HomeMy WebLinkAbout2003-10-20_EQAC_Agaendao�kW�RO CITY OF NEWPORT BEACH
ENVIRONMENTAL QUALITY AFFAIRS
COMMITTEE
c4irpoc+N`r
AGENDA
DATE /TIME: MONDAY, October 20, 2003 — 7:00 P.M.
LOCATION: Police Department Auditorium
870 Santa Barbara Drive
Roll Call
1. Minutes of September 15, 2003 (Draft Minutes Attachment)*
2. Report from Airport Issues Subcommittee on NOP for John Wayne Airport Expansion
3. Review of CEQA Procedures (Attachment)
4. New Projects
a. Environmental documents for Irvine Business Complex office and residential
development
b. Draft EIR for Pacific City, Huntington Beach
c. Supplemental Draft EIR for Centerline
5. Report from EQAC Representative to GPUC
6. Report from EQAC Members on GPAC
7. Report on LCP process
8. Council Member Reports
9. Report from staff on current projects
10. Public Comments
11. Future Agenda Items
NEXT MEETING DATE: November 17, 2003
LOCATION: Police Dept Auditorium
*Attachments can be found on the City's website http://www.city.newport-beach.ca.us. Click on City Council and then
click on Agendas and iWinute.s. The Attachments are also available in the City of Newport Beach Planning Department,
3300 Newport Boulevard. Building C, and 2nd Floor
CITY OF NEWPORT BEACH
ENVIRONMENTAL QUALITY AFFAIRS COMMITTEE
DRAFT Minutes 09 -15 -03
Minutes of the Environmental Quality Affairs Citizens Adviso
Council Chambers, 3300 Newport Boulevard, on September,
Members Present
Richard Nichols, Council Member
arrived at 7:45 p.m.
Robert Hawkins, Chairperson
Cris Trapp, Vice Chairman
Barry Allen
Brent Cooper
Laura Dietz — arrived at 8:10 p.m.
Maggie Fitzgerald
held at the City
Staff Representatives
Sharon Wood, Assistant City Manager
Niki Kallikounis, Planning, _Department Assistant
Members Not Present
Steve Bromberg, Mayor
Phillip Lugar
Gary Borquez
Marge Pantzar
Gus Chabre
Nancy Raney
Thomas Eastmond
Richard Rivett
Ray Halowski
Louis Von Dyl
Carol Hoffman
Others Present
Phillip Bettencourt, Bettencourt &Associates Scott Barnard
Jill Kanzler, Gladstone International
The meeting was called t o order at 7:15 p.m.
A quorum was not present. Chairman Hawkins reordered the agenda to begin with the
discussion items.
3. Discussion of Subcommittee Procedures and Participation
Chairman Hawkins informed the committee that there has been a decline in
member participation in the subcommittees. This problem developed in agenda
item no. 2, the report from the St. Andrew's subcommittee. Chairman Hawkins said
that they needed to enhance the participation.
Chairman Hawkins asked if there were any comments or ideas. Several members
offered suggestions. Discussion ensued. Jennifer Winn noted that, in the past, a
chairperson was appointed to the subcommittee at the time it was formed and that
they go back to that method.
A review was made of some of the current subcommittees and it was noted that the
Airport Issues Subcommittee did not have a chairperson. Maggie Fitzgerald
volunteered to serve on the Airport Issues Subcommittee;''i' `
4. Report from EQAC Representative to GPUC
None.
5. Report from EQAC Members on GPAC
Tom Hyans reported that GPAC discussed the Hazards Assessments.
Sharon Wood reported that GPAC has had four resignations and that she is working
with the City Council Members of GPUC to work on; replacements.
6. Report on LCP Process
Sharon Wood reported that the LCP Certification Committee met twice to discuss
the comments received from the California Coastal Commission staff and the
comments received from all the City review and committees such as GPAC, Harbor
Commission, etc. The LCP committee gave staff direction on some revisions to the
Land Use Plan Ms. Wood said that they have not as yet received comments from
the Coastal Commission's technical and legal staff.
7. - Council MembeirReports
None.
Report_from Staff on Current Projects
Sharon Wood reported on the following:
• South Coast Shipyard
• Regent Newport Beach
• The New Superior Group
• Birch Bay View Plaza II
Jim Miller and Council Member Dick Nichols arrived. There is now a quorum.
E
2. Report from the St. Andrews Subcommittee on the Notice of Preparation (NOP)
Phillip Bettencourt passed handouts to the members and described the project and
the progress and various studies, such as traffic and EIR, made to date. Questions
were asked and discussion ensued.
