HomeMy WebLinkAbout09 - Balboa Village Project - Agreement AmendmentMay 8, 2001
COUNCIL AGENDA
ITEM NO. 9
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: BALBOA VILLAGE PROJECT UPDATE AND APPROVAL OF
AMENDMENT NO. 5 TO PSOMAS AGREEMENT
RECOMMENDATIONS:
1. Receive and file project update report.
2. Approve Amendment No. 5 in the amount of $130,195 to the original Agreement
with Psomas. The amendment provides for a fee increase to cover work beyond the
original scope of services. The Amendment also provides for a time extension to
the Agreement.
PROJECT HISTORY
At the February 22, 2000, City Council meeting, Staff was directed to solicit proposals for
professional services to design pedestrian and streetscape improvements for the Balboa
Village area. The Balboa Village project includes hardscape, landscape, and streetlight
improvements for the Balboa Pier parking lot, pier plaza, Washington Street, Palm Street,
Main Street, Bay Avenue, Balboa Boulevard, Ocean Front, and Peninsula Park.
On May 23, 2000, Council authorized the City to execute an Agreement with Psomas to
provide pre - design, design, and construction services for the Balboa Village Improvement
Project for a fee of $493,131. The original scope of work includes:
• Designing pedestrian and streetscape improvements
• Preparing an odor assessment at Washington Street and Bay Avenue
• Designing water, sewer, streetlight, and storm drain improvements
There are several projects associated with the Balboa Village Project underway
concurrently including:
• Formation of an Underground Utilities Assessment District
• Re- designing the Washington Street and Balboa Pier restrooms
• Designing the landmark tower at the corner of Balboa Boulevard and Palm Avenue
SUBJECT: Balboa Village Project Update and Approval of Amendment No. 5 to Psomas Agreement
May 8, 2001
Page 2
Several studies associated with the project have been commissioned and completed:
• A human health risk assessment for the methane and hydrogen sulfide emissions
at Washington Street and Bay Avenue
• A Negative Declaration for the project
• A biological assessment for the new storm drain outFall at the north end of
Washington Street
• An analysis of the Ficus trees on Main Street with a complementary study by Staff
on tree maintenance costs
PROJECT PHASING
The Village Project will take three years to construct with the first phase beginning in
October 2001. Based on discussions with representatives from the Balboa Inn for the
expansion of the hotel, Phase 1 has been modified to delay some of the proposed
improvements in area of the Inn expansion. If the Inn receives approval for the project,
perhaps in July 2001, then construction drawings will need to be prepared. Construction
could conceivably begin early in 2002.
The following are the major components to be constructed in each phase.
Phase 1 — FY 2001 -2002
Construction of the Balboa Pier Parking Lot improvements (excluding the small metered
parking area to the west of the proposed Inn expansion as well as the sidewalks on the
south and east sides of the Inn expansion), Pier Plaza improvements, Main Street
connection from the A Street Parking Lot, Balboa Boulevard improvements (from Adams
Street to Main Street), and storm drain facilities in Washington Street.
Phase 2 — FY 2002 -2003
Construction of the Oceanfront boardwalk and median area, Balboa Boulevard (from Main
Street to A Street), and streetscape for Palm Street, Washington Street, and Main Street
from Oceanfront to Balboa Boulevard.
Phase 3 — FY 2003 -2004
Construction of streetscape for Palm Street, Washington Street, and Main Street from
Balboa Boulevard to Edgewater Place, Bay Avenue streetscape (including an odor control
system), and improvements for Peninsula Park.
PROJECT STATUS
The City received a third submittal of drawings and specifications from Psomas on March
23, 2001. The documents were reviewed and returned to Psomas on April 20, 2001.
Factoring in the new tasks, the construction drawings are approximately eighty percent
complete. Psomas is revising the drawings for resubmittal on May 23, 2001.
SUBJECT: Balboa Village Project Update and Approval of Amendment No. 5 to Psomas Agreement
May 8, 2001
Page 3
Comments were received from the California Coastal Commission and the City prepared
and submitted a response to the Coastal Commission on April 5, 2001.
Staff selected a concrete material called Lithocrete for use on this project. Staff is
coordinating with a local supplier to prepare samples with the proposed materials,
patterns, and colors for the sidewalks and roadways. Staff has begun the process to pre -
qualify Lithocrete contractors.
Based on an analysis of projected costs, adjustments are being made to keep
construction costs within the allocated budget.
The Army Corps of Engineers and the California Regional Water Quality Control Board are
processing permit applications for the Village project.
