walls Gyp walls (primer only) Gyp ceilings Gyp stMtz Additional mobilization for metal deck treatment 1.0 Isum 1.520.70 1,521 Prepare exposed part of metal deck Mist flashing, not stainless steel PAGE 60 R.A.i 1�L. /liY4r �Pnrt Death Clair Center and Park Newoort eea.n. GA at.16DP8R SMP 1019 OWWI I Nn¢tl: LlNll lk)8iM a ,uJ: 16- Feb -11 07101 16- Feb -II PAGE 61 Budget# Description/Scope of Work Quantity Unit Cost/Unit Total 0991 13 Mockup 100 sqft horizontal and vertical surfaces Mist touch up after ocher trades 1.0 Isum 15,000.00 15,000 Mist caulking and paint at wood I MDF base 099600 High performance coating mockup Community room See scope above Chambers see scepe above Library see scope above Plaster ceilings Paint Temp barricade Paint the existing visible finishes Limestone plaster soffit Acoustical plaster touch up South Park Paint miscellaneous site items Central Park Paint miscellaneous site items Prep time Ipe deck for treatment LO Isum 12,000.00 12,000 Paint structural steel bridges North Park Paint miscellaneous site items 675,165 Blte[aBtoa MM Grand Total Painting 675,165 ='.10 2113 M-, 1- 10 2800 Toilet, Rath, and Laundry Accessories 088300 Mirrors Phase 111 Subcomactor proposal 1.0 Isum 63,183.00 63,183 Gab bar Toilet tissue dispenser B -2840 surface mounted toilet dispenser and utility shelf Liquid soap dispenser Sanitary napkin disposal unit Toilet seat cover dispenser PAGE 61 ei�T �y �n Newnan Beach Civic Center and Park �(x 1 Nia nrt Beach. CA BUILDERS SINCE 1919 01116111 hinaE' snalI Lai wro•.d: 16- Feb-11 #BII01 16 -Feb I I Budget# Description/Scopes of Work Quantity Unit CcuVUnit Total Combination towel dispenseriwaste receptacle - folded towels B -38034 trimline series recessed paper towel dispenser and waste receptacle Urinal screen Toilet partition Toilet partition HC Mirror- backlit2'- 4"x4' -5" 101 Mims , oackft2'- 4 °x4' -10" 102800H Shower curtain rod Shower curtain Folding shower seat Soap dish Towel pin Utility shelf Mop and broom holder paper towel dispenser. folded towels Towel holders Under lavatory Guards Sanitary napkin vendor Warm air dryers add for bulletin l for sandblasted mirrors 1.0 lsum 7.500.00 7.500 Community room Grab bar Toilet tissue dispenser B -2840 surface mounted toilet dispenser and utility shelf Liquid soap dispenser Vendor sanitary napkin Sanitary napkin disposal unit Toilet seat cover dispenser Combination towel dispenser /waste receptacle - folded towels 3-38034 trimline series recessed paper towel dispenser and waste receptacle Warm air dryers Diaper changing station baby changing station KB 110 -SSRE horizontal recessed stainless steel baby changing station Mirror - backlit 2' - 4' x 5. 102800H Urinal screen Toilet partition Toilet partition HC Paper towel dispenser. folded towels Multipurpose soap /towel dispenser unit Under lavaory Guards Chambers Grab bar Toilet tissue dispenser B -2840 surface punted toilet dispenser and utility shelf PAGE 62 bisatiourt Bach Civic Centarsnd Fork LINII .. • W DI1V 1 NrwPslft Reach- CA ".lee I6-Feb -II BUILDERS SINCE 1919 M7101 02116/11 16- Feb-11 PAGE 63 • Budget# Description/Scope of Work Quantity Unit Cost/Unit Total Liquid soap dispenser Vendor sanitary mpkin Saniary mpkin disposal unit Toilet seat cover dispenser Combination towel dispenserMaste receptacle - folded towels B -38034 trindine series recessed paper towel dispenser and waste receptade Mirror 2' x T mirrar 102800H Under lavatory Guards Library 1.0 Isom 14,446.65 14,447 Grab bar Toilet tissue dispenser B -2840 surface mounted toilet dispenser and utility shelf Liquid soap dispenser Vendor. sanitary napkin Sanitary napkin disposal unit Toilet seat cover dispenser Combinaton towel disperser/waste receptacle - folded towels B -38034 trimline series recessed paper towel dispenser and waste receptacle Dauer changing station baby changing station - KB 110 - ARE horizontal recessed stainless steel baby changing sation Urinal screen Toilet partition Toilet partition HC Mirror - backlit 2' - 4'x 4'- 9' 102MH Utility Shelf Mop and broom holder Paper towel dispenser. folded rowels Towel holders Under lavatory Guards warm air dryers 85,130 Alternates Grand Total Toilet Compartments 85.130 n iyi' .089000 'LL 1- is.� -: w,C�!'I .il� I Room Phase III with sheet metal Louvers Louvers at merhanimi penthouses Louvers in chiller room PAGE 63 M`� T Driver Newport Beach CIVIC Center and Park enmd: LI411 lain m . Newport Beach CA aw:m: 16- Feb. ll BUILDERS SINCE I91e 967101 SCOPE AND PRICING SHEETS OU16 111 I&Feb-II Budget# Description /Scope of Work Quantity Unit CosUUnit Total Community room Louvers Louvers at mechanical penthouses Chambers 4 Locations; I wl a concealed door Add for concealed door Library Louve Add for concealed door ' Alternate Grand Total Louvers & Vents 10 36'00 Phase III Corner guards 10.0 each 228.11 2,281 Wall and corner guards LO sun 1,576.46 1,576 Ccennummit, room Wall and termer guards I.0 Isum 1,576.46 1,576 Chambers Wall and corner guards 1.0 hum 1.576.46 1,576 Library Wall and corner guards 1.0 Isum 1.576.96 1,576 8.587 u: Altair, I Grand Total Wall and Door Protecti 8.587 10 11 06 s. Phase III Bulletin beards / white boards 1.0 Isum 10.138.00 10.138 Storage cages in the basement 1.0 Isum 7,603.50 7.604 1011 00 Visual display board mockup for each form of 1.0 Isum unction 800.00 800 PAGE 64 Q.W. Driver thospot Beach C v c Center and Park Newport 8earh. CA KVILDERS SINCE I9I9 .1e, I Mom 16- Feb-II A7101 PAGE 65 16- Feb -11 Budget# DescriptioniScope of Work Quantity Unit Cost/Unit Total 18,542 nest Grand Total Visual Display Surfaces 18,542 10=4 See allowances Altemsous Grand Total Signage l q 51 13 Phase III Metal lockers 18.0 Ink 465.33 8,376 Locker benches - bench cops: laminated clear 22.0 Ink 278.80 6,133 hardwood: fireascandfing pedestals; stainless ,.el 14.510 Alternates Grand Total Metal Lockers 14,510 10 44 A 3 104416 Fire E.d.g.mbnrs Phase III Fire extinguishers 20.0 each 228.11 4,562 Community mom Rne extinguishers 4.0 each 278,11 912 Chambers Fire extinguishers 4.0 each 228.11 912 Library Fire extinguishers 4.0 each 228.11 912 7.299 Alt.'rnn, PAGE 65 Wall Beach Civic Center and Park .1 to Hildisilloart Beach. CA BVIL]l SINCE 1919 16- Feb -II M7101 PAGE 66 16-lceb I I BudWt# Description /Scope of Work Quantity Unit CosdUnit Total Grand Total Fire Extinguishers 7,299 Phase III with alacmail Command center Birailiont,..., Sound masking Dil displays Community room Community room Chambers City council chamber, NBTV room, video conference room Library Library media lab Alternates Grand Total Audiovisual Systems Phase III Audiovisual equipment is with Electric.] Phase III TV's 1.0 each with a/ v Community room Retractable projector screen w/ 117' x 68" 1.0 each proj screen w/ tack wall behind 12,000.00 12,00 Video projector 1.0 each with a/ v Mauro 10 each 1,100.00 1.100 Chambers 7'x 6' Projection screen 410 s,fit 65.00 2.730 13'3" x 8' Projection screen 107.0 sqft 75.00 8,025 V x 6' Projection screen 96.0 sqh 6500 6,240 Mounts 3.0 each IrS00100 4,500 TVs in NBTV room - none shown 3.0 each with a/ v Ws 3.0 each with a/ v Library PAGE 66 ].�./+.iver Nnwnnn 8p,ch Cilk CenM� C 1f� and Park Newport Beach CA BUILDERS SINCE 1919 SCOPE AND PRICING SHEETS AInW: WWII Ii pm r�mrea_ 16 -FeW I pWIDI OV16111 16- Feb-II PAGE 67 Newport Beath Ciy a Center and Park n6,rc : sr.f ada M Q.W. D iSp� No 16 -Fel>I I 861LDEHS SINCE 1919 47101 03116111 16- Feb-II Budget# Description /Scope of Work Quantity Unit CostfUnit Total 21,425 Alternated Grand Total Residential Appliances 21.425 By Owner s BBsraatet Grand Total Artwork 12 2413 Subcontractor Proposal 1.0 Isum 167.800.00 167,800 Phase III Internal shading type IT manual shade list Floor) "Internal shading type 12' light fiherng and BMS controlled shade' Internal shading type 10' manual shade (2nd Floor) Sheet metal closure V AS. I 1 1.0 Isum 9.700.0 9,700 . Community room Internal shading type 12' motorized fight Moaning &blackout shade add for high quality blackout shade not included Chambers Add for the shade going up 1.0 bum 3,500.0 3,500 Internal shading type 14'motorized light filtering & blackout shade Internal shading type IT motorized light filtering & blackout shade - " Blackoua shade -at skylight Library Internal shading type 12' manual shade (I St Floor) Internal shading type 12' Tight filtering and BMS controlled shade Shading at skylight (if necessary - none shown) not included 181.000 Blteou t, PACE 68 NwnnvtR chCivcCentorandPark . a LINIII.1P C. VDriver 16 -Feb I I MAIII)EKS SINCE M9 467141 OLI&I I 16 -Feb -I I PAGE 69 � "nrt R cA Civic Center and park L,., I1.. 1 Llive� Newport Beach CA nw•2a. 16 -FeWI BUILDERS SINCE 1919 M7101 O V 16111 16Feb -I PAGE 70 q ]�� Hewoort Beach Civic Center and Park �/ �' dgylport Bear_h. CG Rl11LDERS SINCE 1919 02116111 v.m,ea u1xu laaean pewee: 16- Feb-II 087101 16 -Feb I 1 PAUL 71 Budget# DescriptioNScope of Work Quantity Unit CostlUnit Total 015.1 Fire Protection 1.0 lsum 667,156 667,156 Phase III Fire sprinklers including the area above the ood ceiling - curved in some places Fire sprinklers at roof overhang not included Fire sprinklers at access goo, not included Community room Add for kitchen -Fire sprinWers Chambers Library pp TO Edit 0 ¢Rtr t'i� �{IDI q i Sysfern fSlnclu'de14nJocatl € i75. .i Add for Lying into existing system at the library 1.0 Isom 2,777.00 2,777 Fire watch 32.0 mnh 77.00 2,464 672,397 Aar Grand Total Fire Protection 672.397' MOM22 00 00 220500 Common work results for plumbing 220519 Meters and gauges for plumbing piping 220523 General duty valves for Plumbing piping 22 05 29 Hangers and supports for plumbing piping and equipment 2205 53 Identification for plumbing piping and equipment 220700 Plumbing insulation 22 11 16 Domestic water piping 22 11 19 Domestic water piping specialties 22 13 16 Sanitary waste and vent piping 22 13 19 Sanitary waste piping specialties 22 U 29 Submersible Pump Systems 22 14 13 Facility storm drainage piping 223300 Electric domestic water beaten 223400 Fuel -fired domestic water heaters 224000 Plumbing natures 224900 Facility natural as piping 235100 Breerbings, chimneys and stacks u applies 31 23 33 Trenching and Backfilling 015.2 plumbing 1.0 [sum 907.030.0 987,030 Phase III PAUL 71 Q.W. �T1Y.,/T' Nownort Bsah Civic Center and Park Naffi, Beach. CA BUILDERS SINCE 1919 0L16111 nbW: LIe111 esiN nwaa i6- Feb -II A7101 16- Feb -II PAGE 72 Budget# DescriptioniScope of Work Quantity Unit Cost/Unit Total Sanitary waste and vent Storm drainage All underground plumbing to Sit line Domestic water systems Pipe & duct hu.ladon Rain leader piping Low flow plumbing fixtures WH/ I Gas water heater SE-I Sewage ejector SP -I Sump pump WC -I Water closet (handy) WC -2 Water dose[ LAV -I Lav handy UR -1 Urinal -light powered and charge themselves -per meeting on 10 -6 -10 SK -1 Sink MS -I Mop sink FD -I Floor dram 2" FD -2 Floor drain 4" ED -I Equipment drain HB -I Hose bib Show, 4" Roof &overflow drain - Roof & overflow drain going through glass 36.0 loc 475.00 17.100 FCO Boor cleanout PRV station (Pressure Reducing Valve) Kitchenette rough in Mist sound prorection measures 120.484.0 sqk 0.44 53,013 Gas regulator SK4 - sink not on legend Recycled water connection Community room Sanitary waste and vent Storm drainage as shown All underground plumbing to S@ line , Domestic water systems Pipe & duct insulation Rain leader piping Low flow plumbing Fixtures WC -I Water ckno,(Handy) WC -2 Water closet LAV.I Lav handy UR -1 Urinal -light powered and charge themselves - per meeting on 10 -6 -10 UR -I Urinal -light powered and charge themselves - per meeting on 10.6 -10 DF-I Drinking fountain FD -I Floor drain HB -I Hose bib Kitchen sink Janitor sink - PAGE 72 hEad,aurt peach Clvlc Cemu Pat LM1tiriver Newport Beach CA RU DERS SINCE 1915 i 02116/11 .,. LINII Imin1 hm =�: 16- Feb-II 487101 16- Feb-II Budgeng DescrfpUONSCOpe of Work Quantity Unit Coso'Unit Total Roof drain Refrigerator rough in Additional sound promotion measures for domestic lines in sound rated walls WCO 4" Storm drain FOE 5" Sanitary sewer POC Chambers Sanitary waste and vent Storm drainage as shown All underground plumbing to 5k line Domestic water systems Pipe & duct insulation Low flow plumbing fixtures EWHII Instant water heater WC -I Water closet (Handy) SK -I Sink Iav -2 FD -I Floor drain Roof drain Janitor sink Library Sanitary waste and vent Storm drainage as shown All underground plumbing to Sft line Domestic water systems Pipe & duct insulation Low flow, plumbing fixtures SK -I Sink WC -1 Waterdeset(Handy) WC -2 Water closet I.R -I Urinal -light powered and charge themselves -per meeting on 10-6 -10 DF -I Drinking fountain FD -I -Floor drain 2" FD -2 - Floor drain 4" Additional sound protection measures for domestic lines in sound rated walls Janitor sink ED -I - Equipment drain - 2" acid resistant coated Flex connection across seismic joint at library POC ac library Connect to existing CW Park Drinking fountain 2.0 ea 4,555.00 9.110 PAGE 73 Nsexplut Ranch Civis, Cwdo,od Park Maim Newport Beach. CA KCIIA)ERS S"ICC IqI9 OW16111 I sod zle" .'r Kwook 16-Feb4i n7 of 16-Feb- I I PACE 74 Budget# D.tcripticau/Scope, of Work Quantity Unit Cost/Unit Total 1.066.253 Aftmuffes Grand Total Plumbing 1,066,253 2340 QU„ 23 0500 Common work results for HVAC 230513 Common motor requirements for HVAC equipment 230516 Expansion fittings and loops for HVAC piping 230519 Meters and gauges for HVAC piping 230523 General duty valves for HVAC piping 230529 HVAC Supports, guldes, h.,er and anchors 230530 Pipe and pip. Ind., 230548 Vibration I solation and seismic restraints 23 05 53 Identification for HVAC Piping and Equipment 23 OS 93 Testing. Adjusting, and Balancing for HVAC 230713 Ductwork insulation 230216 HVAC equipment insulation 230719 HVAC piping insulation 230800 C.norioume., for HVAC Support only 230903 Operator workstations 23 09 23 Instrumentation and controls for HVAC 230993 Sequence ofoperatkmx for HVAC control 232116 Hydronic piping specialties 232118 Underground chilled water piping 232123 Hydrunic Pumps 232300 Refrigeration piping sad specialties 23 25 00 Water treatment 23 31 13 HVAC sheet metal ductwork 23 31 16 HVAC flexible ductwork 23 33 00 Air duct accessories 233400 HVAC fans 233600 Air Terminal Units (23 36 00 Air Flow Control Devices) 23 37 ❑ Diffusers, registers and grilles 234100 Air treatment equipment (filters) 2351 00 Breechings, chimneys and stacks The boiler chimney is in the plus 235216 Condensing boilers 23 57 00 Heat exchangers for HVAC 23 64 23 St,1.11 water chillers 236500 Cooling 1--a 237300 Customized central station air handling its PACE 74 CW��` NewoortBeachCiv'c Center and Park �(V YV N=R,n Beach. CA 81;1 DD,RS SINCE 1919 OV16111 hmeN. )ntlll ream nm•p+: 16- Feb-11 M1a1 16- Feb-II PAGE 75 Budget# DescriptioN5cope of Work Quantity Unit Costlunit Total 238123 Computer Room Air Handling Units 238126 Split system air conditioners 2382 19 Fan coils 238233 Perimeter terminal Unit Heater (23 82 33 Convectors) 238316 Radiant beside, hydrant piping as applies 312333 Trenching and Back011in, 336113 Underground Hydronic Energy Distribution 015.3 HVAC Acouzdcal Isolation Phase 111 HVACtubpropeel 1.0 Isum 6,906,529.00 6.906.529 Chilled water system High efficient, screw chillers of 179 tons High efficiency screw chillers of 106 tons Chilled water pumps VFDs for chilled water pumps. 4500 MBTH external cooling tower Conden er water pumps - Chilled water distribution for each (5) ai handlers Underground condensing water piping including excavation and backfill Underground chilled and heating hot water including excavation and backfill Heating Hot Water System Condensing boilers -high efficiency 799 MBTUH each, Hot water pumps to circulate hot water VFDs for hot water pumps Heating hot water distribution piping to serve the (5) air handlers and the heating reheat ones 4500 MBTH external cooling tower Chilled and heating water air handlers wl VFD Relief /exhaust fans serving the 3 or handling units Under floor cooling zones with perimeter reheat Under poor swirl diffusers Under floor 4 foot floor linear with reheat coil -for radiant hating Under floor supply lnear diffuser at perimeter Package stand alone dx far coil unit- VRV type with a common condenser 13 Units will have dedicated condensing units. Hebert Stand alone split stems Sound taps Exterior wall louvers Additional acoustical isolation 90.219.0 sgft 060 54,131 PAGE 75 C Driver N.wonn Beach Civic CnnMrand Park Newoort Heath. GO 1101,D kits 81NC8 1919 OU16111 me"a, meu ram 's ny.rte. 16 -Feb -II M7101 I&Feb - II PAGE 76 Budget# Description/Scope of Work Quantity Unit Costfunit Total Thermal expansion and seismic separation joints 1.0 bum 33,000.00 33.000 Controls Title 24 insulation - Air test and balance 23 05 29 Mockup of each type of pipe support conditions (hangar, penetration, fire stop) 12.0 each 656.00 7,872 233300 Mockup smoke damper installation complete with wall framing, wallboard, wall opening filler piec s, perimeter mounting angles, sleeve, breakaway duct connection, and duct smoke detector access doer 1.0 Isum 4,555.00 4,555 Community room Chilled and heating water air handler Relieflexhaust 0n serving the air handling unit Radiant cooling/hating Cooling only VAV zones for kitchen and controls rooms Exhaust for Witcher. and support spaces. Place and frame heat exchanger to serve radiant floor in community room Dedicated cooling radiant system - Under floor duct mains for ventilation are included and intended for installation in wench by others Controls 2" of "PEPP lining" at Area Way 0050 at the basement of the Civic Center per note 12, HIM. 2.976.0 stir 2.75 8,184 Additional acoustical isolation 7.177.0 sift, 050 3,589 Tide 24 insulation included Air test and balance Chambers Chilled and heating water air handler Relieflexhaust fan serving the air handling unit General exhaust for support spaces. Under floor duct mains for ventilation are included and intended for installation in the trench by others Under floor swirl diffusers Under floor duct mains for ventilation are included and intended for installation in trench by others Controls Additional acoustical isolation 5.816.0 stir 1.00 5,816 Title 24 insulation included PAGE 76 C W Driver NHwoort Radish C'v''c Center and Park yW' Newport Beach. CA RUILI3ERS SINCE 1919 01116/11 AInW: LINII Isaifn n�aa: I&Febl I M7101 16 -Feb -II PAGE 77 BudgettF DescriptioNScope of Work Quantity Unit Cosb'Unit Total Air rest and balance Library Instal l remove temp filters for the remodel 1.0 Isom 2.500.00 2,500 DX Custom package AHU Split system VRV Fan coil - P.xhaust fans VAV zones with supply and return diffusers Controls Sub contractor cost for relocation of utilities from existing plant with phase I Additional acoustical isolation ark 1.50 Tide 24 insulation -sqk included Air rest and balance only for addition sgft 1.01 Air contend balance for the entire building is not included not inddded 7.026.176 : Al�ei Grand Total HVAC 7,026,176 26.00.00: :. 1 260500 Common Work Results For Electrical 2605 19 Low Voltage Electrical Power Conductors And Cable 260S 26 Grounding And Bonding For Electrical Systems 260529 Mangers And Supports For Electrical System 260533 Raceway And Boxes For Electrical Systems 26 05 53 Identification For Electrical Systems 260800 Commissioning Of Electrical Systems Support only 260933 Central Dimming Lighting Controls 260926 Lighting Controls 26 2200 Low Voltage Tram ommrs 262413 Switchboards 262416 Panslboards 262713 Electricity Metering 262719 Modular Wiring Systems (Addendum #1) 262726 Wiring Devices 262816 Switches and Circuit Breakers 262913 Enclosed Motor Controllers 262923 Variable Frequency Drives 263200 Packaged Generator Assemblies PAGE 77 Na Beach Cw ase COn a,d Pavk C Driver Newport Beach. CA BUILDERS SINCE 1919 OV16111 Pma4' .1.111. of wm..d. 16- Feb -II M7101 16 -Feb I I PAGE 78 Budget/l Description /Scope oFWork Quantity Unit cost/Unit Total 263623 Pumnoidc Transfer Switches 26 51 00 Interior Lighting 265600 Exterior Lighting - Lighting Future Schedule as applies 31 23 33 Trenching and Backfilling 27410 Audio visual system Sound Masking system Mass Ex Street lightfoccoial adjustments by owner Phase III 019.1 Ell sun proposal 1.0 Isum A40 8.664.00 9,40 &664 Electrical - including Coordination drawings /BIM support Primary, secondary & emergency site (eiders Normal and emergency switchgeor & feeders included Power feeders for equipment connections included Building lighting fixtures included Centralized lighting centrals utilizing control panels for specified levels of daylight harvesting and dimmable controls. incuded Lighting branch and local lighting control devices included Powerbmnch, devices & miscellaneous equipment & shades connections included Complete voice/data system cabling and devices included Complete Ore alarm included Complete security system included Conduit for A system included A system included Design build fire alarm life safety system. included Use of c.de approved wiring methods. included Pardle1300kw generators. included Installation of VFDs and pump control panels furnished by others. included Use under floor power discribution systems. Included . Power distribution to future parking structure. included LEED certification support. included Connection of window actuator motors , assumes control by ro s included Empty conduits stubbed to within S' of future parking structure. included VE Delete concrete encasement ofthd ducts included South coast air quality management district permits. 1.0 allow 25,000.00 25.00 Temporary power Add for testing / grounding / coordination adjustments at raised floor 71.000.0 sqft 0.37 26,270 Fuel tank for generator with pad day tank only 26510 Interior lighting fixtures for room or module mockups, complete with power and control connections 1.0 [sum 6,500.00 6,500 Provide power at North Park kir Convoler 1.0 Isom 5,01 5,00 PAGE 78 � �� N^wnort Beach Givic center and Park Newport Beach CA BUILli SI�Cf, 1919 SCOPE AND PRICING SHEETS 02116/11 keee: vim, izssm nw.o. 16 -Feb 11 #8)101 6- Feb-II PAGE 79 Budget# DescriptionlScope of Work Quantity Unit Cost/Unit Total Theatrical lighting at sail on the piping Library See electrical description above Safe off at relocate existing utilities 1.0 allow 15.000.00 15,000 Large pendant fixture relocation 1.0 Isum 2.500.00 2,500 Down light relocation in above Emergency light relocation in above Column light relocation in above Fxit sign relocating in above book sack fixture removal and reworking in above Fire alarm in above audio speaker relocation in above duplex recepade relocation in above Adjustment for existing conditions/ coordinating with garage 400.0 mnhr 127.00 50,800 Site Lighting lemmas Security in the garage primary electric service Secondary elcccric scirviric Electrical transformer Connect to existing TV /telecomm/elearical Connect to existing TV/teleromm/electrical to remain junction box putty fresmp insulation in sound and fire rated walls -per 5 A9.02 356.0 each 147.50 54510 Fixtures to the garage 1.0 Isum 24.288.00 24.288 Connect / test fire alarm to Phase 111 1.0 Isum 4.555.00 4.555 Low voltage for fans for garage 1.0 Isum 5.110.00 5.110 VE Delete concrete encasement of the duffs accepted 9,626,197 AfternStsf Grand Total Electrical 9.626.197 ;'t�.S i,d!iiff 27 00 0U P 4 2705 00 Common Work Results For Communications Systems 2705 26 Grounding And Bonding For Telecommunications Systems 27 0S 28 Pathways For Communications Systems 27 OS 43 Communications Underground Ducts And Raceways 27 05 52 Identification For Communications Systems 27 11 00 Communications Equipment Room Fittings 271300 Communications Backbone cabling 27 15 00 Communications Horizontal Cabling - 2716 19 Communications Patch Cords, Station Cords &Grosz Connect Wine PAGE 79 GWDriver RVILORRS SINCE )919 No—ad OV16111 Hand Clsk, Copper and Park Ness SCOPE AND PRICING SHEETS vlsll I.. 16 -Feb -II 07101 16- Feb -II Budget# Description /Scope of Work Quantity Unit Cost/Unit Total 2y 51 19 Sound Meeting Systems r omentes Gravid Total IT 280000 Electronic Safety and Security 280513 Security Conductors and Cables 280610 Schedules For Electronic Access Crossed 280620 Schedules for Electronic Surveillance 26 0660 Schedules For Electronic Emergency Aid Devices 281000 Electronic Access Control and intrusion Detection System 282300 Electronic Surveillance System 282623 Electronic Emergenc,r Aid Devices 28 31 00 Fire Alarm System 2835 00 Refrigerant Detection and Alarm 285000 Unintoomptible Power Supply System 286000 Security Consoles and Cabinets N,kfir, Ga., L. volts, 10 Isum with electrical r Altam, MEN= F- Grand Total Electronic Safety And S ISO ,,MOJ 23 00 Mftffi14 AjW'jjP I see e,m. file After.. PAGE 80 C.W. Driver N.wne Beach Chrc C....and Pe.p �• W+ NN oft Beach CA RUILDEES SINCE 1919 Aa•�: 16 -Febll M7101 03/16111 16- Feb-II PACE 81 C.W. Driver Ill LDBRS SINGES 1919 Newport Beach Civic Center and Park Value Engineering Log After Bid Version # 2 February 16, 2011 A. (1,800,000) B: (584,000) C: (370,000) Yey j21835Od)' No (8184000} Pending ' +(I 896588 Printed: Gray - Rom resolved Red - CW Diver action Blue - Design team action 1 2 4 5 6 7 8 9 10 1 11 12 43 Arup bas reviewed and responded thli d parry Line No. VE # Trade Sort Value Engineering Suggestion: AND /OR Ideas. Proposed Savings Next Action Step:. Action By: Date - Required .Priority A,B,C Accepted? YeslNo Accepted $Value BC) Notes 1 100 %CD - Electrical Electrical- revise single line. reduce (150,000) response to CWD /Arch A Pending 0 Arup bas reviewed and responded thli d parry I feeder sizes, reduce and eliminate Arup review comments , 1. CW Driver to Issue conservative ROM panels for inclusion in GMP? 1 CW Driver will get response to Arup's.rol e, 2 100 %CD - Electrical Use standard Led Acceptable meters (30,000) confirm CWD /Arch C Pending 0 The proposed manufacturer is acceptable. Contractor 2 compliance se verify the proposed product mews or exceeds Me requirements of specification 26 27 13 including collection and nerage of data in conjunction with the INS and dashboard sysum. 