Laura Dietz arrived.
There was a review of the subcommittee report comments and typos and format
changes were made. There was discussion regarding the parking and the concern
of the committee about the character of use of the gym /classroom building.
Changes were made in the report.
Laura Dietz moved to accept the report as, corrected. Council Member Dick Nichols
seconded the motion. Motion passed unanimously.
1. Minutes of August 18, 2003
Chris Welsh moved to approve the minutes:;: Tom Hyans seconded the motion.
Motion passed unanimously.
9. Public Comments
None.
10. Future Agenda Items
Bio Diesel Presentation to be arranged by Ray Halowski
a Regent Newport Beach NOP in October or November
• St. Mark Presbyterian Church NOP
Chairman Hawkins adjourned the meeting at 8:55 p.m.
J
CEQA -- Introduction Page 1 of 5
Governor's Office of Planning and Research
INTRODUCTION
Overview of the California Environmental Review and Permit.
Approval Process
The California Environmental Quality Act (CEQA) was enacted in 1970 as a system of checks and
balances for land -use development and management decisions in California.
Environmental review is characterized by an Environmental Impact Report (EIR). The EIR records the
scope of the applicant's proposal and analyzes all its known environmental effects. Project information is
used by state and local permitting agencies in their evaluation of the proposed project
In 1977, the California Legislature passed the California Permit Streamlining Act (PSA) and
established the Office of Permit Assistance (OPA). The creation of both OPA and PSA sought to
remedy a complicated and often unresponsive permitting processes. The Permit Streamlining Act
addressed some of CEQA's shortcomings: namely, that it lacked a calendar by which applicants and the
public could expect the prompt review of a given project. The PSA added time- lines.and deadlines to
expedite government review of proposals. While this did not guarantee the approval of projects or their
favorable review, it did give applicants and the public an orderly, standardized process for filing reports
and actions.
California's environmental review is rigorous by anyone's standards. In most cases it extends beyond
federal statutes established under the National Environmental Policy Act (NEPA).
Cities and counties regulate land use by way of planning, zoning, and subdivision controls.
There are currently 58 counties and over 470 incorporated cities in California, each with the same
authority for land use regulation. Local government authority is granted by State law. Cities and
counties have legislative power to adopt local ordinances and rules consistent with state law.
State agencies regulate the private use of state land, resources and certain activities of
statewide significance. There are at least 21 state agencies which are or may be directly involved
in the approval of development projects. The permitting authority of each state agency is
established by statute, usually with additional administrative rules promulgated by the agency.
Federal agencies have permit authority over activities on federal lands and over certain
resources which have been the subject of congressional legislation: i.e., air and water quality,
wildlife, and navigable waters. The U.S. Environmental Protection Agency generally oversees the
federal agencies. In addition, the EPA regulates activities such as the disposal of toxic wastes and
the use of pesticides. The responsibility for implementing some federal regulatory programs, such
as those for air and water quality and toxics management, has been delegated to specific state
agencies.
The Development Permit Process
In California, the development permit process is coordinated with the environmental review process
under CEQA. Every development project which is not exempt from CEQA must be analyzed by the lead
agency to determine the potential environmental effects of the project. This analysis is required by state
law. It must be completed within specified time periods which are concurrent with the time periods in
which an agency is required to approve or deny the project.
http: / /ceres.ca.gov/ topic/ env _law /ceq,i/guidelines /intro.html 09/16/2003
CEQA -- Introduction Page 2 of 5
Once the lead agency is identified, all other involved agencies, whether state or local, become
responsible or trustee agencies. Responsible and trustee agencies must consider the environmental
document prepared by the lead agency and do not, except in rare instances, prepare their own
environmental documents. The procedure for issuing each particular development permit is governed by
the particular law which establishes the permit authority and by the California Permit Streamlining Act.
Summary of the CEQA and Permit Application Process
There are three major phases in the development process as provided by CEQA and the PSA:
• The Pre Application Phase,
• The Application Phase, and
• The.ReviewPhase.
I. Pre - Application Phase:
The Pre- Application Phase begins when the developerapplicant has completed the conceptual and
preliminary design work for a project and is ready to prepare a project proposal. At this point, enough
information should be available to describe project activities and to identify the project's proposed
location. The primary objective of this phase is to identify the appropriate permitting agencies and to
collect as much relevant background information possible.
Many proposals (projects) will require special studies either before or during the formal processing of
the application. All state and local agencies are required to list the type of information and the criteria
they will use in evaluating a project application. DeveloperApplicants may request preapplication
conferences or "scoping" meetings with the permitting agencies to discuss how agencies' specific rules
will apply to their proposed projects.