CONTRACT AMENDMENT NO. 5
Construction documents for the Balboa Village Project are being prepared by Psomas.
The original contract amount with Psomas was $493,136.
Amendments totaling $121,981 (24.7 percent of the original contract amount) have been
previously approved for new planning and design tasks assigned to Psomas. Tasks
covered by the previous amendments included:
• Participating in expanded planning activities and working on design development
for the streetscapes, Peninsula Park refurbishment, pier plaza redesign, and the
landmark tower concept and preliminary design
• Designing landscape areas for the pier plaza, Oceanfront median area, and
Peninsula Park
• Researching options for replacement street trees
• Preparing parking design options for Bay Avenue
• Preparing design options for Balboa Boulevard
• Modifying the design for underground utilities
Amendment No. 5 (attached with Psomas' tasks) for $130,195 has been reviewed by Staff
for new design tasks and revisions. The added tasks to be provided are:
1. Design revisions for the storm drain alignment in Washington Street.
2. Planning and design for the storm drain outFall across Edgewater into Newport
Harbor.
3. Design for a new storm drain tide gate and vault.
4. New design and design revisions for parking, hardscape, trees, landscape, traffic,
and utilities improvements throughout the Village.
5. Adjustment to the drawings to accommodate a change in the limits of Phase 1
construction.
6. Supplemental survey.
7. Revisions to drawings to accommodate new construction phasing.
8. Project planning and coordination.
SUBJECT: Balboa Village Project Update and Approval of Amendment No. 5 to Psomas Agreement
May 8, 2001
Page 4
PROJECT SCHEDULE
Staff anticipates signing the construction drawings by July 16, 2001, and awarding the
contract on September 11, 2001. Construction is anticipated to begin by October 1, 2001.
Amendment No. 5 extends the term of the contract to December 31, 2001.
Funds are available for Amendment No. 5 in the following accounts:
Description Account No. Amount
Balboa Pier Parking 7022- C5100376 $ 77,070
Streetlight Replacement Program 7014- C5300035 11,440
Balboa Village Plan 7023- C5100543 11,685
CDBG Balboa Peninsula Revitalization 7161- C2700518 30,000
Total $130,195
Respectfully submitted,
(IZD
PUBLIC WORKS DEPARTMENT
Don Webb, Director
By: 21A� 2
Robe7 Stein, Project anager
Attachment: Amendment No. 5 to Psomas Professional Services Agreement
BALBOA VILLAGE IMPROVEMENT PLAN
AMENDMENT NO. 5
TO
PROFESSIONAL SERVICES AGREEMENT WITH PSOMAS
THIS AMENDMENT NO. 5 TO PROFESSIONAL SERVICES
AGREEMENT, entered into this day of , 2001, by and
between the CITY OF NEWPORT BEACH, a municipal corporation, (hereinafter
referred to as "CITY ") and Psomas, whose address is 3187 Red Hill Avenue, Suite 250,
Costa Mesa, California, 92626, (hereinafter referred to as "Consultant'), is made with
reference to the following:
RECITALS:
A. On May 23, 2000, CITY and CONSULTANT entered into a
Professional Services Agreement, hereinafter referred to as "AGREEMENT ", for final
design and construction support services for the Balboa Village Improvement Project,
hereinafter referred to as 'PROJECT'.
B. CITY and CONSULTANT have entered into four separate
AMENDMENTS of the AGREEMENT, the latest dated December 20, 2000.
C. CITY desires to enter into this AMENDMENT NO. 5 to reflect
additional services not included in the AGREEMENT or prior AMENDMENTS and to
extend the term of the AGREEMENT to December 31, 2002.
D. CITY desires to compensate CONSULTANT for additional
professional services needed for PROJECT.
E. CITY and CONSULTANT mutually desire to amend AGREEMENT,
hereinafter referred to as "AMENDMENT NO. 5', as provided here below.
NOW, THEREFORE, the parties hereto agree as follows:
1. CONSULTANT shall be compensated for services performed
pursuant to this AMENDMENT NO. 5 according to "Exhibit A" dated April 11, 2001
attached hereto.
2. Total additional compensation to CONSULTANT for services
performed pursuant to this AMENDMENT NO. 5 shall not exceed one hundred thirty
thousand, one hundred ninety -five and 00/100 dollars ($130,195.00).
2002.
