HomeMy WebLinkAbout08 - St. James Road Sewer Relocation & CDS Unit InstallationTO:
FROM
PREPARED BY:
PHONE:
TITLE:
CITY OF
NEWPORT BEACH
City Council Staff Report
August 12, 2014
Agenda Item No. 8.
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
David A. Webb, Public Works Director- (949) 644 -3330,
dawebb @newportbeachca.gov
Frank Tran, Civil Engineer
(949) 644 -3340
St. James Road Sewer Relocation and CDS Unit Installation — Award of Contract
No. 4910 (CAP12 -0027)
ABSTRACT:
Staff has received construction bids for the Saint James Road Sewer Relocation project and requests the
City Council's approval to award the contract to Paulus Engineering, Inc. The project includes installation
of a trash - removal device called a CDS unit.
RECOMMENDATION:
a) Approve the project drawings and specifications;
b) Award Contract No. 4910 to Paulus Engineering, Inc. for the total bid price of $539,645.00, and
authorize the Mayor and City Clerk to execute the contract;
c) Establish a contingency of $54,000.00 to cover the cost of unforeseen work not included in the original
contract; and
d) Approve Budget Amendment No. 15BA -007 transferring $185,600 from Account No. 7541- C7001003
(Wastewater Master Plan Improvements) to Account No. 7541- C7002005 (St. James Road Sewer
Relocation) and appropriating $197,000 from the unappropriated General Fund balance to Account No.
7012- C7002005 (St. James Road Sewer Relocation).
FUNDING REQUIREMENTS:
Upon approval of the proposed Budget Amendment, there will be sufficient funding in the following account
for the award of this contract:
Account Description Account Number Amount
General Fund 7012- C7002005 $ 197,000.00
Wastewater Enterprise 7541- C7002005 $ 409,000.00
Total: $ 606,000.00
Proposed uses are as follows:
Vendor
Paulus Engineering, Inc.
Paulus Engineering, Inc.
Harrington Geotechnical,
Various
DISCUSSION:
Purpose
Construction Contract
Construction Contingency
Inc. Geotechnical Testing
Printing & Incidentals
Total:
Amount
$ 539,645.00
$ 54,000.00
$ 11,430.00
$ 925.00
$ 606,000.00
At 10:00 a.m. on July 9, 2014, the City Clerk opened and read the following bids for this project:
TOTAL BID AMOUNT
$539,645.00
$747,585.00
$795,000.00
$849,496.00
$869,767.00*
$942,095.00
$979,795.00
*Bid as read $872,662.00
The low bid amount is 13% lower than the Engineer's Estimate of $622,000. The low bidder, Paulus
Engineering, Inc., possesses a California state contractor's license classification "A" as required by the
project specifications. A check of the contractor's references indicates satisfactory completion of similar
projects for the City of Newport Beach and other public agencies. Paulus Engineering, Inc. also completed
the Central Balboa Peninsula Water and Sewer Improvement project for the City in 2010.
The work necessary to complete this contract includes constructing sewer improvements such as sewer
mains, manholes, laterals, and cleanouts within the 21 -ft public sewer easement on the property at 745
Dover Drive obtained last year. The goal of the project is to relocate and replace a deteriorated steel sewer
main on the hillside behind homes on St. James Place and St. James Road. The existing sewer main is
underneath decks, patios and, in one property, underneath portions of the house. Replacement of the
sewer in its current location would be very difficult and expensive.
Staff has been working with seven homeowners on St. James so as to eliminate the hillside sewer on their
properties by constructing this improvement project. Five residences either granted a new sewer easement
or signed access agreements to allow construction of private sewer laterals that will connect to this new
proposed sewer.
This work also includes replacing the 8 -in sewer line between properties at 724 and 730 Saint James
Place. Staff recommends approval of the contract award to include a contingency allowance of
approximately 10% to cover the cost of unforeseen conditions.
As part of this sewer project, a hydrodynamic separation storm drain treatment unit on Dover Drive is
included and a General Fund budget appropriation of $197,000 is requested. This work was originally
planned with the installation of other storm drain interceptors throughout the City recently awarded by City
Council on June 10, 2014. However, it was determined prior to the bidding, that there was insufficient grant
funds for this Dover Drive unit and that better cost efficiencies and minimization of public inconvenience
would be realized by adding this treatment unit to this nearby sewer relocation project. Although General
Fund monies are requested for this specific unit, the City was successful in competing and securing
approximately $1.1 million in grant funding from OCTA to construct storm drain treatment units to improve
water quality throughout the City. These storm drain locations receive heavy street litter flows during storm
events and hydrodynamic separator inceptor units will capture it before entering the ocean and bay water.
As part of those grant funds, the City is required to use a local General Fund match.
Staff received a formal bid protest dated July 21, 2014 from the Laborers Pacific Southwest Regional
BIDDER
Low
Paulus Engineering, Inc.
2
Big Ben Inc.
3
SND Construction Inc.
4
TE Roberts Incorporated
5
GCI Construction, Inc.
6
GRFCO Inc.
7
Ramona, Inc.
