HomeMy WebLinkAbout2014-04-09_BVAC_AgendaCITY OF NEWPORT BEACH
BALBOA VILLAGE ADVISORY COMMITTEE AGENDA
ExplorOcean
600 East Bay Avenue
Wednesday, April 9, 2014 - 4:00 p.m. to 5:30 p.m.
Committee Members:
Michael Henn, Council Member (Chair)
Tony Petros, Council Member
Gloria Oakes, Balboa Peninsula Point Association
Ralph Rodheim, Balboa Village Merchant Association Member
Grace Dove, Central Newport Beach Community Association
Tom Pollack, ExplorOcean Representative
Jim Stratton, At -Large Representative
Staff Members:
Kimberly Brandt, Community Development Director
Brenda Wisneski, Deputy Community Development Director
Tony Brine, City Traffic Engineer
Fern Nueno, Associate Planner
CALL MEETING TO ORDER
II. PUBLIC COMMENT ON NON - AGENDIZED ITEMS (comments limited to 3 minutes)
III. ITEMS FOR REVIEW
1. MINUTES OF MARCH 12, 2014 (ATTACHMENT 1)
Recommended Action: Approve March 12, 2014 Minutes
2. UPDATE ON VILLAGE MAINTENANCE
Recommended Action: Receive and file
3. FAQADE IMPROVEMENT PROGRAM OPTIONS (ATTACHMENT 2)
Recommended Action: Review program options, provide direction for future program
consideration
IV. PUBLIC COMMENT
V. ADJOURNMENT (Meeting End Time: 5:30 p.m.)
Next Meeting Date: Wednesday, May 14, 2014, 4:00 p.m.to 5:30 p.m.
Please refer to the City Website, http:// www .newportbeachca.gov /index.aspx ?page =2196, for additional
information regarding the Balboa Village Advisory Committee.
AN AGENDA FOR THIS MEETING HAS BEEN POSTED AT LEAST 72 HOURS IN ADVANCE OF THE MEETING AND THE PUBLIC IS
ALLOWED TO COMMENT ON AGENDA ITEMS.
IT IS THE INTENTION OF THE CITY OF NEWPORT BEACH TO COMPLY WITH THE AMERICANS WITH DISABILITIES ACT (ADA)
IN ALL RESPECTS. IF, AS AN ATTENDEE OR A PARTICIPANT AT THIS MEETING, YOU WILL NEED SPECIAL ASSISTANCE
BEYOND WHAT IS NORMALLY PROVIDED, THE CITY OF NEWPORT BEACH WILL ATTEMPT TO ACCOMMODATE YOU IN EVERY
REASONABLE MANNER. PLEASE CONTACT LEILANI BROWN, CITY CLERK, AT LEAST 72 HOURS PRIOR TO THE MEETING TO
INFORM US OF YOUR PARTICULAR NEEDS AND TO DETERMINE IF ACCOMMODATION IS FEASIBLE (949- 644 -3005 OR
CITYCLERKCNE WPORTBEACHCA.GOV).
1
INTENTIONALLY BLANK PAGE
9
ATTACHMENT 1
March 12, 2014
Meeting Minutes
S
INTENTIONALLY BLANK PAGE
CITY OF NEWPORT BEACH
BALBOA VILLAGE ADVISORY COMMITTEE MINUTES
Location: ExplorOcean
600 East Bay Avenue
Wednesday, March 12, 2014 - 4:00 p.m. to 5:30 p.m.
Call Meeting to Order
Council Member Petros called the meeting to order at 4:03 p.m. He thanked those in
attendance for participating in the process and noted that Council Member Henn would be
absent due to a conflict. The following persons were in attendance:
Balboa Village Advisory Committee Members:
Tony Petros, Council Member
Ralph Rodheim, Balboa Village Merchant Association Member
Grace Dove, Central Newport Beach Community Association (arrived at 4:51 p.m.)
Tom Pollack, ExplorOcean Representative
Jim Stratton, At -Large Representative
Staff Members:
Kimberly Brandt, Community Development Director
Brenda Wisneski, Deputy Community Development Director
Brad Sommers, Senior Civil Engineer
Fern Nueno, Associate Planner
II. Public Comment on Non - Agendized Items
Interested parties were invited to address the Committee on Non - Agendized Items.
There being no one wishing to address the Committee, Council Member Petros closed
the Public Comment on Non - Agenda Items portion of the meeting.
III. Approval of Minutes
Recommended Action: Approve February 12, 2014 Minutes
Council Member Petros noted that Council Member Gardner's name needed correction.
Action: Committee Member Ralph Rodheim moved to approve the minutes of the
February 12, 2014 meeting as amended; Committee Member Jim Stratton seconded
the motion, which carried unanimously.
IV. Bicycle Master Plan — Paul Martin, Alta Planning + Design
Recommended Action: Review Draft Bikeways Plan and provide recommendations
for the Balboa Village area to the Bicycle Master Plan Oversight Committee
5
Council Member Petros introduced the item and deferred to Paul Martin for a
presentation.