3 10 Electrical Alternate lighting fixture package (200,000 novices CWD /Arch C Pending OCW Driver will getapackage that shares specific 3 sample of proposals on substitutions. These will include fixtures, photometric comparisons. compare photometrics 4 100 Electrical Uplighting in garage planters get pricing CWD /Arch o gq has sent two proposed alternate fixtures CW 4 Driver will be getdng revised numbers. 5 100 %CD - HVAC HVAC - use ocher specified system (200.000) Cricchfeld to CWD /Arch B Pending 0 Arup Mechanical now system is acceptable but has not 5 study space been vetted regarding ability m fit in mechanical spaces impacts of - provided. Since the spaces provided are snug and proposal cannot expand, ream decided to postpone decision oe post GMP. CW Driver will get more detailed proposal from sub when appropriate. Not taken now. 6 100 %CD - Glass Glass /Glazing -use ether than (1,500,000) compareboch CWD /Arch A Yes (1.500. 000) Tower has gathered substitution materials from Vision 6 Walters and Wolf system options - and has provided revised numbers from Wavier and Schorr. Design team is reviewing substitution materials. CW Drlver will carry the Schuco delta of approx $110 K In dse GMP. All parties well ni 7 100 %CD - Glass Glass / Glazing -use other than Shute And (349.000) compare bock CWD /Arch B Pending 0 There are important differences between specified 7 windows options operator and substitution proposed. Schuco windows are being assumed for the GMP. Design team gening sample window with operators, as well as confusing drawings and phms. All parties to come to final dalelon shortly. 1 of 5 C.W. Driver BDILDERS SINCE 1919 Newport Beach Civic Center and Park Value Engineering Log After Bid Version # 2 February 16, 2011 A. (1,800,000) B: (584,000) c: (370,000) Yes (2 483i5gtl) Na (88Y Oq0) Pen'dmg , (I 8465$8) Printed: Gray = Item resolved Red =CW Driveraction Blue is Desgn team action 1 2 - 4 5 6' <. 7 8 9 10 11 12 113 line VE Trade ANDIOR Proposed Next Action Date Priority Accepted} Accepted No. N Sort Value Engineering Suggestion: Ideas Savings Action Step:.. Bp Required A,B,C Ves/Ne $ Value BCJ Notes 8 100 1 Glass Remove meal panel at continuous (15,000) generate sketch CWD /Arch Void 0 7 Please clarify. Per A,,x guess at proposal: The 8 Air plenum at spandrel- use extruded metal plenum divider at the facade is critical for she returns above and below m conceal design on the 2nd floor. This VE item Is strongly discouraged or should be further clarified to Insure the gaps raised floor is sealed as this location.' CW Driver is sending sketch clarifying Inmnt 9 1001 Landscape Replace 6' deep concrete root (150,000) to be CWD/Ards A Pending 0 MP revievdng and will send proposed alternate de sign 9 barrier with a combination of researched by shortly Notenough dme to make decblon eyrie, l 6ch "Century" hard phode root barrier PWP CW Driver will price alternates when received. and concrete curb 10100 %CD - Landscape Remove Polymeric Soil Treatment (140,000) to be CWD /Arch C Pending 0 PWP is reviewing soil mix. Will have something to 10 (PAM) researched share by end of February. I I 0i Lentech panels - privacy panels- (40,000) confirm w sub CWD /Arch B Pending 0 sub no confirm thinner panels can achieve spans with I I decrease thickness to 3/8 in lieu of Laming shown. IT' 12 100 1 Acousdal Change Linear Wood Ceiling to TBD get samples CWD /Arch Pending 0 CW Driver is getting samples and will share with BCJ. 12 Ceilings Linear metal with same appearance and acoustical values 13 -13 Stone Pacific Blue limestone in lieu of (446,000) Pending 0 CW Driver vgI provide samples for review. rooms Light Unlikely this decision could be made prior to the 16th of February. 14 -14 Seems Salt and pepper cobblestones In lie (60.200) Pending 0 CW Driver will provide samples for review. of phoenix grey Unlikely this decision could be made prior m the 16th of February. 11 tW, %BCD- dectdtai aearat - :Pow N!C (gexible) (i I5.000) NA No 0 Would he a significant viasai ccmpromise in occcpied 101 <ond::io at exposed areas 'a+ccilings spaces. Net taken. 102 'cl£CL Ct ..i:n!ndfC rg d o new, in duct Sdn:<i 15,000] to bC Ch,,.kk NA No 0 No, raker. I(i2 Wfti:'dr!:p. otherwise - ye., 103 100' /CD- Electrical Eliminate concrete underground (50.000) verified with NA Yes (50,000) Taken. 103 enasement where not required by ARUP code 2of5 C.W. Driver 111 I L D F R S .S I N C I! 1919 Newport Beach Civic Center and Park Value Engineering Log - After Bid Version # 2 February 16, 2011 A. (1,800,000) B: P (584,000) C: (370,000) Yes �2 183 500) No (884000 Pending- (- 896588) Printed: Gray Iiam resolved Red CW Driver action Blue Design team action 1 2 4' - 'S 6 7 8 9 10 `. 11 12 13 Line VE Trade AND/OR Proposed Next Action Date 'Priority Accepted? Accepted No. # Sort Value Engineering Suggestion! Ideas Savings. Action Step: By: :Required A,B,C Yes /No $ Value BCJ Notes 104 ; (`.,iaCU- 1V :,cfel B i,i rud os s': a; equ y ra% noleg accept. ry ret NA No O'Tire F ctnu ne t r eds v Will be moved out of I0e by year yet vAlue in GMP GMPand paldfor with eepa;ate funds. Pouible cost reduaicn. tho::gb none is asm :red for new. ( CWD p,,;g�rs. _ does not recommend per sub Input) 105 i00'eCD- 4`iAC. HVA :.. the. orter,geefcsd sysrem j75.000) verily with NA No 0Not deer. Cnandeld nuw underxtards scope. Scope 105 lo,uLcidN. Tbis was actually e ARVP .dins as m addendum 2. G ,clVield qu =Stier regarding redunslanw of Crnrrols. 106 100`IC17'. Glass Cse 3 /I6- lack Venn hued Panel !20.000) NA No 0 Not ticker. BCJ p,c,idcdlist of nin.slquestitio 106 systen :;n lieu ei ih" {same regard!r:g the proposed reduction in thickness. CW calwcrzs manufzc;crer; Driver me advised City the risk of the change is not - v.'crth dse pro(ased cost reduction. 107 100e„CD- Glass Use --RL Glass hand ^ll m lieu o1 (40.000) to be NA No C No:. taken. 107 Pncmecraic. con0rinuod 108 100 %CD. Some venee Stone - decrease thickness of veneer (26.000) NA Yes (26,OW) Taken. provi,ad sub guarantees ddnner dimension 108 works with panel sizes and atachment methods shown. 109 =00`.tCD- S:cne Pavmp, Smn,, <ec ease thickness of p; :ving TSD NA No 0Not takrn. Profcrii ryas to reduce emry court stone 109 ii, 2 .uhe t D,:e m fire truck,. car or !eke d• ?I .", HG G? :.f [: ..::rd aFe 2 .: ut :u: p6n. pi, sixss : ,n: 3z u: (1(1.000) Ve, t,,J- fcr NA Yes ( 10,000) -nke s a pu of ^aNnyn' Pt• P`NP dc> a possible a: 110 L5 rocs ?uns in :ge trees dvc largest .n.os onh. H. i00.CD- Landscape Substinte Cony oilers `rrn iI12`00% to be NA No ONotaker.. RainMaster!aa City Smndard. 171 3ainMaster ro Rainhed m reduce qty wrdmoed by !.'om 8 and City. d^pnndinii tin did system osed I €h -.(.D- I_an"t t .coda re vi �; assod'sac -. �i• (]O0001. to be NA No ONotaeen Ra :nMascer -zaC -y Sand rd 112 cone oiler s96semunn co ^.kr=ned f i s 00 ;CD- L;:ndsetFe = e e, willow stru :tore from c ".e ( 300.000) NA Yes Q 00, 000) CWD cant conuact vdtb Petrick Dougherty directl, i'. scope- 'a'!ymg an Anvrxnce: Der the To be included In allowances. sc :Apmn usually o :fered at the liner date for pu.di, r u .4ng, 3 of C.W. Driver BIIILDFRS SINCE. 1919 Newport Beach Civic Center and Park Value Engineering Log After Bid Version # 2 February 16, 20 11 A. (1,800,000) B: (584,000) C: (370,000) Printed: Gray= item rasdved Red — CW Driver anion Blue — Design teen azdon 1 2 LMS) 5 -` b, 7 Printed: Gray= item rasdved Red — CW Driver anion Blue — Design teen azdon 1 2 4 5 -` b, 7 8 9 10 - 11 12 ::113 Line VE Trade ANDIOR Proposed Next Action Date Priority Accepted? Accepted No. # Sort Value. Engineering Suggestion: Ideas Savings Action Step: By: Required A,B,C Y65INo $ Value BCj Notes II% iOMCD- non SC IPE i15,0W) NA No ONo: ken, Ner-FSC lot stet woh pardculal, 1;1 un,ii,pirabli . 115 =i,.^•";CD- Sobstlane L.entech panel vdtr, TBD NA No 0 No, `,man. I.S c.,npa,,ible.natvhaL 116 :004C D- Replace specified Al; Gratcn with a (20.000) NA Yes (20,000) Taken. fit v lL^ aS,rMa, icrom ct 117 100 ".LCD- Acamtica1 CInge linear Wood C,jhngs (230,000) to be checked PIA No 0 Nov cken. 1:7(Ai ohgs s.ucies lien +: =.c ,luck to Pori. Ib' 9vmafj 113 -i IS Dnmmll Dc.n, level 5 "nisi, (45.000) NA No C Not taken. Scope is cei,i,d for ail gyp. 119 -119 Roof Use Pelyiso ( one of the specified ) in (470.000) to be NA Yes (470,000) Taken BCj confirmed. lieu of rigid board researched 12 -120 Roof Use Polyiso ( one of the specified) in and (50.000) to be NA Pending 0 Nor. rake.. RCj hae —re, mad an m -ant dncknes: e lieu of rigid board. decrease thickness confirmed by needed at fat I..R re. 4'sns, Thickness is also needed by I" to only achieve R Value RCJ at tte. curved roof, re: clitoris at beach of wave" aIcfmg ce gas rools. fPending for the curved roof) 121 -121 Waterproofing Delete membrane under cast in place (7.500) NA Yes (7.500) Taken. stairs on site .- -122 .al,i1i At- he Stretch Fabric vwli system 180001 NA No O No, taken.Muscmeeta,ouot and pinning properties. nr „"'cure. cn mi "wcrh ;.[,ovum CW Drina has confirmed Propozed sr:hsda:rion does dens'[, indn.'ti Insulaf.xaaoard nos moot..... requir ¢i -id, giasa fiber bca,'d (spoc,f Aj 120 9diw;ak Celese tha Item mmt ft,r FSC: , 5.000:) NA No 0 Not cken. C:ertlfaalioa Yor'v0lor k i - .f1': :1i, wt it die. typb:ai 82 nAlvrerk'abnets (2S.G901 NA No OPlot tai:en. BC, does ^utreccmineod for a budii.- ve,:h Adki S co ors - subes:n m white wnh she design 1,L exuecrpocy ofthe City Kill . meiam'.ne mien¢' for ti panted laf suer rake "v' fn the di ingS 4of5 G.W. Driver BIIILDItRS SINCF 1919. Newport Beach Civic Center and Park Value Engineering Log After Bid Version # 2 February 16, 2011 A. (1,800,000) B: (584,000) C: (370,000) Yes j2 188 500) No (8$4000) Pentlrng ;(I 886568] Primed: Only = -tom roselved Red – CW Driver Indian Blue = Design team action 1 2 4 -:5 6 7 8 9 10 + 11 12 13 Line VE Trade ANOIOR Proposed Next Action Date Priority Accepted? Accepted No. - # Sort Value Engineering Suggestion: Ideas Savings Action Step: By: Required A,B�C YeaNe $ Value BCJ Notes 125 d2S MLIJw.i a b -t e:,yu x Iiworkcabma, " f!0,000) NA Nn 0Not Eaken . BCJ d— not mend fora build, s::b,nc,,, -. write mzlarnieu int"Mr 'xiN t,, ^.e design life ex,etcai o: the City HAI. behl:ol cabinat doors i drawer for the plastic la,me,, noted an dr,:wings 4G d26 ..one'ate Raducc ich regwremern to: ; : : ^e. f 1,383) NA Pending 0 To, one Can be taken. Has been coriinned with bundeaons to 25% ch bcm 5" ash - spvCwral and LEED. CW DAver has indicated value is HWY higher. 177 -127 ACCeSS go., Use florid ncress tioor S,uon in NA No 0 Notwkm.CW Drivernomstbis works wish lieu of meLB dv-! speriPie:!. in the Haworth system only. To be tabled until system Ck nbcrs being used is ceoflr'med. i20 -i?& :.aodscapz USe. "'sec ^;)soil " \n lieu rf "n :snarl' (104.00113 NA No 0No, taken. Nani-di peve is essemrAlly an asptxih c",, produce Techmcsel has been instilled on s projec at Stanford with 2% slopes and is not doing well. so _ PWP does not feel they wn recommend it for our itrc;ect. with S % 51op t. 129 - 129 S tone (: Stma Sound co: :ucl erd, ay :nano 1.15,003) NA No O Not taken. Per: eview by Salarrs ofn<e. the het, of RegupoSOtrb:n proposed alte<':ate has a lower ST iaaing and an useue with mortar toilette, through he porous nsaterial. 130 -13o 6 -dude Cl, Hall s.Aolto 6rsaltdo,, at. l7SD301s NA Ponding 0 CW Driver to provide value aonvn,v, on zd. beddiii protectiea beard only 131 -131 Mechanically fasten insulation at City (62,000) NA Yes CW Driver to provide value. Hall roof as proposed ilo adhesive 5 of February 16, 2011 Newport Beach Civic Center and Park Phase 3 GMP Summary of Allowances The following allowances are included in the Phase 3 GMP to cover various unknown cost items as noted. Costs applied to these allowances will be administered in accordance with Specification Section 0 12 100. Allowance monies not expended are returned 100% to the City. I. Furnish and install the large sliding glass door at the Council Chamber. $110,000 2. Furnish and install the large metal folding doors at the Community Room. $150,000 3. Furnish and install up to 30 additional steel beam penetrations of up to 4" diameter. $36,000 4. Additional field touch up of interior paint. $10,000 5. Provide a professional Facilitator /Training company as required by Specification Section 01 79 00. $25,000 6. Provide a professional videographer to videotape demonstration and training as required by Specification Section 01 79 00. $24,000 7. Adverse conditions/ rock drilling for tie downs $20,475 8. Additional depth /adverse conditions for piles at landscape bridges . $9,000 9. Willow sculpture designed and installed by Patrick Dougherty. 7 pieces in each sculpture. $75,000 10. CWD support for the willow art installation. $25,000 11. Remove and replace glazing at existing clerestory windows at the Library. $134,000 12. Provide premium upholstery at Council Chamber fixed audience seating. $50,000 13. Furnish and install book theft deterent sensor system at Library. $10,000 TOTAL $678,475 EXHIBIT "A" CONTRACT DOCUMENT LISTING NEWPORT BEACH CIVIC CENTER AND PARK PROJECT FEBRUARY 04, 2011 VERSION 1.0 THE LISTING BELOW COMPRISES ALL OF THE DOCUMENTS INCLUDED UNDER THIS CONTRACT. UNLESS OTHERWISE NOTED, ALL DOCUMENTS ARE AS PREPARED BY BOHLIN, CYWINSKI, JACKSON. DRAWINGS ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0001 CSI Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0002 B1.00 Bohlin, Cywinski, Jackson 11/4/2010 11 /4/2010 0003 131.01 Bohlin, Cywinski, Jackson 11/4/2010 11/1812010 0004 B1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0005 B1.03 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0006 81.04 Bohlin, Cywinski, Jackson 11/4/2010 11118/2010 0007 B2.01 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0008 B2.02 Bohlin, Cywinski, Jackson II /4/2010 11/4/2010 0009 C01.01 ARUP 11/4/2010 1/20 /2011 0010 C01.02 ARUP 11/4/2010 1114/2010 0011 C01.03 ARUP 11/4 /2010 11/4/2010 0012 C01.04 ARUP 11/4/2010 12/10/2010 0013 C01.05 ARUP 11/4/2010 12/10/2010 0014 CO2.01 Hall & Foreman, Inc. 11/4/2010 111412010 0015 CO2.02 Hall & Foreman, Inc. 11/4/2010 11/4/2010 0016 CO2.03 Hall & Foreman, Inc. 1114/2010 11/4/2010 OO17 CO2.04 Hall & Foreman, Inc. 1114/2010 11/4/2010 0018 CO2.05 Hall & Foreman, Inc. 11/4/2010 11/4/2010 0019 CO2.06 RBF Consulting 11/4/2010 11/4/2010 0020 CO3.01 ARUP 1114/2010 12/10/2010 0021 CO3.02 ARUP 11/4!2010 12/10/2010 0022 CO3.03 ARUP 11/4!2010 12/10/2010 0023 CO3.04 ARUP 11/4/2010 12/10/2010 0024 CO3.05 ARUP 11 /4 12010 12/10/2010 0025 CO3.06 ARUP 11/4/2010 12/10 /2010 0026 CO3.07 ARUP 11/4 /2010 12/10/2010 0027 CO3.08 ARUP 11/4/2010 12/10/2010 0028 CO3.09 ARUP 11/4/2010 12/10/2010 0029 CO3.10 ARUP 11/4/2010 12/10/2010 0030 C04.01 ARUP 12/10/2010 1/20/2011 0031 C04.02 ARUP 12/10/2010 1/20/2011 0032 C04.03 ARUP 12/10 /2010 1/20/2011 0033 C04.04 ARUP 12/10 /2010 1 /20 /2011 0034 C04.05 ARUP 11/4/2010 12/10/2010 0035 C04.06 ARUP 11/4/2010 11/4/2010 0036 C04.07 ARUP 11/4/2010 11!4/2010 0037 C04.08 ARUP 11/4/2010 11/4/2010 0038 C04.09 ARUP 11 /4 /2010 12110!2010 0039 C04.10 ARUP 11 /4!2010 11/4/2010 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 2 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0040 CO5.01 ARUP 11/4/2010 12/10/2010 0041 C05.02 ARUP 11/4/2010 12/10/2010 0042 C05.03 ARUP 11 /4 /2010 12/10/2010 0043 C05.04 ARUP 11/4/2010 12/10/2010 0044 C05.05 ARUP 11/4/2010 12/10/2010 0045 C05.06 ARUP 11/4/2010 12/10/2010 0046 C05.07 ARUP 11/4/2010 12/10/2010 0047 C05.08 ARUP 11/4/2010 12/10/2010 0048 C05.09 ARUP 11/4/2010 12/10/2010 0049 COS. 10 ARUP 11/4/2010 12/10/2010 0050 C05.11 ARUP 11/10 /2010 12/10/2010 0051 COS. 12 ARUP 11/4/2010 11/4/2010 0052 C05.13 ARUP 11/4 /2010 11/4/2010 0053 C05.14 ARUP 11/4/2010 11/4/2010 0054 C06.01 ARUP 11/4/2010 12/10/2010 0055 C06.02 ARUP 11/4/2010 1/20/2011 0056 C06.03 ARUP 11/4/2010 11/4/2010 0057 C06.04 ARUP 12/10/2010 1/20/2011 0058 C06.05 ARUP 11 /4 /2010 12/10/2010 0059 C06.07 ARUP 11/4/2010 12/10/2010 0060 C06.08 ARUP 11/4/2010 12/10/2010 0061 C06.10 ARUP 11/4/2010 12/10/2010 0062 C06.11 ARUP 11/4 /2010 12/10/2010 0063 C0&12 ARUP 11 /4/2010 12/10/2010 0064 C06.20 ARUP 11/4/2010 11/4/2010 0065 C06.21 ARUP 11/4/2010 1/20/2011 0066 C06.22 ARUP 11/4/2010 1/20/2011 0067 C06.23 ARUP 11/4/2010 1/20/2011 0068 C06.24 ARUP 11/4/2010 1/20/2011 0069 C06.25 ARUP 11/4/2010 11/412010 0070 C06.30 ARUP 11/4/2010 11/4/2010 0071 C06.31 ARUP 11/4 /2010 11/4/2010 0072 C06.32 ARUP 11/4/2010 11/4/2010 0073 C06.33 ARUP 11/4/2010 11/4/2010 0074 C06.34 ARUP 11/4/2010 11/4/2010 0075 C06.35 ARUP 11/412010 11/4/2010 0076 C06.37 ARUP 11/4/2010 11 /4 12010 0077 C07.01 ARUP 11/4/2010 12/10/2010 0078 C07.02 ARUP 11/4/2010 12/10/2010 0079 C07.03 ARUP 11 /4 /2010 12/10/2010 0080 C07.04 ARUP 11/4/2010 12/10/2010 0081 C07.05 ARUP 11 /4 /2010 12/10 /2010 0082 C08.00 ARUP 11/4/2010 11/4/2010 0083 C08.01 ARUP 11/4/2010 12/10/2010 0084 C08.02 ARUP 11/4/2010 12110/2010 0085 C08.03 ARUP 11/4/2010 12/10/2010 Exhibit A - Contract Document Listing Page 2 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 3 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0086 C08.04 ARUP 11/4/2010 12/10 /2010 0087 C08.05 ARUP 11/4/2010 12/10/2010 0088 C08.06 ARUP 11/4/2010 12110/2010 0089 C08.07 ARUP 11/4/2010 12/10/2010 0090 C08.08 ARUP 11/4/2010 12110/2010 0091 C09.01 ARUP 11/4/2010 11/4/2010 0092 C09.02 ARUP 11/4/2010 11/4/2010 0093 C09.03 ARUP 11/4/2010 1114/2010 0094 C09.04 ARUP 11/4/2010 11 /4 12010 0095 C09.05 ARUP 11/4/2010 1/20/2011 0096 C09.06 ARUP 11/4/2010 12/10/2010 0097 C10.01 ARUP 11/4/2010 1/20/2011 0098 C10.02 ARUP 11/4/2010 12/10/2010 0099 C10.03 ARUP 11/4/2010 12/10/2010 0100 1-0.01 Peter Walker Partners 12/10/2010 1/20/2011 0101 1-0.02 Peter Walker Partners 12110/2010 1/20/2011 0102 1-0.03 Peter Walker Partners 11/4/2010 12/1012010 0103 1-0.04 Peter Walker Partners 11 /4/2010 11/4/2010 0104 1-0.05 Peter Walker Partners 11/4/2010 12/10/2010 0105 1-0.06 Peter Walker Partners 11/4/2010 12/10/2010 0106 1-0.07 Peter Walker Partners 12110 /2010 1/20/2011 0107 1-0.10 Peter Walker Partners 1114/2010 12/10/2010 0108 1-0.11 Peter Walker Partners 11/4/2010 12/10/2010 0109 LO. 12 Peter Walker Partners 1114/2010 12 /10 /2010 0110 L01.01 Peter Walker Partners 11/4/2010 12/10/2010 0111 L01.02 Peter Walker Partners II /4/2010 12/10/2010 0112 L01.03 Peter Walker Partners 11/4/2010 12/10/2010 01 13 LO 1.04 Peter Walker Partners 11/4/2010 12/10/2010 0114 L02.01 Peter Walker Partners 1114/2010 12/10/2010 0115 L02.02 Peter Walker Partners 11/4/2010 12/10 /2010 0116 L02.03 Peter Walker Partners 11/4/2010 12/1012010 0117 L02.04 Peter Walker Partners 11/4/2010 12 /10 /2010 0118 L02.05 Peter Walker Partners 11/4/2010 11/4/2010 0119 L02.06 Peter Walker Partners II /4 /2010 12 /10/2010 0120 L02.07 Peter Walker Partners 12/10/2010 1/20/2011 0121 L02.08 Peter Walker Partners 12/1012010 1/20/2011 0122 L02.09 Peter Walker Partners 12/1012010 1/20/2011 0123 L02.10 Peter Walker Partners 12/1012010 1/20/2011 0124 1-02.11 Peter Walker Partners 12/10/2010 1/20/2011 0125 1-02.12 Peter Walker Partners 1114/2010 12/10/2010 0126 L02.13 Peter Walker Partners 11/4/2010 1114/2010 0127 1-02.14 Peter Walker Partners 12110/2010 1/2012011 0128 1-02.15 Peter Walker Partners 12/10/2010 1/20/2011 0129 L02.16 Peter Walker Partners 11/4/2010 12/10 /2010 0130 1-02.17 Peter Walker Partners 11/4/2010 12/10/2010 0131 1-02.18 Peter Walker Partners 12/10/2010 1/20/2011 Exhibit A - Contract Document Listing Page 3 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 4 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0132 L04.01 Peter Walker Partners 11/4/2010 12/10/2010 0133 L04.02 Peter Walker Partners 11/4/2010 12/10/2010 0134 L04.03 Peter Walker Partners 11/4/2010 12/10/2010 0135 L04.04 Peter Walker Partners 1114/2010 12/10/2010 0136 L05.01 Peter Walker Partners 11/4/2010 12110/2010 0137 L05.02 Peter Walker Partners 11/4/2010 12/10/2010 0138 L05.03 Peter Walker Partners 11/4/2010 12/10/2010 0139 1-05.04 Peter Walker Partners 11/4/2010 12/10 /2010 0140 L06.01 Peter Walker Partners 11 /4 /2010 12/1012010 0141 L06.02 Peter Walker Partners 11/4/2010 12/10/2010 0142 L06.03 Peter Walker Partners 11/4/2010 12/10/2010 0143 L06.04 Peter Walker Partners 12/10/2010 1120/2011 0144 L06.06 Peter Walker Partners 11/4/2010 12/10 /2010 0145 L06.07 Peter Walker Partners 11/4/2010 12/10/2010 0146 L06.08 Peter Walker Partners 11/4/2010 12110 /2010 0147 L06.09 Peter Walker Partners 11/4/2010 12110/2010 0148 L07.01 Peter Walker Partners 12/10/2010 I /20 /2011 0149 L07.02 Peter Walker Partners 12 /10 /2010 1/20/2011 0150 L07.03 Peter Walker Partners 12 /10 /2010 1/20/2011 0151 L07.04 Peter Walker Partners 12110 /2010 1/20/2011 0152 L07.05 Peter Walker Partners 12/10/2010 1120/2011 0153 L07.06 Peter Walker Partners 12110/2010 1/20/2011 0154 L07.07 Peter Walker Partners 12 /10 /2010 1 /20 /2011 0155 L07.08 Peter Walker Partners 12 /10 /2010 1120/2011 0156 L07.09 Peter Walker Partners 12/10/2010 1/2012011 0157 LOT 10 Peter Walker Partners 11/4/2010 11/4/2010 0158 L07.11 Peter Walker Partners 1/20/2011 1/20/2011 0159 L09.01 Peter Walker Partners 11/4/2010 11/4/2010 0160 L09.02 Peter Walker Partners 1114/2010 12/10/2010 0161 L09.03 Peter Walker Partners 11/4/2010 12/10/2010 0162 1-09.03A Peter Walker Partners 1 1/4/2010 12/10/2010 0163 L09.04 Peter Walker Partners 1 1/412010 11/4/2010 0164 L09.05 Peter Walker Partners 11/4/2010 12/10 /2010 0165 L09.06 Peter Walker Partners 11/4/2010 12/1012010 0166 L09.07 Peter Walker Partners 1114/2010 12/1012010 0167 L09.08 Peter Walker Partners 11/4/2010 12/10/2010 0168 L09.09 Peter Walker Partners 11/4/2010 12 110 12010 0169 L09.10 Peter Walker Partners - 11/4/2010 12/10/2010 0170 L09.1 I Peter Walker Partners 11 /4 /2010 12/10/2010 0171 1-09.12 Peter Walker Partners 1114/2010 1/20/2011 0172 L09.13 Peter Walker Partners 11/4/2010 11/4/2010 0173 L09.14 Peter Walker Partners 11/4/2010 12/10/2010 0174 L09.15 Peter Walker Partners 11/4/2010 12/10/2010 0175 L09.16 Peter Walker Partners 11/4/2010 12/10/2010 0176 L09.17 Peter Walker Partners 11/4/2010 11/412010 0177 L09.18 Peter Walker Partners 11/4/2010 12/10/2010 Exhibit A - Contract Document Listing Page 4 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 5 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0178 L09.19 Peter Walker Partners 11/4/2010 12110/2010 0179 L09.20 Peter Walker Partners 1114/2010 11/4/2010 0180 L09.20A Peter Walker Partners 11/412010 12/10/2010 0181 L09.21 Peter Walker Partners 11/4/2010 12/10 /2010 0182 L09.22 Peter Walker Partners 11/4/2010 12/10/2010 0183 L09.23 Peter Walker Partners 1114/2010 12/10/2010 0184 L09.31 Peter Walker Partners 11/4/2010 11/412010 0185 L09.32 Peter Walker Partners 11/4/2010 12/10/2010 0186 1-09.32A Peter Walker Partners 11/4/2010 12/10/2010 0187 L09.32B Peter Walker Partners 11/412010 12/10/2010 0188 L09.33 Peter Walker Partners 11/4/2010 1114/2010 0189 L09.35 Peter Walker Partners 12/10/2010 1/2012011 0190 1-09.36 Peter Walker Partners 12110/2010 1/20/2011 0191 L09.37 Peter Walker Partners 111412010 12/10/2010 0192 L09.38 Peter Walker Partners 12/10/2010 1/20/2011 0193 L09.39 Peter Walker Partners 1 /20 /2011 1/20/2011 0194 L09.40 Peter Walker Partners 1114/2010 12/10/2010 0195 1-09.41 Peter Walker Partners 11/412010 12/10/2010 0196 L09.42 Peter Walker Partners 1114/2010 1211012010 0197 L09.44 Peter Walker Partners 11/4/2010 12 /10 /2010 0198 L09.45 Peter Walker Partners 11/4/2010 12/10/2010 0199 L09.46 Peter Walker Partners 1/20/2011 1/20/2011 0200 1-10.01 Peter Walker Partners 11/4/2010 12/10/2010 0201 L10.02 Peter Walker Partners 11/4/2010 12110/2010 0202 L10.03 Peter Walker Partners 11/4/2010 12/10/2010 0203 L10.04 Peter Walker Partners 11/4/2010 12/10/2010 0204 L10.05 Peter Walker Partners 11/4/2010 12/10/2010 0205 L10.06 Peter Walker Partners 11 /4 /2010 12/10/2010 0206 L10.07 Peter Walker Partners 11/4/2010 12/10/2010 0207 LI 1.10 Peter Walker Partners 11 /4 /2010 12/10/2010 0208 LI 1.11 Peter Walker Partners 11/4/2010 12110/2010 0209 L11.12 Peter Walker Partners 11 /4 /2010 12/10/2010 0210 LI 1.13 Peter Walker Partners 11 14 /2010 12/10/2010 0211 1-11.14 Peter Walker Partners 1114/2010 12/10/2010 0212 L11.15 Peter Walker Partners 11/4/2010 12/10/2010 0213 L11.16 Peter Walker Partners 12/1012010 1 /20 /2011 0214 1-11.17 Peter Walker Partners 11/4/2010 12/1012010 0215 LI 1.18 Peter Walker Partners 11/4/2010 12/10 /2010 0216 LI 1.19 Peter Walker Partners 11/4/2010 12/10/2010 0217 LI 1.20 Peter Walker Partners 12 110 /2010 1/20/2011 0218 LI 1.21 Peter Walker Partners 12/10/2010 1/20/2011 0219 L11.22 Peter Walker Partners 11/4/2010 12/10/2010 0220 LI 1.23 Peter Walker Partners 11 /4 /2010 12/10/2010 0221 LI 1.24 Peter Walker Partners 11 /4 12010 12/10/2010 0222 L11.25 Peter Walker Partners 11/4/2010 12/10/2010 0223 L11.26 Peter Walker Partners 11/4/2010 12/10/2010 Exhibit A- Contract Document Listing Page 5 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 6 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0224 L12.01 Peter Walker Partners 1 1/4/2010 1 1/4/2010 0225 L12.02 Peter Walker Partners 1114/2010 11/4/2010 0226 1-12.03 Peter Walker Partners 11/4/2010 12/10/2010 0227 L12.04 Peter Walker