3. The term of the AGREEMENT shall be extended to December 31,
4. Except as expressly modified herein, all other provisions, terms,
and covenants set forth in AGREEMENT shall remain unchanged and shall be in full
force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this AMENDMENT
NO. 5 on the date first above written.
CITY OF NEWPORT BEACH,
A municipal corporation
AN
APPROVED AS TO FORM: Garold B. Adams, Mayor
City of Newport Beach
City Attorney
ATTEST:
By:
LaVonne Harkless
City Clerk
Psomas
Li'E
f:\ users \pbw\shared\balboa village \agreements \psomas\amendment 5 041101.doc
BALBOA VILLAGE IMPROVEMENT PLAN
AMENDMENT NO. 5 - EXHIBIT A
May 1, 2001
With
PSOMAS
3187 Red Hill Avenue, Suite 250
Costa Mesa, CA 92626
As requested by the City, Psomas has been asked to perform new design and
planning tasks for the Balboa Village Improvement Project including:
• Design Revisions for the storm drain in Washington Street,
• Design for a new storm drain tide gate and vault,
• New design and design revisions for hardscape, landscape, and utilities
improvements throughout the Village, and
• Revisions to drawings to accommodate new construction phasing.
The tasks are detailed below.
Task 1 Redesign Storm Drain Line A in Washington Street (Task 1 Request
$9,423)
The proposed storm drain will be revised at the request of SCE to avoid some its
facilities that will be very costly to relocate. Additionally, the City has decided to
include in this project a new storm drain outfall across Edgewater into Newport
Harbor. Psomas shall:
a) Determine a new alignment to eliminate interference's between SCE facilities,
b) Coordinate with the City and Ron Yeo for storm drain line alignment within the
restroom plaza area,
c) Coordinate with SCE for relocation of its facilities,
d) Extend the system into Newport Bay including design of a new bulkhead
penetration and pipe anchors, and removal of the existing facilities,
e) Revise alignment as required by new tide gate (Task 2 below).
f) Coordinate research for interfering utilities in Edgewater,
g) Coordinate with the City and property owners for other interference's in
Edgewater,
h) Re- connect two existing catch basin in Washington Street to the new system,
and
i) Revise the specification for trenching, demolition, access and other
requirement.
F1UsemXPBNAShared \Ba11b0a Village \Agreements\Psomas\Amemdment 5 Exhibit A 050101.doc
j) Coordinate with the City and Nuvis to relocate proposed trees on Washington
Street between Balboa Boulevard and Bay Avenue. including coordination
with Nuvis for the final location of trees on Washington Street north of Bay
Avenue including the landscape area. This task also includes coordination
with SCE regarding pipeline alignment and profile.
Task 2 Tide Gate Planning and Design (Task 2 Request $12,684)
Psomas shall perform site studies and coordinate with the City to locate the vault
for the new tide -gate valve within the landscape area on the north end of
Washington Street. The site plan will show the odor vent mast, tide gate vault
and control pedestal, backflow valve, fire department connection, post indicator
valve and connections to the two catch basins. The vault shall be located so that
it does not impede pedestrian movements in Washington Street and Edgewater.
Structural calculations shall be performed and details prepared for the new
construction. A new electrical circuit for the tide gate shall be designed.
Task 3 Planning Coordination Meetings (Task 3 Request: $3,465)
At the request of the City, Nuvis attended seven coordination meetings to discuss
options for the landscaping, landmark tower, hardscape materials and pavement
pattern. A contingency of 18 hours for future meetings is included in this task.
Task 4 Hardscape, Landscape and Utility Design Revisions for the Period
January to April 2001 (Task 4 Request: $38,303)
As requested by the City, Psomas shall perform the following new or revised
design tasks:
a. Modify the curb line on Balboa Boulevard near Edison vault. (Subtask
request: $1,700)
b. Provide a wall detail and horizontal control for the seat wall between the Pier
Plaza and Peninsula Park. (Subtask request: $1,253)
c. Prepare details to modify an existing french drain in the Pier Parking Lot
based on information provided by the City. (Subtask request: $950)
d. Prepare full improvements for the alley (plan and profile) linking Bay Avenue
and Balboa Blvd between Washington St and Main Street (Subtask request:
$3,482)
e. Redesign the proposed water line in Washington Street to eliminate
interference's between existing SCE facilities and proposed water
improvements. (Subtask request: $2,000)
f. Delete the proposed sanitary sewer replacement in Bay Avenue East from the
plans. (Subtask request: $701)
g. Prepare a salvage plan for the existing palm trees in the Balboa Pier Parking
Lot. (Subtask request: $1,200)
FAUsers\PBVV\Shared \Balboa Village \Agreements \Psomas\Amemdment 5 Exhibit A 050101.doc
h. Shift the two parallel parking stall in front of the Pharmacy on Balboa
Boulevard (Subtask request: $1,897)
i. Revise landscape and hardscape design to accommodate changed parking
on Balboa Blvd in front of pharmacy, driveway at Palm St, modified utility
locations at restroom, planter at north end of Washington St to accommodate
gas emission, relocate tree wells and planting areas between Adams and
Palm on Balboa Boulevard (Subtask request: $3,100)
j. Add trees to the Balboa Pier Parking Lot. The original design included
removal of all trees within the interior of the Pier Parking Lot. Based on
Council and community comments, trees will be installed within the parking lot
interior in a geometric pattern that will not interfere with the new parking
layout. The demolition and improvement plans, as well as the hardscape,
planting and irrigation designs shall be revised to accommodate the change.