Paul Martin, consultant from Alta Planning and Design, discussed the Bicycle Master Plan
Project and presented slides to outline the project purpose and goals of the plan. It is to
create a comprehensive network with an eye for sustainability and a connection with the
community and bicycle network throughout the City. The plan also seeks to educate and
encourage the community and youth on bicycle safety, as well as working with law
enforcement to monitor progress. Details of the draft network were displayed, noting that
these plans are available for viewing on a dedicated website and the public is encouraged
to leave comments, inputs, and ideas. On May 31s` at West Coast Highway, a table will
be set up for cyclists to weigh in on the development of the Master Plan. The City Council
will review of the Master Plan in the fall.
Council Member Tony Petros noted the importance of funding and focusing on what the
most desirable mode of transportation is within Newport Beach.
Tom Pollack stated that bicycles are a staple of the City and that he hopes the plan will
include parking for bicyclists and offer lit wayfinding signage.
Jim Stratton added that it is important to encourage bicyclists to ride in the area and that
there needs to be bicycle storage space that will not be an eyesore.
Ralph Rodheim stated that he would prefer to ride down the ocean path, as opposed to
riding in a bike lane down Balboa Boulevard.
Council Member Petros discussed the bike share program and added that he would like
to see remote parking off of congested locations and off the peninsula so visitors could
park and rent a bike.
Bill Dildine noted that at the last Bicycle Master Plan Oversight Committee meeting, there
were two letters about extending the path beyond the wedge and onto the beach, yet that
provides problems with residents.
Alison Ryffel, Balboa Peninsula Point Association, responded that the association has
been working closely with the police department and the City to configure a safe way to
mitigate the safety problem residents' face.
Janis Dinwiddle discussed the Centennial celebration.
Howard Hall added that extending the trail down to the wedge will increase traffic and that
residents will fight it.
Ralph Rodheim stated that a walking path and a riding path back and forth from the
wedge will not be in the plans.
N
Jim Mosher stated that he comes to Balboa once a month to attend meetings and only
comes by bike. He noted that if signage is overdone, it can be overwhelming and also
that he ties his bike to the railing because of the way he approaches the building and the
inability to find a bike rack.
Council Member Petros added that wayfinding does not have to be a sign, but there
should be a common color or sign to alert bicyclists of parking locations for bikes.
Alison Ryffel noted the hordes of bicycles piled up in front of Cabo Cantina recently, and
the subsequent need for organized bike parking and signage.
Brad Sommers added that parking and wayfinding need to be convenient, simple, and
effective.
Council Member Petros thanked the staff and the community for their dedication to this
process and the development of the Master Plan.
V. Review 2014 Work Program Action Plan
Recommended Action: Review Action Plan
Fern Nueno, Associate Planner, discussed the proposed schedule for the rest of the year,
as well as the scope of work for the consultants. Each of the five proposed programs was
outlined, starting with the Commercial Fagade Improvement Plan. The Targeted Tenant
Attraction Program, Design Guidelines, and Streetscape Plan and Wayfinding were briefly
discussed in regards to timelines and presentation dates.
Ralph Rodheim discussed what the Balboa Village Merchants Association (BVMA) is
planning with the silk flowers. Janis Dinwiddie and Terri Pasquale shared pictures of the
existing streetscape, including the current garden pots, and the new silk flowers. Mr.
Rodheim stated that this is just an informational item and he will continue to communicate
with the BVAC regarding BVMA items. The plan is for live plants not be used, which will
save the City money, and they could be changed out seasonally
Kimberly Brandt discussed the Pilot Plant Program, which would encourage consistency
among the garden pots being used and communication with staff.
Brenda Wisneski, Deputy Community Development Director, proposed.
Council Member Petros asked that the record reflect that Grace Dove, Central Newport
Beach Community Association, arrived to the meeting.
Ralph Rodheim stated that City staff has put so much time and effort into the Village and
that BVMA appreciates all the work.
7
Action: The committee concurred with the proposed schedule.
VI. Review Project Scopes of Work
1. Design Guidelines
Recommended Action: Review and Finalize Scope of Work
2. Streetscape Improvements and Wayfinding Sign Program
Recommended Action: Review and Finalize Scope of Work
Brenda Wisneski, Deputy Community Development Director, discussed the scopes of
work and the proposed plan of using consultants. The consultants will be provided with a
framework, which they can use to design the best plan of work.
Council Member Petros added that it is critical to involve residents and allow them an
opportunity to provide input.
Brenda Wisneski discussed the plans for improvement, including landscaping, community
involvement, and coordination with Public Works.
Kimberly Brandt, Community Development Director, added that staff will select
consultants and then return to the Committee.
Council Member Petros requested that an update on maintenance efforts be put on a
future agenda.
Alison Ryffel stated that an email blast can be sent out to all members with the Peninsula
Point Association Members and publications.
