HomeMy WebLinkAbout04 - Santa Ana Heights Pavement Restoration NOCTO:
FROM:
PREPARED BY:
PHONE:
TITLE:
ABSTRACT:
CITY OF
NEWPORT BEACH
City Council Staff Report
June 24, 2014
Agenda Item No. 4.
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
David A. Webb, Public Works Director- (949) 644 -3330,
dawebb @newportbeachca.gov
Patrick Arciniega, Senior Civil Engineer
949 - 644 -3347
Santa Ana Heights Pavement Restoration Project - Notice of Completion and
Acceptance of Contract No. 4707 (CAP11 -0022)
On February 26, 2013, City Council awarded Contract No. 4707, Santa Ana Heights Pavement
Restoration Project to All American Asphalt, for a total contract cost of $1,156,156 plus an
$115,000 allowance for contingencies. The required work is now complete and staff requests
City Council acceptance and close out of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for
the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of
Completion has been recorded in accordance with applicable portions of the Civil Code; and
c) Release the Faithful Performance Bond one year after acceptance by the City Council.
FUNDING REQUIREMENTS:
Funds for the construction contract were expended from the following accounts:
Account Description
Santa Ana Pavement Restoration
Slurry Seal Program
IRWD Contribution
Account Number
7459- C5100879
7013- C2001011
7251- C5100879
Total:
Amount
$ 1,323,189.81
$ 37,372.18
$ 115,724.64
$ 1,476,286.63
DISCUSSION:
The City of Newport Beach annexed East Santa Ana Heights in July 2003. In concert with the
County of Orange, Newport Beach began to manage and complete approved capital projects
formed prior to annexation under the County of Orange's Redevelopment Agency (County
RDA). One of these County RDA projects included undergrounding overhead utilities along
Cypress, Mesa (and more), restoring the existing streets & improving the multi -use trail system
along Cypress and Mesa. This County RDA project was broken down into two separate City
construction projects.
The first City project administered was to underground the overhead utility lines running along
Mesa Drive and Cypress Street. This project served two purposes; the first was to remove the
unsightly overhead lines and the high concentration of utilities that lined both sides of Cypress
Street; the second was to improve pedestrian and equestrian access to the sidewalks and
horse trail system as many of the existing utility poles were located directly in the path of the
horse trail or sidewalks. At certain locations, the poles severely restricted the horse trail width.
The City facilitated the formation of an Underground Utility District, provided construction
inspection, and assisted with management of the project. Work began with the undergrounding
of the overhead utilities in June 2009 and completed with the last conversions of the private
property services in March of 2012. As a result of the utility undergrounding project, numerous
street pavement trenches & patches, trail /sidewalk patches, as well as grading issues caused
by the undergrounding trenching and pole removals needed to be addressed.
The second City project, the Santa Ana Heights Street Rehabilitation project was designed to
repave the area streets, re -grade and improve trails, repair and replace sidewalks, and address
ADA access requirements resulting from the overhead utility undergrounding project. This
street and trail /sidewalk rehabilitation project was advertised in the Fall of 2012, just ahead of
the State mandated County RDA closure deadline for the County of Orange. A summary of the
final cost is as follows:
Overall Contract Cost/Time Summary
The work necessary to complete this contract included construction of missing and damaged
sidewalk, curb and gutter, curb access ramps, driveways, horse trail and railing, storm drain
improvements, Cypress street end re- landscaping, sub - surface utility relocations,
reconstructing portions of the street, cold milling and placement of an asphalt pavement
overlay on Cypress Street, Mesa Drive and Orchard Drive. In addition, the following safety
improvements were completed on Mesa Drive between Cypress Street and Mesa Birch Park;
connecting a missing horse trail link on the south side of the street, connecting a missing
% Due
Awarded
Final Cost
Contingency
to
% Due to
Contract
at
Allowance
Actual Contract Change
Directed
Unforeseen
Amount
Completion
Change
Change
$1,156,156.00
$1,476,286
10% or less
+27.7%
14.1%
13.6%
Allowed Contract Time
100
Actual Time Under ( -) or Over ( +)
0
(days)
The work necessary to complete this contract included construction of missing and damaged
sidewalk, curb and gutter, curb access ramps, driveways, horse trail and railing, storm drain
improvements, Cypress street end re- landscaping, sub - surface utility relocations,
reconstructing portions of the street, cold milling and placement of an asphalt pavement
overlay on Cypress Street, Mesa Drive and Orchard Drive. In addition, the following safety
improvements were completed on Mesa Drive between Cypress Street and Mesa Birch Park;
connecting a missing horse trail link on the south side of the street, connecting a missing
sidewalk link on the north side of the street to ensure ADA access, and completing the work
needed to correct a sight distance issue with the street grade. This portion of the job along
Mesa also required modifications to the drainage flow lines on both sides of the street, which
impacted resident frontages resulting in an assortment of private grading, wall, driveway, and
landscape modifications and replacements. The project originally included approximately
$100,000 for restoring and repairing anticipated resident frontage improvements, however
additional frontage work and contract change orders were necessitated as a result of varying
site conditions; property owner negotiations over adequate replacement of, and connection to
existing improvements; as well as several safety modifications to address concerns raised by
the equestrian community during construction.