Partners 11/4/2010 12110 /2010 0228 L12.05 Peter Walker Partners 11/4/2010 12/10/2010 0229 L12.06 Peter Walker Partners 11/4/2010 12/10/2010 0230 L12.07 Peter Walker Partners 11/4/2010 12110/2010 0231 L13.01 Peter Walker Partners 11/4 /2010 12/10 /2010 0232 L13.02 Peter Walker Partners 1114/2010 12/10/2010 0233 L14.01 Peter Walker Partners 11/4/2010 11/4/2010 0234 1-14.02 Peter Walker Partners 11/4/2010 12/10 /2010 0235 L14.03 Peter Walker Partners 11/4/2010 12/10/2010 0236 L14.04 Peter Walker Partners 11/4/2010 11/4/2010 0237 1-14.05 Peter Walker Partners 11/4/2010 12110/2010 0238 L15.01 Peter Walker Partners 11/4/2010 12/10/2010 0239 L15.02 Peter Walker Partners 11/4/2010 12/10/2010 0240 L15.03 Peter Walker Partners 11/4/2010 12/10/2010 0241 L15.04 Peter Walker Partners 11/4/2010 12/10/2010 0242 L15.05 Peter Walker Partners 11/4/2010 12/10/2010 0243 L15.06 Peter Walker Partners 11 /4 /2010 12/10/2010 0244 L15.07 Peter Walker Partners II /4 /2010 12/10/2010 0245 L16.01 Peter Walker Partners 11 14 /2010 12/10/2010 0246 L17.01 Peter Walker Partners 11/4/2010 11/4/2010 0247 L18.01 Peter Walker Partners 11/4/2010 12/10/2010 0248 L18.02 Peter Walker Partners 11/4/2010 12/10 /2010 0249 L18.03 Peter Walker Partners 11/4/2010 12/10/2010 0250 L18.04 Peter Walker Partners 11/4/2010 12/10/2010 0251 L18.05 Peter Walker Partners 11/4/2010 12 /10/2010 0252 L18.06 Peter Walker Partners 11/4/2010 11/4/2010 0253 L18.07 Peter Walker Partners 11/4/2010 12110/2010 0254 L18.08 Peter Walker Partners 11/4/2010 12/10/2010 0255 L18.09 Peter Walker Partners 11/4/2010 12/10/2010 0256 - L18.10 Peter Walker Partners 11/4/2010 12/10 /2010 0257 1-I8.11 Peter Walker Partners 1 1/4/2010 12/10/2010 0258 L18.12 Peter Walker Partners 11/4/2010 12/10/2010 0259 L18.13 Peter Walker Partners 1 1/4/2010 12/10 /2010 0260 L18.14 Peter Walker Partners 11/4/2010 121.1012010 0261 L18.15 Peter Walker Partners 11/4/2010 12/1012010 0262 L18.16 Peter Walker Partners 11/4/2010 12/10/2010 0263 1-18.17 Peter Walker Partners 11/4/2010 12/10/2010 0264 L18.18 Peter Walker Partners 11 /4/2010 12/10/2010 0265 L18.19 Peter Walker Partners 11/4/2010 11/4/2010 0266 L18.20 Peter Walker Partners 11 /4/2010 12/10/2010 0267 L19.01 Peter Walker Partners 11/4/2010 12/10/2010 0268 L19.02 Peter Walker Partners 11/4/2010 12/10/2010 0269 L19.03 Peter Walker Partners 11/4/2010 12110/2010 Exhibit A- Contract Document Listing Page 6 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 7 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0270 L19.03A Peter Walker Partners 11/4/2010 12/10/2010 0271 L19.04 Peter Walker Partners 11/4/2010 12/10/2010 0272 L19.05 Peter Walker Partners 11/4/2010 12/10/2010 0273 L19.06 Peter Walker Partners 11/4/2010 12/10/2010 0274 L19.07 Peter Walker Partners l l /4/2010 12/10 /2010 0275 L19.08 Peter Walker Partners 11/4/2010 12/10/2010 0276 L19.09 Peter Walker Partners 11/4/2010 12/10/2010 0277 L19.09A Peter Walker Partners 12/10/2010 1/20/2011 0278 L19.09B Peter Walker Partners 12/10/2010 1/20/2011 0279 L19.09C Peter Walker Partners 11/4/2010 12110/2010 0280 L19.09D Peter Walker Partners 11/4/2010 12/10/2010 0281 L19.10 Peter Walker Partners 11/4/2010 12/10 12010 0282 L19.11 Peter Walker Partners 12/10/2010 1/20/2011 0283 L20.01 Peter Walker Partners 11/4/2010 12/10/2010 0284 L20.02 Peter Walker Partners 11/4/2010 12/10/2010 0285 L20.03 Peter Walker Partners 11/4/2010 11/4/2010 0286 L20.04 Peter Walker Partners 1 1/4/2010 11/4/2010 0287 L20.05 Peter Walker Partners 11/4/2010 12/10/2010 0288 L20.06 Peter Walker Partners 11/4/2010 11/4/2010 0289 L20.07 Peter Walker Partners 11/4/2010 1114/2010 0290 L20.08 Peter Walker Partners 1 1/4/2010 11/412010 0291 L20.09 Peter Walker Partners 1 1/4/2010 12/10/2010 0292 L20.10 Peter Walker Partners 11/4/2010 12/10/2010 0293 L20.1 I Peter Walker Partners 11/412010 12/10/2010 0294 L21.01 Peter Walker Partners 1114/2010 12/10/2010 0295 L21.02 Peter Walker Partners 11/4/2010 11/4/2010 0296 L2I.03 Peter Walker Partners 11/4/2010 12/10/2010 0297 L21.04 Peter Walker Partners 1 1/4/2010 12/10/2010 0298 L21.05 Peter Walker Partners 11/4/2010 1114/2010 0299 L2I.06 Peter Walker Partners 1 1/4/2010 11/4/2010 0300 L21.07 Peter Walker Partners 1 1/4/2010 11/4/2010 0301 1_2I.08 Peter Walker Partners 1 1/4/2010 12/10/2010 0302 L21.09 Peter Walker Partners. 11/4/2010 12110/2010 0303 L21.10 Peter Walker Partners 11/4/2010 12/10/2010 0304 L21.11 Peter Walker Partners 1114/2010 12 /10 /2010 0305 L2I.12 Peter Walker Partners 11/4/2010 12/10/2010 0306 L22.01 Peter Walker Partners 11/4/2010 12/10/2010 0307 L22.02 Peter Walker Partners 11/4/2010 12/10/2010 0308 L22.03 Peter Walker Partners 11/4/2010 12110/2010 0309 A1.01 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0310 A1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0311 A1.03 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0312 A1.04 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0313 A1.05 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0314 A1.06 Bohlin, Cywinski, Jackson 12/10 /2010 1/2012011 0315 A1.07 Bohlin, Cywinski, Jackson 12/10 /2010 I /20/2011 Exhibit A- Contract Document Listing Page 7 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 8 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0316 A1.08 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0317 AI.09 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0318 A1.10 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0319 A1.15 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0320 A1.16 Bohlin, Cywinski, Jackson 11 /4/2010 12/10/2010 0321 A1.17 Bohlin, Cywinski, Jackson 11 /4 /2010 12/1012010 0322 A1.18 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0323 A1.19 Bohlin, Cywinski, Jackson 11/4/2010 12/10 12010 0324 A1.20 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0325 A1.21 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0326 A1.25 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0327 A1.26 Bohlin, Cywinski, Jackson 12/10/2010 I /20 /201 I 0328 A1.27 Bohlin, Cywinski, Jackson 12/10 /2010 1/20/2011 0329 A1.28 Bohlin, Cywinski, Jackson 12/10 /2010 1120/2011 0330 A1.31 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0331 A1.50 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0332 X1.51 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0333 AI.52 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0334 A2.01 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0335 A2.02 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0336 A2.03 Bohlin, Cywinski, Jackson 11/4/2010 12 110 /2010 0337 A2.50 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0338 A3.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0339 A3.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0340 A3.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0341 A3.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0342 A3.50 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0343 A3.51 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0344 A4.01 Bohlin, Cywinski, Jackson 11/4/2010 12 /10 /2010 0345 A4.02 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0346 A4.03 Bohlin, Cywinski, Jackson 11/4/2010 12/1012010 0347 A4.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10 12010 0348 A4.05 Bohlin, Cywinski, Jackson 1114/2010 12 /10 12010 0349 A4.06 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0350 A4.10 Bohlin, Cywinski, Jackson 11/412010 11 /18 /2010 0351 A4.11 Bohlin, Cywinski, Jackson 11 /4/2010 12/10/2010 0352 A4.12 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0353 A4.13 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0354 A4.14 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0355 A4.15 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0356 A4.16 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0357 A4.17 Bohlin, Cywinski, Jackson 11 14 /2010 12/10/2010 0358 A4.18 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0359 A4.19 Bohlin, Cywinski, Jackson 11 1412010 II /4 /2010 0360 A4.30 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0361 A4.50 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 Exhibit A- Contract Document Listing Page 8 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 9 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0362 A4.51 Bohlin, Cywinski, Jackson 11/4/2010 12110 /2010 0363 A4.55 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0364 A4.56 Bohlin, Cywinski, Jackson 1114/2010 12/10 /2010 0365 A5.01 Bohlin, Cywinski, Jackson 11/412010 12/10 /2010 0366 A5.02 Bohlin, Cywinski, Jackson 11/4/2010 12/1012010 0367 A5.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0368 A5.05 Bohlin, Cywinski, Jackson 11118/2010 1/20/2011 0369 A5.06 Bohlin, Cywinski, Jackson 1114/2010 12110/2010 0370 A5.07 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0371 A5.08 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0372 A5.10 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0373 AS. 11 Bohlin, Cywinski, Jackson 12/10 /2010 1/20/2011 0374 A5.12 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0375 A5.13 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0376 A5.14 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0377 A5.15 Bohlin, Cywinski, Jackson 111412010 12110 /2010 0378 A5.19 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0379 A5.20 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0380 A5.21 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0381 A5.22 Bohlin, Cywinski, Jackson 12/1012010 1/20/2011 0382 A5.23 Bohlin, Cywinski, Jackson 11/4/2010 12110 /2010 0383 A5.24 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0384 A5.25 I Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0385 A5.26 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0386 A5.27 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0387 A5.28 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0388 A5.29 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0389 A5.30 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0390 A5.31 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0391 A5.32 Bohlin, Cywinski, Jackson 11/4/20 10 1 1/4/2010 0392 A5.33 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0393 A5.35 Bohlin, Cywinski, Jackson 12/10/2010 1120/2011 0394 A5.36 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0395 A5.50 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0396 A5.51 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0397 A5.52 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0398 A5.53 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0399 A5.70 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0400 AS.71 Bohlin, Cywinski, Jackson 11 /18/2010 1/20/2011 0401 A5.72 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0402 A5.75 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0403 A5.80 Bohlin, Cywinski, Jackson 11/4/2010 1111812010 0404 A5.81 Bohlin, Cywinski, Jackson 1 12/10/2010 1120/2011 0405 A5.82 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0406 A5.90 Bohlin, Cywinski,Jackson 11/4/2010 12/10/2010 0407 A6.10 Bohlin, Cywinski,fackson 1 1/412010 11/4/2010 Exhibit A - Contract Document Listing Page 9 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 10 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0408 A6.20 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0409 A6.21 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0410 A6.25 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0411 A6.30 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 0412 A6.40 Bohlin, Cywinski, Jackson 11/4/2010 12/1012010 0413 A6.41 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0414 A6.50 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0415 A6.51 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0416 A6.70 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0417 A7.00 Bohlin, Cywinski, Jackson 11/412010 11/18/2010 0418 A7.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0419 A7.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0420 A7.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0421 A7.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0422 A7.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0423 A7.06 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10 /2010 0424 A7.07 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0425 A7.08 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0426 A7.09 Bohlin, Cywinski, Jackson 11/4/2010 12/1012010. 0427 A7.10 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0428 A7.1 I Bohlin, Cywinski, Jackson 11/4/2010 12110 /2010 0429 A7.12 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10 /2010 0430 A7.13 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0431 A7.14 Bohlin, Cywinski, Jackson 12/10/2010 1/2012011 0432 A7.15 Bohlin, Cywinski, Jackson 11/4/2010 12 /10 /2010 0433 A7.16 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0434 A7.17 Bohlin, Cywinski, Jackson 11/4/2010 12 110 /2010 0435 A7.18 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0436 A7.19 Bohlin, Cywinski, Jackson 12/10/2010 1 /20/2011 0437 A7.20 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0438 A7.22 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0439 A7.23 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 0440 A7.24 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0441 A7.25 Bohlin, Cywinski, Jackson 1 114 /2010 1/20/2011 0442 A7.26 Bohlin, Cywinski, Jackson 1 1/412010 11/4/2010 0443 A7.27 Bohlin, Cywinski, Jackson 11 /4/2010 12/10/2010 0444 A7.2713 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0445 A7.28 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0446 A7.29 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0447 A7.30 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0448 A7.31 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0449 A7.32 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0450 A7.33 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0451 A7.34 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0452 A7.35 Bohlin, Cywinski, Jackson 11/4/2010 1/20/201 1 0453 ATM Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 Exhibit A.- Contract Document Listing Page 10 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE I I OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0454 A7.40 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0455 A7.50 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0456 ATS1 Bohlin, Cywinski, Jackson 1211012010 1/20/2011 0457 A7.52 Bohlin, Cywinski, Jackson 111412010 12/10 12010 0458 A7.53 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0459 A7.54 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0460 A7.55 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0461 A7.60 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0462 A7.61 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0463 A7.62 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0464 A7.63 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0465 AT64 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0466 A7.65 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0467 A7.66 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0468 A7.70 Bohlin, Cywinski, Jackson 12/10/2010 1120/2011 0469 A8.01 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0470 A8.02 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0471 A8.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0472 A8.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0473 A8.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0474 A8.50 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0475 A9.01 Bohlin, Cywinski, Jackson 1114/2010 11/412010 0476 A9.02 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0477 A9.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0478 A9.11 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0479 A9.12 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0480 A9.13 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0481 A9.21 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0482 CS2 Bohlin, Cywinski, Jackson 1 1/4/2010 11/18/2010 0483 50.01 Bohlin, Cywinski, Jackson 11 14 /2010 11/4/2010 0484 50.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0485 50.03 Bohlin, Cywinski, Jackson 11 /4 12010 12/10/2010 0486 50.1 I Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0487 50.21 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0488 50.31 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0489 51.00 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0490 51.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0491 51.02 Bohlin, Cywinski, Jackson . 11/4/2010 12/10/2010 0492 51.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0493 51.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0494 51.05 Bohlin, Cywinski, Jackson 1 1/412010 12/10/2010 0495 51.06 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10/2010 0496 51.07 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10 /2010 0497 51.08 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0498 S1.09 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0499 51.10 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 Exhibit A - Contract Document Listing Page I I of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 12 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0500 51.11 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0501 SI.12 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0502 51.21 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0503 51.22 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0504 51.31 Bohlin, Cywinski, Jackson 11 /4 /2010 1 1/4/2010 0505 S2.11 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0506 52.12 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0507 52.13 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0508 52.14 Bohlin, Cywinski, Jackson 11/4/2010 1 1/4/2010 0509 52.21 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0510 52.41 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0511 52.42 Bohlin, Cywinski, Jackson 111412010 11/4/2010 0512 S3.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0513 53.02 Bohlin, Cywinski, Jackson 11142010 11/412010 0514 53.03 Bohlin, Cywinski, Jackson 11/42010 12/10/2010 0515 53.04 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0516 53.05 Bohlin, Cywinski, Jackson 1 1/4/2010 1114/2010 0517 53.11 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0518 53.12 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0519 53.13 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10/2010 0520 53.21 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0521 53.22 Bohlin, Cywinski, Jackson 1,1/4/2010 12/10/2010 0522 55.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0523 55.02 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10/2010 0524 55.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0525 55.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0526 55.05 Bohlin, Cywinski, Jackson II /4/2010 12/102010 0527 55.06 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0528 55.07 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0529 55.08 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0530 S5.11 Bohlin, Cywinski, Jackson 12/10/2010 1120/2011 0531 55.12 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0532 55.13 Bohlin, Cywinski, Jackson 12/10 /2010 1/20/2011 0533 55.14 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10/2010 0534 55.15 Bohlin, Cywinski, Jackson 12 /10 /2010 1/20/2011 0535 55.16 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10/2010 0536 55.17 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0537 55.21 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0538 55.22 Bohlin, Cywinski, Jackson 11/4/2010 12 110 /2010 0539 55.23 Bohlin, Cywinski, Jackson 11/4 /2010 12 /10 /2010 0540 55.24 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0541 55.25 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0542 5631 I Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0543 56.32 Bohlin, Cywinski, Jackson 11/4/2010 1 1/4/2010 0544 56.35 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0545 57.10 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 Exhibit A- Contract Document Listing Page 12 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 13 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0546 57.11 Bohlin, Cywinski, Jackson 11/412010 12110/2010 0547 M0.00 Bohlin, Cywinski, Jackson 11/42010 12/10/2010 0548 M0.01 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0549 M0.02 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 0550 M0.03 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0551 M0.04 Bohlin, Cywinski, Jackson 11/42010 12/10/2010 0552 M0.05 Bohlin, Cywinski, Jackson 11/42010 11/18/2010 0553 M0.06 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0554 M0.07 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0555 M0.08 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0556 M0.09 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0557 M0.10 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0558 M1.00 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0559 M1.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0560 M1.04 Bohlin, Cywinski, Jackson 12110/2010 1/20/2011 0561 M 1.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0562 MI.05U Bohlin, Cywinski, Jackson 111412010 12/10/2010 0563 M1.06 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0564 M1.06U Bohlin, Cywinski, Jackson 12/10/2010 1 /20 /2011 0565 M 1.07 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0566 M1.07U Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0567 M 1.08 Bohlin, Cywinski, Jackson 11/42010 12/10/2010 0568 M 1.080 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0569 M1.09 Bohlin, Cywinski, Jackson 11/4/2010 11 /18 12010 0570 M1.10 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0571 M2.00 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0572 M2.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0573 M3.00 Bohlin, Cywinski, Jackson 11 /4!2010 12110/2010 0574 M3.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0575 M3.02 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0576 M3.03 Bohlin, Cywinski, Jackson 11/4/2010 1/2012011 0577 M3.04 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0578 M4.00 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0579 M4.01 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0580 M4.02 Bohlin, Cywinski, Jackson 11/4/2010 11 14 /2010 0581 M4.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0582 M4.04 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0583 M5.00 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0584 M5.01 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0585 M5.02 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0586 M5.03 Bohlin, Cywinski, Jackson 11/4/2010 12/1012010 0587 M5D5 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0588 M5.04 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0589 M6.00 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0590 M6.01 Bohlin, Cywinski, Jackson 11!4/2010 12/10!2010 0591 M6.02 Bohlin, Cywinski, Jackson 11/4 /2010 12/10/2010 Exhibit A- Contract Document Listing Page 13 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 14 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0592 E0.01 Bohlin, Cywinski, Jackson 11/4/2010 11 /18 /2010 0593 E0.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0594 E0.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0595 E0.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0596 EI.01 Bohlin, Cywinski, Jackson 11/4/2010 11118/2010 0597 E1.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0598 E1.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0599 E1.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0600 E1.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0601 E2.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0602 E2.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0603 E2.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0604 E2.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0605 E2.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0606 E2.06 Bohlin, Cywinski, Jackson 1114/2010 12110/2010 0607 E2.07 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0608 E2.12 Bohlin, Cywinski, Jackson 11/4/2010 12110 /2010 0609 E2.13 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0610 E3.00 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0611 E3.10 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0612 E3.1 I Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0613 E3.20 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0614 E3.21 Bohlin, Cywinski, Jackson 11/4/2010 12 /10/2010 0615 E3.30 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0616 E3.31 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0617 E3.32 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0618 E3.33 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0619 E4.00 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0620 E4.01 Bohlin, Cywinski, Jackson 11/4/2010 11118/2010 0621 E4.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0622 E4.03 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0623 E4.04 Bohlin, Cywinski, Jackson 11/412010 1114/2010 0624 E5.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0625 E5.02 Bohlin, Cywinski, Jackson 111412010 12/10/2010 0626 E5.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4 /2010 0627 E5.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0628 E5.05 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 0629 E5.06 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0630 E5.07 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0631 E6.