Ms. Wisneski concluded her presentation discussing the wayfinding and signage.
Committee Member Grace Dove added that she is frequently stopped by people asking
for directions and that wayfinding is an important issue to address.
Action: The committee provided direction to move forward with the scopes of work.
VII. VII. Public Comment
Ralph Rodheim noted that Steve Beazley is currently present, representing the Balboa
Theater, and that with the support of the community, there will be a theater in the future.
VIII. Adjournment
There being no further business to come before the Balboa Village Advisory Committee,
Council Member Petros adjourned the meeting at 5:17 p.m.
Next Meeting Date: Wednesday, April 9, 2014 4:00 p.m. to 5:30 p.m.
2
ATTACHMENT 2
Facade Improvement
Program Memo
9
INTENTIONALLY BLANK PAGE
10
Memorandum
CITY OF NEWPORT BEACH
COMMUNITY DEVELOPMENT DEPARTMENT
100 CIVIC CENTER DRIVE
NEWPORT BEACH, CA 92660
(949) 644 -3227
To: Balboa Village Advisory Committee
From: Fern Nueno, Associate Planner
Date: April 3, 2014
Re: Commercial Fagade Improvement Program
The Balboa Village Master Plan included a recommendation to develop a fagade
improvement program to incentive property owners to invest in the rehabilitation of their
buildings. The excerpt from the Master Plan is attached. The program could offset all, or a
portion of, the costs for items such as paint, signage, awnings, window casings, and
structural repairs. While the costs of these improvements can be relatively minimal, they can
significantly improve the appearance and overall appeal of the Village.
These types of programs are common among districts like the Village, but can vary
significantly. The following information and attachments highlight potential programs, funding
options, and recommendations.
TAP Report Recommendations
The Urban Land Institute (ULI) Technical Assistance Panel (TAP) Report (excerpt attached)
also includes recommendations for a fagade program. The TAP Report provides
recommendations for public realm improvements that would provide the "most bang for the
buck," one of which is improving the building fagades to enhance the pedestrian experience
and creating a "storefront fund" to assist the business and property owners. The report also
states that visitors and residents arriving to the Village by ferry would have a better
experience if improvements were made to adjacent building fagades. The report prioritized
blocks for both the Fagade and Tenant Attraction programs as follows:
1. Balboa Boulevard
2. Palm Street
3. Bay Avenue
4. Main Street
5. Alleys
11
Balboa Boulevard could be targeted for initial funding as a model block that will have the
most impact upon completion. This will help spur other property owners to participate in the
program after seeing the results from the model block.
Program Options
Fagade improvement programs range in cost and level of change desired. Some cities have
created programs simply offering funds to off -set the costs of basic improvements, such as
awnings, signage, and paint. These programs can be relatively inexpensive. Some
programs started with as little as $25,000 for the first year. Other cities, seeking to make a
greater impact, complete the design and improvements on behalf of the property
owners /businesses.
Seed Money Program (less expensive, less aggressive)
• Establish loan or grant fund
• Identify maximum funds per building
• Funds for property owners /tenants for qualified projects
• Financial assistance can be based on the linear feet encompassed by the facade, or
project scope
• City could identify priority areas, notify property owners, and provide technical
assistance in the preparation of the applications
• Cost estimate is $999- 30,000 per suite depending on program elements
2. Full Cost Program (more expensive, more aggressive)
• City controls process and design elements
• City bears entire cost
• Property owners grant the City a fagade easement for a ten year period
• Property owners are responsible for upkeep
• Requires participation of all owners in target area
• Cost estimate for Balboa Village is $100,000- 175,000 per building
Programs in Other Jurisdictions
The cities of Saratoga, San Clemente, Santa Cruz, Westminster, and Fontana have
implemented Commercial Fagade Improvement Programs (additional information is
attached). Some of the concepts include:
• Application process with property owner consent required
• Grants awarded for up to 50% of the project costs up to a maximum amount
• Money is reimbursed at completion of project after receipts have been submitted
• Maximum funds based on tenant frontage, or project scope
• Projects must be completed within one year of approval
Properties eligible once every ten years
• City permit requirements still applicable
12
Allowed fagade improvements must be visible from primary streets and include
painting, lighting, anti - graffiti film coating, awnings, landscaping, window treatments,
and other improvements to architectural features
Grants could be awarded for architectural or design services
Fontana implemented a full cost program with fagade easements
Recommendation
As stated in the ULI TAP Report, revitalization efforts should embrace the Village's
personality and improve the experience for the local community. The village character is
appreciated, and only needs enhancement. For this reason, it is recommended that a fagade
improvement program take a less aggressive approach to implementation. Simply offering
seed money can be the incentive needed to replace some of the fading signs, chipped paint,
or weathered window treatments in the Village.
