HomeMy WebLinkAbout12 - Award of Contract - Sound Walls for Segment 2 of MacArthur Boulevard WideningJanuary 11, 1999 CITY COUNCIL AGENDA ITEM NO. 12 TO: MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: PUBLIC WORKS DEPARTMENT SUBJECT: AWARD OF CONTRACT NO. 2825 (K) —SOUND WALLS FOR SEGMENT 2 OF MACARTHUR BOULEVARD WIDENING RECOMMENDATIONS: 1. Award Contract No. 2825(K) to the lowbidder, Cooper Backhoe and Equipment, Inc., for the total bid amount of $148,823.00; and authorize the Mayor and the City Clerk to execute the contract. 2. Establish an amount of $14,883.00 for unforeseen work and changed conditions. 3. Approve a budget amendment appropriating $163,712.50 from the Circulation and Transportation Fund to Account No. 7261- C5100066. DISCUSSION: On October 26, 1998, the City Council approved the plans and specifications for the sound wall construction associated with Segment 2 of the MacArthur Boulevard Widening Project, and authorized the staff to advertise for bids. The Segment 2 Sound Walls are to be constructed along the rear of six residential lots fronting on Port Manleigh (see attached exhibit). At 2:00 PM on December 17, 1998, the City Clerk opened and read six bids for the subject work. One of the bids was disqualified because the Bid Proposal was unsigned. The five responsive bids are as follows: BIDDER TOTAL BID AMOUNT Low Cooper Backhoe and Equipment, Inc. $148,829.50 2 KAS Equipment & Rental, Inc. 149,378.50 3 4 -CON Engineering, Inc. 169,563.50 4 M. Ahmadi Construction & Engineering, Inc. 191,659.00 5 R. J. Bullard Construction, Inc. 219,270.00 The low total bid amount is 0.8% below the Engineer's Estimate of $149,985.00. F:\ Users \PBW\Shared \COUNCIL \FY98- 99Uan -11 \Sound Walls C- 2825 -K.doc SUBJECT: AWARD OF CONTRACT NO. 2825 (K) — SOUND WALLS FOR SEGMENT 2 OF MACARTHUR BOULEVARD WIDENING January 11, 1999 Page: 2 RECOMMENDATION: The low bidder, Cooper Backhoe and Equipment, Inc., has not previously performed any construction work under contract with the City of Newport Beach, however, their bid indicates they have satisfactorily performed similar projects under contracts with Caltrans and the City of San Clemente. The references listed in their bid were checked and positive responses and recommendations were received. Staff therefore recommends award of the contract for construction of the MacArthur Boulevard Segment 2 Sound Walls to Cooper Backhoe and Equipment, Inc. The contract specifications provide for the work to be completed in 50 working days. This means that if construction work commences by February 1, 1999, it should be completed by approximately April 15, 1999. Construction management and inspection for this contract will be provided by the firm of Deist - Binsfield, Inc., based upon authorizations approved by the City Council on June 9, 1997 and on December 14, 1998. Similarly, geotechnical services and materials testing will be provided by the firm of AGRA Earth and Environmental based upon authorizations approved by the City Council on the above dates. FUNDING: FROM I TO AMOUNT Circulation and Transportation Fund I 7261- C5100066 $163,713.00 Respectfully submitt , PUBLIC RKS DEPARTMENT Don Webb, Director BY_�/ .c t..,.Z'� Gall Plckart. Project Management Consultant Attachments: Project Location Map Exhibit "A" Bid Summary f:\ users \pbw\ shared \council \fy98- 99 \jan- 11\sound walls c- 2825 -k.doc 2 ob 1 m 'S SCALE 1" =1000' FASHION ISLAND SEGMENT 1 CONSTRUCTION \v �C ISEGMENT 2 I CONSTRUCTION {v, �O ft Q,o A D LOW u 1 W Q ti z W Z v 0 v W. =a d 3 tj LL O w C7 Q IL Z U W Q � W 00 Q W 00 a � Y w IX Z O LL 3: O V J U m a E w u Q °o O N ui m r U Q Y 0 w m Y u U m W U c S r U U Z w 0Q Q w O J 0 m m w F F W Q d' � W ii W Z U) LU K W W z' C7 O Z Of w a E w ci r 6iO fV tii m r S U U o Q Q w m Y Y u U m W U S r Q U Z w O Q Q w O O m m d J O (D QL U N O N (A w F F z Y N a a N d W Q 6' 2 w ii w Q U) wF w U ww z' C7 O Z Of wa City of Newport Beach BUDGET AMENDMENT 1998 -99 ECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates X Increase Budget Appropriations AND Transfer Budget Appropriations from existing budget appropriations from additional estimated revenues Px from unappropriated fund balance EXPLANATION: NO. BA- 034 AMOUNT: Increase in Budgetary Fund Balance Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance This budget amendment is requested to provide for the following: To appropriate $163,713 to construct a soundwall as part of the MacArthur widening Project Segment 2. The soundwall will be located along the rear of six residential lots fronting on Port Manleigh. This multi -year project has several different funding sources including the Gas Tax Fund, Contributions Fund, Circulation and Transportation Fund, CIOSA Fund and Measure M Fund. Original estimated appropriations for all funding sources from this project totaled $11,800,000. Alterations of estimates and budget amendments over the project's life have resulted in an increase to $14,464,047. Funding sources for the amendments were mostly from CIOSA and Circulation and Transportation Fund Balances. ACCOUNTING ENTRY: Amount BUDGETARY FUND BALANCE Debit Credit Fund Account Description 260 3605 Fund Balance Control $163.712.50 REVENUE APPROPRIATIONS (3601) Fund /Division Account Description EXPENDITURE APPROPRIATIONS (3603) Description Division Number 7261 Transportation and Circulation Account Number C5100066 MacArthur Widening Improvements $163,712.50 Division Number Account Number Division Number Account Number Division Number Account Number Division Number Account Number / • Automatic System Entry. Signed: Financii pproval: Finance Director Siy,ied: �C/�i�u�v� C nc . �l�Xix —� ATminis°trative Approval: City M nager Date Signed: City Council Approval: City Clerk Date