(Subtask request: $3,336)
k. Reduce tree well sizes on Balboa Boulevard and adjust paving patterns and
hardscape plans to accommodate these changes. (Subtask request: $7,764)
I. Design decorative elements for the meandering wall and conical pilasters
along the Oceanfront boardwalk. Design to include footings and wall cap.
Also, at the direction of the City, revise Pier Plaza geometry and decorative
pilasters. (Subtask request: $3,375)
m. Provide concept to provide trellises and vines for the area on Washington
Street north of Bay Avenue. Provide a planting concept for the landscape
area at the north end of Washington Street in order to accommodate the odor
vent'mast'. (Subtask request: $2,000)
n. Modify the loop detector in Balboa Boulevard at Main Street due to changes
in the street geometry. (Subtask request: $1,650)
o. Redesign the intersection between Main Street and Bay Avenue to construct
Main Street north of Balboa Boulevard in Phase 2 rather than in Phase 3. The
existing design is based upon a different phasing sequence. Because the
finish elevations of the existing and proposed improvements are not identical
at the new match line, the design shall be modified and a transition detail
shall be created. (Subtask request: $1,200)
p. Revise Balboa Boulevard improvements between Alley 220 (East of Main
Street) and A• Street to construct this section in Phase 2 rather than Phase 1.
The design of the project is somewhat dependent on how the project is
phased. The City has indicated that some elements of the project initially
planned in Phase 1 may be moved to later phases. This will require some
adjustment to the street details at the interface between phases, changes in
the traffic control plans, street light design and circuitry, and irrigation
drawings. (Subtask request: $2,695)
Task 5 Hardscape, Landscape and Utility Design Revisions Subsequent to the
95% Complete Submittal (Task 5 Request: $42,000)
Based on the review of the 95 percent complete drawings, the City has indicated
that the following list of changes to the project. Psomas will meet with the City to
F: \Users \PBVV\Shared \Balboa Village \Agreements \Psomas \Amemdment 5 Exhibit A 050101.doc
discuss the proposed additional work in detail. Prior to proceeding with any of
the tasks listed below, Psomas will obtain written authorization from the City.
a. Revise the storm drain lateral alignment in Palm Street between the catch
basins and the main line in Balboa Boulevard.
b. Revise the radius of the curb return on the northeast corner of the Balboa
Boulevard Intersection with Palm Street. Design the intersection pattern
to include lithocrete and stained concrete. The pattern will extend into the
Landmark Tower Plaza area. This task also includes relocating a fire
hydrant, traffic signal pole and conduit modifications, redesigning the
handicap ramp, revising the phasing detail, and reworking the demolition
plan and hardscape horizontal control plan, revising hardscape and
landscape plans, revising the traffic signal modifications, and revising
street signing and striping.
c. Revise the Pier Parking Lot curb alignment at the ingress and egress
points from Washington Street. The work includes revising the horizontal
control plan, redesigning the handicap ramps, revising the demolition plan,
revising the 10 -scale detail at Washington Street, revising the parking lot
lighting, revising the traffic control plan, and revising the hardscape
horizontal control plan, revising parking stalls within the lot.
d. Revise the limits of Phase 1 and Phase 2 in the Pier Parking Lot to allow
the Balboa Inn to construct modifications during the construction of Phase
1 improvements in the vicinity of Main Street and the parking lot frontage
road. The work includes revising the improvement and demolition plans,
creating a detail of the interim transition between the existing condition
and the proposed Phase 1 improvements, revising the landscape /
hardscape / irrigation designs, revising the traffic control plan, create
interim traffic signing and striping, revising lighting circuits, revising the
quantities, and revising construction estimate and specification for the
area.