Program Implementation Steps
• Develop program criteria and application process
• Identify program costs and identify funding sources
• Obtain City Council approval
• Outreach to property owners and tenants
• Provide technical assistance for application
• Administer program
i3
• Residential development is an economic engine for mixed -use development
opportunities; carries the cost of ground floor commercial
• Cultural catalysts - ExplorOcean and Balboa Theater
• City -owned parking lot on Palm Street may be developed and serve as a catalyst
to promote economic development in Balboa Village
Strategies:
• Pursue adoption of a Local Coastal Plan to expedite project review /permit
issuance
• Eliminate parking requirements for new or intensified commercial uses
• Support/facilitate development of ExplorOcean/Balboa Theater
• Create financial incentive programs to encourage facade improvement and
rehabilitation of commercial properties
• Support and encourage a variety of events and activities in the Village to improve
community interest and increase business sales for local merchants
• Consider developing the Palm Street parking lot with a mixed use project, either
hotel or residential with a small amount of ground -floor commercial
• Identify new revenue sources to assist in funding programs and projects
recommended for Balboa Village
The following recommendations were made by the CAP in order of priority by category
based on need and the ability to make the greatest impact with the limited resources
available.
ECONOMIC DEVELOPMENT
A number of economic development related tools and strategies must be employed in
Balboa Village to enhance its ability to be a viable commercial and tourist district. The
following priority recommendations are ranked in the order provided:
1. Develop and Implement a Commercial Facade Improvement Program
There are approximately 55 commercial buildings located in Balboa Village, some of
which contain residential units above the ground floor commercial space. Many of these
buildings are in need of exterior renovations, such as paint, signage, awnings, window
casings, and structural repairs. The KMA report concluded that, while commercial space
rents in this area are adequate by market comparison, on balance, the property owners do
not perceive that investing in exterior improvements will generate significant rent
increases. The deterioration of these buildings is a key contributor to the overall declining
appearance and appeal of the area to residents and visitors alike.
In an effort to incentivize property owners to invest in the rehabilitation of their
buildings, it is recommended that the City Council create a facade improvement program
and fund a portion of the costs to rehabilitate these commercial structures. These types of
Balboa Village Master Plan
0
programs are common in special districts such as Balboa Village, and the success of such
a program would lead to a renewed sense of place.
As noted in the KMA study, there are several options the City could consider when
developing such a program. The CAP is recommending that a tiered, matching fund
grant program be created. The program would be designed to insure that City funds are
not expended until such time as the owner's funds are available, such as requiring an
escrow account for draw -down purposes. The City should consider a range of rebates
based on the extent of improvements needed for a particular building, as suggested
below:
Minor Building Improvements
These would include items such as sign removal and replacement, and exterior painting
(no major repairs involved). The rebate would be based on scope as opposed to building
frontage, with a not to exceed rebate of $15,000 per building.
Major Building Improvements
MW
Up to 25' frontage $15,000
25' to 50' frontage $25,000
50' to 75' frontage $37,500
75' and above $50,000
Key to the program's success will be the targeting of initial funding to a model block that
will have the most impact upon completion. This will demonstrate to the owners the
potential for their buildings, and give tenants, residents and visitors renewed hope in the
Balboa Village Master Plan
revitalization of the area's commercial district. Often, these building improvements will
lead to interior tenant improvements with existing businesses and /or attract new tenants
to better serve the area. The specifics of such a program and potential funding sources
will be developed if, and when, the City Council approves moving forward with such an
incentive. A potential funding source would be the use of CDBG funding which is
discussed in further detail below.
2. Develop and Implement a Targeted Tenant Attraction Program.
A complementary effort to the Facade Improvement Program is a key tenant, targeted
marketing program. Based on the findings of the KMA market study, there exists a
limited opportunity to attract a few key tenants and developments to the area(e.g., sit -
down restaurant, quality boutique retail, and a boutique hotel). To do so, however, may
require financial incentives on the part of the City to encourage such uses to locate in the
Village. These might include fee waivers for plan check and building permits, and
perhaps a tenant improvement loan program to offset the expense of opening a new
restaurant in the area. Once the incentive programs are developed, a method to provide
outreach will be needed to make potential tenants aware of the opportunities. First
Balboa Village Master Plan ���
To: Kimberly Brandt, City of Newport Beach April 10, 2012
Subject: Balboa Village: Implementation Strategies Page 6
establishments could benefit from the increased visitation created by these
developments. Therefore, it would be advantageous for the City to support and facilitate
the development of these uses.
Fagade Improvement Programs
Fagade improvement programs can be implemented to assist in creating aesthetically
pleasing, tenant preferred, commercial space. A well designed program can increase
business exposure, enhance visual attractiveness, stimulate private investment and
create harmonious commercial districts. Fagade improvement assistance programs run
the gamut from the provision of seed money to property owners, to programs that fund
100% of the approved fagade improvement costs.
To entice property owners to participate in the program, fagade improvement assistance
is often provided in the form of a grant. However, to ensure that the desired tenancies
remain in place over a specified timeframe, this assistance is sometimes treated as a
forgivable loan. For example, the loan could be forgiven in 20% increments over a five
year period. In that case, if a tenant remains for the entire five years, then the loan is
forgiven in full.