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0632 E6.02 Bohlin, Cywinski, Jackson 11/4/2010 12./10/2010 0633 E6.03 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0634 E6.04 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0635 E6.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0636 E6.06 Bohlin, Cywinski, Jackson 11/4/2010 11/1812010 0637 E6.07 Bohlin, Cywinski, Jackson 11/4/2010 11 /18/2010 Exhibit A- Contract Document Listing Page 14 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 15 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0638 E6.08 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0639 E6.09 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0640 E6.10 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0641 E6.1 I Bohlin, Cywinski, Jackson 11/4 /2010 11/18/2010 0642 E6.12 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0643 E6.13 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0644 E6.14 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0645 E6.15 Bohlin, Cywinski, Jackson 11 14 /2010 12110 /2010 0646 E6.16 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0647 E6.17 Bohlin, Cywinski, Jackson 11/4/2010 11/18 /2010 0648 E7.00 Bohlin, Cywinski, Jackson 11/412010 12/1012010 0649 E7.01 Bohlin, Cywinski, Jackson 11/4 /2010 12/10/2010 0650 E7.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0651 E7.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0652 E7.04 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0653 E7.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0654 E7.06 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0655 E7.07 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0656 E7.08 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0657 E7.09 Bohlin, Cywinski, Jackson 11 /4/2010 12/10/2010 0658 E7.10 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0659 E7.11 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0660 E7.12 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0661 E7.13 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0662 E7.14 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0663 ET 15 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0664 E7.16 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0665 FPR1.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0666 FPR1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0667 FPR1.04 Bohlin, Cywinski, Jackson 1/20/2011 1 120 /2011 0668 FPR1.06 Bohlin, Cywinski, Jackson 1/20/2011 1/20/201.1 0669 FPR5.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0670 P0.0 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0671 P0.1 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0672 P1.0 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0673 P1.04 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0674 P1.04U Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0675 P1.05 Bohlin, Cywinski, Jackson 12/10/2010 1/2012011 0676 P1.05U Bohlin, Cywinski, Jackson 11 14 /2010 12/10/2010 0677 P1.06 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0678 P1.06U Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0679 P1.07 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0680 P1.08 t Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0681 P1.09 Bohlin, Cywinski, Jackson 12/10/2010 1 /20/2011 0682 P1.10 Bohlin, Cywinski, Jackson 11/4/2010 1210/2010 0683 P1.11 Bohlin, Cywinski, Jackson 11/4/2010 II /4 /2010 Exhibit A - Contract Document Listing Page 15 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 16 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0684 P3.01 Bohlin, Cywinski, Jackson 11/4/2010 12/1012010 0685 P5.01 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0686 P5.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0687 P5.03 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0688 P5.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0689 P6.01 Bohlin, Cywinski, Jackson 11/42010 12/10/2010 0690 P6.02 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0691 P6.03 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0692 P6.04 Bohlin, Cywinski, Jackson 11/4/2010 1/2012011 0693 FP 1.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0694 FP 1.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0695 FP 1.06 Bohlin, Cywinski, Jackson 11 /4 /2010 12/1012010 0696 FPI.07 Bohlin, Cywinski, Jackson 11/4/2010 1.2/10/2010 0697 FP 1.08 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0698 FP3.01 Bohlin, Cywinski, Jackson 1 /20/2011 1/20/2011 0699 FP5.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0700 FP5.02 Bohlin, Cywinski, Jackson 1114/2010 11/412010 0701 T0.10 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 0702 TO. 11 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 0703 T1.04 Bohlin, Cywinski, Jackson 1 114/2010 11/4/2010 0704 T1.05 Bohlin, Cywinski, Jackson 111412010 11/4/2010 0705 T1.06 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0706 T1.07 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 0707 T1.08 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0708 T4.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0709 T4.02 Bohlin, Cywinski, Jackson 1114/2010 1114/2010 0710 T4.03 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0711 T4.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0712 T4.05 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0713 T4.06 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0714 T4.07 Bohlin, Cywinski, Jackson 11 /4 /2010 1 1/4/2010 0715 T4.08 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0716 T4.09 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0717 T4.10 Bohlin, Cywinski, Jackson 11/4 /2010 11/4/2010 0718 T5.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0719 T5.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0720 T5.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0721 TG 1.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0722 TG 1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0723 TG4.01 Bohlin, Cywinski, Jackson 11/4/2010 1 1/4/2010 0724 TY0.00 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0725 TY1.00 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0726 TY1.01 Bohlin, Cywinski, Jackson 1 1/4/2010 1 114/2010 0727 TY1.04 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0728 TY1.06 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0729 TY1.07 Bohlin, Cywinski, Jackson II /4 /2010 12/10/2010 Exhibit A- Contract Document Listing Page 16 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 17 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0730 TY1.08 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0731 TY1.09 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0732 TYI.10 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0733 TY1.11 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0734 TY1.31 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0735 TY4.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0736 TY4.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0737 TY5.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0738 TY5.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0739 TY5.03 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0740 TY5.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0741 TYG 1.01 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0742 TYG1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0743 AV 1.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0744 AV 1.04 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0745 AV 1.05 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0746 AV 1.06 Bohlin, Cywinski, Jackson 11 /4/2010 12/10/2010 0747 AV 1.07 Bohlin, Cywinski; Jackson 11/4/2010 12/10 /2010 0748 AV 1.08 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0749 AV2.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0750 AV2.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0751 AV2.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0752 AV3.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0753 AV3.02 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0754 AV3.03 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0755 AV3.04 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0756 EV1.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0757 EV1.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0758 EV1.05 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0759 EV1.06 Bohlin, Cywinski, Jackson 1 1/412010 1 1/4/2010 0760 EV1.07 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0761 EV1.08 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0762 EV2.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0763 CS3 Bohlin, Cywinski, Jackson 11/4/2010 11 /18/2010 0764 RBI.01 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0765 RB1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0766 RD 1.01 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0767 RD 1.02 Bohlin, Cywinski, Jackson 11/4/2010 12 /10 /2010 0768 RD 1.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0769 RD2.01 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0770 R 1.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0771 R1.02 Bohlin, Cywinski, Jackson 12/10/2010 1 /20/2011 0772 R1.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0773 R1.04 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0774 R1.05 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0775 R1.12 Bohlin, Cywinski, Jackson 11/4/2010 1 12/10/2010 Exhibit A - Contract Document Listing Page 17 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 18 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0776 R1.13 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0777 R1.14 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0778 RLIS Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0779 R2.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0780 R2.02 Bohlin, Cywinski, Jackson 11/4/2010 12/102010 0781 R3.01 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0782 R3.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0783 R3.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0784 R4.01 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0785 R4.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0786 R4.03 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0787 R4.04 Bohlin, Cywinski, Jackson 11 /4/2010 12/10/2010 0788 R4.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0789 R4.06 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0790 R4.07 Bohlin, Cywinski, Jackson 1 1/42010 12/10 /2010 0791 R5.01 Bohlin, Cywinski, Jackson 11/42010 12/10/2010 0792 R5.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0793 R5.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0794 R5.06 Bohlin, Cywinski, Jackson 11/4/2010 12/10 12010 0795 R5.07 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0796 R5.08 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0797 R5.09 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0798 R5.10 Bohlin, Cywinski, Jackson 11/42010 12/10/2010 0799 R5.1 I Bohlin, Cywinski, Jackson 11/412010 12/10 /2010 0800 R5.12 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0801 R5.13 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0802 R5.15 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0803 R5.20 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0804 R5.21 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0805 R6.01 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10/2010 0806 R6.02 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0807 R6.03 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0808 R6.04 Bohlin, Cywinski „Jackson 11/4/2010 12/10/2010 0809 R7.01 Bohlin, Cywinski, Jackson 1 1/4/2010 11/18/2010 0810 R7.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0811 R7.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0812 R7.04 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0813 R8.02 Bohlin, Cywinski, Jackson 11/4/2010 12/102010 0814 R8.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0815 R8.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0816 R9.01 Bohlin, Cywinski; Jackson 11 /4 /2010 12/10 /2010 0817 R9.02 Bohlin, Cywinski, Jackson 11/4/2010 11/18/2010 0818 R9.51 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0819 R9.61 Bohlin, Cywinski, Jackson 11/412010 12/10/2010 0820 SR0.11 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0821 SR1.01 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 Exhibit A- Contract Document Listing Page 18 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 19 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0822 SR 1.02 Bohlin, Cywinski, Jackson 11/412010 12110/2010 0823 SR 1.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0824 SR 1.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0825 SR 1.05 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0826 SR2.51 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0827 SR2.52 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0828 SR3.51 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0829 SR3.52 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0830 SR5.51 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0831 SR5.52 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0832 SR5.53 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0833 SR5.54 Bohlin, Cywinski, Jackson 11/412010 12/10 /2010 0834 SR5.55 Bohlin, Cywinski, Jackson 11/412010 11/412010 0835 SR5.56 Bohlin, Cywinski, Jackson 12/10/2010 1/20/2011 0836 SR5.57 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0837 SR7.51 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0838 MR0.00 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0839 MR0.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0840 MR0.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0841 MR0.03 Bohlin, Cywinski, Jackson 1114/2010 12/1012010 0842 MR0.04 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0843 MR1.01 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0844 MR1.01P Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0845 MR1.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0846 MR1.03 Bohlin, Cywinski, Jackson 11/4/2010 12 /10/2010 0847 MR2.00 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0848 MR3.00 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0849 MR3.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0850 MR3.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0851 MR4.00 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0852 MR4.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0853 MR4.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0854 MR5.00 Bohlin, Cywinski, Jackson 11/412010 .1 1/4/2010 0855 MR5.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0856 MR6.00 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0857 MR6.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0858 MR6.02 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0859 MR6.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0860 ER2.00 Bohlin, Cywinski, Jackson 11 /4/2010 12/10/2010 0861 ER2.01 Bohlin, Cywinski, Jackson 1 1/4/2010 12/10/2010 0862 ER2.10 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 0863 ER2.1 I Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0864 ER3.00 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0865 ER3.10 Bohlin, Cywinski, Jackson 1 1/4 /2010 12/10 /2010 0866 ER3.20 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0867 ER4.00 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 Exhibit A - Contract Document Listing Page 19 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 20 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0868 ER5.01 Bohlin, Cywinski, Jackson 11/4/2010 11118 /2010 0869 ERS.02 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0870 ER6.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0871 ER6.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0872 ER6.03 Bohlin, Cywinski, Jackson 11/4/2010 12/10 /2010 0873 ER7.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0874 ER7.02 Bohlin, Cywinski, Jackson 11/4/2010 12110/2010 0875 ER7.03 Bohlin, Cywinski, Jackson 11/4/2010 11 /18 /2010 0876 PRI.OIU Bohlin, Cywinski, Jackson II /4 /2010 12/10/2010 0877 PR 1.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0878 PR 1.02 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0879 PR 1.03 Bohlin, Cywinski, Jackson 1114/2010 12/10/2010 0880 PR2.01 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0881 PR2.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0882 PR3.01 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0883 PRS.01 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0884 PR5.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0885 PR5.03 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0886 FPRI_01 Bohlin, Cywinski, Jackson 11/4 /2010 11/4/2010 0887 FPRI_02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0888 FPRS_01 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0889 TR1.01 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 12010 0890 TR1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0891 TR4.01 I Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0892 FS 1.00 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0893 FSI.000 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0894 FS2.00 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0895 FS2.01 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0896 TYR1.01 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0897 TYR1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0898 AVR1.02 Bohlin, Cywinski, Jackson 11/4/2010. 12/10/2010 0899 EVR1.02 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0900 011000 Bohlin, Cywinski, Jackson: 11/4/2010 1 1/4/2010 0901 012100 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0902 012200 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0903 012300 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0904 012500 Bohlin, Cywinski, Jackson 1114/2010 11/412010 0905 012600 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 0906 012900 Bohlin, Cywinski, Jackson 1 1/4/2010 11 /4/2010 0907 013100 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0908 013200 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0909 013233 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 0910 013300 Bohlin, Cywinski, Jackson 11/4/2010 1 1/4/2010 0911 014000 Bohlin, Cywinski, Jackson 11/4/2010 I I /412010 0912 014100 Bohlin, Cywinski, Jackson 11/4/2010 I I /18/2010 0913 014200 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 Exhibit A — Contract Document Listing Page 20 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 21 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0914 015000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0915 015639 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0916 016000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0917 017300 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0918 017320 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0919 017419 Bohlin, Cywinski, Jackson 111412010 11/4/2010 0920 017700 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0921 1 017823 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0922 017839 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0923 017900 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0924 018113 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0925 019113 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0926 024113 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0927 024119 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0928 032000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0929 032001 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0930 033000 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0931 033001 Bohlin, Cywinski, Jackson 1114 /2010 11/4/2010 0932 033100 Bohlin, Cywinski, Jackson 1 1/4/2010 11 /4/2010 0933 033313 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0934 033713 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0935 042200 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0936 142223 Bohlin, Cywinski, Jackson 1 1/4/2010 1/20/2011 0937 044200 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4 /2010 - 0938 044213 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0939 051200 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 0940 051250 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0941 053000 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0942 054000 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0943 055000 Bohlin, Cywinski, Jackson 11/4/2010 11 /4/2010 0944 055100 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 /2010 0945 055300 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 0946 056000 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 0947 057300 Bohlin, Cywinski, Jackson 11/4/2010 11/1812010 0948 061000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0949 061500 Bohlin, Cywinski, Jackson - 11/4/2010 11/18/2010 0950 061535 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0951 061600 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0952 064023 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 0953 066100 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 0954 066400 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 0955 071 116 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0956 071326 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0957 071327 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0958 071355 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0959 071700 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 Exhibit A— Contract Document Listing Page 21 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 22 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 0960 071923 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0961 072100 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0962 072726 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0963 073116 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0964 074213 Bohlin, Cywinski, Jackson 11 /4 /2010 11 /4 /2010 0965 074216 Bohlin, Cywinski, Jackson 11/412010 1 1/18/2010 0966 074219 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 /2010 0967 075419 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 0968 076200 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0969 077200 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0970 078100 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0971 078413 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0972 078446 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0973 079200 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0974 079214 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0975 079500 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0976 081113 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0977 081 166 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0978 081416 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0979 083113 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0980 083213 Bohlin, Cywinski, Jackson 11 /4 /2010 12/10/2010 0981 083215 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 0982 083217 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0983 083326 Bohlin, Cywinski, Jackson 11 /4 /2010 11 /4 /2010 0984 083473 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0985 084113 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0986 084413 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0987 084433 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0988 085113 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0989 087100 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0990 088000 Bohlin, Cywinski, Jackson 11/412010 1/20/2011 0991 088300 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 0992 089000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0993 092117 Bohlin, Cywinski, Jackson 11/4/2010 11 /4/2010 0994 092216 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 0995 092350 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0996 092400 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 0997 092600 Bohlin, Cywinski, Jackson 111412010 12/10/2010 0998 092900 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 0999 093013 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1000 093033 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1001 095113 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1002 095426 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1003 095430 Bohlin, Cywinski, Jackson 11/4/2010 II /4 /2010 1004 095440 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1005 095443 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 Exhibit A— Contract Document Listing Page 22 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 23 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 1006 096313 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1007 096513 Bohlin, Cywinski, Jackson 11/4/2010 II /4 /2010 1008 096516 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1009 096519 Bohlin, Cywinski, Jackson II /4 /2010 11/4/2010 1010 096536 Bohlin, Cywinski, Jackson 1 1/412010 1114/2010 1011 096623 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1012 096813 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1013 096816 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1014 096900 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1015 