SUBJECT: Newport Dunes Resort Environmental Impact Report
SUGGESTED
ACTION: Approve amendment to the professional services agreement with LSA
Associates, Inc.
The City Council approved an amendment to the professional services agreement with LSA
Associates with regard to changes in the project on April 11, 2000. This amendment is for
$10,500. The amendment with regard to additional work on responses to comments and
preparation of the Final EIR ($27,500) was continued, with requests for a status report on the
EIR and for the consultant to be present at the meeting of April 25.
LSA Associates has prepared the attached status report, and will have a representative at the
Council meeting. As the status report indicates, the consultant has provided additional responses
to comments and questions from the Environmental Quality Affairs Committee (EQAC). This
information was available for the Planning Commission's consideration on April 20. In addition,
EQAC's chairman intends to place this report on the EQAC agenda for May to enable the
Committee to make its recommendation on the adequacy of the EIR to the City Council when it
is conducting public hearings on the project.
Staff believes the requested amendment for additional work is justified, as there has been an
unusually high amount of public interest in the Newport Dunes Resort project and commensurate
amount of comments on the EIR.
Assistant City Manager
,A�C
Attachment: Memorandum from LSA Associates, Inc.
CITY OF NEWPORT BEACH
Hearing Date:
April 25, 2000
zEWOOR,
o�
COMMUNITY AND ECONOMIC
Agenda Item
DEVELOPMENT
No.:
9
PLANNING DEPARTMENT
Staff Person:
Sharon Z. Wood
3300 NEWPORT BOULEVARD
(949) 644 -3222
NEWPORT BEACH, CA 92658
(714) 644 -3200; FAX (714) 644 -3250
REPORT TO THE MAYOR AND CITY COUNCIL
SUBJECT: Newport Dunes Resort Environmental Impact Report
SUGGESTED
ACTION: Approve amendment to the professional services agreement with LSA
Associates, Inc.
The City Council approved an amendment to the professional services agreement with LSA
Associates with regard to changes in the project on April 11, 2000. This amendment is for
$10,500. The amendment with regard to additional work on responses to comments and
preparation of the Final EIR ($27,500) was continued, with requests for a status report on the
EIR and for the consultant to be present at the meeting of April 25.
LSA Associates has prepared the attached status report, and will have a representative at the
Council meeting. As the status report indicates, the consultant has provided additional responses
to comments and questions from the Environmental Quality Affairs Committee (EQAC). This
information was available for the Planning Commission's consideration on April 20. In addition,
EQAC's chairman intends to place this report on the EQAC agenda for May to enable the
Committee to make its recommendation on the adequacy of the EIR to the City Council when it
is conducting public hearings on the project.
Staff believes the requested amendment for additional work is justified, as there has been an
unusually high amount of public interest in the Newport Dunes Resort project and commensurate
amount of comments on the EIR.
Assistant City Manager
,A�C
Attachment: Memorandum from LSA Associates, Inc.
LSA PARK PLAZA INC.
ONE PARK PLAZA, SUITE $00
IRVINE, CALIFORNIA 92614
MEMORANDUM
DATE: April 14, 2000
To, Sharon Wood, Assistant City Manager
FROM, Robert W. Balen, Principal
OTHER OFFICES;
949.5530666 TEL BERKELEY RIVERSIDE
949.553.8076 FAX PT. RICHMOND ROCKLIN
SUBJECT. Status of Newport Dunes Resort EIR Process
This memorandum is provided in response to the City Council's April 11 request for a status report
on the progress of the Newport Dunes Resort EIR. LSA Associates, Inc. (LSA) is in the process of
preparing the Final EIR package for review and certification by the City Council. The status is
summarized below.
Responses to Comments
LSA prepared a Draft Responses to Comments (DRTC) document on January 28, 2000, with the
input of the City Planning Department, the City Attorney's office, and subconsultants responsible for
preparing technical studies included in the DEIR, as well as the applicant. The DRTC included
responses to the comments raised by the City's Environmental Quality Affairs Committee (EQAC),
charged with reviewing the DEIR. The City Attorney's office has reviewed the DRTC and found the
document consistent with the requirements of CEQA.
On March 23, 2000, the EQAC submitted a letter to the Planning Commission listing their concerns
with the DRTC. In response to EQAC's letter, LSA has provided a memo report, dated April 14,
2000, which attempts to further clarify the responses with which EQAC had concerns. We believe
this memorandum provides additional clarification of issues, as well as an explanation of the level of
analysis required for compliance with CEQA.
At its meeting on April 6, 2000, this Planning Commission evaluated the adequacy of the DEIR, and
DRTC and found the documents to be consistent with the requirements of CEQA. Therefore, with
the City's approval, LSA will now prepare a Final Responses to Comments document for inclusion in
the Final EIR package.
Environmental Evaluation of the Revised Project
At its meeting on April 11, the City Council authorized LSA and its subconsultant, Mestre Greve
Associates, to prepare for its review an environmental analysis of the revised Newport Dunes Resort
as modified by the Planning Commission. This revised environmental analysis is necessary for the
purposes of CEQA to document that the; revised project has no new environmental impacts not
anticipated in the DEIR or the subsequent analyses of the project modifications prepared by LSA. In
4 /14 /00((PACN13834\A.dmin \4 -14 status memompd>>
LSA ASSOCIATES, INC.
addition, the analysis will determine whether any of the significant impacts identified in the DEIR (air
quality, traffic, visual resources) have been reduced to less than significant levels through the
redesign of the project. LSA and Mestre Greve Associates are currently preparing this revised
analysis, and we plan to submit a draft copy to the City Planning Department for review on April 28.
Final EIR Package
LSA will compile the Final EIR package for certification by the City Council. The Final EIR will
include Volumes I and II the Draft EIR, the Responses to Comments, Errata, the Revised
Environmental Analysis, Facts & Findings, Planning Commission and City Council staff reports and
resolutions, and a Statement of Overriding Considerations. This Final EIR package will be compiled
for certification by the City Council after the completion of the environmental evaluation of the
revised project.
LSA will continue to work expeditiously at the direction of the City staff to complete the CEQA
process for the Newport Dunes Resort project. Please do not hesitate to call me if there are any
issues that you would like to discuss.