Further large change orders were generated due to strict water line standards required by the
Irvine Ranch Water District (IRWD). Over the course of constructing new curb and gutter
within the project, it was necessary to relocate ten IRWD water meters. IRWD policy required
a new water service lateral be installed from the main to the meter as part of these meter
relocations. This cost was unforeseen in design and added substantially to the change order
total. All IRWD related costs are reimbursable through a prior signed agreement between the
City of Newport Beach and IRWD.
The contract has now been completed to the satisfaction of the Public Works Department. A
summary of the contract cost is as follows:
Original bid amount:
$1,156,156.00
% of actual cost
Cost Reduction due to reduced bid
$11,175.00
1.0%
items constructed:
Private Property interface related
$119,133.00
10.3%
change orders:
City directed change orders:
Flagship Rd., chain link fencing, SCE
$52,869.00
4.6%
utility
Unforeseen change orders: IRWD,
survey design, landscape irrigation,
$159,303.00
13.8%
utility relocation
Total change orders:
$320,130.00
27.7%
Final contract cost:
$1,476,286.00
The actual cost of bid items constructed was $11,175.00 less than the original bid amount due
to slightly less asphalt tonnage used than originally estimated. The final contract cost was
approximately 27.7% above the original bid amount with change orders totaling $320,130.00.
IRWD's portion of extra work that is being reimbursed on this job totaled $115,724.64.
Santa Ana Heights Pavement Rehabilitation project was awarded on February 26, 2013
however, the notice to proceed could not be issued until funding was secured from the County
of Orange's RDA. Per the specifications for this job the contractor was required to delay
construction until funding was in place. The City issued the notice to proceed on May 20,
2013, which allowed for a 60 -day construction schedule. The original completion date was
hoped to be August 21, 2013. Due to scheduling and coordination issues associated with the
necessary underground utility relocations, the project was delayed for approximately six
months. During this time Southern California Edison, AT &T, Time Warner Cable, Southern
California Gas, and IRWD water services were relocated or upgraded prior to restoration of the
street, curb, gutter and sidewalk. Taking into account the delays associated with necessary
utility relocations, the project began significant street construction in mid - December 2013. On
April 28, 2014 the project was substantially complete. Due to the delays for these utility
relocations, the contractor was allowed an additional 30 contract working days.
A summary of the project schedule is as follows:
Estimated Completion Date per 2013 Baseline Schedule 8/30/2013
Project Awarded for Construction 2/26/2013
Contract Completion Date with Approved Extensions 4/28/2014
Actual Substantial Construction Completion Date 4/28/2014
This project began over a decade ago thanks to the interest of several Santa Ana Heights
residents, including Barbara Venezia. Later, as chairperson of the Santa Ana Heights Project
Advisory Committee, Ms. Venezia and other members of the SAH PAC championed the project
through several challenging hurdles - from methods of funding to the scope of the trail project
to clean -up items at the end. City staff has appreciated the manner in which all of the former
PAC members as well as staff from Supervisor John M.W. Moorlach's office (including
Supervisor Moorlach himself, Mario Mainero, Ian Rudge, Bob Wilson and others) worked with
us through the process, and wish to thank them for their patience with this very challenging
project.
ENVIRONMENTAL REVIEW:
City Council found this project exempt from the California Environmental Quality Act ( "CEQA ") pursuant to Section
15301(c). This exemption covers the minor alteration of existing public facilities with negligible expansion of the
faci I i ti es i n areas that are not envi ronmental I y sensi tive.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of the
meeting at which the City Council considers the item).
ATTACHMENTS:
Description
Attachment A - Project Location Map
ATTACHMENT A
1R p�IEN�� �,p�sTO
V11VE l
FT
02
PG 5
O�� F
Q�
opcyQ
z
�a
N
CITY OF NEWPORT BEACH
Santa Ana Heights Pavement PUBLIC WORKS DEPARTMENT
Restoration Project Location Map C -4707 1 06/24/2014