097713 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 1016 099100 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1017 099600 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1018 099713.23 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 1019 101 100 Bohlin, Cywinski, Jackson 1114/2010 1114/2010 1020 102113 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1021 102600 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 1022 102800 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1023 104413 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1024 104416 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1025 105113 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1026 113100 Bohlin, Cywinski, Jackson 1 1 /4/2010 11/4/2010 1027 114000 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1028 115213 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1029 122413 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1030 124813 Bohlin, Cywinski, Jackson 11/4/2010 111412010 1031 124816 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1032 126100 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 1033 129300 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 1034 133123 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 1035 141000 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1036 142100 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 1037 211000 Bohlin, Cywinski, Jackson 11 /4 /2010 1/20/2011 1038 220500 Bohlin, Cywinski, Jackson 1 1/412010 1114/2010 1039 220519 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1040 220523 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 1041 220529 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 1042 220553 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1043 220700 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1044 221 1 16 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1045 221119 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1046 221316 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1047 221319 Bohlin, Cywinski, Jackson 11/4/2010 111412010 1048 221329 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 1049 221413 Bohlin, Cywinski, Jackson 11 /42010 11/4/2010 1050 223300 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1051 22 3400 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 Exhibit A — Contract Document Listing Page 23 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 24 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 1052 224000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1053 224900 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1054 230500 Bohlin, Cywinski, Jackson 11/4/20 10 1 1/4/2010 1055 230513 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1056 230516 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1057 230519 Bohlin, Cywinski, Jackson 11 /4/2010 1114/2010 1058 230523 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 1059 230529 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1060 230530 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1061 230548 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1062 230553 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1063 230593 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1064 230713 Bohlin, Cywinski, Jackson 1 1/4/2010 1114/2010 1065 230716 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1066 230719 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1067 230800 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1068 230903 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1069 230923 Bohlin, Cywinski, Jackson II /4 /2010 11/4/2010 1070 230993 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 1071 232116 Bohlin, Cywinski, Jackson 111412010 1 1/4/2010 1072 232123 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1073 232300 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1074 232500 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 1075 233113 Bohlin, Cywinski, Jackson 11/4/2010 1 1/4/2010 1076 233116 Bohlin, Cywinski, Jackson 1114/2010 11/412010 1077 233300 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1078 233400 Bohlin, Cywinski, Jackson 1114/2010 1114/2010 1079 233600 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1080 233713 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 1081 234100 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1082 235100 Bohlin, Cywinski, Jackson 11/4/2010 11 /4/2010 1083 235216 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1084 235700 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 1085 236423 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 1086 236500 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 12010 1087 237300 Bohlin, Cywinski, Jackson 1114/2010 1 1/4/2010 1088 238123 Bohlin, Cywinski, Jackson 1 1/4/2010 1 1/4 /2010 1089 238126 Bohlin, Cywinski, Jackson 1 1/4/2010 1.1/4/2010 1090 238219 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1091 238233 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1092 238316 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1093 260500 Bohlin, Cywinski, Jackson 11/4/2010 11 /4/2010 1094 260519 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1095 260526 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1096 260529 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1097 260533 Bohlin, Cywinski, Jackson 11/412010 11/4/2010 Exhibit A— Contract Document Listing Page 24 of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 25 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 1098 260553 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1099 260800 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1100 260933 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1101 262200 Bohlin, Cywinski, Jackson 11/42010 11 /4/2010 1102 262413 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 /2010 1 103 262416 Bohlin, Cywinski, Jackson 1114/2010 11/4/20 10 1 104 262713 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1105 262719 Bohlin, Cywinski, Jackson 11/4/2010 12/10/2010 1106 262726 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1 107 262816 Bohlin, Cywinski, Jackson 1114120 IT 1 1/4/2010 1108 262913 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1109 262923 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1 1 10 263200 Bohlin, Cywinski, Jackson 1114/2010 111412010 I III 263623 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1112 265100 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1113 265600 Bohlin, Cywinski, Jackson 11/4/2010 11/42010 1114 000000 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 12010 HIS 270500 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1116 270526 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1117 270528 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1118 270543 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1119 270553 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1 120 271100 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 1121 271300 Bohlin, Cywinski, Jackson 11 /4/2010 11/4/2010 1 122 271500 Bohlin, Cywinski, Jackson 1 1/4/2010 11/412010 1 123 271619 Bohlin, Cywinski, Jackson 11/412010 1114/2010 1 124 274100 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1125 275119 Bohlin, Cywinski, Jackson 111412010 11/412010 1126 280000 Bohlin, Cywinski, Jackson 11/4/2010 II /4 /2010 1127 280513 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1128 280610 Bohlin, Cywinski, Jackson 1114/2010 11/42010 1129 280620 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 /2010 1130 280660 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1131 281000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1132 282300 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1133 282623 Bohlin, Cywinski, Jackson 11/4/2010 1 1/4/2010 1134 283100 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1135 283500 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1136 285000 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1 137 286000 Bohlin, Cywinski, Jackson 11/412010 1114/2010 1138 311000 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 12010 1 139 312333 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 1 140 316800 Bohlin, Cywinski, Jackson 1114/2010 1/20/2011 1 141 320190 Bohlin, Cywinski, Jackson - 11/4/2010 11/4/2010 1 142 321123 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1143 321216 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 Exhibit A — Contract Document Listing Page 2S of 26 EXHIBIT "A" CONTRACT DOCUMENT LISTING PAGE 26 OF 26 ORIGINAL LATEST ITEM # SHEET PREPARED BY ISSUE DATE REV DATE 1144 321300 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1145 321400 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 /2010 1 146 321410 Bohlin, Cywinski, Jackson 11/4/2010 111412010 1 147 321413 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1 148 321413.16 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1149 321500 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1150 321723 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1151 328400 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1152 329113 Bohlin, Cywinski, Jackson 11/4/2010 1114/2010 1153 329119 Bohlin, Cywinski, Jackson 11/4/2010 11/412010 1 154 3291 19.13 Bohlin, Cywinski, Jackson 1 1/4/2010 1 1/4/2010 1155 329119.23 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1156 329210 Bohlin, Cywinski, Jackson 11/4/2010 1 1/4/2010 1157 329221 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1158 329222 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1159 329223 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1160 329300 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1161 331100 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1162 333100 Bohlin, Cywinski, Jackson 11 /4 /2010 11/4/2010 1 163 333913 Bohlin, Cywinski, Jackson 1114/2010 11/4/2010 1164 334100 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1165 334119 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1 166 334419 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 1 167 334600 Bohlin, Cywinski, Jackson 11/4/2010 11 /4 /2010 1168 334913 ohlin, Cywinski, Jackson 11/4/2010 1/20/2011 1169 335100 Bohlin, Cywinski, Jackson 1 1/4/2010 11/4/2010 117 1 3361 13 Bohlin, Cywinski, Jackson 11/4/2010 1/20/2011 1171 481413 Bohlin, Cywinski, Jackson 11/4/2010 11/4/2010 SPECIFICATION MANUAL Project Specification Manual prepared by Bohlin, Cywinski, Jackson dated November 4, 2010 entitled Newport Beach Civic Center and Park divisions I through 48 inclusive. SOILS REPORT Soils Report prepared by Leighton Consulting dated April 2, 2010 entitled Geotechnical Exploration Report for the City Hall / Civic Center and Park Development Plan Newport Beach, Orange County, California and Addendum dated September 10, 2010 in review of shoring plan for permanent shoring Wall. ADDENDA Addenda Prepared by Bohlin, Cywinski, Jackson as follows: Addenda Number I dated November 18, 2010 Addenda Number 2 dated December 10, 2010 Bulletin Number I dated January 20, 2011 Exhibit A — Contract Document Listing Page 26 of 26 T,nde63m I...,: ,$JTE LMLITIES Be 0021 Project: Newpen Beach Oil Cm:erann Park SUBCOI Dore 4Fire.,20il C.W. Driver nDll.uen9 fls;n 1cm Subcontractor Name NO. Descriptionl5c.pc orwOr4 Delta Pipeline G C I Construction Ran.Pipellmt L &S Construction Imerpipe Contracting HPS Mechanical Atladeti llutl Hall ConstrueGOn Proposal. Par Plans and Specs 050,551 986,05] 1,044,060 1,102,560 1,201,561D 1,566,246 1,710,560 1,710.072 aid as p...d - 835.918 964.297 1,026.500 1.085,80 1,184.000 1.548,686 1.693.080 1,691312 Piequalliad Yoe Y,e Yes y9x yax Yex yes Ycs CA License Curren, yes Yn Yee Yes no Ya-a Ycs yes Per Plans and Specs YP-x Yes yer Ycs ye, Yes yex Ycs Aclmnwledg9 Addenda land 2 & Bulletin I Yes yes no Yes Ym yes Yes no Bid Bond Included Yes yex Yes yes yes Y. I. Y. Prevailing Wage Yo Yes yes Yes yes in yn re Compliance will Projea Schedule yes Yes yes yez yes Yee yes yes Uemd Suhmnrracmri yer Yes ym yex Yes yex y9r yes ALLO WANCESIADIUSTNBNTB Ne,noenden 5 - 5 - 5 - 5 - 3 Post BNFNr 5 - E 5,000.00 4 - Dnlle4n 1 $ 14,633.011 17,559.60 5 17,559.60 5 17359.60 5 17.559.60 E 17,559.60 5 17.559.60 5 17.559.0 3 - II !I d, 1lII 11 -. „�:'ii tL'uiDl. 'li ': -I'i ,I,.A,d I011}I nil LIY... ii III ,1 Il 1. t ,Ill tll I l � itnnfn[t Ann t i1 3 . 65.551 a0t j 1 1 1 1 1........q i, ... ...� .. i a e 1lhap 70119 ....: i 1 1 1 1j1ph 9!3959391 1n e 1u 11111] 1111110116 ,'hl:nl 311 l"! �91 9,�ti -., {. :.: iL Ii �n l'.I 61,ih1p1.6 6.p1 �1i1�D� ENV 8,.iNL:I,ii,lne � l {l1 k1.31Y60.'� .I�iI GLn,D, p11.link b B l�li � ilBt�I jr, to 1IdIBI�J,,,II'] ';1il 311 �i n� L1 ]ii Ilu �jd!11H 6A�IiNtl VOLUNTARYAMPINAT55 "., ar, - 5 - 5 5 - Y - E - 1J 1 I�,i. S I x.TaCl YOI r7 Allemut9.Amoentl - - :u 51 11��l ' f ill jlill loll r. 1,11 ken 5.. '.1 � t Ill If 1. slall:',. ,I,: ;,II SSE 11 i'il ld� 1p ?.,�, E II llj'�i�l I011it l..•I' 411i1 -- .IQ In 1ff11v1 "., ar, Trade /Bid Package: SITE CONCRETE BP 002.3 'L-+. V V Driver nnILDERS a1tiCP. w1'� Project: Newport Beach Civic Center and Pad, SUBCONTRACTOR COMPARISON SPREADSHEET Date: 4 February 2DI I Subcontractor Name NO. Descriptionl5copeaf Wierit Demcon Concrete CnntraCCOrs Griffith Company )euawsid & Markel Shaw & Sons Trademark Concrete Proposal -Per Plans and Specs 3,075,000 2,957,160 3,355,184 3,548,543 3,325,541 Bid as opened ZIOO,DDO 1,446,477 1355.181 3,548,543 3,325,541 Prequalified Yes Yes Yes Yez yes CA License Current yes yes yes Yes yes Per Plans and Specs Yes Yes yes Yes Yes Acknowledge Addenda land 2. & Bulletin I yes yes Fee Yes Yes Bid Bond Included Yes yes Y. Yes Yes Prevailing Wage Yes yes Yee Yes Yes Compliance with Project Schedule Yes yes as yes yes Listed Subcontractors Yes Yes yes Yes yes ALLOWANCES /ADJUSTMENTS NcreeMb fte $ 975.000X0 5 1.510.693.00 3 - $ - $ - Past Did FRI. §' - 5 - 5 - $ - $ - Bulletin 1 S - $ - 5 - $ - § - .PI'S t :.lit fln t;iit _.Ili t 'l. II 11 1 tuu tit,...... lut.. 11 .III. { I I1546[ontrattLt'rCOnt @[L'A Onnt r :., I sl .: -<;a ,.• t '� .al ,. .. .,... ".el l hi it 11111: t, ... I u. hl ...0 Iin 1 § BeI�'yedOXa .t ilil 111.1.1 .t ait 111 -rl „11111.11 lulp 11.u... L,lun. . 10:01 L ,it �U,1de'�DUrI ul. 1i; 1. ., "1�� -I t 411. 111 IUJ IainiLUn,lli tt 1111j .3(35516400 lj i'l ii IIN�;Il�ulii tt �l ll l' 1 ,'ll' llln- L .Ii.adu. Ile .1 Bi. d,it.u8.l S s tit B� bli I1u11�'; ��Ji, li :u�l91��14,lvI -"tl I1.. . •• I1..uttFl >i1 Id1.lLiitBfllll IIfl110u „- kri>axss1�4,41 •M IIIIIIOf- qItld 111'�31ht]�li� - lin.•.' ..IhDlblll ill II tl18111.1131e p0. il:�l.: P,03ki. r,l VOLUNTARY ALTERNATES t, Ile 1 71 1 Total ountary Itema �. ( ,tid ,'l I.L11�� to m unt :# 5; j�. I 11 :4 $ It j l� I�1]siF . ;ii Ii i; @ - Nav 1 011 TradelSid Package: LANDSCAPE & IRRIGATION SP 002.4 C.W. Driver RUMDERS SINCE 1919 Project. Newport Beach Civic Center and Park SUBCONTRACTOR COMPARISON SPREADSHEET Date: 4 February 2011 Subcontractor Name NO. DescriptionlScope of Work Marina Park West Landsape Valley Crest Landscape Proposal - Per Plans and Specs 5,249,364 4,747,829 4,863,615 Bid as opened 4,746,564 4,498,577 4.011.700 Prequali0ed yes yes yes CA License Current yes yes yes Per Plans and Specs yes yes yes Acknowledge Addenda land 2, & Bulletin I yes yes yes Bid Bond Included yes yes yes Prevailing Wage yes yes yes Compliance With Project Schedule yes yes yes Listed Subcontractors yes yes yes ALLOW ANCESIADJUSTMENTS Normalization $ 477,865 $ 226,602.00 $ 65,000 Post Bid FRI, $ - $ - $ (38,000) Bulletin I $ 24,915.00 $ 22,650.00 $ 24,915.00 $ Is $ -:;l 1.�M Wuilp ii �' -. l' 1!11 .111 jj Ai:' IM:�lil (IIL�,L�'�I�i�� ��i 1��11 hd1 Iii � -.,a: t Il91J- I!iup'PIII r "'L !,.! I.�,...'�..i 111 5ubcudliattarConti'Z<N'hmount g .111: _ 1 ;(1 ':. � lul ��Il�,!li 11'11'1- .11'GVIIill1101111'Iltl'Il Irk l!,i41'11{1�s]q �i "1 �L�I jpllli�ll sill n {I�. IF010H1!!!tiii! ;3 . -i00i .a11i 11 "9iH:16 ;ia IIIVI,.fl111Jl!U�. ' ii { of A p7 az9 d! �l! Ski h f114111�1�i.W�i 1 �l6llul i}'SI WNiCirii hlk $ 3111y)1!I,IIIIII'd','863613 �1h.11111 -:Il _: -��'LI i „1,111 tl Lidil'li Ob1 ! � III dl f 111! ff -10a. dig” 1. -i 1. b�i�ll..l llllt� IJ4? II, InJiA !9itl!,1!!I;!li!{!I!!i!!J:f!iN !i; 1. ] i!It Hll��!!F�III��ii�� i!it r 1. VOLUNTARY ALTERNATES Reduce Maintenance Period $ (50,000) $ (102,000) $ (62.000) Use "technsoil" in lieu of "nacura' pave $ - $ (104,000.00) $ - $ $ $ I1 a SI " 1 Total Vnlunfa Aitemate'Amaunt{ '.,yl ry 1 $ �1 (50000.00) $ 1, (20600.00) i !1 ! 111(62,0110.00) .iRtyale: ;. Paga I of l TradelSid Package: AC PAVING. STRIPING & SIGNAGE Project: Newport Beach Civic Center and Park Date: 4 February 2011 BP 002.5 SUBCONTRACTOR COMPARISON SPREADSHEET C.V. Driver nun.Daas srar-c rnv Subcontractor Name NO. Description. Scope of Work Hardy & Harper Terra Pave, Inc. Western Paving $ Proposal - Per Plans and Specs 199,919 223,700 275,500 Bid as opened 199.919 223.70D 275,500 Prequalkied NIA NIA NIA CA License Current yes yes yes 5 ! :kl! - lII,I 1 - " $ i '�. .y . :� ; $ : 1111 Fi•.I �� 1 I" Per Plans and Specs yes yes yes Acknowledge Addenda land 2, & Bulletin I yes yes yes Bid Bond Included - yes yes yes Prevailing Wage yes yes yes Compliance with Project Schedule yes yes -yes Listed Subcontractors yes yes yes ALLO W ANCESIADJUSTM ENTS Normalization $ - $ - $ - Post Bid FRIs $ - $ - $ - Bullean 1 ilpwiq 1r; 0 i,ul4 I. nl:l t '.'i. u„I 11,id i`II IYI 't�' ILl.l�l. �I Sub tractor CantractAmovnt .;il, ! i„ III II IILII!;, illlv!Ii,: "h.. !n: $� n iI d99919:ob 6 - I.:.i Y.iu911 uI!14mt Jddtdtl li!r.II'lii 1,4 151 ..I 122371Itl tltll :I i._M1a I!IY III�IF{,llli9 PI {$h hI N. nitYY' fI!II'!B!lY!,lY!1�!L`fit,i!rltilt �. - Plli lt27�S SaUU o: , 1x11::1 i1111Itll;llf�bd p!iIIIII li ;hl'I�II ii;4�l!�VI�L������i. IINILCI!';IIiIII1Al -�'.j3 1iill' "i'li'!..1J;:idl!IF,YRE n -tl. E.. .r�latl, Iilil !.S Ili �ull! ^��' 6, Yt!YI @Y'. , is yEi, �..:�I���I��1�,!1•(��1�"< „!!611ialYAS;,YE ,II. VOLUNTARY ALTERNATES $ $ $ d�fY'h �1Trd1 III 111i+i 5: €Total Yblontary Alternate AM6Lnt' 5 ! :kl! - lII,I 1 - " $ i '�. .y . :� ; $ : 1111 Fi•.I �� 1 I" -ft_I '" QII - l�1 Pe9e 1 011 Trade/Bid Package: FINISH GRADING BP 002.6 C.W. Driver BUILDERS SINCE 1901 Project: Newport Beach Civic Center and Park Date: 4 February 201 I Subcontractor Name NO. Description /Scope of Work Sharma Contractors Stice Proposal - Per Plans and Specs 1,284,207 1,262,300 Bid as opened 5 1,138000.00 S 2B6.300.00 Prequal!fed yes yes CA License Current yes yes Per Plans and Specs yes yes Acknowledge Addenda I and 2, & Bulletin I yes yes Bid Bond Included yes yes Prevailing Wage yes yes Compliance with Project Schedule yes yes Listed Subcontractors yes yes ALLO WANCESIADJ USTM ENTS Normalization $ 146,207.00 $ (24,000.00) Post Bid FRIs $ - $ - Bulletin 1 $ $ - II '-. + 1 '.!.!r! Sabots.;;ctor ContrattAmouht� k I °�i, =,11 Ixu fLI11!gl.11r+l!! ,+!m:! §7:!n1erJl a §� 17B4,M700t i.i �Aili'in "I!6d,II:!!I!t:!hle 5 6]a0o U0jl l:Ii'r..hi. 111kIh11•nilhlnlfl i +l llijl!�lll l:nn ail iiti!iiui i.' d !ill! ? "4;+I9il;;4'hrif•py1` ' jl�'�yj tp, iltinilifil li �II� 'illlid0n +nilnli!luiulnl -!b I�Ilj j��j Pilul_!111, ill VOLUNTARY ALTERNATES P., 1011 $ $ $ $ + +' i' , i +I -I1' Total Voluntary Alternate Amount i P., 1011 T,ade/Bid Package STRUCTURAL CONCRETE & REBAR Project, Newport&ach Civic Centerand Park Date: 4 February 2011 SP 003.1 SUBCONTRACTOR COMPARISON SPREADSHEET C W Driver Inn LDERS 51NCa la,, Subcontractor Name NO. Description /Scope of Work Boreal Construction Conco J T Wimsabt Morley Construction Prizio Construction Proposal - Per Plans and Specs 4,212,397 4,521.554 4,190,000 - 5.277,777 4.125,750 Bid as opened s 3.210202.00 5 4521.554.00 5 4.10000000 5 5277T77.00 S 3.900,75000 Prequa110ed Y. Yes yes Yes yes CA License Current Yes Yes Yes yes Yes Per Plans and Specs yes Yes Yes Y. Y. Acknowledge Addenda land 2, & Bulletin I yes ms yes yes yes Aid Bond Included Y. Yes Yes yes Yes Prevailing Wage yes Yes Yes Yes yes Compliance with Project Schedule Yes Y. yes Yes yes Listed Subcontracwrs yes yes Yes Yos yes ALLOW ANCESIADJUSTMENTS Normxliration $ 9914.135.00 $ 2 ODD.00 Post Bid FRI, 5 - S - $ - S Bvuetin I $ - 3 - $ - $ - $ 5 $ $ S -li 1! I!''i i , ;.I - ru! avt !{.A, s ..JS t ..I - ..-- �!!... li.s,.. $ebCent,aC}Ar CbntYddt'AmOUnt ...i.., Ii:.R II IVI S- A +! ?i.!:: ,IxI $t '14'21].3s700 ILII -.P; l %r. A -.' .I iILI!9111nIIVt E 451 6400; xlll!iisl4 la !1!!il 717 51 'I if.190,tle0.Otl! M!ial ld.ailf 1. I1601.IIIL Ah qq!, S I - 52 T tltl Iln!;1IPIIIII- .IGho;!hld.!4!��� !Aiii ,'I' ! I'1.0'IL!Y loi I.. 6!{ 4.1=50A0 IIII1111kflNlNlhlEll'nlll!111911 ,L,Ilnj la!IIA!i0!!!III VOLUNTARY ALTERNATES PaOCic,i 4 S $ $ $ $ - 5 - $ - Total Voluntary Altematc Amount !1,< $ PaOCic,i Tmtlel0id Pencil GROUND ANCHORS & DRILLED CONCRETE PIERS Project: Newport0esch Civic Center and Park Darn: 4 February 2011 BP 002.1 SUBCONTRACTOR COMPARISON SPREADSHEET C.W. Driver IIPILnlinti sill. IOIo Subconeractor Name NO. Descriptionl5cope of Work Anderson Drilling D8M Contractors Drill Tech Drilling 8 Sharing Malcolm Drilling Company Sharing Engineers Proposal - Per Plans and Specs 713,300 854,330 Disqualified 605,863 531,260 Bidasapened 5 550.500.00 S 554.]]0.00 3 409,740.01) 5 505.63.00 5 5310NO DO Famc..lified yes yes yes yes yes CA License Current yes yes Y. yes yes Per Plans and 5pecs yes yes yes yes Yes Acknowledge Addenda land 2, g Bulletin I yes yn, yes yes yes Bid Bond Included yes yes yes yes yes Prevailing Wage yes yes yes yes yes Compliance with Projea Schedule yes yes yes yes ya Ustod 5ubeontrxaors yes yes yes yes yes Missing scope, ALLO WANCESIADJUSTMENTS Nmmalleadon _ $ 154,800.00 $ - 5 - $ - S - lamc aid F0ls 5 5 - $ - S 5 - Bulletin 1 S - $ - S - $ 3 - 5 - S - S - $ - .S 1 II lil {I ill l`{ (1,1 {�s nil iii t , "' ^.n 0!71 11:1 -. i!INRII !111 f -. ff!! 5116cetitYSttOr Con[rdCY!Ameu t r 1 ,- ].Lr:' -i lilt 101.1 -.1 .: 1101. 11111 ,' T3pseyo015i. Will,$n.,di, 'Ifllillfl!!'!'+i.. "i!i.l'dl lilt il:i !4'iI155/d35:0a .I':; {1'11�1i 11 LI11!'e �dj.iJ ltil.- ;II FI( IIII, ,IL.I011J r!11115 {I {4:1 {, {��I: i�l�lglll��!�e, II11AiOJltl;l!IIYIItl 1111311;.'dll!'1 �, t 6-0S'6yA0 lit, !J. -k IIOtLI,iL �i!!�ill -,t ..,if! 110 Ii1351,1SOaO {EiilVi lh,wlI 1:1!:Ilf.,d0i 101:III0:l 1: �l {:11.1 ifllfl!iEl!116!lilf0 :� y��,i :1' �:IlkMUi 1'�I ".:�, BI {IJ1,:1: VOLUNTARY ALTERNATES 5 - S - + , LJII{t111 Toni VOlunLtiy'l�iteynatc Am0un[Iyi X3{[3 J, 1� § j{} '! 1' I,',,, {,t {illik 1111 L 11 n., { ":1II -- •_ frill {1,11 ;� i ii i. ,., 1usl TradefBid package: MASONRY BP 004.1 QW. Driver eu1.0ans SINCE Iv!v Projects Newport Beach Civic Center and Parka SUBCONTRACTOR COMPARISON SPREADSHEET Date: 4 February 2011 Subcontractor Name NO. Description /Scope of VVorlc Frank R. Smith Griffith New Dimension $ Proposal . Per Plans and Specs 1,140,330 $ 1,648,1140 $ Bid as opened 5 1.190.330A0 S 799566.00 S 1.648640.96 $1= i Prequalified yes yes yes CA License Current yes yes yes Per Plans and Specs yes no yes Acknowledge Addenda land 2, & Bulletin 1 yes yes yes Bid Bond Included yes yes yes Prevailing Wage Yes yes yes Compliance with Project Schedule yes yes yes Listed Subcontractors yes yes yes n ALLOWANCES /ADJUSTMENTS Nonnalisnion $ - $ - $ Post Bid PRIs '$ - $ - $ Bulletin 1 $ - $ - $ $ $ $ - iIt is "': ;1! �1 I � ii i,��l�!1111 s'. e.lsti !;� "!' +1i'!i li! +!;,il e!!.,h .n :I ii?.! 4" i- IliP! Ii.; 4�! i;' i' i!!' 5ubtiintrector ConkracglAmaunt is ; I' � 1!I' ! i� ,F �I {�� i-'. Iuk, hi!' elulN9{ 41N11 !i4.l:tl!uli!I!!il5u!!ni!I!IIIR S lit {I; k[ 190 36.99 RI •xi� !�L�: n;l4ltin;ii.' +.!fl5 S I! � li pIy'i� 1y956606, �!���JI[�l�l.( c:k us $1'�j� ��1.��������f��1 ill ii! It1IdIl1luu! i�!! ul;!:!iidla.h!Ik'U!fi'ii �I�I;i.I :6/6,84900 �I�1 !� 11 "s!41Pil i! � ' {i�11���!�111�1��1 L'fi.IkU!!iY;.ili!i!w!i!!all!�P ! I � �' II 1 ���� i!1!!I'91!ii f!�i ��I I, �.� VOLUNTARY ALTERNATES $ $ $ $ $ $ Viii t!i. ii�k t III fl Ta - tal Volunta ry Atternafa Am96nti ": - I f s $1= i P.,. , of t Trade/sid Package: STONE WORK Project: Newport Beach Civic Censer and Park Date: 4 February 2011 BP 004.2 Q.W. Driver RUILDERS SINCE IgI9 SUBCONTRACTOR COMPARISON SPREADSHEET Subcontractor Name NO. Description /Scope of Work Carnevale & Lohr Italian Marble and Tile Co. Proposal - Per Plans and Specs 3,603,490 3,610,000 Bid as opened S 3634.490.00 $ 3.410000.00 $ ! ! Prequali0ed yes yes i.lii;! .S I r:.h 'l. 1 in CA License Current yes yes Per Plans and Specs yes yes Acknowledge Addenda land 2. & Bulletin I yes yes Bid Bond Included yes yes Prevalling Wage yes yes, Compliance with Project Schedule yes yes Listed 5ubconeractors yes yes ALLOWANCES /ADJUSTMENTS N.mch.tion $ (5.000.00) $ 200.000.00 Pass Bid FRis $ - If - Builedn 1 $ - $ - Stone Thickness VE $ (26.000.00) $ - I'I,rJl t, 11..1 yuas 111 �t 1 1J17 :.1!':.:hu'Ih:tom,il0:fm!Ii:l' 114: d ;!ieu.:I:hi'- I.i:l'i!!I!Ini!I Sebcontractar'Conlrnct Amouetl k naf i' ni wl 1.: , F:..n�u,4:l.i. lh}'Ii1�� i1611u ci i!P!ilildda- '1i:ni!nHil ail! 3603190.001 ulLii fi11Nm1 :S �i�l +1j �.�.�.n n'! 1111 !i!PIi1i4r1lii:I +!i!'it.tlinii; 1 I!�1 njd d7C 00000 lf91i6'tl'inR!Iailiii!Nr,IIWi.i j: [ i���!