Typically, the eligible work is limited to upgrading the facades that are visible from the
street. The eligible improvements can include painting, masonry cleaning, exterior
lighting, signage, accessibility improvements and so forth.
Seed Money Program
In a seed money program, the City would establish a loan or grant fund that provides
qualified property owners with a grant or loan equal to a portion of the fagade
improvement costs. For example the City could contribute up to 50% of the eligible
fagade improvement costs up to a defined limit. One way to measure the grants is to tie
the assistance to the number of linear feet encompassed by the fagade. For example,
seed money assistance could be set within the following range:
Fagade under 25 feet $15,000
Fagade between 25 and 50 feet $25,000
Fagade between 50 and 75 feet $37,500
Fagade above 75 feet $50,000
In a seed money program it is advisable for the City staff to identify target buildings, and
to notify the property owners that the program is available. To further encourage
participation, it may be useful to offer technical assistance to these owners in the
preparation of the loan /grant applications.
1202003_5; NB:KHH:KEE
16092.001tgy-
To: Kimberly Brandt, City of Newport Beach April 10, 2012
Subject: Balboa Village: Implementation Strategies Page 7
Full Cost Proaram
A more aggressive program would involve the City controlling the entire process. In this
program, the City would bear the entire cost burden for the fagade improvements. In
return, building owners would grant the City a fagade easement, typically in the range of
10 years. In addition, after the improvements are completed, the property owners would
be responsible for ongoing upkeep of the improvements.
To achieve the maximum impact, this type of program would require the participation of
all the owners within the designated target area. With the City controlling the process,
the design elements would be consistent, economies of scale could be achieved for the
construction costs, and the improvements could be completed expeditiously. For
reference purposes, the costs incurred by other programs have fallen in the range of
$1,000 to $1,800 per linear foot. Based on the characteristics of Balboa Village
commercial properties, the total cost is estimated to range from approximately $100,000
to $175,000 per building
Tenant Improvement Loans
Tenant improvement loan programs are designed to bring new desirable tenants to an
area. The tenants that are selected to receive assistance should meet defined City
objectives such as significant sales tax generation; ability to attract shoppers, diners,
and visitors; and /or creation of "spin off' benefits to other businesses in the area. These
programs are typically utilized to catalyze an area that is underperforming by making it
financially attractive for desired tenants to rent space in the area.
In a tenant improvement loan program, the City assistance would be provided to
qualified businesses to improve building interiors; assistance related to business
operations should not be provided. Tenant improvement loans are particularly useful for
restaurants, which have higher tenant improvement costs than other commercial uses
due to the required kitchen equipment, decor and furnishings. However, they can also
be used to attract desired retail shop space.
Programs that KMA has assisted in structuring require the building owner, the tenant
and the City to contribute funds for the tenant improvement costs. The City contribution
is typically capped at no more than 50% of the tenant improvement costs, and the
assistance costs have fallen in the range of $30 to $70 per square foot of building area.
The cost range is directly tied to type of tenancy and the magnitude of the improvements
being constructed.
1202003_5; NB:KHH:KEE
16092.001&9
To: Kimberly Brandt, City of Newport Beach
Subject: Balboa Village: Implementation Strategies
April 10, 2012
Page 10
Source
Description
Community Development Block Grant
These funds are awarded to the City by
Funds (CDBG)
the federal government. The funds can
be used to achieve defined national
objectives, including the construction of
public improvements such as
streetscape improvements.
Disposition of City Assets
The City can sell or lease City owned
property to attract desired uses.
General Fund
Includes sales taxes, transient
occupancy taxes (TOT), property taxes,
motor vehicle license fees, etc. These
funds can be used to fund economic
development and capital programs.
Parking Benefit District Revenues and
Parking revenues can be used to fill gap
Recreational Vehicle Parking Revenues
in funding existing parking obligations.
In the future, the City Council could
make the policy decision to direct
revenues back into Balboa Village to
fund implementation activities.
Community Facilities Districts (CFD)
A special tax is assessed on properties
and Special Assessment Districts
to fund public facilities and services.
Development Impact Fees
The City can impose impact fees directly
tied to improvements and /or services
necessitated by development.
Developer Advances
Developers can be asked to pay for
public improvements in return for
repayment from the public revenues
generated by their project over time.
California Infrastructure and Economic
The Bank offers a low interest bonds for
Development Bank ([BANK)
projects such as streets, parks, and
transit. The loans range from $250,000
to $10 million.
1202003_5; NB:KHH:KEE
16092.001 "0
ATTACHMENT 1- TABLE T
POTENTIAL FUNDINDG MECHANIST
IMPLEMENTATION STRATEGIES
BALBOA VILLAGE IMPLEMENTATI(
NEWPORT BEACH. CALIFORNIA
Prepared by: Keyser Marston Associates, Inc.
