HomeMy WebLinkAbout07 - C-2804 Seismic Retrofit of Lido Isle Bridge & NewJuly'26, 1999
CITY COUNCIL AGENDA
ITEM NO. 7
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: SEISMIC RETROFIT OF LIDO ISLE BRIDGE AND NEWPORT ISLAND
BRIDGE — CONTRACT NO. 2804
RECOMMENDATION:
Approve Amendment No. 2 to the Professional Services Agreement with Dokken Engineering
and authorize the Mayor and the City Clerk to execute the Amendment.
DISCUSSION:
On June 8, 1998, the City Council awarded Contract No. 2804 to Peterson -Chase General
Engineering Construction, Inc., and retained the structural engineering firm of Dokken
Engineering to provide construction management (CM) services for the project.
All work was scheduled to be completed by November 13, 1998; however, differing site
conditions required extra work, and Peterson -Chase was granted 31 additional working days to
complete the project. All work was completed on January 14, 1999.
On March 8, 1999, the City Council accepted the work and directed the City Clerk to file a
Notice of Completion for the project (see attachment). Dokken has submitted a final invoice for
CM services (see attached Invoice No. 8311R dated 4/19/99). The invoice is $19,966.45
($18,625.18 actual costs + $1,341.27 fixed fee) over the agreed contract amount for CM
services. Dokken is requesting compensation for the additional inspection and materials testing
associated with the extension of the construction period.
Funds to cover the additional CM cost are available in Account No. 7013- C5100067, Bridge
Retrofit Program. Caltrans has determined that these bridges are eligible for 100%
reimbursement of design, construction, and construction management costs by the Federal
Highway Administration and the State of California.
Respectfully submitted,
Public Works Department
Don Webb, Director
19 Llo d Dalton, P.E.
Design Engineer
Attachments: Amendment No. 2
March 8, 1999, Council Report
Dokken Invoice
f:W sersVbwl sharedfcoundl %"9-OOVuly- 265seisrric-dokken a2804.doc
AMENDMENT NO. 2
TO
PROFESSIONAL SERVICES AGREEMENT
FOR
SEISMIC: RETROFIT
LIDO ISLE AND NEWPORT ISLAND BRIDGES
THIS AMENDMENT No. 2 TO PROFESSIONAL SERVICES AGREEMENT
(hereinafter referred to as "Amendment No. 2 "), entered into this day of
1999, by and between the City of Newport Beach, a Municipal
Corporation (hereinafter referred to as "City "), and Dokken Engineering, whose
address is 3914 Murphy Canyon Road Suite A -153, San Diego, California
92123. (hereinafter referred to as "Consultant "), is made to amend the
Professional Services Agreement entered into the 8t' day of June, 1998, by and
between the aforementioned parties, (hereinafter referred to as "Agreement ") as
follows:
RECITALS
A. On December 30, 1998, City and Consultant entered into Amendment No.
1 to Agreement to provide for construction management services for
construction of Seismic Retrofit of Balboa Island Bridge.
B. Consultant has performed additional construction management services
pertaining to Seismic Retrofit of Newport Island Bridge and Lido Isle
Bridge.
C. Consultant has invoiced City for said additional services pertaining to
Seismic Retrofit of Newport Island Bridge and Lido Isle Bridge.
L�
D. City and Consultant mutually desire to further amend Agreement to
compensate Consultant for the additional construction management
services.
1. TERM
The term of Agreement and Amendment No. 2 is unchanged.
2. SERVICES TO BE PERFORMED
Consultant has completed all duties for the additional services as set forth in
Scope of Services, Exhibit "A% of Agreement.
3. COMPENSATION TO CONSULTANT
0 City shall pay Consultant for additional actual costs (including labor, employee
benefits, overhead, and other direct costs) incurred by Consultant and
subconsultants listed in Agreement and Amendment No. 2 in the performance of
services in an additional amount not to exceed $18,625.18, for a total actual
costs not to exceed $267,680.76 exclusive of any fixed fee.
City shall compensate Consultant an additional fixed fee in an additional amount
of $1341.27 for a total fixed fee of $18,412.81.
The schedule of billing rates for extra work compensated in this Amendment No.
2 are as set forth in Compensation to Consultant, Exhibit "B ", of Agreement.
IN WITNESS WHEREOF, the parties have caused this Amendment No., 2 to be
executed on the day and year first written above.
APPROVED AS TO FORM: CITY OF NEWPORT BEACH
A Municipal Corporation
By: By:
Robin Clauson Dennis D O'Neil, Mayor
Assistant City Attorney City of Newport Beach
ATTEST: CONSULTANT
By: By:
LaVonne Harkless Richard T. Liptak, P.E.
City Clerk Project Manager
f:l usersl pbwMdalton lagreemtsldokken.004.doc 0
0
L� _
MAR � 8
TO: Mayor And Members Of The City Council
FROM: Public Works Department
March 8, 1999
CITY COUNCIL AGENDA
ITEM NO. 9
SUBJECT: SEISMIC RETROFIT OF NEWPORT ISLAND AND LIDO ISLE BRIDGES
CONTRACT NO. 2804 - COMPLETION AND ACCEPTANCE
RECOMMENDATIONS:
1. Accept the work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the bonds 35 days after the Notice of
Completion has been recorded in accordance with applicable portions of the Civil
Code.
