HomeMy WebLinkAbout07 - Traffic Signal Improvements, Contract No. 3210 - Completion and AcceptanceFebruary 22, 1999
CITY COUNCIL AGENDA
ITEM NO. 7
TO: MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: PUBLIC WORKS DEPARTMENT
SUBJECT: BACKBAY DRIVE ROADWAY AND BRIDGE APPROACHES REPAIRS,
CONTRACT NO. 3180 - COMPLETION AND ACCEPTANCE
RECOMMENDATIONS:
1. Accept the work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the bonds 35 days after the Notice of
Completion has been recorded in accordance with applicable portions of the Civil
Code.
DISCUSSION:
On June 22, 1998, the City Council authorized the award of the Back Bay Drive
Roadway and Bridge Approach Repair, Contract No. 3180, to Summit Contracting of
Duarte, California. The contract provided for the repair of bridge approaches, the
construction of a depressed concrete roadway for purposes of providing a drainage
swail and other pertinent repair work needed to correct damages caused by the 1997 -
1998 El Nirio winter storms. The contract has now been completed to the satisfaction
of the Public Works Department. A summary of the contract cost is as follows:
Original bid amount: $174,990.67
Actual amount of bid items constructed: 177,948.00
Total amount of change orders: 30,268.67
Final contract cost: $208,216.67
The increase in the amount of actual bid items constructed over the original bid amount
resulted from the need for additional riprap exceeding the bid item quantities. The final
overall construction cost including change orders was 19.0% over the original bid
amount.
A total of two (2) change orders were issued to complete the project. They were as
follows:
1. A change order in the amount of $30,000.00 provided for the removal of a massive
landslide from an Irvine Company slope onto Backbay Drive near Shellmaker Island.
Funds for the $30,000.00 were deposited from The Irvine Company with the City.
Subject: Backbay Drive Roadway And Bridge Approach Repairs, Contract No. 3180 -Completion And
Acceptance
February 22, 1999
Page 2
2. A change order in the amount of $268.67 provided for the construction of timber
railings at the bridge wingwalls.
Funds for the project were budgeted in the General Fund and Contributions Fund as
follows:
Description
Account Number
Amount
Disaster Remediation Backba Drive
7025- C5100427
182,580.00
Contributions Backba Drive
7251- C5100427
30,000.00
TOTAL
$212,580.00
The contract specified completion of all work within twenty (20) working days from the
Notice to Proceed date. Based upon the August 31, 1998 proceed date, the completion
date was September 28, 1998. Due to extra work, inclement weather, the December
holiday season and the non - availability of treated lumber piles, the completion date was
extended to January 11, 1999. All work was substantially completed by that date.
Respe Ily su miffed,
PUBLIC WORKS DEPARTMENT
Don Webb, Director
By:
Horst Hlawaty, P.E.
Construction Engineer