�i i��lltin. NnN1!snly:u ,fit �J §y -i!in ndi.Nl: it u. VOLUNTARY ALTERNATES P., 1011 $ $ $ $ Total Voluntary, a I- A-mbunt - � $ ! ! i.lii;! .S I r:.h 'l. 1 in j�i P., 1011 TmdeBid Paclane: STRUCTURAL STEEL BP 005.1 - C.W. Driver 0911.D4JIs SINCE Ivl•I Project Newport Baach Civic Cancer and Park SUBCONTRACTOR COMPARISON SPREAD SHEET Date: 4 February 2011 Subcontractor Name NO. Description /Scope of Work Plas -Tal Mfg. Co S & H Steel S M E Steel W & W Steel Company Proposal - Per Plans and Specs 9,424,001 6,235,000 6, 142,652 8,895,000 Bid as opened 5 9,794.0 00,0 S 6555.000.00 S 0142.652.00 S 8095000.90 $ Prequalified yes yes yes yes $ CA License Current yes yes yes yes $.. I 'd -' Per Plans and Specs yes yes yes yes Aclmowledge Addenda land 2, & Bulletin I ycs yes yes yes Bid Bond Included yes yes yes yes Prevailing Wage yes yes Yes Yes Compliance with Project Schedule yes yes yes yes Listed Subcontractors yes yes yes yet ALLOWANCESIADJUSTMENTS Narmalixasion $ (369,999.00) $ 1,600.000.00 Pas[ Bid FRIs $ - § - $ Oullecin 1 $ - $ - $ - $ - r� } it 11 ! i'�III III ...:� i __ -i 1 1 I i lj iL 111 ' 11T t ll4 ',I� lI I.. v..0 ..,..- ":.i, -9 1 ,-- ',1,.,1 1 I �1 I it 1 illl. SubcentratYOr Omtr4ct Amount 1 1 dill :'.: �1 �.si it it ,. ,.,al ! ,Wr I1 it 'I, I�uLI 1111 1BI117NIIl s 1 i s 119,gx4,001i001 A,•INtI II i0 ,- - i,Ii'll'L-- 81117'{. S, fill l Ilji j1 I.O xas,90t o6 •. ,1 ta, 1701110107ili16i y It III ft ml� olliJi AiII:H,11107 Odlillll : p 14A09E00 I,uG Ilr r,iinl: .171111 �' irz•: Iilll�- ,III !!!i' " ='IiiS%I:.I!OR Alhl �IIlI Li a:895,90R,60 Llllh�, l{ Sa ildO a'd110010llllil; � �, 101k 181:1:0 -11 ::I }, f'll l 1111611 VOLUNTARY ALTERNATES S $ $ $ $ $ $ $ 1=.. ... . Total Vaiunta Alternate Amount,,, � ., 7 FIB .. _:. , P _ 5 I �,1 1 li� 51 'I $.. I 'd -' ' F.'a l of l Trade/Bid Package METAL DECK BP 005.2 PralecC Newport Beach Civic Center and Park Date: 4 february 2011 C.W. Driver DUI LUens S: NC..n rno Subcontractor Name NO. DescriptioNScope of Work Anning - Johnson Eckles Construction J D 2 The McIntyre Co. 5 &H Steel Proposal - Per Plans and Specs 560,956 697,950 750,000 1 622:755 1 737,700 Bid as Opened 5 523 X00.00 5 70t 050.00 5 750000,00 $ 594.450.00 5 73].]00.00 Prequaliled yes yes yes yes yes CA License Current yes as yes yes yes .tl!.: I, J rg Per Plans and Specs yes yes yes yes yes Acknowledge Addenda land 2. & Bulletin I yes yes yes yes yes Bid Bond Included yes yes yes into - yes Prevailing Wage yes yes yes yes yes Compliance with Prolua Schedule yes yes yes yes yes Listed Submntraacors yes yes yes yes yes ALLOWANCESIADJUSTMENTS A.moluseen 5 57.356.00 $ (4.000.00} S - $ 16305.00 $ - Past Bid Mh, S - $ - IF - $ - $ - Bulletin 1 $ - $ - $ - $ - $ - .7aorIsm m al! ar•�, I.b� .n , 1, 1�1 .: -f�.1i;.11. 11r .1 . 11]i1,1 .�-.,r {. i l.LlIl r • SUIb! 4v'n1:.tt:L'I; i5I. Plc:tI. oO r E!! o-rn , t tLa- ,c1.tuA�1:; c .mn..I v ..0 , ti .i t : " r ItI LIL,1 Ih- ly:'.i- ',-n 'ii 4; 1 1.1I 1 11 INt t IItl-.' .tlr.Y.h l� . . iIS 'jr.n.. . r.6d .! tlI l •L: .I m •! .. l; n ._,c I lL'I5I.r.0pl .0 IIt 9 II5I6 Ir IUGOfii d I5I 1-1 l.{n .:. .;ti, I ti... . t r•,i l h'hn,i•n•9ire.t . r : 6 in9i Tr 893-60: �AI 11 l 0 i It r IY- r I I ata L .L.: 1114. TilU. If, ILr. '11'j; l II.b. 1U,. lINIII.!� 1111- 1 ..blcll.,r..`l•ll U'p; .LII I UI-nI .! 1(11 i�t L• rt=:1lty'.. . '{ .1 Iil,lI I�.: r.11 Will! I �� lay , iI" h Plant, 5.11 rt 1 ..�• VOLUNTARY ALTERNATES ,.as s a 1 5 - $ $ - $ - $ - „! t a, 4n :9iIM76!�:i111111i�;r I111Total YolontaryA(Eemate�Atiwunt- F [ 1, -In lli s s ° Ir•. 10i:1� 1llls, .: s 111 ;�1I 1 ; !I, {- ��1r4�1i�lI19I, rNlonit,l {:, ! s r.i1 ,r�.l- • . hlli �h�iC .tl!.: I, J rg ,.as s a 1 TradMOid Package MISC. & ORNAMENTAL METALS Ble 005.3 C.W. D(- 1`Tej' Project. Newport Beach Civic Center and Park SUBCONTRACTOR COMPARISON SPREADSHEET BUILDERS suet Ior, Date: 4 Febrmry 2011 Subcontractor Name NO, DescriptionlScope of Work Baplco Metal S & H Steel Southwest Steel Proposal - Per Plans and Specs 2,1 19,083 2,612,500 2,1 10,348 Bid as Opened S 2.119.08300 s 3052.00D.00 5 2.275.421.00 Prequali0ed yes yes yes $,1 1$ IT? 1- CA License Current yes yes yes Per Plans and Specs yes yes yes Acknowledge Addenda land 2, & Bulletin I yes yes yes Bid Bond Included yes yes yes Prevailing Wage yes yes yes Compliance with Project Schedule yes Yes yes Listed Subcontractors yes yes yes ALLOWANCES /ADJUSTMENTS Normalization $ - 5 (439,500,00) $ (165,073,00) Post Bid FRIs $ - $ - $ - Bulletin 1 $ - S - S - $ S $ 11111 li iii 1 al' j�ir i1 1l_ It 1 „1 Cillfl { -.1 "IL Ittill .,'I'Ii Mill ! - .;'i,p iii iii a..:1.15 .; alU Subcontractor Cener'zceAmount l..`j 1 Ii il.,i!dll l!7�1,6J111;15`IIlpB S 119081.00 1 I� III M1ilf bnii illlU4lili f II i:Ai 141',Llliul „I1.�!IBI $ Il�.it'; 111 OO.Oa I.11111t� ItI'tli lilllAll:kCi ll lil 11k II II 11�i ;itox4800 1311111;IlII1011!u j �jil li tl Ii71f,811IIIIlil 'il 5l U,f- 111411 III ! VOLUNTARY ALTERNATES P.,1 a $ $ IS $ $ $ s $ $ i ,lit, 11.v1 11� u. w ,d Total Volun ary AleefdatC Amau ❑F $,1 1$ IT? 1- P.,1 a Tradelaid Packager ROUGH CARPENTRY BP 006.1 C.W. Driver Project- Newperc Beach Civic Centerand Park SUBCONTRACTOR COMPARISON SPREADSHEET IIUIIIDaRS ww Date: 4 February 2011 Subcontractor Name NO. Description /Scope of Work - Abdellatif Enterprises D W McCasland Golden State Framers WSJ ern Contractors Proposal - Per Plans and Specs 780,500 717,775 663,607 744,886 Bid as Opened s 592,P00.00 s 592,000 $ 820.40 00 5 419,65000 Prequal0ted yes yes yes Y. CA License Current yes yes yes yes lie hj,�,',l Per Plans and Specs yes yes yes yes Acknowledge Addenda I and 2, 6 Bulletin I yes yes yes yes Bid Bond Included yes yes yes yes Prevailing Wage yes yes yes yes Compliance wish Project Schedule yes yes yes Yes Listed Subcontractors yes - Yes yes Yes ALLOW ANCESIADJUSTMENTS IVermalicldon (bodges added m[he base l § 108,500.00 § 175,775.00 1 $ 43.207.00 1 325228.001 1 Post Bid Felt £ $ S $ Bulletin 1 5 £ S § $ $ S $ 1 ,: d!Ill �l III- {��_!I1 II��)- Iriit111114Jl,IRR it %�J, I; ,t„ -;:; 1 n.8r. ti7n.R. 11111' "! "d111111I Iof hl Fr +111 $IIBGOntr`z`civrGOrnrzcn.AlnouhBr illlFi .i lilllrv> -i ri,in.:'r,.y i.Ilri it :!Dili i.AIIO.NiildA�Idwiimf91ciudl4 la II'�Il�i O80t5a000 rlII I!11!dflt ?Ai!I!dfd!IIii3!I Bnnli l!ildltn,irt ti1lf�Nr�ijlt•.71.7:;i5 ce s, �Ilr 663,607Aa ll¢aio1101111'Iill dflli dhgFinmil�rai S y IvTq 0e6Aa +uiir.,l -bid IUrd a!i1103 r P., rorr S $ $ $ 8 $ 5 S $ § S $ 8 $ S �Ih�'5�161i11r- rn.l„i �rl`�!h T�i!TOfal Voluntary AlternateAmountljrj6l ,Iljr -:, t 5 ll�: ,.1 ,'I „ICI rS1L !.� I�I�Si'Ijin�ir }11.1 j', { r "11 i�.11.l�ll rl,.�t: lie hj,�,',l P., rorr Trade/Bid Package: FINISH CARPENTRY 13P 006.2 Prajecc Newport Beach Civic Ctr.rand Pals SUBCONTRACTOR COMPARISON SPREADSHEET Dace: 4 February MI I C VV Driver II IIILDG R4 til Y(: IL tU19 Subcontractor Name NO. DescriptionlScope of Work Pacific Architectural Millwork Montbleau & Associates S M I Millwork Seeley Brothers Northwestern Proposal - Per Plans and Specs 11966,912 1.163459 2,904y56 M. 8.905 71600,71. Bid as Opened 6 104400000 s 1.971.60000 $ 2.004955.0 s 2.151.161.00 s 2.505,715W Prequalified yo Y. yes yes yes CA License Curren[ yes Yes yes yes yes I .i Per Plans and Specs Yes ycs yes yes yes Acknowledge Addenda land 2, & Bulledn I yes yes Yes Yes yes Bid Bond Included Yes yes Yes yes yes Prevailing Wage Y. Yes Yes Yes yes Compliance with Project Schedule y.x yes yes Yes yes Listed Subconrsaaors y.6 Yes Yes Yes yes ALLOWANCESIAD)USTMENTS Normxliradon 3 137,300.00 $ 98,195.00 $ - 5 - $ - Pas. Bid FRis $ (14.39690) $ (6,228.00) $ $ eulletin 1 $ - 5 - - $ - S 27.754.00 $ - 1111 l +..n e�ulrL ,'n ail - -t.ni. BIlLn�lllli 11111111 i- .11alri' jl -ryli 111:'11 1111 }It� Sniicontracto CrontfderAallDant +,1.1 1 ..iii ! f u:— Il�',i ie u�ai u u . 1, .111 41- ;Ir+.t lAe lfll itl , illruiiil s 1 ki l;I;; 1196691109 +I$ j. i iruiL,I It liln iiiri 19di1i101101A9011 P ?�Oi090111 1 til1+1:11i�I1i1111311111i 111111 LI �15,11921,11"DI 151'_',.'}�i�111170, C56'ODI; D I. _I b.. 1 l .;in �li l d.�li .17 i 9:na +!!li�tnln ily li+'�IIIIIIIIIIIE `l "I i1,1211a pi;�'Ii1111. 4t ..11411111 Iillllyi- i,iriill 1511Lr11i68!'GI'i C. 7AOO�yII 17.1 1.1:,11111 l' 11!'1,18..1.91 VOLUNTARY ALTERNATES e uI.,I Is - 5 - $ - 5 - $ - $ $ $ $ $ 111 +i+j 11� -Total VoYunl9ryAitemate Amoun I E 111 �' r II ;;�I I ii �,j i I I .i e uI.,I TradeaM id Package: Project: Newport Beach Civic Career and Felt Date: 4 February 2011 BP 007.1 SUBCONTRACTOR COMPARISON SPREADSHEET Q.W. Driver uun -ueos slack: sow Subcontractor Name NO- Description /Scope of Work - Angelus Waterproofing D R I Commercial Mark Beamish Waterproofing Troyer Contracting Proposal - Per Plans and Specs 801,373 1,057,460 1,286,406 06,111 Bid as Opened s 895823.00 s I117.46DM 5 1346 A05.00 s 1.216477.00 Prequalified yes yes yes yes CA License Current yes yes yes yes S II Per Plans and Specs yes yes yes Yes Acknowledge Addenda land 2, & Bulletin I yes yes yes yes Bid Bond included Yes Yes yes yes Prevailing Wage yes yes yes yes Compliance with Project Schedule yes yes yes yes Listed Subcontractors yes yes yes yes ALLOWANCES /ADJUSTMENTS Normaiiratien s 45550.00 $ - $ - 5 - Fest Bid FRIs S - $ - $ - 5 - Bulletin I s - $ - $ - F - Underslabinsulation (VE) $ (M000.00) $ (60.W0.00) $ (60,000.00) 5 (6(hD0D-00) 11111: +Bill Ili n -f'+I ;li;,+ll i�II11.P', �1+5.t,t �11,1�,igl ij,�IJ ,,iA IIjIJ -B.i. i >LMf _I_I!6A,,IAh I!1171k. Qs111, f14 i. Ill id4k.nL,:10 S46mrQreQOr CanCYCt Ainhunt .. -:I ,, k I. :,p !. :ey as li.n 1„ JIL:; II IJ $ Itii, kiIlli eel 3)3 D 111111, 3.r. hl�l' +ISI I + i :�Ld 14ftBPAli 11 61. +Wit i it sl {IIASTi60gq0 .,nl lt�i0�li ill li�ltijkn+{il if-1:l II IR.L1I' +0:g1 IL'0 tllll iPillB �e 1 :Fll i; L]86�IOSiOC,k ��Iauh�l�l�4j+i� FII I:IILiGim rllll�{- UP;E 1111 ?I'll1'Im 01:'il p@II +o1V Ll 'k.+7 i,tI861r/]OD 41��1:7:�Ill a "I+�uk :. i( "I(Pi III181i1k lABII�IIRId616;i nl kj llV V. ,nj�i j =j 0;i 1�� " "I'jl�ll' �J?•I(01)�, .�;' VOLUNTARY ALTERNATES Po9e 10 t Under slab insulation taken -60000 $ $ $ S $ $ $ -- y ki ll ilk .17V I 1 {sY� of �Ifli,l:lliki -I'vi� I,,:1s ToLal Vdluntary Altern3te�Amcuntl !� 1] I ,'f 1 I,Irla lni,l ml $ 1 + €a s. �IIllll: I ? ,1 ¢ '1 _: €i i- S II Po9e 10 t Trinidad Padrage: ROOFING BP 007.2 Project: Newport Beach Civic Center and Park Date: 4 Fehruary 2011 C..I. Driver UU1,01in$ ti1NCl! 1919 Subcontractor Name NO. DestriptiontScope of Work Anning - Johnson Company Eberhard Roofing Letner Roofing Co. Troyer Contracting Company Proposal - Per Plans and Specs 11201,160 I.S77,7011 1,796,093 2,214,277 - BidasOpened s 1.813210.00 5 1.5/7.780.00 5 1796.693.00 S 2.214.277.00 PrequaGOed yes Y'A yes yes CA License Current yes yes yes yes S 1i 1: Per Plans and Specs Y. yes yes yes Acknowledge Addenda land 2, & Bulletin I yes yes yes yes Bid Bond Included yes yes yes yes Prevailing Wage yes yes yes yes Compliance wilt Project Schedule yes yes yes yes Listed Subcontractors yes yes yes yes ALLOWANCES /ADJUSTMENTS Normalization $ 756,000.00 $ 134.000.00 $ Post aid i $ - $ - $ $ Bulletin I in VE 18,810 S - $ - $ Accepted VE $ (53;050.00) S (756,00000) $ (134,000.00) TBD i� 1 I1 f�i I! 1�i1 'k:,li l' -Il, f� l�l you „1� �Li 11114�t1 I1f 8k1'I,h „J19 Li,.IrN l,fl161 "! h l ,l,y ,.�,.,LS f 1 f!li'}i Miil .III! 1113 if!'I�'�:�SUlleentl Ltter CentrattAln� b1 111.'15' oal t {J .., x'r. �' -11;, I=In .LG.LIL i'li l! 1 1lliif 11 I__I,I2HIi16tl ,li,lli,.,,,l Jh1'i'8111W'.i0k17 tltl !, In, lU 1.,.,u51)i: 1 f13117tib11 d,1111111d11 91J_,i 1 IU677y76tl pU� 41ud .1t1�. {'11 'I'IiP,!!t' I,iFli., 1. 1.f1 p,; $.:.1 Ii796�p9Stl0 _�I l: 17El8ILi 81Pp 1:! ` J 111 {ibll'8181r17i6t!d:N'r'. S 1_II''xgIq,2T/oo .L JIU! Iq IIJfwI,ilfl llrtl:Ill l- ,�,I�I��I!1, 11�J,I'�u ifii11,!! I >IP" 3 r ii, VOLUNTARY ALTERNATES Use P0lyiso ( one of the specified )n lieu of rigid board Accepted - 472050 $ - use anchors in list, ohdhesive Accepted -60000 S +i iI ilift �11i 17 IIni1 h�l�jli 1k1i i Tol� Voluntary Aiteinate'AMOhnt, 3 I I 1 ? ' 1 t i S 1i 1: Pape I&I Tredel0id Package: SHEET METAL Project: Newport Beach Civic Center and Paric Date IFebruary2011 BP 007.3 SUBCONTRACTOR COMPARISON SPREADSHEET C.W. Driver HUI1,0ERS SINCE 1919 Subcontractor Name NO. DescriptionlScope of Work American Sheet Metal C M F (Custom Metal Fabricators) Crowder Sheet Metal Products Weiss Sheet Metal Proposal - Per Plans and Specs 1,313,00a 1,173.627 3,161,129 1,104:003 Bid as Opened 5 1.313000.013 S 1.173.827.00 S 2.151.129.00 S 1.184.002,00 Pnequali0ed YES yes yes yes CA License Current - yes yes yes yes Per Plans and Specs yes yes Y. yes Acknowledge Addenda I and 2, & Bulletin I yes yes yes yes Bid Bond Included yes yes yes yes Prevailing Wage yes yes yes yes Compliance with Project Schedule yes yes yes yes Listed Subcontractors yes yes yes yes ALLOWANCESIADj USTMENTS Normalirarion 5 - $ - $ - Post Bid FRis $ - $ - Bulledn $ ,1111 I,i I -iil lh I;nl I i1j,11 III1 ii �I� {�7 li, { Y�, 11 I f111F11;'::1 1 .,.,I ,I ,t ,I II LI1 IL li3 (.'1111 i1 n81fle 1S IIli,71i SUbD4ti1]°d[tor COOtracGAmaelrtl 11 ill,l s - ,f.��51 1.. ci hI11i•:,111Bl.r is ll .; �l 71,11 I. 'i 1{71 tu1b.IX9lillir111 �1 '�n113000A0 atl hJI lSi li 1111,11a,I „a uh.ullr i,l di i.f IS. 011 'I 1]31'61]104[( II IL. 11 1.;11,Ie1,i�,1�,1Uli li} 11111li:Illhlll 1pil l6 ti h. JU.i;l i� -_I JII,- ";161'129.00 i�filllil�,4lUui,,:[irr ll ill l -. ,II 111Ti Ifl0111 Ll ild yXi {11.f:ul,lAiXli:I QllllF,:9:y1: -1 ph L'i�,L111 LII. „i {1111f1111{ 1, 4: orP!�iilel:i; {I VOLUNTARY ALTERNATE$ P., I of, $ $ $ $ $ $ $ $ Total_ Voluria ryUd 1 1, -' P., I of, TradelB!d Package: BUILDING INSULATION Project Newport Beach Civic Center and Parka Date: 4 Febluvy 2011 BP 007.4 SUBCONTRACTOR COMPARISON SPREADSHEET C.W. Driver IIL'ILDLU1 SIN:e Irvin Subcontractor Name NO. DescriptionlScope ofWoric Altai Arcade Contracting dba Alert Insulation Company F Rodgers Corporation K H S & S Viking Insulation Proposal - Per Plans and Specs S 260,900 160.370 262.212 Bid as Opened 5 161.1m M 5 139875.00 247.500 242870 262212 Prequaliled NIA NIA NIA NIA WA CA License Current yes Yes yes yes Yes Li. I Per Plans and Specs E clusions Exclusions yes Yes Yes Acknowledge Addenda land 2, & Bulletin I yes Yes yes M yrs Bid Bond Included yes Yes yes Y. Yes Prevailing Wage Y. Y. Yes Yes Y. Compliance with Project Schedule Yes Yes Yes Yes Yes Lisced Subcontractors yes yes Yes Y. yes ALLOWANCESIA13JUSTMENTS - Normalicadon $ - $ - $ 12500.00 $ 17. 500.00 S - Pon Bid Fills 6 - $ - $ - $ - $ - Buikcin 1 $ - $ - $ 1 y -j 4i ,t ly 'l yl I,f� 11 i1�\i���'I!�SdbcantactahCOnt2ci j'I' 1111.,1 .f.Yr 1 -. ; -al 116:i:..1471 i. II!Ilt 11 h't!III IPII ,14d.Y 4tllrl di}IlfilialGll*!1!11.!11. Al'noLt :, I.� IaiI 1111!!'1114.P.IalPf $ II Ii6�µ' -�i Al� 1. !:vll.]1l10t 1191 i81ai!f'li i5 ijl !IS9 a�Sa�;�1 Ulifl .I III- ,P§hyll_ {I I!�11364000,0U� Il +i;f9111}IILI �flu411n: Ill llul]611]]aaa :I d:L! -i. Bin $II 1961x111 a0i 11i.li JIJI ,1, .' J'!ILI!1! IIIIIIYh'I. „IIIj�(i'1�: N %.::IVi31 VOLUNTARY ALTERNATES P... 1.11 - S - $ $ S -Ir lil 1 1 1.111 Ill TaLTI VOIti Alternate Aniovne' otary ,I:� $ $ %1 -. :!!$H jllni:' -. bit Li. I .l P... 1.11 TraddBid Package: DOORS. FRAMES & HARDWARE Project: Newport B each Civic Center and Park Date: 4 February 2011 BP 008.1 SUBCONTRACTOR COMPARISON SPREADSHEET C.W. Driver n1:ILn21ts SINCE In19 Subcontractor Name NO, Descriptioot5cope of Work Construction Hardware Co. R P G Enterprises Roy E. Whitehead Seeley Brothers Proposal - Per Plans and Specs 604.700 660,000 632,760 607,170 Bid es Opened 5 664.700.00 5 6,I8 000.00 5 682,760.00 5 5]1.1] .00 Prequalified yes yes yes yes CA License Current yes yes yes yes ' sl ltli711 {, 1 Per Plans and Spec yes yes yes yes Acknowledge Addenda land 2, & Bulletin I yes Yes yes Yes Bid Bond Included yes Yes yea yes Prevailing Wage yes yes - Y. yes Compliance with Project Schedule yes yes yes yes Listed Subcontractors yes yes yes yes I ALLO WANCESIADJUSTMENTS Normalization $ - $ 20:000.00 $ - $ 36.000.00 Post Bid FRIs $ . $ - $ - $ - Bulletin 1 $ . $ - $ - $ - $ - $ $ $ :... I;y,ilpp �llj(1 1.. i t I 1 IJ �:�.11 lihilmil' {,1 .,....:.I ... . {. II .: .. ,., i l it LL n:.4 11 if 111 71LI111 I 1191n.k n II 1 1 I ,.,. ,II SUbton[Cdekar Conera$IAinaunt I i;i l { I''j ' t , 14j1 , ! 11 II t y{ Y I. u � n:. .. !11 tl I 1 .i.i III 1 1111 5 I1 6,,,fa4)700001 1 1 faitlFr l ! 11.1 C. I 1 1 I.II Irla�:,:6n. Po 0001111 III 11 - .... ,111E Ill Ii1 .Al j -II�ya '11t 11 II{ 568,090001 Ii1.ltyilYlx 111 1; > � a!Ih'nlrl 11, 1, i' u1. .1 unl,: l..Inla; II„ .,10111. 11.1u 1.1411 $'. I��- i`E !1 ., t�16d ;760.06 II I -11171�'11,;�u.I1111i I.., i it ` LUl ala;l ..n, �l.n,la ma:nn:. y i .,1 LIni , 5 �141111'I IP{ !607A7d eG A- 11:11 =4u1�� l!i ll!I i, ^'='0mt >:.:1n a11:1.in:a.n.u.l IL:,,, i j ; i 111 1.1�!II�II� ldsrr ��f�lll` VOLUNTARY ALTERNATES P.O, 1.11 ia..Fjli!1}���dlili �l- �1'N111.ITe[al {iia,hl�.l ! .LLLIIIiu, YO�unta�y Alternate`�tmotfnej '..- . 1:.,.11 5ii I�I�..IL, ill s {�I t11 111 Y�1 :f({ I� f: �`b1 .Ill ' sl ltli711 {, 1 1 {IIJ ,jl1` P.O, 1.11 Trad➢lBid Pad.,itc EXTERIOR CURTAINWALL AND GLASS BP 000.3 & GLAZING Projam Newporticadi CiOc Centerrand Park SUBCONTRACTOR COMPARISON SPREADSHEET Date: 4 Fabmar, 201 1 C,W Driver ➢IIILOF.119 .v'I SCIi !Vlu Subcontractor Name NO. DescriptloniScope of Work Architectural Glass & Aluminum Heinaman Contract Glazing Tower Glass Walters Be Wolf Woodbridge Glass 8 - Proposal - Per Plans and Specs 7,335,200 7,936,740 6,839,000 8,849,203 7,777,000 3 S - Bid as Opened 7335. o➢O0 7.805.74400 6839,00M e,aaQ MM) ]]]].00100 3 - 6 - Prequalif!ed yes yes yes yes yes CA License Current yes yes yes yes yes IS 1. 1$I L i. i�lj jI. Per Plans and Specs yes yes yes yes yes Acknowledge Addenda land 2, & Bulletin I yea yes yes yes yes Bid Bond Included yes yes yes yes yes Prevailing Wage ycs ycs ycs yes yes Compliance with Project Schedule yes yes Y. Y. yes Listed Subcomraemrs ycs yes yes yes yes ALLOWANCESIADIUSTMENTS Normatuauon 5 - 5 - $ - S Past &d FNs 3 - 3 - $ - S - S - oohed. 1 S S - s - 5 - 3 - $ - s - ! Iwnew ..,..I, I1 i!. fl f 111 !.1:8(.0!!.1 i .N ..tl!.I QYifi It ' III Ill�ir lV SeBCOntractaf2'[l trdctAmount P �9 - : il. �I 111. !!I.:JII !t f41111i "II III IIY 3 ii 1]RSa00.W1 II1111,1, 1 n II'If!tl llllllfi111. 9difll!! e,iil'NIQiIl i$ ]0E']A ➢00 ry ,It F1j 111 II!Illil li'I, III y_ 11111..1. 01 SI IIIn1� 16,5J9000 UQ,y .II ih,,iiVill -1N il!'!:.In!1N ffi 1111!!1 111111I!i. I� 1(sa"529300 ,f l,llaktl 1-1 y, -I 1 11111!1! Ifi!FI`.Ilhli lN!!IIIVIfV111I1i111111a I I lq'1y9,0 00: jCi i�'17fill; 11,11 . -, f11dV III jBd nulwaill)II@i! Itl' !i111111�1uI VOLUNTARY ALTERNATES 3 - $ - S - 3 - 8 - $ - 1, - S - 3 S - 3 - 5 - S - 3 - 6 - 5 Total:YalunwrYAlternareAmaun[ !{ s .11...111 eil I% t i f - IS 1. 1$I L i. i�lj jI. ii III �!Iil I�i��f� Pavel ett DRYWALL. FRAMING - LATH & PLASTER TmdPiBid Palmgm BP 009.1 AND FIREPROOFING Proleec Newport DOaMCivit Certd,9ed Park SUBCONTRACTOR COMPARISON SPREADSHEET Dad.: 9 F,ld a,2011 Q.W. Driver MI'LDH.S SISCH rn Subcontractor Name NO- DescriptionlScope of'Worl< Arming- Johnsen Brady Company ICHS &S Martin Brothers Martin Corp Performance Contracting Superior Wall Systoms Proposal - Per Plans and Specs 3,717,070 3,440$70 32059,699 2,710,5 -02 3,646,470 2,636,967 2,627.000 Bid .Opened S 3.599.50.00 5 B Mean.. S 3EaDAM oe s 2565 wzm s s62590. s 7,1109700 S 2.725B05.00 Prequa flied yes es yos yes re yes yez CA Liteese Curren[ ym yoz ycz yes yes ycs ycs ;f.lf a Il Per Plans and Specs ycz ym ycs yes yes Ye- yez Acknowledge Addenda land 2, S, B.11.1nl Yo' yos ye ms Yes yos Yu Bid Bond Included Yes ym yos ycs ycz Y. yes P.111ng Wage yos ym Yes ycs ycs ym yes Compliance with Project Schedule yes yes ycs yos ycs Ye yos Wiled SubconRactoss Y. yes yos ym to ycs yes ALLOW ANOESIAD)USTMENTS $ - S (110.905.00) P.. Bid FR4 5 20,570.00 S 70370.00 5 20.570.00 5 147090 S 20.570.0 5 20570.00 5 12,01 Bullerin I 5 5 5 - 5 - $ - 5 - ; - �I!F F II t 1 inl In ^, :n :9l9 - -'. 411n bu IeA '... {. .n v i,q r.9 -' •, 1.9r i fi Pen[ ;.: r SPemnernctpr,<PPUa¢A s r I'iru 11 ,- - ,• l9r r I•Aip IIOb.al1 ^l IOYA'tl S .ir )371T0} :.3 ..r V. e iniNr u64r II0:I P+:d i j13910570 V0. ,, ild r Ibf ".B},1: -.I:. l rl n.. p ; ']6990900 -Y9i v u l ld:r.dll iu bel.IGr't l r l yN 12P6 y.. >ti ,. l e. Uil ( l rl....nl an l L'. Viiing u99 Il 1L'!,Ar.R0l f 2616 yOAn (:. I` la l.,: Iti /.n 111 wild lltil l .i19npI1I9719Mr i I7s] 96TA0! S, a9Ftid i l.lf Rqu idl l9 ! 4i- .1.91i. l......il lii II i 6n W0Ap i t. v1, i Lli: IIf9e,Rl!rdU{ VOLUNTARYALTERNATIRS 1,' 11 5 - 5 S - 5 - 5 - 5 - 5 5 - S - 5 - 5 - S - 5 - 5 - 5 - ! - �1in�r �1j�,>;I)i 1i �11i11r TOGl Volvnsnry Almrnam Amount ` it i e,rLal li +91.1 5(., ..r� .,i L ',. 'I, ... .... S ,r 1•I e) i n `1 i11 ��il 1, ,7, .iPi1L Ila,,hi rl r i'��i I j, l -luili �9 [uilli it ��;Id 11411, .iI1l lyfl -1 II f �illl �tlrrli.l ���: ��fjt'Irii ifd ii A ;f.lf a Il 1,' 11 Trade/Did Pac!iage: CERAMIC TILE BP 009.2 Q.W. Driver nun. nuns SiNcr. 19ns Project: Navperc Beach Civic Center and Par, SUBCONTRACTOR COMPARISON SPREADSHEET Date: 4 February 2011 Subcontractor Marne MO. DescripticnlScope of Work Charles McCandless Tile Inland Pacific Tile Italian Marble & Tile Premier Tile & Marble Proposal - Per Plans and Specs 194,695 269,290 282,500 181,635 Bid as Opened s 18100000 <_ 279000M s 300.000.00 S 174446.00 9 . Prequalifed ns yes yes yes CA License Current ycs M yes yes Per Plans and Specs yes yes yes yes Acknowledge Addenda land 2, & Bulletin I yes yes yes yes Bid Band Included yes yes yes yes Prevailing Wage yes yes Y. yes Compliance with Project Schedule yes yes yes yes Lined Subcantmcmrs yes yes yes yes ALLOWANCES /ADJUSTMENTS Ncimelbation $ 26,195.00 $ 2,790.00 $ (5,000.00) $ 19.689,00 Post Bid FRis S (12,500.00) $ (12,50000) $ (12,500.00) $ (8500.00) Bulletin 1 - $ S S $ ij ���1�11'Ii1111�{n 11 ilfl, j 11' !Il i.',,, uat: �'�1 .t' L„t�l'+111'Ilflii -.1 „411 i1P Ilaii,J t; '- 4i:. 5ubtamreeear CanMapt Amount e ' I -,,! I Iii t lupil, LdI11H IpII S 1 it94,696.00' y�iltiLAi :..Li, IiIJl�f ul la, -, „ -4 .ul, 14111f1111J 5 1,1269,�q000 111tIX1;J, t1, i�jtlut 1110111d!IiPI INnIyi 1'ai i'hL� ;1t 170117 S 2iIT,690.901 =,!.It 1111 -I i1b11{f11Wi,IlU ill l6il ¢yl 1 1 1 f'; 1i 1!011635.00 iul'4nhithi)r {!11{,1171.. 111 .i�l IL t :�. d,!-15q . 0. 1x r Iljlll'1�1iv1; VOLUNTARY ALTERNATES P., I F I $ 5 $ $ 0 - ') f j RI ,1 Totaf V91unt0 Alternate Amnunt :! S J i ;1” S i ; ill. t 9 . P., I F I Tradeleld Package: ACOUSTICAL & WOOD CEILINGS Proloctt Newport Beach Civic Censer and Park Date; 4 February 2011 SP 009.3 SUBCONTRACTOR COMPARISON SPREADSHEET C.V. Driver Iq:11.IJF.Qs SINCP. 1919 Subcontractor Name NO. DescriptionlScope of Work Elijay Acoustics Hutchison Corporation K H S & S Preferred Ceilings Proposal- Per Plans and Specs 2,195,470 2,372,092 3,042,211 2,180,000 Bid as Opened s 2.195470.00 5 12092.011 s Z.0,12211.00 s 2,180,00aso Prequalified yes Yes Y. Y. CA License Current yes Yes yes _ yes I 5 - {lui -I Per Plans and Specs yes Yes yes Yes Acknowledge Addenda land 2, & Bulletin I Yes yes yes yes Bid Bond Included yes Yes yes yes Prevailing Wage yes yes yes yes Compliance with Project Schedule yes yes yes yes Listed Subcontractors Yes yes yes yes ALLOWANCESIADJUSTMENTS Normali..r $ - $ - $ - $ - Post Bid FRIs $ - $ - $ - $ . Bulletin I $ - $ - S - $ - !!I. �; 111111 1111' :1;111'IP1 1l 1111 "'11i!�i:iil5ubcontiACior -� 1 I• 1tpp I� 11�1�({ �� .1171.11,11 III,,,,,: la :.Il {tillflt ll?!il l0lli nulfl4 ,,: COntsactlAtnauntl l" 1 ;, 1:•'i; , 1i Ru JI 11 {':,! df IIIII91ii111111111i 1:1 In4 tSi 1I111I1.f;f,,95910 QQI iJi 111:IiIF Ird 1 ..nd,�idll S. del. lilt li dl lP„'81111111117 -1j� I�p3.]71,04bOQ$ �I I!I,IJII011i 1111 i�1'lll'l l6ul ?i1111,;,d,l!it •:';11]UII.21 ,001�5!41t11.•..I•IT,lB0A8Q , ip i, ?1, I�'p!en IAI lil9f IIII7111!,' iilll II!��IOIp1,�l,a ii!ilh,ilJi Q0 IPA V, aii 19!.P"I'll,111;1i6, I,,i!• -;jlN. Ui1 { ?1j -410 71ir.1�1,u1i VOLUNTARY ALTERNATES Pnev 1 01 I $ $ $ s $ s $ $ jl�(i�ti�l {�11 i11111!j!1r.��IT�TOtal Volugbry.Alteinata Ameunt_ 1;1 s uil �i 1j'I� 5 .I I 5 - {lui -I s ry; Pnev 1 01 I Tradelaid Package: FABRIC WALL & CEILING PANELS BP 009.4 Pending Clarifications Project: Newport Beach Civic Center and Park Date: 4 February 2011 SUBCONTRACTOR COMPARISON SPREADSHEET Q.W. Driver BUILDERS SINCE 11.11, Subcontractor Name NO. DescriptkonlScope, of Work Elljay Acoustics Fabric Wallc Lift Modem Interiors Preferred Ceilings Proposal - Per Plans and Specs 455,947 402,662 306,060 305,000 Bid as Opened 402.662.010 S ?513.6610 00 $ 385000.00 Prequalified yes yes yes CA License Current yes yes yrs Per Plans and Specs nywl ye. yes yes Acknowledge Addenda Iand 2, & Bulletin I yes yes yes Bid Bond Included yes yes yes Prevailing Wage yea yes yes Compliance with Projea Schedule yes yes Y. yes Listed Subcontractors yes yes yes yes ALLOW ANCESIADJUSTMENTS Normalization $ - $ - $ 130.000.00 $ - Post Bid FRI, $ - $ - $ - $ - Bulledn 1 $ - S - $ - S ii i - 111 Iii, VIII nQl. 61 ., ....E, 1 7111 IIIII I: 1 f 1 iIIlU1 I I„IA Ii :N:i 11 I171'u-, _ el lf�.I�i 71111 .1 411j {:i, 5'- —iiii ° wCdnta"ac AAmount' ' ! II 1 IW {� 1111 1 jJihj�l la illl db MreGO :.,.:1 ,i Itt j 1, ltf'fa ,r :. :, ...,1,,l 11tl IIII li5.6y1 11 A11 IIn.1.11.n, S !Ilmy '455,9h 00'. jil Mill ll9l t -I IOLtp:iillh - -w, +. illllillll1lD IIhN Il.,w:,l u,ialp0l.I S 1 -'I: 4U 613200 l�,ill' i, r t.1i,111'llt ., ,I a, ..,... 1,..,.......1•.:,1: dllllli d.hI1.ILII„r: k,IPoiGI', IIII 15 "'IIII'i. '., 1 nab eda4bi 1.11':1tI11iE'.i Ilf 1.'.S'itllthltdlddl OA,i.L,., tdl St P ;�IRls�ll�l „�;,, 1.11 i5,1ih4,ihC,.4e1111.A7.LIhI1., B,I '108S,00dA0. ii Lf ,7..11{n1.1111111.11111111i -i: i, f, ,.....,1.. VOLUNTARY ALTERNATES $ $ $ $ $ § $ $ $ $ $ $ TOtal Yalunbry Alternatx Amount 'I pl I� II § .31rii�i S I:` :I lr':I 5 I h I:'yi $ „i7!f1. - k':i I`i I��l i Page loll TradeMid Peril FLOOR COVERINGS BP 009.5 Projece Newport Beach Civic Cenrerand Parl, SUBCOI Date: 4 February 2011 QW.. Driver BUILDERS SINCE 1-111t Subcontractor Name NO. DescriptionJScope of Worit Continental Flooring Lawrence W. Rosine Co. The M.S. Rouse Company Tangram Fabricators Proposal - Per Plans and Specs 381,126 388,500 1 312,000 326,425 Bid as Opened S 381,126.00 s MUM 00 s 312 0)0.00 S 309.430.00 Prequalified NIA NIA NIA N/A CA License Current Yes Yes Yes Yes . 