File name: NB Balboa PF_4_10_12; Aft 1 20
Loan & Grant Programs
I-Bank - Infrastructure State Revolving Fund
Program
A. Description
•
City can administer revolving loan funds,
•
Low cost financing to public agencies for a
low interest loan programs or loan
wide variety of infrastructure projects.
guarantee programs.
•
Local or regional lenders can be
apprroached to ascertain their interest in
contributing funds for lending.
B. Eligible Uses
•
Tenant improvement loans
•
City streets.
•
Fagade improvement loans
•
Educational facilities.
•
Small business start -up loans
•
Environmental mitigation measures.
•
Parks and recreational facilities.
•
Public transit.
C. Funding Parameters
•
Funds wold be available to applicants on a
•
The Infrastructure State Revolving Fund
demonstrated needs basis.
Program offered by the I -Bank offers loans
ranging between $250,000 to $10,000,000
with eligible repayment sources including
General Fund revenues, tax increment
revenues, and property assessments.
D, Funding Responsibilty
•
Funding provided by City based on scale
•
Repaid by City with local tax revnues,
of program.
Prepared by: Keyser Marston Associates, Inc.
File name: NB Balboa PF_4_10_12; Aft 1 20
Arrival into Balboa Village
Citing the success of the Balboa Island Ferry, the panelists felt that traveling to Balboa Village should be a fun, enjoyable experience.
They suggested adding more alternatives to the automobile, specifically water taxis, wheel -based trolleys (designed to look like the
old Southern Pacific trains), light rail, and bike - sharing stations located through-
out the peninsula and the rest of Newport Beach. Branding opportunities are
available to local merchants and organizations, including logos, messaging and tD
artwork displayed on both land- and water -based vehicles. FAIFTA rrn n V IA GA
Arriving to the village by ferry, visitors and residents would have a better experi-
ence if improvements were made to adjacent building fagades. In particular,
Palm Street, the major corridor for cars and bicycles arriving on the ferry, would
be more welcoming if buildings fronted Palm.
Regarding signage, the TAP recommended installing gateway signs or land-
mark structures that identify all entrances and exit points. These markers will
not only improve the village's identity, but also enhance the arrival experience. _
The first point of entry for drivers is Balboa Boulevard at Adams Street, which
would benefit from an eye- catching identifier, such as an archway, monument - or vintage sign welcoming people to Balboa Village. Likewise, a similar gateway -
exit (and entrance) should be installed at Balboa Boulevard and A Street. The
panelists also recommended that both the Beach Boardwalk and Fun Zone Boardwalk be marked with entry and exit signs at Adams
Street as well as A Street. All designs should be consistent with the village's branding guidelines.
arie� i gMptWQmenta
The TAP was asked to suggest improvements in the pub-
lic realm that would provide the "most bang for the buck"
in the immediate future. Here are the recommendations:
» Widen sidewalks to enable outdoor sidewalk cafes.
Ideally, the sidewalk widening should not reduce the
quantity of parallel parking, which is needed in part
for pedestrian security.
» Improve building fagades to enhance the pedestrian
experience. A "storefront fund" could be created to
assist business and property owners.
» Install gateway and wayfinding signage that is con-
sistent with the village's heritage (current vintage
signs at the drug store and "U- drive' are good ex-
amples).
» Enhance landscaping, especially creating a tree can-
opy over sidewalks and using plants to soften areas
where the vertical building edge meets the horizontal
sidewalk edge.
» Enhance streetscapes, especially adding more out-
door seating and creating parklettes, or mini parks.
» Upgrade night lighting for better quality and safety.
Add string lights across one or more streets to add
to the ambiance.
» Improve walkability by closing Bay.
r 'IF
Above is a vintage sign at the Fun Zone. Examples of vintage signs below.
f
M'
n �
,
Approximately 2 million visitors come to Balboa Village each year, but most of them visit only during the peak summer months. About
80 percent of these guests are "day trippers." The TAP was asked to recommend off - season activities as well as identify locations to
host these programs. Areas within the public realm that are well- suited for special events include Balboa Park, the boardwalks, beach,
streets, alleys and sidewalks. Panelists suggested some of the following activities to draw residents and visitors year- round:
» Farmers market » Vintage car shows Seasonal music festivals
» Craft shows » Expanded Holiday Boat » "Taste of Balboa"
» Art shows Parade activities » Food trucks
» Boat shows » Craft beer festival
It may be necessary to use management strategies such as valet parking or to
run a shuttle to more distant parking areas when it is required to meet demand.
(Shared Parking, by Mary S. Smith, p. 22)
Prioritizing Improvements and Guidelines
The TAP was tasked with prioritizing the village blocks for the city- sponsored com-
mercial fagade improvement program and the targeted tenant attraction program.
Because the panelists were pleased with the street improvements already imple-
mented on Main Street, it did not rank this street high on the list; however, this does
not minimize the importance of Main Street as a major focal point in the village.