TOTAL BID AMOUNT
$539,645.00
$747,585.00
$795,000.00
$849,496.00
$869,767.00*
$942,095.00
$979,795.00
*Bid as read $872,662.00
The low bid amount is 13% lower than the Engineer's Estimate of $622,000. The low bidder, Paulus
Engineering, Inc., possesses a California state contractor's license classification "A" as required by the
project specifications. A check of the contractor's references indicates satisfactory completion of similar
projects for the City of Newport Beach and other public agencies. Paulus Engineering, Inc. also completed
the Central Balboa Peninsula Water and Sewer Improvement project for the City in 2010.
The work necessary to complete this contract includes constructing sewer improvements such as sewer
mains, manholes, laterals, and cleanouts within the 21 -ft public sewer easement on the property at 745
Dover Drive obtained last year. The goal of the project is to relocate and replace a deteriorated steel sewer
main on the hillside behind homes on St. James Place and St. James Road. The existing sewer main is
underneath decks, patios and, in one property, underneath portions of the house. Replacement of the
sewer in its current location would be very difficult and expensive.
Staff has been working with seven homeowners on St. James so as to eliminate the hillside sewer on their
properties by constructing this improvement project. Five residences either granted a new sewer easement
or signed access agreements to allow construction of private sewer laterals that will connect to this new
proposed sewer.
This work also includes replacing the 8 -in sewer line between properties at 724 and 730 Saint James
Place. Staff recommends approval of the contract award to include a contingency allowance of
approximately 10% to cover the cost of unforeseen conditions.
As part of this sewer project, a hydrodynamic separation storm drain treatment unit on Dover Drive is
included and a General Fund budget appropriation of $197,000 is requested. This work was originally
planned with the installation of other storm drain interceptors throughout the City recently awarded by City
Council on June 10, 2014. However, it was determined prior to the bidding, that there was insufficient grant
funds for this Dover Drive unit and that better cost efficiencies and minimization of public inconvenience
would be realized by adding this treatment unit to this nearby sewer relocation project. Although General
Fund monies are requested for this specific unit, the City was successful in competing and securing
approximately $1.1 million in grant funding from OCTA to construct storm drain treatment units to improve
water quality throughout the City. These storm drain locations receive heavy street litter flows during storm
events and hydrodynamic separator inceptor units will capture it before entering the ocean and bay water.
As part of those grant funds, the City is required to use a local General Fund match.
Staff received a formal bid protest dated July 21, 2014 from the Laborers Pacific Southwest Regional
Organizing Coalition regarding the large difference in bids between Paulus Engineering, Inc. and the
second low bidder. Staff discussed this issue with Paulus Engineering, Inc., reviewed the contractor's
references, including previous work with the City, and determined that Paulus Engineering, Inc. has
submitted a responsive bid. The contractor will be responsible to ensure all work is completed properly and
in accordance with all requirements, laws and regulations including Prevailing Wage. Therefore, staff
recommends approval of the contract.
Pursuant to the contract specifications, the Contractor will have 90 consecutive working days to complete
the work.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California Environmental Quality Act
( "CEQA ") pursuant to Section 15302 (replacement of existing facilities involving negligible expansion of
capacity) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at
which the City Council considers the item).
ATTACHMENTS:
Description
Attachment A - Location Map
Attachment B - Budget Amendment
� s
'i
5Z
s
ATTACHMENT A
SEWER
tAL
CITY OF NEWPORT BEACH
ST JAMES SEWER RELOCATION PUBLIC WORKS DEPARTMENT
LOCATION MAP C -4910 1 08/12/2014
ATTACHMENT B City of Newport Beach NO. BA- 15BA -007
BUDGET AMENDMENT
2014 -15 AMOUNT: $3s2,600.00
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates Increase in Budgetary Fund Balance
NX Increase Expenditure Appropriations AND �X Decrease in Budgetary Fund Balance
Transfer Budget Appropriations No effect on Budgetary Fund Balance
SOURCE:
X from existing budget appropriations
from additional estimated revenues
X from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
To increase expenditure appropriations from the General Fund fund balance and transfer appropriations from the Wastewater
Master Plan Program into the St. James Place Sewer Relocation accounts in budget units 7541 and 7012 in order to secure
sufficient funds for the St. James Road Sewer Relocation project and for the award of the associated construction contract to PEI.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Account
010 3605
REVENUE ESTIMATES (3601)
Fund /Division Account
EXPENDITUREAPPROPRIATIONS (3603)
Description
General Fund - Fund Balance
Description
Description
Division Number 7541 Sewer Main Replacement
Account Number C7001003 Wastewater Mst Pln Prgm
Account Number C7002005 St. James PI Sewer Relctn
Division Number 7012 Drainage
Account Number C7002005 St. James PI Sewer Relctn
Amount
Debit Credit
$197,000.00
$185,600.00
$185,600.00
$197,000.00
. Automatic System Entry.
Signed: g►— S sy
Fi ial Approval: Finance Director Date
Signed:
Signed:
Approval: City
City Council Approval: City Clerk
Date
Date