By the end of the preapplication phase, the developer- applicant should have a good understanding of the
detailed project information required, a list of probable permitting agencies, and an indication of the
degree of environmental analysis required by the agencies.
At this point, the applicant will learn which agency (if there will be more than one permitting agency)
will be the "lead agency." The lead agency is the single agency responsible for determining the type of
environmental analysis CEQA requires. In addition, the lead agency must prepare the environmental
review document it calls for. The agency with the greatest authority over the project will usually assume
the lead agency role. Criteria for determining the lead agency are provided in the. CEQA Guidelines at
Section 15051. In the event of a dispute over the lead agency status between or among agencies, the
Office of Planning and Research may designate the lead. However, once the lead agency is identified, all
other involved agencies, whether state or local, become responsible or trustee agencies.
II. The Application Phase:
The Application Phase begins with the filing of the necessary permit application forms along with a
detailed project description. Supporting documents must also be filed, where CEQA requires, with the
respective agencies. Unless otherwise specified, the sequence of filing applications is left up to the
applicant. It must be noted, however, that the failure of some agencies to accept an application until
certain other permit approvals have been granted does not in any way impact the time limits under
which the agency must act.
http: / /ceres.ca.gov /topic/ env _law /cega/guidelines /intro.html 09/16/2003
CEQA -- Introduction Page 3 of 5
During this phase, each receiving agency must review the submitted application to determine if the
individual filing is complete. The lead agency must make its determination in writing within 30 days.
Should the agency fail to make its determination within 30 days, the application will be deemed
accepted as complete by operation of law. If the application is determined to be incomplete, the agency
must specify the deficiencies and the manner in which the deficiencies may be corrected. The developer -
applicant may then refile the corrected application. Upon refrling, the agency has another 30 days to
review for completeness. If the application is again determined to be incomplete, the agency must
provide a process for an appeal of the determination and reach a decision within 60 days. Further dispute
may be adjudicated. This step is critical to the process. A permit may not be denied for failure to provide
information not requested.
Once an application is accepted as complete, the lead agency has six months to approve or disapprove a
project for which an Environmental Impact Report (EIR) has been certified. The time limit in all other
cases is three months after a negative declaration is adopted or an exemption issued.
11I. Review Phase:
The Review Process begins immediately with the completion of the specific application. In recognition
of §65941 of Chapter 4.5 of the Permit Streamlining Act, the lead agency will simultaneously review the
project under the applicable permit rules and conduct the necessary environmental analysis. Permit rules
vary depending on the particular permit authority in question, but the process generally involves
comparing the proposed project with existing statutes. The procedure usually results in a public hearing
followed by a written decision by the agency or its designated officer. Typically, a project may be
approved, denied, or approved subject to specified conditions.
The CEQA procedure involves a number of steps which produce an environmental document examining
the lead agency's as well as the responsible and /or trustee agencies' permit decisions.
The first step in the CEQA process is to determine whether the proposed project is subject to CEQA.
There are a number of statutory and categorical exemptions. If the proposal is not covered by CEQA, the
lead agency may file a Notice of Exemption. If the project is covered by CEQA, the lead agency must
prepare an Initial Study to determine whether the project may have a significant adverse impact on the
environment. The initial study must be completed within 30 days after an application is accepted as
complete.
If the Initial Study shows that the project will not have a significant effect on the environment, the lead
agency must prepare and circulate a Negative Declaration. Where potential significant effects are
shown, but the project is modified such that the effects are rendered insignificant, the lead agency must
prepare and circulate a mitigated Negative Declaration. In either case, the Negative Declaration must be
circulated for review for 30 days and must be ready for adoption by the lead agency within 105 days
after a completed application is accepted.
If, on the other hand, the Initial Study shows that the project may have one or more significant effects,
the lead agency must circulate a Notice of Preparation (NOP) in anticipation of preparing an
environmental impact report (EIR) and must consult with responsible and trustee agencies as to the
content of the environmental analysis. Responsible agencies must respond to the NOP within 30 days. If
a responsible or trustee agency fails to respond, the lead agency may assume that the responsible agency
has no response to make. Further, if a responsible agency fails to respond or responds incompletely, the
responsible agency may not subsequently raise issues or objections regarding the adequacy of the
environmental review.
http: / /ceres.ca.gov /topic /env_law /cega /guidelines /intro,html 09/16/2003
CEQA -- Introduction Page 4 of 5
At the close of this period, the lead agency must prepare and circulate a Draft Environmental Impact
Report (DEIR). All concerned agencies and the public may review the DEIR. All comments on the
DEIR must be made within the 45 day review period.
