Loading...
HomeMy WebLinkAbout05 - Misc Street RepairsTO: FROM PREPARED BY: PHONE: TITLE: CITY OF NEWPORT BEACH City Council Staff Report August 12, 2014 Agenda Item No. 5. HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL David A. Webb, Public Works Director- (949) 644 -3330, dawebb @newportbeachca.gov Frank Tran, Civil Engineer (949) 644 -3340 2013 -2014 Miscellaneous Street Repairs - Notice of Completion and Acceptance of Contract No. 5343 (CAP13 -0014) ABSTRACT: On April 22, 2014, City Council awarded Contract No. 5343 for the Fiscal Year 2013 -14 Miscellaneous Street Repairs project to PALP, Inc., DBA Excel Paving for a total contract cost of $339,077.00 plus a 10% allowance for contingencies. The required work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion; b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with the applicable portions of the Civil Code; and c) Release the Faithful Performance Bond one year after Council acceptance. FUNDING REQUIREMENTS: Funds for the construction contract were expended from the following account: Account Description Account Number Amount Measure M Fair Share 7282- C2002047 $ 344,723.75 Total: $ 344,723.75 DISCUSSION: Overall Contract Cost/Time Summary The work necessary to complete this contract included repairing the existing pavement on various arterials throughout the City as shown on the Location Map. This contract also included isolated dig -outs, asphalt grind and overlay, pruning tree roots and installing tree root barriers. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $339,077.00 Actual cost of bid items constructed: $344,723.75 Contract change order: 0 Final contract cost: $344,723.75 The final overall construction cost was approximately 1.7% over the original bid amount, which is attributed to actual quantities constructed. The contract allowed for 60 consecutive working days to complete the scope of the work. The project was substantially completed on July 11, 2014, which was 20 working days ahead of the allotted contract time. A summary of the project schedule is as follows: Estimated Completion Date per 11/2013 Baseline Schedule: August 29, 2014 Project Awarded for Construction: April 22, 2014 Completion Date per Contract & Approved Extensions August 7, 2014 Actual Substantial Construction Completion Date: July 11, 2014 ENVIRONMENTAL REVIEW: City Council found this project exempt from the California Environmental Quality Act ( "CEQA ") pursuant to Section 15301(c). This exemption covers the minor alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Description Attachment A - Location Map % Due Awarded Final Cost at Contingency to % Due to Contract Completion Allowance Actual Contract Change Directed Unforeseen Amount Change Change $339,077.00 $344,723.75 10% or less +1.7% 0% 1.7% Allowed Contract Time 60 Actual Time Under ( -) or 20 (days) Over (+) The work necessary to complete this contract included repairing the existing pavement on various arterials throughout the City as shown on the Location Map. This contract also included isolated dig -outs, asphalt grind and overlay, pruning tree roots and installing tree root barriers. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $339,077.00 Actual cost of bid items constructed: $344,723.75 Contract change order: 0 Final contract cost: $344,723.75 The final overall construction cost was approximately 1.7% over the original bid amount, which is attributed to actual quantities constructed. The contract allowed for 60 consecutive working days to complete the scope of the work. The project was substantially completed on July 11, 2014, which was 20 working days ahead of the allotted contract time. A summary of the project schedule is as follows: Estimated Completion Date per 11/2013 Baseline Schedule: August 29, 2014 Project Awarded for Construction: April 22, 2014 Completion Date per Contract & Approved Extensions August 7, 2014 Actual Substantial Construction Completion Date: July 11, 2014 ENVIRONMENTAL REVIEW: City Council found this project exempt from the California Environmental Quality Act ( "CEQA ") pursuant to Section 15301(c). This exemption covers the minor alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Description Attachment A - Location Map ATTACHMENT A i 0 BONITA CANYON DRIVE SUPERIOR AVE ® HOAG HEALTH CENTER and SUPERIOR AVE @ HOSPITAL RD A x _ NEWPORT BLVD. MACARTHUR BLVD. NEWPORT COAST DR. SAN JOAQUIN HILLS RD. (26TH TO 30TH STREETS) @ COAST HWY. EAST @ RIDGE PARK RD. FREE RIGHT @ JAMBOREE RD. - - - ---I ol�\ I---------- - - - - -- -- ; 75TH STREETI 15TH STREET - -- �` k'\ - I I I I I I I I I I 11 4-ji L ` ---- �.}--- }J - - - --- ORMOE AVE BOI$A AYE WESIN116TIRAVE BAMTAMIAAYE RE➢IMID AVE 15TH STREET MISC. REPAIRS CITY OF NEWPORT BEACH FY 13 -14 MISCELLANEOUS STREET PUBLIC WORKS DEPARTMENT PAVEMENT REPAIRS — LOCATION MAP C -5343 08/12/2014