HomeMy WebLinkAboutSS2 - Review of 14-15 Budget - CIP PowerPointMay 13, 2014
Agenda Item No. SS2
Public Works Department
FY 2014 -2015 Capital Improvement Program
Dave Webb, P.E.
Director of Public Works
City Council Study Session
May 13, 2014
Capital Improvement Program
• Sets Priorities and Appropriates Funds
• Provides a Basis for Project Planning and Identifies
Potential Conflicts
• Develops and Constructs Identified Public
Improvements
• Addresses Significant Maintenance Projects
• Responds to Changing Priorities and Conditions
(which evolve — thus so does the CIP)
Recap of the 2013 -2014 CIP
On Schedule
(Completed
within 2 months)
Goal 85%
Actual
82%
Within Budget
(Plus 10%
Contingency)
Goal 90%
Actual
71% *
✓ 17 Major Construction
Projects Completed"
Total Value: $20.98 Million
* Six projects approved with more then 10% to capture favorable pricing
** Projected through June 30, 2014
Within Budget
(Plus Approved
Contingency)
N/A
Actual
94%
mm
160
140
120
100
m
M.,
m
c 20
0
00
CIP Funding History
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
PW - 33 33 33 33 33 34 33 33 33 33 32 33 35 34 35
FTE
350
300
250
200
150
100
50
0
Workload Indicators
Professional Services Agreements
05/06 06/07 07/08 08/09 09/10 10/11 11/12 12/13 13/14
Contract Services increased 353% since 2005/06
Projects Currently in Construction
Project Name
• Annual Sidewalk, Curb & Gutter Improvements
• Lifeguard Headquarters Rehabilitation
• Balboa Boulevard Beautification
• Dolphin Deep Water Well Rehabilitation
• CdM Water Transmission Main
• Newport Coast Community Center Stage
• Mariners /WestCliff Area Streetlight Rehabilitation
• Sunset Ridge Park
• Marina Park
Scheduled
Completion
May 2014
July 2014
July 2014
August 2014
Summer 2014
Fall 2014
Fall 2014
Spring 2015
Spring 2016
Projects Nearing Construction
Project Name
• 151h St. / Monrovia Ave. Landscaping
• Various Residential Street Rehabilitation
• Traffic Signal Modernization Phase 6
• San Miguel Park Restroom /Picnic Area
• Newport Heights Street Slurry
• Harbor Piers Maintenance
• Eastbluff Bike Lanes
• Storm Drain - Trash /Debris Removal Devices
• BCR Auxiliary Maintenance Yard
Construction Start
June 2014
June 2014
June 2014
June 2014
July 2014
July 2014
July 2014
July 2014
August 2014
Projects Currently in Design
Project Name
• Sunset View Park Addition
• Ocean Piers Maintenance
• Corona del Mar Pocket Park
• East Coast Highway Signal Rehabilitation
• Campus Dr. & San Joaquin Hills Rd. Pavement
• Newport Blvd. Water Main Rehabilitation
• Dover Dr. & Westcliff Dr. Rehabilitation
• Ocean Blvd. & Marguerite Concrete - Phase 1
Construction Start
July 2014
September 2014
October 2014
October 2014
October 2014
November 2014
January 2015
January 2015
And Much More...