e. Revise the plans to remove and replace selected sections of the AC
paving in the Pier Parking Lot. The work includes modifying the parking
lot improvement plan, revising the quantities and construction estimate,
and revising the specification and bid item to address the proposed
construction.
f. Revise the parking lot design to include an island around the parking
meters in the large parking lot between Palm Street and Washington
Street South of Oceanfront. The work includes revising the improvement
plan, horizontal control plan, hardscape horizontal control plan, revising
the drainage pattern in the parking lot, revising the striping plan, and
revising landscaping and irrigation plans.
g. Revise the storm drain in Washington Street at Bay Avenue by adding a
grate inlet in Washington Streetjust South of Bay Avenue. The work
includes revising the storm drain plan, revising the intersection design,
revising hydraulic calculations, and updating the quantities and
construction estimate.
FAUSers \PBMShared \Balboa Village \Agreements \Psomas\Amemdment 5 Exhibit A 050101.doc
h. Design a sanitary sewer service lateral to the trash enclosure east of the
new restroom on Washington Street. The work includes designing a detai
for the enclosure, revising the finish grades around the enclosure, revising
the specification, and updating the quantity and construction estimate.
i. Design miscellaneous revisions to the improvement plans including
revising catch basins 7 and 9 to City Standard 300 -L -A; moving the tree
wells on Balboa Boulevard between Adam Street and Palm Street to the
back of the sidewalk; and reducing the length of the median nose in the
Pier Parking Lot by pulling it about 15 -feet to the north including relocating
a proposed street light.
j. Revise the patterns at Palm Street, Washington Street and Main Street
intersections along Oceanfront. The work includes revising the hardscape
horizontal control plan, along with the hardscape and landscape plans.
Task 6 Additional Field Survey (Task 6 Request: $1,550)
Additional survey is required beyond the right -of -way on Palm Street in order to
design a driveway and two alley access - points to ADA standards.
Task 7 Extend the 240 -Volt Street Light Circuitry Outside the Project Limits
(Task 7 Request: $7,040)
Austin Foust will design a 240 -volt street light circuit to replace the series circuit
that lies outside the project area on Adams Street, Bay Avenue, Edgewater and
A Street.
Task 8 Project Planning and Coordination (Task 8 Request: $13,730)
The original Psomas budget for Project Management addressed the coordination
anticipated for the original scope of work. The design elements of the Balboa
Village evolved over the course of the project in response to discussions and
meetings by the Psomas team with City staff, the City Council, representatives of
various businesses in the village, and other City consultants.
Because the scope of the project changed as the improvement plans were being
developed, substantial coordination efforts and costs have resulted. Initiating
project changes involves researching design options, considering alternative
design concepts, discussing and evaluating design suggestions by city staff,
documenting the process, and distributing information to the city, consultants and
other interested parties. These preparation efforts are not covered within specific
design tasks.
Additional costs have also resulted from ascertaining the impact of the proposed
changes on the construction drawings and coordinating the added work with
Psomas' subconsultants, City staff and other City consultants.
F:\Users\PBVV\Shared \Balboa Village \Agreements \Psomas\Amemdment 5 Exhibit A 050101.doc
In addition, there has been a significant effort by Psomas' Project Manager to
prepare change orders in response to the City's requests for additional items of
work. Psomas has developed cost estimates to provide additional requested
services. This task involves developing a conceptual design, making site visits,
calling sub - consultant or vendors for research, confirming assumptions and
design parameters with city staff, developing labor hours, reproduction costs and
other costs, and listing assumptions. The City has implemented about half of
the options that they have requested Psomas to develop.
Most recently, the City has requested further modifications (see Task 5) to the
site plan, storm drain design, landscaping, parking lot modifications, street light
modifications, phasing changes and other miscellaneous changes. Psomas has
assumed an additional 30 hours of project management time to track and
implement these changes.
Finally, the project planning that is running concurrently with the design has
stretched out the design schedule which does impact the project budget by
adding meetings and coordination time.
This requested task budget would cover this period through the July 15th 2001.
Task 9 Reproduction: (Task 9 Request: $2,000)
This task will provide a supplement to the reimbursables budget to accommodate
the extra plan sets and documents that have been produced to support the
ongoing design effort as well as the anticipated revisions to complete the
construction documents.
Total Fee Request for Amendment 5: $130,195