OCITY COUNCIL AGENDA
ITEM NO. 7
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: NEWPORT BOULEVARD (SR55) / PACIFIC COAST HIGHWAY (SR1)
"ARCHES" INTERCHANGE IMPROVEMENTS, CONTRACT NO. 2886 —
COMPLETION AND ACCEPTANCE
RECOMMENDATIONS:
1. Accept the work and approve the As -Built Plans and Specifications.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the bonds 35 days after the Notice of
Completion has been recorded in accordance with applicable sections of the Civil
Code.
DISCUSSION:
OOn June 23, 1997, the City Council authorized the award of Newport Boulevard
(SR55) /Pacific Coast Highway (SR1) "Arches" Interchange Improvements contract to
Brutoco Engineering and Construction, Inc., of Fontana, California. The contract
provided for a new grade separation bridge at Newport Boulevard and Pacific Coast
Highway, widening of the Newport Channel bridge, street widening, ramp
reconstruction, and interchange landscaping. Construction operations began in
September 1997 and were substantially completed by the end of May 1999 when a
formal dedication ceremony was conducted. The widening improvements at Newport
Boulevard and Short Street were delayed until the Orange County Sanitation District's
contractor, Advanco Constructors, removed the old Lido Sewage Pump Station in mid -
September 1999.
The contract has now been completed to the satisfaction of the Public Works
Department and we recommend formal acceptance of the improvements by the City
Council. A summary of the contract cost is as follows:
Initial Award Amount: $11,933,916.50
Authorization for unforeseen work and changed circumstances 796,026.50
Budget Amendment on 5/11/98 2,206,438.78
Budget Amendment on 6/28/99 737,141.22
Budget Amendment on 9/27/99 26.477.00
Final contract authorization $15,700,000.00
aActual Amount of Contract Bid Items Constructed $12,295,292.71
Amount of Contract Change Orders Constructed 3.397.061.88
Final contract cost $15,692,354.59
SUBJECT: NEWPORT BOULEVARD (SR55yPACIFIC COAST HIGHWAY (SR 1) -ARCHES- INTERCHANGE
IMPROVEMENTS, CONTRACT NO. 2886— COMPLETION AND ACCEPTANCE
October 25, 1999
Page 2
A total of 34 contract change orders were issued to complete the work. More than
$2,200,000 of the $3,397,061.88 contract change order total related to the addition of
the reinforced concrete box (RCB) stone drainage culvert across Pacific Coast Highway
and the associated water and sewer main relocation work. A listing of the most
significant change order items is as follows:
ADDED WORK TO CONSTRUCTION CONTRACT WITH BRUTOCO
RCB storm drain crossing PCH - CALTRANS
$1,470,000.00
Water main relocation and replacement
323,300.00
OCSD sewer main relocation and replacement
710,200.00
Heavy Sandblasting of retaining walls
83,600.00
Slope paving under channel bridge, bike path reconstruction,
and installation of underground drains adjacent to Balboa
Coves boundary wall
47,000.00
Traffic signal modifications at Hospital Road for left-turn phases
65,800.00
Earthwork quantity overrun
108,600.00
Traffic control modifications for public convenience and
Channel Bridge retrofitting
79,000.00
Offsite riparian mitigation in Lower Big Canyon for RCB along
Old Newport Boulevard
49,000.00
Bypass pumps at Lido Pump Station
30,200.00
Removal of existing walls along Clubhouse Avenue
to accommodate sound wall construction
64,500.00
Total
$3,031,200.00
Funds for the project were budgeted in the following accounts:
Description tion
Account No.
Amount
Federal ISTEA
7282 - (:5100199
$ 5,457,872.00
OCTA Measure M
7284 - (:5100199
1,499,380.37
CIOSA Loan
7432- C5100199
3,784,334.75
Contributions
7251- 05100199
3,561,811.00
1
Water Main Replacement
7501 - 05500386
323,254.78
Traffic Signal Upgrade
7181- C:5100068
65,855.00
Circulation and Transportation
7261- C:5100199
999,846.69
TOTAL
$15,692,354.59
(1) Hoag Hospital $440,000.00; Orange County Sanitation District $1,753,514.00; and Caltrans
$1,368,297.00.
Respectful itted
PUBLIC WORKS ARTMENT
Don Webb, Director
y, 6 -a- IF � , JE '
Gail Pickart, P.E.
Project Manager Consultant