Traffic and Specialty Studies Underway
• General Plan Update
• Local Coastal Plan
• Lido House Hotel
• JWA Airport Traffic Study
• OCTA - PCH Corridor Study
• Mariners Mile Circulation /Land Use Study
• CdM & Balboa Parking Studies
Special Projects and Priorities
600
• Balboa Blvd 20a Utility Undergrounding 500
• 6 Private Utility Assessment Districts
Water Taxi Study 400
• Mooring Service Changes 300
• Seawalls and Seawater Rise 200
• Renewal of Countywide NPDES Permit 100
• Coordination with Non -City Projects:
0
Other Agencies, Utilities, Private Developments
Bicycle Master Plan
Major Development Projects
➢ Explore Ocean
➢ Back Bay Landing
➢ Balboa Marina West
➢ Westcliff Medical Office
➢ San Joaquin Plaza Apartments
Encroachment Permits
2007 2008 2009 2010 2011 2012 2013 2014
Continued Progress Being Made
• Neighborhood Beautification On -Going
• Several New Parks Underway
• Several Existing Parks being Rehabilitated
• Continue with a $5M General Fund Contribution to Capital
Projects
CIP General Fund Budget
$7,000,000
$6,000,000
$5,000,000
$4,000,000
$3,000,000
$2,000,000
$1,000,000
$
FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15
Continued Progress Being Made
• City Pavement Condition Improving
Pavement Condition Index (PCI)
m
m
81
a
79
fC
CC 77
d75
73
71
2009 2011 2013
Arterial
- Residential
-*--Citywide
Continued Progress Being Made
Traffic Signal System Upgrades Since 2007
■ 6 New Traffic Signals Installed
■ 100 of 123 Traffic Signals Modernized
■ 31 of 39 Planned CCTV Cameras Installed
■ 29 of 123 Traffic Signals Rehabilitated
City Owned Streetlight Upgrades Since 2009
■ 486 of 6,464 Streetlights Converted to LED's
■ 9 Street Light Circuits Rehabilitated
■ 247,272 KWH Saved Each Year = — $120,000 Cost Savings
Significant Capital Investment in Newport Harbor
• Upper & Lower Bay Dredging
• Rhine Channel Cleaned & Dredged
• Rhine Channel Wharf & Pier Construction
Continued Progress Being Made
Facilities Replaced, Rehabilitated or Upgraded since 2007
• Newport Theater Arts Center Rehabilitation
• Mariners Park Restroom Replacement
• Little Corona Beach Restroom Replacement
• OASIS Senior Center Replacement
• Community Youth Center in CdM Rehabilitation
• Carroll Beek Community Center Rehabilitation
• City Hall Replacement
• Central Library Addition
• Lifeguard Headquarters Rehabilitation
• Utility Yard Building No.3 Remodel
• Police Facility Lobby Remodel
So How are Projects Selected for the CIP?
• Identified by Council, Community or Staff
• Developed to Support Council Goals and Objectives
• City Master Plans
• Facilities Financing Plan
• Facilities Maintenance Plan
• Pavement Management Plan
• Water Master Plan
• Sewer Master Plan
• Streetlight Master Plan
• Tidelands Capital Plan
• Required by Federal, State or Legal Action
Address City Council Priorities
Neighborhood Revitalization:
• Rehabilitate Aging Public Infrastructure
• Improve Citywide Vehicle, Cycle and Pedestrian Flow
• Install New or Improved Landscaping
• Encourage Private Redevelopment
• Building /Improving Parks & Recreational Facilities
• Overhead Utility Undergrounding
Address City Council Priorities
Tidelands Management:
• Improve Boating and Visitor - Supporting Facilities and
Services
• Repair /Maintain Beaches, Piers, Bulkheads and Seawalls
• Dredging
• Improve Water Quality
Proposed 2014 -15 CI P
Includes 82 Items
• Projects, Programs, Studies, Re- Budgets
• Organized by Categories
Total = $61.7 Million
• $40.3 Million New Funding
• $21.4 Million Re- Budgets
= Lots Getting Done
fir, r
L
.d.!� go NO
� a3fld
Proposed Capital Improvement Program for Fiscal Year 2014/2015
PROJECT PORTFOLIO
■��+
kill
� 5 911
_r. -
; _�•
L
.d.!� go NO
� a3fld
Proposed Capital Improvement Program for Fiscal Year 2014/2015
PROJECT PORTFOLIO
Facilities
$8.8 Million
• Big Canyon Reservoir Auxiliary Maintenance Yard (Construction)
• Existing Facility Capital Maintenance - Master Plan (Construction)
(Carpet, Painting, HVAC Replacement, etc.)