At the close of the review and comment period, the lead agency must respond to the comments received.
Comments from responsible or trustee agencies shall be limited to those project activities which are
within the agency's area of expertise, are required to be carried out or approved by the agency, or will be
subject to the exercise of powers by the agency.
The lead agency prepares and certifies a Final Environmental Impact Report (FEIR). If the lead agency
approves the project, it must find that each significant impact will be mitigated below the level of
significance where feasible, and that overriding social or economic concerns merit the approval of the
project in the face of unavoidable effects.
With the CEQA and permit review process completed, the lead agency must approve or deny the permit
within 6 months of certifying the EIR or within 3 months of adopting the Negative Declaration and file a
Notice of Determination (NOD). Responsible agencies must then act within six months after the lead
agency's action or, if the developerapplicant has not already filed an application with a responsible
agency, within six months from the time the application is filed (except as modified under Health and
Safety Code §25199.6).
Environmental documents for projects involving one or more state agencies or involving issues of
areawide or statewide significance must be sent to the State Clearinghouse for distribution to interested
state agencies. The State Clearinghouse will link the lead agency with the responsible state agencies.
Special Concerns in the CEQA/Permit Process
There are several key points that agencies, developer - applicants and the public must be aware of in order
to avoid misunderstandings and delays:
• The time limits for completing the requirements of CEQA and acting on a permit are concurrent
and not consecutive. The Permit Streamlining Act discourages a government agency from
requiring a completed EIR before accepting a permit application.
• CEQA can help resolve public policy disputes relating to development projects. Technical issues
that find their way into policy disputes, no matter how dependent on scientific considerations, are
inherently value - laden. CEQA specifically addresses the potential for conflicting expert
discussions and mandates that all sides of an issue are considered.
• Under the Permit Streamlining Act, if a public agency does not approve or deny a project within
the statutory time limit, the project may be deemed approved. The proponent must give notice to
invoke the Permit Streamlining Act.
• The Permit Streamlining Act time limits are not applicable to all permit applications. Time limits
only apply to development projects as defined in the PSA. The Streamlining Act specifically
excludes ministerial permits such as certain building permits. The time limits do not apply to
legislative actions such as the adoption or amendment of zoning ordinances. The time limits do
not operate where a federal law specifies a longer or shorter period for action and, with the
consent of the developer- applicant, the lead agency may waive the time limit if a joint
environmental document is being prepared with a federal permitting agency.
• Where a public agency (or series of agencies) will issue more than one permit for a project, the
agency(ies) makes each approval separately, but must still act upon the entire project within the
statutory time limit.
65
http: / /ceres.ca.gov /topic/ env _law /cega/guidelines /intro.html 09/16/2003
CEQA -- Introduction
Page 5 of 5
All Permit Streamlining Act time limits are maximum. Public agencies should act in a shorter
time whenever possible.
Members of the public may challenge, in court, a wide variety of public agency action and
inaction, but only if they first present those challenges to the agency itself within 30 to 180 days
after the occurrence of the challenged action, depending upon whether an NOD was filed or not
by the agency.
Assistance for Developer - Applicants
The permit and environmental review processes are complicated. There are often several agencies and
many persons involved. Hundreds of laws and rules may apply to a particular project. Agencies are
constantly revising their procedures and changing personnel. The Legislature and the Governor created
the Office of Permit Assistance (OPA) within the Trade and Commerce Agency to help project
applicants, localities and the public to understand CEQA and the permitting process. The primary
mission of the Office of Permit Assistance is to provide assistance and information to parties interested
in the permit process.
• A single point of contact for state agency permits is available at the Office of Permit Assistance.
Any questions about the permit process will be answered promptly.
• All state or local permits required for any project can be identified. The Office can convene all
state agencies at one time to identify and explain which permits are required for a project.
• Seeping meetings can be arranged through the Office. The Office convenes meetings of the
environmental staff of state and local agencies who will be involved in the CEQA review of
projects. These meetings provide developer - applicants and environmental consultants with a
chance to discuss all environmental issues and concerns early in the process in order to avoid
wasted effort and unwarranted surprises in the EIR process.
• The Office of Permit Assistance has authority to convene meetings to resolve questions or mediate
disputes. When uncertainties or disagreements among agencies stall the permit process, the Office
may be called upon to provide a forum for resolving the problem. Not every problem can be dealt
with in this manner, but when appropriate, the process can be very useful.
The Office of Permit Assistance can be contacted by telephone at 916/322 -4245 (ATSS 473 - 4245). Its