DISCUSSION:
On June 8, 1998, the City Council authorized award of the Seismic Retrofit of Lido Isle
Bridge and Newport Island Bridge - Contract No. 2804, to Peterson -Chase of Irvine,
California. The contract provided for strengthening the Lido Isle and Newport Island
bridges to increase their resistance to collapse due to earthquake forces. The contract
has now been completed to the satisfaction of the Public Works Department. A
summary of the contract cost are as follows:
Original bid amount:
$494,278.50
Actual amount of bid items constructed:
475,038.50
Total amount of change orders:
61,597.18
Deductions:
(455.00)
Final contract amount:
$536,180.68
The actual amount of bid items constructed was less than the original bid amount
because no work was performed under Bid Item No. 11. Bid Item No. 11 provided for
making shallow concrete repairs at spalled areas on the Newport Island bridge.
Inasmuch as the spalled areas were much deeper than anticipated, certain reinforcing
steel had to be replaced; accordingly, Bid Item No. 11 could not be used, and the spall
repairs were performed as an Extra Work change order.
Five change orders were issued on this contract. The first was for $4448.50 to furnish
and install structural steel to satisfy as -built conditions on the Lido Isle bridge. The
second was for $30,753 to construct a supplemental pile needed because of buried
manmade objects at the Lido Isle bridge. The third change order was for $2061 to
reposition two piles to clear an existing Lido Isle bridge footing. The fourth was for
Subject: Seismic Retrofit Of Newport And Lido Isle Bridges. Contract No. 2804. Completion And Acceptance
March 8, 1999
Page 2
$647.47 to sawcut the pavement removals sit the Newport Island bridge, and the fifth
was for $23,687.21 to perform the spall repair's mentioned above.
Loads imposed upon a City street light pole by the Contractor's temporary traffic signal
cable and a Lido Isle Community Association banner led to the failure of the pole. The
Contractor has been assessed a $455.00 deduction in contract amount to reimburse
the City for half of the labor and materials costs to replace the pole.
The final construction cost, including change orders and the street light pole deduction,
is 8%2% above the original bid amount. Design and construction management was
provided by Dokken Engineering. Design, construction and construction management
is 100% funded by the Federal Highway Administration and the State of California.
Funds for the project were budgeted under Account No. 7251- C5100067, Bridge
Retrofit Program.
The scheduled completion date was November 13, 1998. Due to the extra work and
differing site conditions, the Contractor was granted 31 additional working days. All
work was completed on January 14, 1999.
Respectfully sub itt d,
PUBLIC WORKS DEPARTMENT
Don Webb, Director
/ /rt /�
Lloyd O/Dalton,
Design Engineer
t lusersNpbwl shared\councihty98- g9Vnar- 8vetrofit c- 2804.doc
0
0
DOKKEN
E N G 1 N E E R I N G
INVOICE
BILLTO: BIWNG DATE: 4/19/99
City of Newport Beach
Public Works Department
3300 Newport Boulevard
Newport Beach, CA 92659 -1768
INVOICE NO: 8311R
PROJECT NO.: 939 -50
P.O. NO.:
Atten: Uoyd R. Dalton, P.E.
Due and payable upon presentation
Project Seismic Retrofit of Lido Isle & Newport Island Bridges (C -2804)
Construction Support Services from 1111 /98 through 1/31199
Direct Labor HIS Rata IOU
Registered Engineer (RF)
Inspector (GW)
Labor Overhead
AMLBPOer(1A805)
Direct Costs -
�, Tnsck Cortputec etc. 0 W.00/day x 10 days
5ubconsultants -
.. Ninyo & Moore
Agra
42 31.00
$1,302.00
346.5 18.50
$6,410.25
. Total Direct Labor Cost
$7,712.25 '
Total Labor Overhead
$11,417.99
.
$580.00.
"
$8,453:50 .
- ..
$835.00 ✓
Total Subconsultants Costs $9,288.50,
Fee
. Fee (1036) -
TOTAL AMOUNT DUE:
i=:
1,913
530,911. - -
� gkl�s�
��.
Project Manager Appr6vol
TERMS: Net can upon Presentation. Past due balances wW be subject to Interest at the highest prevoNng
Interest rate established by law wtdch wal be charged an past due accents over 30days.
3914 MUWW CW(ON ROAD, Sure A -153 • SAN DIEGO. CA 92123
TEL: 619.514.8377 'Fnx: 619.514.86D8
Budget
$69,277.12
Previous
$56,331.81
Current
530.91176
Balance
-S 19,966.45 V'
i=:
1,913
530,911. - -
� gkl�s�
��.
Project Manager Appr6vol
TERMS: Net can upon Presentation. Past due balances wW be subject to Interest at the highest prevoNng
Interest rate established by law wtdch wal be charged an past due accents over 30days.
3914 MUWW CW(ON ROAD, Sure A -153 • SAN DIEGO. CA 92123
TEL: 619.514.8377 'Fnx: 619.514.86D8