As previously stated, the panelists prioritized development of a Central Park or
Plaza as most worthy of the city's attention and resources. Following that, the
blocks were prioritized as follows:
1. Balboa Boulevard
2. Palm Street
3. Bay Street
4. Main Street
5. Alleys
The panelists also strongly recommended that the city incorporate new form -
based codes and design standards to preserve and enhance Balboa Village's
special urban character and to improve the pedestrian experience. Form -based
codes are guidelines that consider the form and mass of buildings in relation to
one another, the size and types of streets, and the ways in which building fagades
and public spaces relate to each other. These codes have been adopted in over
200 cities in the U.S. and offer an alternative to conventional zoning.
Designing for the human
scale, creating destina-
tions, and improving physi-
cal access will all help
improve the definition, con-
nectivity, and walkability of
communities. It will also
provide a greater variety
of sensory experiences,
which will invite people to
stay, explore, and enjoy.
(Creating Walkable Places, p. 55)
TECHNICAL ASSISTANCE PANEL REPORT � 19
City of Saratoga, California
http://www.saratocia.ca.us/abouVviI[age
Village property owners or business owners (with property owner consent) can receive up to a
50% reimbursement of total project costs for fagade improvements. The maximum award for
an approved fagade improvement to a storefront visible from Big Basin Way is $5,000.
Exterior improvements to storefronts in the Village Commercial District that are visible from Big
Basin Way are eligible for the program. Projects range from new paint, installation of an
awning, to landscaping.
To receive grant money, participants must submit an application and project proposal to the
City. If the project meets necessary requirements and funding is available, then the project will
be approved by the City Council Village Ad Hoc Committee and staff will notify the applicant if
any permits or approvals need to be obtained. Fagade improvements must be completed
within 1 year of project approval and original receipts for all project expenses (labor, materials,
etc.) are required for reimbursement. Village
Fagade Improvement Program funds are distributed on a first - come - first -serve basis.
• Exterior improvements, visible from Big Basin Way
• Painting, signage, lighting, and exterior repair projects that follow Village Design
Guidelines
• Addition of shade feature to storefronts, particularly awnings
• Landscaping that beautifies Big Basin Way streetscape
• Improvements that enhance design elements and architectural features, such as inlaid
tile, brick, decorative cornices, enhanced doors or window treatments
Examples of Approved Projects:
• New exterior paint Installation or replacement of canvas awning
• Improvements to sidewalk seating areas, including landscaping
• New signage or improvements to existing signage Enhancements to doors and
windows, including new trim
• Installation of exterior planter boxes
City of San Clemente, California
http: / /san -cle me nte. o rg /sc /standard .aspx? page id =653
http : / /san -cle mente. o rg /sc /standard . aspx? page id =650
Programs and Incentives
The Los Molinos Business District currently has funds available for the successful and award
winning Los Molinos Business District Fagade and Site Enhancement Grant Program (LMBD
Fagade Grant). In the three year history of the program, there have been substantial
improvements to facades and signage within the District. In addition to the funds provided by
the City, for most projects, all related City fees are waived, allowing additional cost savings to
be passed onto the business /property owners to promote more investment and enhancement
in the District. Funds are available on a first come first serve basis, and funds are still available
for this program.
Grant Program
A fagade and site enhancement program (modeled after the Los Molinos Program) is available
for North Beach commercial properties. The individual grants are up to $999 and are to help
assist existing businesses with signage and improvements that would increase the pedestrian
friendly atmosphere.
M,
City of Santa Cruz, California
http://www.citvofsantacruz.com/index.aspx?page=1 707
The Facade Improvement Program provides grants to businesses or property owners to
enhance and restore their storefronts. Since 1994, more than 100 facade improvement
projects have been completed, aiding over 260 businesses. Facade Improvement grants
prioritize:
1. Painting entire buildings
2. Improving public safety lighting
3. Installing anti - graffiti film coating on display glass windows and doors
If these priorities are met in a grant project budget and design, then the grant may also include
signage, awnings, and limited landscaping. These noticeable improvements help to attract
customers, leverage private investment from owners, and inspire improvements to neighboring
buildings.
Grants are provided as reimbursements to the participant after the project is completed and do
not have to be repaid. The Facade Improvement Program includes:
• Up to $10,000 whole grant for the project
• Up to $5,000 matching grant per storefront when the participant provides a match of
$5,000
• Up to $1,000 beyond the grants to cover the cost of a City - selected designer to help you
choose paint colors and other elements for your unique storefront design
All commercial properties with ground floor retail access to each occupied and operating
storefront are eligible. Proof of three years or more remaining on each storefront lease must be
provided. Properties cannot participate in the program more than once in any ten -year period.
City of Westminster, California
http: // www. westminster- ca.gov /depts /citymanager /econdev /fags. asp
The Commercial Facade Improvement Program is designed to stimulate private investment in
high quality building improvements that contribute to the overall strength of Westminster's retail
centers as shopping and dining destinations. Through this program, the Westminster
Redevelopment Agency will share the cost of improving building exteriors, thereby promoting
joint private /public action and investment, which will complement and enhance redevelopment
efforts.