1. Per Plans and Specs yes yes yes yes Acknowledge Addenda land 2, & Bulledn I yes yes yes yes Bid Bond Included Yes yes Yes yes Prevailing Wage Yes yes yes yes Compliance with Project Schedule yes yes yes yes Listed Subtnncractars Yes yes yes yes ALLOWAN CESIADJUSTMENTS Normalization $ - 5 - F - b 16,995.00 Pos9 Bid FRIs $ - 4l - 5 - S - Bulletin 1 $ - b - 5 - 8 - $ $ $ . $ �f �IIi11� lit 11, l,i� lhilp{i 1 11111 Y I11� lfr II, sl i ' III ,I;ItLi0,411 ,t 1 i a, s;. !1 I' Ihi {I 71 "IL il,ill61 11 ,I h. 1 Sabenntlatter COntraCt AleODnC 1,l yl �:j fl f Ill flg'I IIlll u,l, ;l! ;1� 3 1 Ilil I I, I]eI IZ600 II, II le.�l 11 d. 411IiJ Ilf L IIL,IU J`, UI'I .� ,i l llll I�[ 36850000 , :y,[�'! ,,, �I �. ! ; till ili "1i,f1 S,81111t i1! I. rl,itl llllilliY {Ii j j II[ifal 666.60, „1�lij {13jj, �l �! I� l I!0! iF IIIJ6r„ 1111A„b" S !i 3$61C]$60, ', �j 1, IVI! i111�0 ,i1 t iIiN el 4111l "f116,!,,, , 1111 Ii. 17,4!<551 VOLUNTARY ALTERNATES Page I e11 $ $ $ $ - 5 $ 5 $ y g $ 5 jI1 {ylll, illllgllf __Ij �rf, jl ld u6�I1!,jtI �U ;� Total Vofunt Afte'rnate-Ammvt uI $ ifbi'p r hl:j i�, S„ , i , 1. Jilt, S '6 ,1 y „j 111, ki t, llir•I . 1. jll Page I e11 Trade/Bid Package: ACCESS FLOORING BP 009.6 C. yy, g}'riyer 1111; Project: Newport Beach Civic Center and Parlk SUBCONTRACTOR COMPARISON SPREADSHEET nU1LDERS SINCE. Date: 4 February 201 I Subcontractor Name NO. Description /Scope of Work Bayside Interiors PSI Partiton Specialties Pugliese Interior Systems Proposal - Per Plans and Specs 949,800 11012,118 1,081,838 Bid as Opened s 1.13E.800.00 S 1.213.000.00 5 1.110.838.00 TotahYoluntary Alternate Amount4 - + ! P I l i$ l[ PrequaliFied yes yes yes u�is �liliul „a 113 ua lu AR CA License Current yes yes yes it .i..'H Per Plans and Specs Cant knn(irm one of the tests yes yes Acknowledge Addenda land 2. & Bulletin I yes yes yes Bid Bond Included yes yes yes Prevailing Wage yes yes yes Compliance with Project Schedule yes yes yes Listed Subcontractors yes yes yes - ALLOWANCESIADJUSTMENTS Normalization $ (187.000.00) $ (200,02.011) $ (29,000.00) Port Bid FRb $ - $ - $ - Bulletin 1 $ $ - $ - I" ol i II r, itluk Ji l,l l: ,aru;ri _I1 Ur. pu�?v ,lllwJiltrllU,I17:'IiFJI "idli ;i� �� �hl G11bli �L 506Wht �actUr'ContracklAmount li.l�..l 3 i�l I011I;i .I iii 414 ,.I ,� lJ: nnl'i1i01111V1111 $ ,III 17 t9498C01gDI =illhl'intlCii .II. II.II, nfu:F „rh ISI I�II�,III Bft'!: uJiil A;111161!!111 7 11 0 11111 1 ii dl li rii1S 1'll I�IIi, ,.!I IOBI B300q_ 11 n�1:�1 9, 4r �h.i Iill!Nl yllphllh ��i���i��u JI l�lµ III 9i'1,t,;i1'J list _jl VOLUNTARY ALTERNATES P., 1.11 $ $ $ 1 ail {k�� �i -i j I TotahYoluntary Alternate Amount4 - + ! P I l i$ l[ $ i - u�is �liliul „a 113 ua lu AR �I li - sl � 1 it .i..'H P., 1.11 TradelRid Package: PAINTING Project: Newport Beach Civic Center and Park Date: 4 February 201 I BP 009.7 SUBCONTRACTOR COMPARISON S RE DS C.W. Driver u VILDERS."NCH Ivrn Subcontractor Name NO. DescriptionJScope of Work Borbon C T Georgiou Painting Western Painting And Wallcover Wilson & Hampton Painting Contractors Proposal - Per Plans and Specs 660,400 634,000 630,894 965,220 Bid as Opened 5 589.480.00 $ 634.000.00 s 605.894.00 S 9552ED00 Prequalifed yes yes yes yes CA License Current yes yes yes yes Per Plans and Specs yes yes yes yes Acknowledge Addenda land 2, & Bulletin I Y. yes yes yes' Bid Bond Included yes yes yes yes Prevailing Wage Yes Y"3' yet yes Compliance with Project Schedule yea yes yet yes Listed Subcontractors yes yes yes yes ALLOWANCES /ADJUSTMENTS Normalization $ 71,000.00 $ - S 25.000.00 $ - Post Bid FRIs $ - $ - $ - $ - Bulletin 1 $ - $ - $ - $ - g $ $ g '- II „ ,SILt,�r_ d+:1 :I1 -ti rftll "arr.1C111Irt pil, p yl qi �i!i)� -� IP 11..,1 ,. rtt k.. t fu, ../1 Ituil -6.k4 Subcddf'ractor Cantrd�tAmountl • I, :. r +. '.I ➢i'I : r1 ,.:! r I:I:; t' Olt tt i, ill YI1111, S .,.r „ff! 660,N8tl 06 t.:1 t tJ!!f of 3`'' = '63b,Otlall, jS 1� �1' n❑ r Ur l:� {I i. 4. 8 i..r fLLil:a iulOi ti30,894Atl r�,l.lsd!E�I iO t�J lnmua fl ! r. 3 I,u I::I! i1983,i3b iS'I IrMF1- ��fl - rL htl•I` qu!16 ! i!Lp.ill!ll!I +I�I loll !iRNA..LIJI 'I• +!II !� f Ili,•: Il ril!' - ll:r. f,;: t1.8- ;!9NILtN 1'N . VOLUNTARY ALTERNATES rneo t ou $ $ $ b $ 5 b S S b $ $ �141;VI I(! W1tik. rlti�!! �ifll1rfi41 !TaaiYulentayyA3[mnteAmounb >. 3 a rneo t ou TradelBid Package: FOOD SERVICE EO W PMENT Project: Newport Beach Civic Center and Park Date: 4 Febttlary 281 I BP 01 I.1 SUBCONTRACTOR COMPARISON SPREADSHEET C W Driver nun.pr ns SINGE 1"t0 Subcontractor Name NO. - Description /Scope of Work Kamran & Co., Inc. Booker Contract & Design of CA J P Duncan Industries Proposal - Per Plans and Specs 125,850 121,470 135,584 Bid as Opened 5 125,860,0 186,211 135.584 $ f �ljf `�.� $ 1 !i Ij 11 LI Prequalified NIA N/A NIA i,Ill 1 Li CA License Current yes yes yes Per Plans and Specs yes yes yes Acknowledge Addenda Iand 2, & Bulletin I yes yes yes Bid Bond Included yes yes yes Prevailing Wage yes yes yes Compliance with Project Schedule yes yes yes Listed Subcontractors yes yes yes ALLO WANCESIADJ USTMENTS Norinalicnion $ - $ 15,759.80 $ Pon Bid Fills $ - $ - $ - Bulletin I $ - $ - $ - $ $ $ '.ilili !� ily..l4il f 1'illul.l 11 1i hill ll ll ..,.:it, 11k11 it mil;gl.¢I1:111 I!I 11111_, Ili, 11 ,,ry11:i.11,i11111{t Q11111!11IIII 1�� Li 11 i nil SubconfVacton Conk ct Amount { S i l 1 i" I1, ! 1 z. i,1 � 1.p.'..i•. .I ul - ,..! ( tv.i -i _il I,fi1111 fI I1l I1Vr 1 Nlll_JIlii.11illitin, R ' 135 60: l I' >,l L.$� 11111V1i 111 II it4..l.f,i $ t f21 4 e-rr,pp 3 i II h�1 !s. -?il __ klrvl iL! " ", A1k,1118kN A10A 15- I114,lQ $ _i 1355 4A0 .1 11 � 1i1111f1...il i.l{Ifl to ! �I ly.11�l�� F,�I l{k1f,11121ai III 11 ljt ,�, 1. 1'11.. �i�!!Il ill.jl!i - u VOLUNTARY ALTERNATES Pagv t ell $ $ $ $ - $ $ _N 1 1i 1 j Ili h it n1 N 11 Total Voluntary Alternate Amount l s i� - - $ f �ljf `�.� $ 1 !i Ij 11 LI `l', Mrt!;; i,Ill 1 Li 1 Pagv t ell TraddOid Package: ROLLER SHADES BP 012.1 Q W Driver Proleee: Newport0ench CMI:Centerard Park SUBCONTRACTOR COMPARISON SPREADSHEET _ ew LO!ws clae8191" Date 4Febroi, 2011 Subcontractor Name NO. DesciimimsScope of Work Candlelight Systems Contract Decar Diversified Windows Fabric Wallerieft Interior Services Pacific Shading Shawazd &San & Sons $ - Proposal - Per Plans and Specs 24I,BgII 167,800 255,910 3011640 249,767 721,994 169,686 Bid az Opened 5 390.om b8 5 14 nom 5 255910 11e s ]os 4o.ao s 240,7070 0 5 M'99100 0 IS U9600100 Prsgealieed NIA NIA NIA NIA NYA NIA WA L;; CA Utense Current yci yea yes yea yes Yes ns C�, Per Plans and Specs yes yes yar yes yea yaa yc Acknowledge Addenda land 2• &6nifeinI yes Y. yez yea yes yci yes Bid Bond Included yes yez Y. m yes y9a ym Prevailing Wage yes yes Yv, ycs yea yas yes Compliance with Project Schedule yas yc yes Yes ycs yes ycs Lined Subcontraerom yes ycs ycs Yes yea Yes ycs ALLO WANCESIADJUSIMENTS Nori,.WSio 5 (50,9]500) 5 29,310.00 S - S N,, Bid Fllls S - S - s - s - S - 5 - 5 - Bullevin I 5 5 - 5 $ - 5 - s - S - 5 5 S - S - 5 - '!!j t.i_ 1 .< ., t 1'SUb[eno-iator Contract Aisiebpt II ai: 1. i S I' IYIl00BM11 1 d ^IUi 9..1 f 1111.11. 1151W ..id l!. fll till ff! 11, iIW.aQa ad f. - -II. I!ii! .1 - ; f 85.910.0 f 9 9i _y iv111411111PIIOIOi1!IN "i!I, '.100Qd49A0 II! 111`11 I ! 11 i lB v.M(vSII dll 'Ifi j li tlR0 001 ;lA�ino 1 llli0!piil 1111 III II , 1,!, 1,111 II: I ,A!!If!I, )]hq9 {.Ue I, . Ov 111191:. fhl .il 1!1',.11 Iii l'l i II I!II!hI n ' ^11.91i!u1' +6p, 1 1111hI! VOLUNTARTALTERNATES S - 5 - $ $ - 5 - $ - $ - s - s - s - s - s - s 5 - 5 - 5 - $ - s - 5 $ 5 - s - $ - s - $ - L;; flA O ,aenta�yAlt6mate Amount t �.Il.l t.uil utl $ 1. II {�II 1111 Nl! -{ t { I.I {'..r s - _ {' III II' 1 l {!{ {111 5i s '� C�, PAeI e1, Trade /Bid Package: ELEVATORS Project: Newport Beach Civic Cancer and Park Date: 4 February 2011 BP 014.1 SUBCONTRACTOR COMPARISON SPREADSHEET C.W. Qfiver DUn.DCUS SINCE 1911) Subcontractor Name NO. DescriptioniScope of Work Kone Elevator Otis Elevator Co. Proposal - Per Plans and Specs - 185,223 240,000 Bid as Opened 3 175.128.00 S 350.D00.00 Prequaliiied N/A NIA CA License Current yes yes Per Plans and Specs yes yes Acknowledge Addenda I and 2, & Bulletin I yes yes Bid Bond Included - yes yes Prevailing Wage yes yes Compliance with Project Schedule yes yes Listed Subcontractors yes yes i —, —+— ALLOWANCES /ADJUSTMENTS N.,rndsatien $ 10,045.00 $ (110,000.00) Post Bid FRIs $ - $ - Bulletin 1 $ ii11:,['ll>tl1��111,IrG li Jl..v�l1 +�it!'a� Nil 1, 1 -. �(1( -1117 1111111 II17N IIlI11'llllllhl11111:i9i lrll #Il tl lloP'i 111JINIIti tl4111111 I1:r I' 1f. SUbmntrpctorlCont)-dct ArnoUaE �irr nirlE _ %lai, 11141' ji'a 11�;ly r,u - '..,i. r :!; .I i.,, v'II ili .r I1 - ,u�!1 -!I 111191 1 itl91'•!'ni11lI 1105223a0U1$r 1F.UI 1, I: .11 �l !'ti h! ?e11,i'k "i.l'lIC!'Ifl`.N`( 1117,- 2ao 000.0011 1 11 �,GI 11 r I9, G ill "'.It. CEi,q,ulf:.?i.14A4,[, 11. ,6,11;11 x-11, •. 1.61 „I I,J:�r51! VOLUNTARY ALTERNATES Page 1 of 1 $ $ 111 . . a .F.�L:'I it 1tl rt1111,. �� , Total Vu140602A b' ernate mou ul Page 1 of 1 Trade /Bid Package: Project: Newport Beach Civic Center and Park Date: 4 February 201 I BP 015.1 SUBCONTRACTOR COMPARISON SPREADSHEET Q.W. Driver BUILDens ss!vice tnw Subcontractor Name NO. DescriptionlScope.of Worlc Cosco Fire Tsansbay Fire Underwriters Proposal - Per Plans and Specs 2,200,000 863,000 1 667,155 Bid as Opened 5 2,200.000.00 s 863 000.00 s 543200. $ Prequalified yes yes yes i!'f 11.f' i b1111 CA License Current yes yes - yes Per Plans and Specs yes yes yes Adwowledge Addenda land 2, & Bulletin I yes yes yes Bid Bond Included yes yes yes Prevailing Wage yes yes yes Compliance with Project Schedule yes yes yes listed Subcontractors yes yes - yes ALLOWANCESIADJUSTMENTS Normalization $ - $ - $ 123,955.00 Post Bid M. $ - $ - $ Bulletin 1 - $ - $ $ - ',i III ��i�'Il�i'�i!i;l��ihll�1i .IIUJ!�iH��l: rl�� ill %Oiilili ;'1j';!1`iL i11j15ub5ositiartor I':11ILLf! „il lildtLlf01 0111 ILI „I� 101 .!hR 1, ifl _., t1i,111111- tt PII`,',In'!IIi I Co`dtrdit Amount) !,;,_y,,, I='ll .: H! ! , ai t. !: ! 14sT1! 1 ndn 1, �I �V 111.It111Itl111i ! - 111 ;'ini i' ilpllll 151 1 I:` s,2oaA0aa6 1171 II'I v�, 'n111,UIS llUNl11'ILNiI f :i. 11111eIi1111 'ii '' E63 oo0:ao!I ,�I I�I�Ii lui li�� 1 II :il,.. -Ili 011!11!117 1 liu6i t9111t11A1N01i §II I!lEb]k ;51bo h$ll�nll131 =I 111.1.6 h,j =11'4111 1171111 i41 'k {E 1.1 15'1!' 111 �Iilitl0lailfll.Ji1N' I' 1111 'll������llii��1� if! I',Jpl'IPi I�I�, lt'llii i1, VOLUNTARY ALTERNATES P.,1oft $ $ $ II,. INSI(1�111- �,4t:II�I��1'�il�ttr{ji q 1 y' Tdial Volunia�L. �. ,i �l L-k dsl - $ I1 iit. `1111:; $ .' lu:i ilternateArtl9'unf - 'I.IIN I a i!'f 11.f' i b1111 �I 111 I P.,1oft T- deABldleacMNge: PLUMBING Pralem NawpertOcacM1 Civic Cenar and Pods Data: 4 February 2011 BP 015.2 SUBCONTRACTOR COMPARISON SPREADSHEET C.W. Driver III:I LI]IfNA i1N4L I�IIn Subconvactar Name NO. DesmiptionlSmp.Of Werh A O Reed & Co. D K Mechanical Dan Brandei Plumbing H P S Mechanical Alpha Mechanical Interpipe Contracting Pan Patifc Plumbing & M.:l Proposal- Per Plans and Specs 1,184,600 1,307,900 1,117,635 1,051,356 1,074,400 997,000 907,030 Bid .Opened s I.I8n.aau.e0 S 1.]0].90089 5 1.11]8]599 s 1.9]B unla 1'079.400 5 YMD98 s 926...000 Pregwliried ycs Yes ycs yes yes - yes yes CA License Current yes Y. Yes Yes yes yes yes Per Plansand Specs yes yes yes yes yex yes yes Adtn.Medge Addenda land 7 & Bulletin I yns yes Yes ycs ycs yes yes ' Bid Bond Included Yes yex Ye yet Y. yex yps Prevailing Wage yes Y. Yes ycs ye: yes ycs Campli.nce with Project Schedule Yes Ye: yes yez Yes yex yex Lhted Subconuactars Y9t ycs yes ' yes yes yes ALLOW ANCESIADf USTMENTS Namalivsien 5 - $ - 5 - $ 13.200.00 S - 5 S 61,030.00 Pose Did FRI, $ - $ S - 5 - S - 5 - 5 - 0e9edn I 5 - 5 - S - S S - 5 5 - 5 - S - S - $ - i!iF, 31 ", >I .I,I'ilb,Pll'1111 AIOn111M1l11 lIIIII'!111:I4P. "l+il.11 rtn 9L'- ul'N'11.! ill'- II' Iftlfll! lil !i! +'i+li!.1!'!.IL- II9.nf111`t call lf9 1 9 1111 11{; IIIP Oif all: �f .., .113 HI!RmM1LPIe1111l ill- di,J11!'1 „II.ILfIL- LgIIVl3fil iM1 -,L :: A.1 .11..1011'111IIIIIIILIdB,Ii; IN ln..el.!I >;II- IIg!IB3l11Bd Idl i,al..I,!.1 ..lt lllil llhll.il' �i141'f7)111 1I iCjl1j�j!11�91�"�;�I1 it111ll1I1 pr�ii jjf1�'�� Sa62fip41 rC9ntncCAmount 1 {I�IIII ".S', .' , ol. jll Ij '91� IID15tl0.q 1' lo-ll�¢ ii1111 F- ra�39]9a0A :I1V11 id 1I,.' ,i ft, 1 S a -' �'ril llYalBAO ,t�I�I {{;IU!s , Sai',II III'I lias Ask.. .1r1!Ilanl, .I II 111 5 1 i'� @p0]9400.99 ��1 �t�1lt,11 ff, ;Yt -. ,{du, 194TD6R00':9 u!Filnt,9{ -il Ia'9B]9)a90 - _,bl!5 =1 II) -,: '� VOLUNTARY ALTERNATES $ - S - 5 - S - S - 5 - 5 - 5 - S - 5 - S - 5 - 5 S - S 5 - S - 6 - S - S - . °!II Pi411 {yy !1111 fl TvF.{I Volui{eatyAh rmta Atn�Une 1 LIIh 111 3sl 1=s{ 3' l 5 t t 1t�d, f i�l�n 'o S 41111I�1�1 i 1 t i� IIII =1•' { 1 jl -ryr eoa. rnl TratlaiBid PaEkage: HVAC Project. Newport Beach Civic Center and Park Date: 4 February 2011 BP 015.3 SUBCONTRACTOR COMPARISON SPREADSHEET C.V. Driver BUILDERS SINCE 1'1111 Subcontractor Name NO. DescriptionlScope of Work A O Reed & Co. ACCO Engineered Systems Critchfield Mechanical Proposal - Per Plans and Spess 8,020,186 7,762,490 6,906,529 Bid as Opened 5 8.239. coo ,00 S 7704.690.00 3 5953.000.00 11,- Prequali0ed yes yes yes (II CA License Current yes yes yes Per Plans and Specs yes yes yes Acknowledge Addenda I and 2. & Bulletin I yes yes yes Bid Band Included yes yes yes Prevailing Wage yes yes yes Compliance with Project Schedule yes yes yes Listed Subcontractors yes yes yes ALLOWANCESIA DI USTM ENTS Narmali=ion $ (218.814.00) $ 57,600.00 $ 953.529.00 Post Bid FRIs $ - $ - TBD Bulletin $ - $ - TBD $ $ $ .�..,, I I si 1 ! -III All 111 II III i1(II ..i �i4L II ��.II, ✓,Ip ly,l 3 - II tall) li ili` „y,.l, i r „�::,,. 11 Illf 11 I 116.,: 1;17 tits i L{ :, r 50mntrectar Cantrat�Amaunti I} 111[ r ( ni.ti { �� I ':rsrl.i; pl I !,r !, !1 I { %i'.q „1!I ! . +11111 ,�$ !1 I .6 I H+Yfrll dul ll,. hl, II lI�h7tl ,1 fI01d 146'd01 � III I;A IIii 1111 :.:11.11 L 1;1:1, 111, 1 :IhIIq:l6dlp.{fIlI76..nilii6l:l $11�1� Ii '�I 776;490,00 �1 I ��i Iasi - 19 S - 6,966529.00 I� i • Z , [ ; _! L`.:I I Ilr li�l�lli��liil�l :I l� VOLUNTARY ALTERNATES P0,1011 $ $ $ ! 1 �? IGIla rl nl� 1. Totd(VbiuntaryoAiternafebtno6nt 5 11,- !: j'- 6�1; .11141 �114r,rr�'i'I� (II rflUj14;Ir��IIII'Lbi611,.�G�l- P0,1011 TradeMid Package: ELECTRICAL Project; Newport Beach Civic Center and Park Date: 4 February 2011 BP 016.1 SUBCONTRACTOR COMPARISON SPREADSHEET Q.N. Driver uol LDERSe1 \C8 t91e Subcontractor Name - NO. DescriptioniScope of Work Anderson & Howard Electric Bergelectric Corp, Morrow- Meadows Corp. Rosendin Electric $ Proposal- Per Plans and Specs 9,925,630 11,008,630 9,918,630 $ - $ (150.000.00) Bid as Opened 5 9915.000.01] 5 10.996000.00 5 .908.000.00 5 9.449000.00 $ (30,000.00) Prequalified - yes yes yes yes $ (200,00D.00) CA License Current yes Y. yes Yes not accepted,- (15,000) Per Plans and Specs yes Yes yes yes Accepted -50000 Acknowledge Addenda land 2, & Bulletin I yes yes Y. yes iilll!, 50 .: (9a0,000.00J Bid Bond Included yes Yes Yes yes Prevailing Wage yes yes yes yes Compliance with Project Schedule yes yes yes yes Listed Subcontractors yes yes yes yes ALLO WANCESIADJUSTM ENTS Normalintion $ - $ - $ - $ Past Bid Fulls $ - $ - § - $ - Winen 1 $ 10,630.40 $ 10,630.40 § 10,630.40 $ 9,664.OD VE accepted Eliminate concrete undeground encasement where noc required by code $ - § - $ - $ ($D,000.00) t!;li - 11111 r ill 'I11ili4G .;Jii IrI!.IA L.�,I IL r:nrr:,nnr r:u: r„r: l; l' Il n. Ii 0' tr ••r..l, ._ n: r':r: 1'r„rr,: , ri111J11r, u,. o-rr.,,.rilnl.r.r „rrr:r,rJ:rr'; In.r.i..1. 1411. rirnill! IL. L. dLLrii111Jwii. Jr: 7Lrdk, bl., d91f. A.,. Subcontract' or GOntracc`A'mou i 1 _! ,'.:nP:. 1�, Ii J, 1p1 ilk i, _ - r.':.ir rre r., rr, yrr, ,n it ..,,1,,. rmneunirr .yh,fl,Va,.,,lllurtlAJllu,:A.4. s 1 - 1 �II 1 �y?356a0A0I 1111,!1 -b!! II1II.IIII , .• .•r r .. r:.11"Ni:urrlyn:rnl 111{ 19r111xIIhltAkibrlLArrdrar.,,. d.. n, Ar. 5 �11 ij46a0d01 - !,00' l rl ,I..I` rl r pr ,r:...lr: r. h ..N,1.1.. {LIII0t1:L9N19dN6.,k11 I11191110nblilllrlrlrigirrr:,!{ g1���i��e�I�kO�yil i11i11919630AV kIV r:rr: raid ' Ilrn hIA. hLrrl! ftiN ..r,lllitl9:l9.1".1111174Y.11111 �d °jl 11 9'!(Ij,16dA0rt� Inr r111ueFrrrr.r!rq:!rll.!rl Iiillli l�l 1 to VOLUNTARY ALTERNATES $ $ $ $ Elecerkal-revise single l'me- reduce feeder size, reduce and eliminate panels $ - $ - $ - $ (150.000.00) Use standard Lead Acceptable meters $ - $ - $ - $ (30,000.00) Alternate lighting fxmre package $ - $ - $ - $ (200,00D.00) Eliminate rigid elbows in duct banks $ - $ - $ - not accepted,- (15,000) Eliminate concrete undeground encasemem: where net required by code $ - $ - $ - Accepted -50000 ijjM- IIITotal Voluntary Altemace Am 5091 _ 5 ._, :.5 .;: 5.,.. iilll!, 50 .: (9a0,000.00J ii Poeu 1 nl l ie Design Build Notice to Proceed Submit Design for Permit Building Permit North Wall Complete Start Construction Top Out Decks Ready For Permanent Power Substantial Completion Final Acceptance 4 22-Apir-11-i- ............. Start Construction Steel Erection Building Weather Tight Substantial Completion Final Acce lance ................... ----- ------------- Complete Construction Documents St St Building Su Final Building Permit Bid Day Submit GMAX GIVIAX Owner Approval Start Construction Foundations Complete + Steel Erection ........... - Building .Weat erTi Int - lr g I ''I'll..... .-I - -_------I . ... ........................... Substantial Completion Final Acceplarice 28-Jim-11:: Bid & Award Design Build-& Permit ................... .. .. .. r 13• bill Construction Documents Budding Permft BidPhase A Prequal Process ....... ........ ------ ............... ------ ..................... ...... ........ Bid Phase B Prequal Process Project Bid Phase 0:22•Ftib-11' Pnme cwmt Buyout 26- Apr -11:' Start Date: 27-Apr-10 Run Date: i6- Feb -11 Page 1 of 2 Newport Beach Civic Center GIWDnver End Date: 11- Feb -1s Master Summary Construction Schedule IBUI i.j.),IRRS ... S'..J.-NC r tyl9 Foundations / Underslab I Slab on Grade Structural Seel /Decks Exterior Roof Interior rat Floor 2i Bay A Grid Lines 1 - 6 16•Nov -11 i 28- Aug -12 Bay a Grid dines 6 -to Bay CGrid Lines to - ta - -. ..... ............. ............ 8 %Apr 1'',1 : : g-1 gay BavDGrid lanes to -16 - 3-Apr-,11 23-Mg-12i eav EGrid ones le -2t 18- Apt, -11 , 01 -Aug -02 -- Bay F Grid Lines 22 -26 - I 21- Apf•11 i29- Aug•1'L, i26•Apr•11, 31•Jul•12! _.._. _ Foundations / Underslab Utilities / Slab on Grade .. -.. ...... - ---.. -_.. _ -- ._.. ------ ...... .. ....... .. ........ ....... .... _ rr��r -- - - ' - -- - ' 26- Apr -it- 11 Aug 11 Structural Steel /Boot Deck i i � 12 <Aug -11� 16- Sep•11 � ' ' ' Exterior 19•Se ; -11� p 13Jani12 . Foot '30•D'ec -11 10•Febj12 Interior _ 100c01 31-Jul-12: 31- 25 May :-- - ....... ............ . ............ ................ - -.E OS Sep•12 .. ;.. Site Utilities 26•Jn -121, Site Finishes : : i i30- Dec -11, 0 &Sep•12 . i27•JUn•1 11-Feb-13 i27JUn -1 YO•Deb -12 ' e• •. c. _ ..!- — F ...... .....:......:..... ...... . - - - - Start 2� Run Date: 16- Feb -11 Newport Beach Civic Center dam` " "' =j n Page 2 of 2 wP V er End Dale: Master Summa Construction Schedule Summary iti.l?R.Ri3V l�?t'.Q. 11- Feb -13 a -T' EXHIBIT 2 1.1 Overview. The City has determined that this project ( "Project ") shall be insured under an Owner Controlled Insurance Program ( "OCIP "). The OCIP is more fully described in the OCIP Manual (the "OCIP Manual") for the Project, which is incorporated herein and by this reference. Parties performing labor or services at the Project site are eligible to enroll in the OCIP, unless they are Excluded Parties (as defined below). The insurance coverage under the OCIP is provided pursuant to policies of insurance ( "OCIP Policies ") issued by insurance companies ( "OCIP Insurers ") that provide for specified coverage ( "OCIP Coverage "). The OCIP Insurers will provide to Enrolled Parties (as defined below) and not to Excluded Parties, Workers' Compensation and Employer's Liability insurance, Commercial General Liability insurance, and Excess Liability insurance, as summarily described below, in connection with the performance of the Work ( "OCIP Coverages "). 1.2 Enrolled Parties and Their Insurance Obligations. OCIP Coverages shall cover the City, the OCIP Administrator, and Enrolled Parties. Enrolled Parties are: the CM and eligible subcontractors of all tiers that enroll in the OCIP, and such other persons or entities as the City may designate, in its sole discretion (each party insured under the OCIP is an "Enrolled Party "). Participation in the OCIP is mandatory, but not automatic for CM and all eligible subcontractors, of every Tier, each of whom must enroll in the OCIP as required by the terms of the OCIP Manual. Enrolled Parties shall obtain and maintain, and shall require each of its or their subcontractors to obtain and maintain, the insurance coverage specified in Section 1. 10, below, and in the OCIP Manual. 1.3 Excluded Parties and Their Insurance Obligations. The OCIP Coverages do not cover the following "Excluded Parties": (a) Hazardous materials remediation, removal and/or transport companies and their consultants; (b) Architects, surveyors, engineers, and their consultants; (c) Vendors, suppliers, fabricators (unless they also install), material dealers, truckers, haulers, drivers and others who merely transport, pickup, deliver, or carry materials, personnel, parts or equipment, or any other items or persons to or from the Project site; (d) CM and each of its or their respective subcontractors of all tiers that do not perform any actual labor on the Project site; and (e) Any parties or entities not specifically identified in this Exhibit 2 or excluded by the City in its sole discretion, even if they are otherwise eligible. The OCIP, OCIP Policies and OCIP Coverages shall not apply to Excluded Parties, even if erroneously enrolled in the OCIP. Excluded Parties and parties no longer enrolled in or covered by the OCIP shall obtain and maintain, and shall require each of its or their subcontractors of all tiers to obtain and maintain, the insurance coverage specified in Section 1.10, below, and in the OCIP Manual for all on -site and off -site operations. 1.4 OCIP Insurance Policies Establish the OCIP Coverages. The OCIP coverages and exclusions summarized in this Exhibit 2 and in the other Contract Documents are set forth in full in their respective insurance policies. The summary descriptions of the OCIP Coverages in this Exhibit 2 or the OCIP Manual are not intended to be complete or to alter or amend any provision of the actual OCIP Coverages. In the event that any provision of this Exhibit 2, the summary below, the OCIP Manual, or the Contract Documents conflicts with the OCIP insurance policies, the provisions of the actual OCIP insurance policies shall govern. OCIP Exhibit Net Bid 1.5 Summary of OCIP Coverages. OCIP Coverages shall apply only to those operations of each Enrolled Party performed at the Project site in connection with the Work, and only to Enrolled Parties that are eligible for the OCIP. OCIP coverages shall not apply to Excluded parties, even if they are erroneously enrolled in the OCIP. An Enrolled Parry's operations away from the Project site, including product manufacturing, assembling, or otherwise, shall only be covered if such off -site operations are identified and are dedicated solely to the Project. Off -site operations are not covered until CM or subcontractor receives written acknowledgement of OCIP coverage for off -site operations from the OCIP Administrator. The OCIP shall provide only the following insurance to eligible and Enrolled Parties: Summary Only Workers' Compensation Insurance Statutory Limit This insurance is primary for all occurrences at the Project site Employer's Liability Insurance Bodily Injury by Accident, each accident $1,000,000 Bodily Injury by Disease, each employee $1,000,000 Bodily hyury by Disease, policy limit $1,000,000 This insurance is primary for all occurrences at the Project site. Commercial General Liability Insurance Equivalent to ISO Occurrence Form, or its equivalent. Each Occurrence Limit $2,000,000 General Aggregate Limit for all Enrolled Parties $4,000,000 Ten (10) Years Products & Completed Operations Extension Products & Completed Operations Aggregate for all Enrolled Parties $4,000,000 *This insurance is primary for all occurrences at the Project site. The OCIP Commercial General Liability policy shall not provide coverage for any claim that could be covered under a Property or Builder's Risk policy. Excess Liability Insurance (over Employer's Liability & General Liability) Combined Single Limit $50,000,000 General Annual Aggregate for all Enrolled Parties $50,000,000 Ten (10) Years Products & Completed Operations Extension Products & Completed Operations Aggregate for all Enrolled Parties $50,000,000 General Liability Deductible Assessment Obligation The CM or its subcontractor primarily responsible for causing any bodily injury or property damage liability loss shall be responsible for payment of a deductible assessment. The assessment will equal the deductible under the responsible CM's or responsible subcontractor's general liability policy up to a maximum assessment of $25,000. The minimum assessment shall be the actual loss or $5,000 whichever is less. The assessment shall be applied on the same basis as applied under the responsible CM's or responsible subcontractor's primary general liability insurance policy. Upon request the responsible CM and/or responsible subcontractors are required to provide the City a copy of their commercial general liability insurance declarations page for determining the deductible assessment. If the loss exceeds $5,000 and information necessary to determine the applicable deductible as stated on the general insurance certificate is not available to the City, the City will assess the actual loss up to a $25,000 maximum per occurrence until receipt of documentation from the responsible CM or responsible subcontractor's commercial general insurance policy evidencing the actual deductible. If the loss is less OCIP Exhibit Net Bid than $5,000, the City will charge the actual loss. The City will charge the CM and/or subcontractor deductible assessment by processing administrative deductions on the CM's progress payments. At the option of the City, this deductible assessment may also be processed by direct billing, construction change orders, or any other method deemed appropriate by the City. The deductible assessment does not apply to workers' compensation claims by an employee of the CM or a subcontractor. 