• Newport Aquatic Center Restroom Renovation (Construction)
• San Miguel Park Restroom & Picnic Structure (Construction)
• West Newport Community Center (Concept Development)
Facilities 'continued)
• Corona del Mar Fire
Station and Branch
Library Replacement
(Concept /Design /Construction)
• Lido Fire Station Replacement (Concept /Design)
4. ttt
,
Street] and Drainage
$24.4 Million $8 Million for Arterial Streets
• $14 Million for Local Streets & Alleys
• $1 Million for Streetlights
• $561,000 for Drainage
• $934,530 for Street Landscaping
Arterial Streets
• Dover Drive / Westcliff Drive Pavement & Median Rehabilitation
(Construction)
• Irvine Avenue Pavement & Median Rehabilitation (Design /Construction)
Santiago to Monte Vista
• Newport Blvd at
32nd Street
Modification
Via Lido to 301h Street
(Design /Construction)
I I
I
,
m�
• Old Newport Blvd / West Coast Highway Modification (Design)
• Various Arterial Street Pavement Overlay (Design /Construction)
MacArthur, San Miguel, Campus, San Joaquin Hills
Local Streets and Alleys
• Annual Slurry Seal Program (Design /Construction)
• Corona del Mar Concrete Streets Phases 1 & 2
(Concept /Design /Construction)
• Bay Ave and Area Pavement Reconstruction
(Construction)
• Newport Heights Alley Reconstruction
(Design /Construction)
• Annual Sidewalk, Curb and Gutter Replacements
(Design /Construction)
• Park Ave Bridge Replacement over Grand Canal
(Construction)
x
d
m
[�i
k--
y
�P
j
15th Street / Balboa Blvd. Reconstruction (Design)
i
n
Streetlights and Storm Drains
Streetlight Replacement (DesignIConstruction)
System Repairs
(Construction)
Street Landscape Projects
• 15th Street and Monrovia Avenue (Construction)
• Newport Boulevard Landscaping (Concept /Design)
301h St. to Balboa Blvd.
• West Coast Highway Landscaping (Design)
Santa Ana River to Newport Blvd.
• Corona del Mar Entry Plaza (Design /Construction)
• Various Spot Landscape Enhancements
(Design /Construction)
Bristol St. South Landscaping
Transportation $5.8 Million
� J
1
• Mariners Mile Highway Configuration & Land Use Review (Concept)
• Newport Blvd Traffic Signal Synchronization (Construction)
• Bristol St Traffic Signal Synchronization (Construction)
• East Coast Highway Signal Rehabilitation (Construction)
• Traffic Signal Modernization Phase 6 (Construction)
San Joaquin Hills Rd., Newport Coast Dr.
• Traffic Signal Modernization Phase 8 (Design /Construction)
San Miguel Rd., Bayside Dr. /Marine Ave., Birch St
Transportation - Continued
• Superior Ave. /Coast Highway Pedestrian
Crossing /Intersection Imprv. (Concept)
• Ea st b I uff Bike Lane (Construction)
• Newport Beach Bike Lane Project (Construction)
• Bonita Canyon Sports Park Parking
Improvement (Construction)
• Tustin Ave. Modifications (Design /Construction)
Santiago Dr. to 231d St.
MAY USE
ULL LANE
Parks, Harbors, and Beaches
$6./ Million
• Lower Castaways Park (Concept)
• Cd M Pocket Park (Construction)
• Sunset View Park (Construction)
Upper Portion Only
• Back Bay View Park Enhancements (Design /Construction)
• Bonita Creek Park Synthetic Turf (Design /Construction)
• San Joaquin Hills Park Pickleball Courts (Construction)
• Spyglass Hill Reservoir Park Rehabilitation (Construction)
Parks, Harbors, and Beaches
continued
0
0
0
0
0
0
0
Balboa Island Seawalls (Design)
Beach Sand Management (Construction)
Central Ave Public Pier (Design /Construction)
Ocean Piers Maintenance (Construction)
Harbor Piers Maintenance (Construction)
Mooring Field Realignment (Construction)
Tidegate Retrofits and Upgrades (Design /Construction)
Harbor -wide Seawalls & Bulkheads (Design /Construction)
I.