After a citywide survey of Westminster's commercial areas, along with an assessment of high
visibility corridors and City gateway and entry areas, the City's commercial areas have been
classified using the following priority evaluation criteria below.
Priority Area Evaluation Criteria:
Area 1) Visual and Physical blight at City entryways or high traffic areas
Area 11) Visual and Physical blight not located at entryways or high traffic areas
Area 111) Physical and Economic blighted areas
Area IV) Areas with no Visual /Physical blight, but economically underutilized
Owners and tenants of property within the Areas above are eligible to apply for assistance.
Tenants must have the property owners consent before any improvements are made. In
addition, the grant application must be signed by the property owners.
2.5
The program funds are to be used for exterior building improvements rather than simple
maintenance. Applications will not be accepted to refinance improvements already completed,
nor improvements made to the interior building. The program provides funding of eligible costs
on a reimbursement basis after work has been completed. Any applicant business(es) must
have a current business license and must be in compliance with all municipal codes and be
free of any outstanding violations. In order to receive funds, a completed grant application
must be submitted to and approved by the program administrator prior to the beginning of
work. Grants of up to $30,000 per storefront are available, conditioned upon proper
maintenance of the improvements for 10 years.
Any renovations must result in significant long -term improvements to the building such as:
• Exterior wall repair, re- plastering, and painting
• Landscaping and sidewalk replacement
• Awning purchase, repair, or replacement
• Sign purchase, repair, or replacement
• Lighting purchase, repair, or replacement
• Door and window repair, or replacement
• Roofing improvements
The Commercial Fagade Improvement Program will not reimburse funds for removal of illegal
improvements, and /or routine maintenance.
Funding
Funding eligible property owners and /or tenants who propose fagade improvements can apply
for a grant up to 50 percent of the cost upon completion of improvements. The City's matching
grants are based on the amount of linear footage as shown below, but maybe amended by the
Executive Director given the need of specific projects:
Linear Feet of Facade
Maximum Grant (assuming
50% of total cost
25'
or less
$ 7,000
26'
to 50'
15,000
51'
to 75'
20,000
76'
or more
30,000
City of Fontana (Full Cost Program)
http: / /www.caIredevelop.org/ External /W CPages/ WCWebContent /WebContentPage.aspx ?Cont
entlD =1449
By 2002, Fontana's Downtown was in very poor shape and needed revitalization and a
dramatic visual enhancement. Property owners were scrambling to keep their buildings
occupied with anybody who would pay the rent on time; they were not inclined to make needed
improvements to their buildings. The challenge was to achieve the goals and objectives that
were set down by the City Council acting as the Redevelopment Agency to:
(1) Create a safe and attractive Downtown through the elimination of blight;
(2) Revitalize the economic energy that was once there;
(3) Create a friendly family and community atmosphere; and
(4) Nurture and support the business community as it makes its recovery.
20
Most other city facade programs have historically included matching dollar investment,
forgivable grants, and "not to exceed" dollar amount programs. In most cases, 100%
participation by property owners and /or businesses was rarely achievable resulting in only
moderate, and largely unnoticed or unremarkable, improvement. To achieve the
Council's /Agency's goals and objectives, staff determined that a very non - traditional Fagade
Program approach was necessary.
Fontana opted to implement a facade renovation program in the Core downtown area, along
Sierra Avenue, that would have a maximum visual impact, and hopefully change `perceptions'.
As a first step towards downtown revitalization, passersby needed to "see" a new look to the
downtown. Maximum control over the entire process was paramount. A three - phase,
multiyear program was prepared, and each year a separate block of facades along Sierra
Avenue would be renovated.
The City also decided to use Redevelopment Agency revenues to completely fund the entire
three block facade renovation. The property and business owners are not responsible for
design or construction costs. The next challenge was to secure an 18" Fagade Easement from
the property owners. The City would "own" the first 18 inches of each building front on the
block for a period of ten years. The property owner would receive back 10% ownership of the
building facade every year, achieving total re- ownership of their building facade in the tenth
year. Per the terms of each property's facade easement, after the new facade has been built,
the property owner is required to maintain the new facade and is subject to City ordinances
regarding signage, music, banners, temporary signs, and lighting. If the property or business
changes ownership or character, the new owner /tenant is responsible for new signage and
lighting costs. Any changes to the facades would be subject to City approval.
The Redevelopment Agency is funding the entire Fagade Renovation program including the
architectural fees and construction costs. Phase 1 construction costs for nine businesses
totaled $688,070.00. The average facade improvement cost was about $50,000.00 per
business.
The innovative approach that the Fontana has taken with the facade renovation program is
both unique, and the concept is easily transferred to other communities. Fontana wanted to
create a successful program that would positively impact the residents, property, and business
owners.
27