1.6 Property Insurance (a) Purchase by City. Unless otherwise provided, the City shall purchase and maintain builder's risk insurance in an appropriate amounts for the insurable Work at the Site. (b) Builder's Risk Deductible Assessment. The CM will be assessed for the amount of any loss payable under the OCIP Builder's Risk Policy. The fast $5,000 of any such occurrence will be paid by CM. This includes all expenses or claim payments incurred by the OCIP Insurer for losses attributable to the CM's work, acts or omissions, or the work, acts or omissions of any tier of subcontractor. CM may elect to pass this charge through to any responsible subcontractor but in no event may require total subcontractor reimbursement in excess of $5,000. Notwithstanding the above paragraph, City may purchase builder's risk insurance that involves a deductible greater than $5,000. CM or its subcontractor shall pay all costs not covered because of such deductibles if the loss is the result of the willful actions (including failure to protect the City's property or work), gross negligence, misconduct, or failure to follow the instructions of a representative of the City, by CM or by any subcontractors of any tier. (c) Off -Site Storage. Unless otherwise provided in the Contract Documents, the property insurance required by this Section 1.6 shall not cover portions of the Work stored off the Site without written approval of the City. CM shall be responsible for reporting such property or work to the City Risk Manager if ownership has been transferred to the City. If ownership rests with the CM or its subcontractor, CM or subcontractor shall be responsible for obtaining insurance to protect its interests. (d) Machinery, Tools. The insurance required by this Section 1.6 is not intended to cover machinery, tools or equipment owned or rented by the CM or subcontractors that are utilized in the performance of the Work but not incorporated into the permanent structure. The CM or subcontractor shall, at the CM's or subcontractor's own expense, provide insurance coverage for such owned or rented machinery, tools or equipment. (e) Partial Occupancy. Partial occupancy or use shall not commence until the insurance company or companies providing property insurance have consented to such partial occupancy or use by endorsement or otherwise. The City and the CM shall take reasonable steps to obtain consent of the insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse or reduction of insurance. 1.7 City's Insurance Obligations. The City shall pay the costs of premiums for the OCIP Coverages. The City will receive or pay, as the case may be, all adjustments to such costs, whether by way of dividends, retroactive adjustments, return premiums, other moneys due, audits or otherwise. CM hereby assigns to the City the right to receive all such adjustments, and shall use its best efforts to ensure that each of its subcontractors of every tier assigns to the City the right to receive all such adjustments. The City assumes no obligation to provide insurance other than that specified in this Exhibit 2, and in the OCIP insurance policies. The City's furnishing of OCIP Coverages shall in no way relieve or limit, or be construed to relieve or limit, CM or any of its subcontractors of any tier of any responsibility, liability, or OCIP Exhibit Net Bid obligation imposed by the Contract Documents, the OCIP insurance policies, or by law, including, without limitation, any indemnification obligations which CM or any of its subcontractors has to the City thereunder. The City reserves the right at its option, without obligation to do so, to furnish other insurance coverage of various types and limits provided that such coverage is not less than that specified in the Contract Documents. 1.8 CM & Subcontractor Obligations: (a) Incorporate the terms of this Exhibit 2 in all subcontract agreements. (b) Enroll in the OCIP within five (5) days of execution of the Contract and maintain enrollment in the OCIP for the duration of the Contract, and assure that each of CM's eligible subcontractors of every tier enroll in the OCIP, and maintain enrollment in the OCIP for the duration of their respective subcontract within five (5) days of subcontracting and prior to the commencement of Work at the Project site. (c) Comply with all of the administrative, safety, insurance, and other requirements outlined in this Exhibit 2, the OCIP Manual, the OCIP insurance policies, or elsewhere in the Contract Documents. (d) Provide to each of its subcontractors of every tier a copy of the OCIP Manual, and ensure subcontractor compliance with the provisions of the OCIP insurance policies, the OCIP Manual, this Exhibit 2, and the Contract Documents. The failure of (a) the City to include the OCIP Manual in the bid documents or (b) CM to provide to each of its eligible subcontractors of every tier a copy of the same shall not relieve CM or any of its subcontractors from any of the obligations contained therein. (e) Acknowledge, and require all of its subcontractors of every tier to acknowledge, in writing, that the City and the OCIP Administrator are not agents, partners or guarantors of the insurance companies providing coverage under the OCIP (each such insurer, an "OCIP Insurer "), that neither the City nor the OCIP Administrator are responsible for any claims or disputes between or among CM, its subcontractors of any tier, and any OCIP Insurer(s), and that neither the City nor OCIP Administrator guarantees the solvency or the availability of limits of any OCIP Insurer(s). Any type of insurance coverage or limits of liability in addition to the OCIP Coverages that CM or its subcontractors of any tier require for its or their own protection, or that is required by applicable laws or regulations, shall be CM's or its subcontractors' sole responsibility and expense, and shall not be billed to the City. (t) Cooperate fully with the OCIP Administrator and the OCIP Insurers, as applicable, in its or their administration of the OCIP. Any information that is required by the OCIP Manual or determined by City, in its sole discretion, to be relevant to the OCIP, including, without limitation, insurance underwriting, payroll, rating, safety or loss history information, certified copies of insurance policies, declaration pages of coverages, certificates of insurance, OSHA citations and other information or records, shall be provided by CM or subcontractor to the City within seven (7) Days of request by the City or the OCIP Administrator. (g) Provide, within five (5) days of the City's or the OCIP Administrator's request, all documents or information as requested of CM or its subcontractors. Such information may include, but may not be limited to, payroll records, certified copies of insurance coverages, declaration pages of coverages, certificates of insurance, underwriting data, prior loss history information, safety records or history, OSHA citations, construction cost estimates for this Project, including auditable records of the calculation of the bid or Contract Price /Contract Sum or any subcontract amount, pricing for each cost included in the bid or Contract Price /Contract Sum or any subcontract amount, or such other data or information as the City, the OCIP Administrator, or OCIP Insurers may request in the administration of the OCIP, to verify that the Costs of OCIP Coverages were not included in the Contract Price /Contract Sum or any OCIP Exhibit Net Bid subcontract amount, or as required by the OCIP Manual. All such records shall be maintained through the term of the Contract and for a period of one (1) year thereafter. (h) Comply, and require all of its subcontractors to comply with OCIP Administrator's instructions for electronically enrolling in the OCIP using "Aon Wrap" and for electronically reporting payroll using "AonWrap." (i) Pay to the City (without limitation to any of the City's other rights under the Contract Documents) a sum of up to $25,000 for each occurrence, including court costs, attorneys fees and costs of defense for bodily injury or property damage to the extent losses payable under the OCIP Commercial General Liability Policy are attributable to CM's Work, acts, or omissions, the Work, acts, or omissions of any of CM's subcontractors of any tier, or the Work, acts or omissions of any other entity or party for whom CM or its subcontractor may be responsible ( "General Liability Deductible Assessment Obligation "). The General Liability Obligation shall remain uninsured by CM and subcontractors, and will not be covered by the OCIP Coverages. This obligation shall be assessed as detailed in Section 1.5 of this Exhibit 2 above. 1.9 Method Of Calculation Of Credit Or Compensation for Premium. CM and each subcontractor shall bid the Project `net' of insurance costs due to eligibility for the OCIP. CM shall exclude the Cost of OCIP Coverages from its bid, and ensure that each subcontractor of every tier excludes the Cost of OCIP Coverages from their respective bids. The "Costs of OCIP Coverages" is defined as the amount of CM's and its subcontractors' reduction in insurance costs due to eligibility for OCIP Coverages, as determined by using Aon Form -1, Aon Form -2, and Aon Form -3 which are located in the OCIP Manual. The Costs of OCIP Coverages includes reduction in insurance premiums, related taxes and assessments, markup on the insurance premiums and losses retained through the use of the self - funded program, self - insured retention, or deductible program. The Cost of OCIP Coverages must include expected losses within any retained risk. CM must deduct the Cost of OCIP Coverages for all subcontractors in addition to their own Cost of OCIP Coverages. Change orders must also be priced to exclude the Cost of OCIP Coverages. 1.10 Additional Insurance Required From Enrolled Parties and Excluded Parties. CM shall obtain and maintain, and shall require each of its subcontractors of all tiers to obtain and maintain, the insurance coverage specified in this Section 1.10 in a form and from insurance companies reasonably acceptable to the City. The insurance limits may be provided through a combination of primary and excess policies, including the umbrella form of policy. Each policy required under this Section 1. 10, except the Workers' Compensation policy, shall include or be endorsed to include the City, the OCIP Administrator, their respective officers, agents and employees, and any additional entities as the City may request, as additional insureds. The policy or any additional insured endorsement shall provide that the coverage provided to the additional insureds is primary and non- contributory with respect to any other insurance available to the additional insureds. CM and subcontractors shall provide certificates of insurance coverage to the City or the OCIP Administrator as required by the OCIP Manual. All required insurance shall be maintained without interruption from the date of commencement of the Work until the date of the Final Payment unless otherwise specified elsewhere in the Contract Documents or the OCIP Manual. Insurance required by this section, shall be written by a company or companies lawfully authorized to do business in the State of California and having a current A.M. Best's rating of no less than A -: VI unless otherwise approved in writing by the City. All insurance coverage and limits required of or provided by CM or the subcontractors are intended to apply to the full extent of the policies. Nothing contained in this Section or elsewhere in the Contract Documents relating to the City or its operations is intended to limit the application of such insurance coverage. OCIP Exhibit Net Bid CM and its subcontractors must agree to provide, or to require CM's or subcontractor's broker or insurer to provide, immediate written notice to the City if any of the insurance required by this agreement is suspended, voided, canceled or not renewed during the term of this agreement. CM and its subcontractors acknowledge and agree that any actual or alleged failure on the part of the City to inform CM of non - compliance, or CM's actual or alleged failure to inform subcontractors of non- compliance with any insurance requirement in no way imposes any additional obligations on the City nor does it waive any rights hereunder in this or any other regard. Any type of insurance or any increase of limits of liability not described in this Section, which CM or subcontractor requires for its own protection or on account of any statute, shall be CM's or subcontractor's responsibility and at CM's or subcontractor's own expense. City shall have no responsibility for arranging coverage or for payment of premiums for any insurance coverage required of any CM or Subcontractor under this Section. Enrolled Parties are to provide evidence of Worker's Compensation, Employer's Liability, General Liability, and Excess Liability insurance, as set out below, for work performed away from the project site, and evidence of Automobile Liability insurance for all activities on and off the project site. Excluded Parties must provide evidence of all insurance set out below for both on -site and off -site activities. (a) Business Automobile Coverage providing coverage not less than the standard ISO form CA 00 01, covering all owned, non - owned, and hired automobiles, trucks, and trailers with a limit of not less than $1,000,000 (b) Statutory Workers' Compensation Insurance and Employer's Liability insurance with statutory limits as required by law, including Maritime coverage, if appropriate, and Employer's Liability limits of not less than $1,000,000 each accident, $1,000,000 each employee, and with a $1,000,000 policy limit. (c) Commercial General Liability Insurance in a form providing coverage not less than the standard ISO Commercial General Liability insurance policy ( "Occurrence Form "). The limits shall be no less than: Enrolled Parties & Excluded Parties Each Occurrence $1,000,000 General Aggregate $2,000,000 Products /Completed Operations Aggregate $2,000,000 Personal /Advertising Injury Aggregate $1,000,000 (d) If required by the City, Aviation and/or Watercraft Liability Insurance or other insurance, in form and with limits of liability and from an insuring entity reasonably satisfactory to the City. (e) Contractor's pollution liability insurance (for CM or any subcontractors performing Hazardous Substance remediation or as required by the City) shall be written on a form acceptable to the City providing coverage for liability arising out of sudden, accidental and gradual pollution. The policy limit shall be no less than $1,000,000 per claim and in the aggregate. When this insurance is required, all activities comprising the Work shall be specifically scheduled on the policy as "covered operations." The policy shall provide coverage for the hauling of waste from the Site to the final disposal location, including non - owned disposal sites. Products /completed operations coverage shall extend a minimum of three (3) years after Final Completion. Coverage shall be included on behalf of the insured for covered claims arising out of the actions of independent contractors. If the insured is using subcontractors said policy must include work performed "by or on behalf' of the insured. Said policy shall contain no language that would invalidate or remove the insurer's duty to defend or indemnify for claims or suits expressly excluded from coverage. Said policy shall OCIP Exhibit Net Bid specifically provide for a duty to defend on the part of the insurer. If the covered operations involve Hazardous Substances remediation under a subcontracting arrangement, CM shall insure that the subcontractor performing the remediation complies with this requirement. Such subcontractors shall be ineligible for the OCIP. If transporting hazardous waste/materials from the Site, appropriate MCS -90 Endorsement must be attached and supplied to the City on a primary basis with $5,000,000 limits of liability. (f) Professional Liability Insurance (if any professional services are to be provided) in the amount of not less than $2,000,000 per claim and in the aggregate. CM agrees to maintain continuous coverage for professional liability applicable to Work performed for a period no less than five years after completion of the Work. Any claims -made policy used to meet the requirements of the Contract Documents shall have a retroactive date prior to commencement of the Work. If professional services are to be provided through a subcontractor or subconsultant, CM shall insure that the subcontractor or subconsultant complies with this requirement. Such subcontractors and/or subconsultants shall be ineligible for the OCIP. (g) Other Insurance as may be required by the City to protect CM, the subcontractors, and other Indemnitees from loss related to the Work or the performance thereof. CM's failure to procure or maintain the insurance required by this Exhibit 2 and/or to ensure that all of its subcontractors of every tier maintain the required insurance during the entire term of their respective contracts shall constitute a material breach of this Agreement pursuant to which the City may immediately suspend or terminate this Agreement or, at its discretion, procure or renew such insurance to protect the City's interests, pay any and all premiums in connection therewith, and withhold or recover all monies so paid from CM. 1.11 CM's Representations and Warranties to the City. CM represents and warrants to the City, and shall use its best efforts to ensure that each of its subcontractors of every tier represent and warrant to the City that: (a) All information they submit to the City, or to the OCIP Administrator, shall be accurate and complete. (b) They have had the opportunity to read and analyze copies of the OCIP insurance policies that are on file in the City's office, and that they understand the OCIP Coverages. Any reference or summary in the Agreement, this Exhibit 2, the OCIP Manual, or elsewhere in any other Contract Document as to amount, nature, type or extent of OCIP Coverages and/or potential applicability to any potential claim or loss is for reference only. CM and its subcontractors of all tiers have not relied upon said reference, but solely upon their own independent review and analysis of the OCIP Coverages in formulating any understanding and/or belief as to amount, nature, type or extent of any OCIP Coverages and/or its potential applicability to any potential claim or loss. (c) The Costs of OCIP Coverages were not included in CM's or subcontractor's bid or proposal for the Work, the Contract Price /Contract Sum, and will not be included in any change order or any request for payment for the Work or extra work (d) CM acknowledges that the City shall not pay or compensate CM or any subcontractor of any tier, in any manner, for the Costs of OCIP Coverages. 1.12 Audits. CM agrees that the City, the OCIP Administrator, and/or any OCIP Insurer may audit CM's or any of its subcontractors' payroll records, books and records, insurance coverages, insurance cost information, bid estimates, pricing for any cost in the Contract Price /Contract Sum or any subcontracted Work, or any information that CM or its subcontractors provide to the City, the OCIP Administrator, or the OCIP Insurers to confirm their accuracy, and to ensure that the Costs of OCIP Coverages are not included in any payment for the Work OCIP Exhibit Net Bid 1.13 City's Election to Modify or Discontinue the OCIP. The City may, for any reason, modify the OCIP Coverages, discontinue the OCIP, or request that CM or any of its subcontractors of any tier withdraw from the OCIP upon thirty (30) days written notice. Upon such notice CM and/or one or more of its subcontractors, as specified by the City in such notice, shall obtain and thereafter maintain during the performance of the Work, all (or a portion thereof as specified by the City) of the CUP Coverages. The form, content, limits of liability, cost, and the insurer issuing such replacement insurance shall be subject to the City's approval. The cost of the replacement coverage shall be at the City's expense, but only to the extent of the applicable Costs of OCIP Coverages. 1.14 Withholding Payments. The City may withhold from any payment owed or owing to CM or its subcontractors of any tier the Costs of OCIP Coverages if they are included in a request for payment. In the event of the City's audit of CM's or subcontractors' records and information as permitted in the Contract, this Exhibit 2, or in other Contract Documents reveals a discrepancy in the insurance, payroll, safety, or any other information required by the Contract Documents to be provided by CM to the City, or to the OCIP Administrator, or reveals the inclusion of the Cost of OCIP Coverages in any payment for the Work, The City shall have the right to full deduction from the Contract Price /Contract Sum of all such Costs of OCIP Coverages and all audit costs. Audit costs shall include, but shall not be limited to, the fees of the OCIP Administrator, and the fees of attorneys and accountants conducting the audit and review. If the CM or its subcontractors fail to timely comply with the provisions of this Exhibit 2, the City may withhold any payments due to CM and/or its subcontractors of any tier until such time as they have performed the requirements of this Exhibit 2. Such withholding by the City shall not be deemed to be a default under the Contract Documents. 1.15 Waiver of Subrogation. Where pemmitted by law, CM hereby waives all rights of recovery by subrogation because of deductible clauses, inadequacy of limits of any insurance policy, limitations or exclusions of coverage, or any other reason against the City, the OCIP Administrator, its or their officers, agents, or employees, and any other contractor or subcontractor performing Work or rendering services on behalf of the City in connection with the planning, development and construction of the Project. The City shall also require that all CM maintained insurance coverage related to the Work, include clauses providing that each insurer shall waive all of its rights of recovery by subrogation against CM together with the same parties referenced immediately above in this Section 1.15. Where permitted by law, CM shall require similar written express waivers and insurance clauses from each of its subcontractors. A waiver of subrogation shall be effective as to any individual or entity even if such individual or entity (a) would otherwise have a duty of indemnification, contractual or otherwise, (b) did not pay the insurance premium directly or indirectly, and (c) whether or not such individual or entity has an insurable interest in the property damaged. 1.16 Duty of Care. Nothing contained in this Exhibit 2 or the OCIP Manual shall relieve the CM or any of its subcontractors of any tier of their respective obligations to exercise due care in the performance of their duties in connection with the Work, and to complete the Work in strict compliance with the Contract Documents. 1.17 Conflicts. In the event of a conflict, the provisions of the OCIP insurance policies shall govern, then the provisions of the Contract and its other related Contact Documents, then the provisions of the OCIP Manual. 1.18 Safety. CM shall be solely responsible for safety on the project. CM shall establish a safety program that, at a minimum, complies with all local, state and Federal safety standards, and any safety standards established by the City for the Project. 1.19 Remedies. Without limitation upon any of the City's other rights or remedies, any failure by CM or any subcontractor to comply with any provision of this Section 1.18 or the OCIP Manual shall be deemed a material breach of the Construction Contract, thereby entitling the City, at its option, upon notice to CM to suspend performance by CM or subcontractor, without any adjustment to Contract Sum Payable or Contract Time, until there is full compliance, or (2) or terminate this Construction Contract for cause. 8 OCIP Exhibit Net Bid 1.20 No Release. The provision of the OCIP shall in no way be interpreted as relieving CM or any subcontractor of any responsibility or liability under the Contract Documents, the OCIP Policies, or Applicable Laws, including, without limitation, CM's and subcontractor's responsibilities relative to indemnification and their obligation to exercise due care in the performance of the Work and to complete the Work in strict compliance with the Contract Documents. OCIP Exhibit Net Bid