�il�
Water Quality and Environmental
$8.7 Million
• Bayview Heights Drainage and Runoff Treatment (DesignIConstruction)
• Big Canyon Wash - Water Quality & Restoration (Design /Construction)
• Domingo Drive Litter Removal Device (Design /Construction)
• Little Corona Infiltration Gallery (Design /Construction)
Santa Ana Delhi Regional Project (DesignIConstruction)
Semeniuk Slough Dredging (Design /Construction)
Storm Drain Litter Interceptors (Design /Construction)
Turf Replacement /Irrigation Retrofits (Construction)
Water Conservation Irrigation Controller Replacements (Construction)
Water System
$6 Million
w
�1
a -
I A
w1 a
I'
r
c�
• Newport Boulevard Water Main Rehabilitation (Design /Construction)
• Dolphin and Tamura Well Rehabilitation (Design /Construction)
• SCADA System Upgrade
• Water Main Master Replacement Program (Design /Construction)
Wastewater System
$627,954
Saint James Road Sewer Relocation (Construction)
• Wastewater Master Plan Improvements (Design /Construction)
Miscellaneous
$575,000
• Balboa
Village
Entry Arch
Sign (Design /Construction)
• Balboa
Island
Entry Arch
Sign (Design /Construction)
• Arts and Culture Master Plan
• Local Coastal Program Implementation
CIP Budget Summary
Category
Re- budget
New Budget
%
Total
Facilities
$1,014,900
$7,800,000
14%
$8,814,900
Streets & Drainage
$8,704,528
$15,701,000
40%
$24,405,528
Traffic
$2,853,295
$3,013,482
9%
$5,866,777
Parks, Harbors & Beaches
$2,874,617
$3,883,600
11%
$6,758,217
Water Quality /Environmental
$4,312,964
$4,401,780
14%
$8,714,744
Water
$1,280,300
$4,750,000
10%
$6,030,300
Wastewater
$227,954
$400,000
1 %
$627,954
Miscellaneous
$175,000
$400,000
1 %
$575,000
Total
j $21,443,558
$40,349,862 1
100%
j $61,793,420
36
Proposed CIP — by Funding Source
Wastewater Enterprise
$rnn ,„
Facilities Maintenance
$1,525 4%
Major Facilities
Financing Plan
$8,575 21%
Building Excise
$284 1%
New = $40,349,862
Water Enterprise General Fund
$4,900 12% $5,200 13%
Measure M Fair Share Competitive
$3,2008% $4,676 12%
Gas Tax
,625 11%
Tidelands
$2,3606%
ontributions
?4,406 11%
Dollars in Thousands
The Great News
✓ Continuing a $5M General Fund Contribution
✓ Neighborhoods are Being Beautified
✓ Parks being Added and Upgraded
✓ City Pavement Condition Improving
✓ Capital Investment in Newport Harbor
✓ Traffic Signal Synchronization in Final Phases
✓ City Facilities are being Rehabilitated and
Modernized
Need Direction
MacArthur Blvd Slope Landscaping Enhancement
West Side of MacArthur along Big Canyon
• Work with Big Canyon to Add Irrigation & Landscaping to Slope Face
Hydro- Seed /Irrigation /Some Shrubs & Trees
• Approx. 143,000 SF of Unimproved Slope Area
• Estimated Cost = $290,000
Questions &Comments
%L'-'FOai
Public Works Department
A Well- Engineered Machine
Protecting and Providing Quality
Public Improvements and Services
www.newportbeachca.gov /budget