CITY COUNCIL AGENDA
ITEM NO. 13
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: APPROVAL OF A COOPERATION AND REIMBURSEMENT
AGREEMENT BETWEEN THE ORANGE COUNTY SANITATION
DISTRICT AND THE CITY OF NEWPORT BEACH
RECOMMENDATIONS:
1. Approve the project plans for the Back Bay Drive Road Reconstruction between
Jamboree Road and Shellmaker Road.
2. Approve a Cooperation and Reimbursement Agreement between Orange County
Sanitation District (OCSD) and the City of Newport Beach ($122,162.25 City's
share) for the reconstruction of Back Bay Drive between Jamboree Road and
Shellmaker Road as part of OCSD's Backbay Trunk Sewer Project and authorize
the Mayor and City Clerk to execute the agreement. Funds are available in
Account No. 7181- C5100591.
3. Establish an amount of $10,000.00 to cover the cost of unforeseen work.
DISCUSSION:
On June 27, 2001, OCSD awarded the $5.5 million Back Bay Trunk Sewer
Replacement contract to Ken Thompson, Incorporated. In an effort to minimize
construction impacts to the community, the City requested the road reconstruction
originally planned as part of next year's pavement management to be included in the
OCSD project.
The portions of the road reconstruction within the trunk sewer construction area will be
paid for by OCSD. The area of road reconstruction between Jamboree Road and the
entrance to the Dunes will be paid for by the City, see attached exhibit.
Attached for the Council's consideration is the reimbursement agreement for the City to
pay $122,162.25 for our share of the costs related to the road reconstruction. The City
will also be responsible for completing the road reconstruction plans to be included in
the OCSD bid package.
SUBJECT: Approval of a Cooperation and Reimbursement Agreement Between the OCSD and the City of Newport Beach
July 10, 2001
Page 2
The construction of the trunk sewer is scheduled to start in September and will take
approximately one year to complete.
The City's obligation under the proposed reimbursement agreement is $122,162.25.
There are sufficient funds available in the Gas Tax Funds under Capital Project
Account No. 7181- C5100591. Staff recommends approval of the reimbursement
agreement.
Respectfully sub e , 0)
BLIC WORKS DEPARTMENT
Don Webb, Director
By:
Michael I Sinacori, P.E.
Utilities Engineer
Attachment: Cooperation and Reimbursement Agreement
Project Exhibit
f:\ users \pbw\ shared \council \fy01 -02 \july- 10 \ocsd agmt.doc
COOPERATION AND REIMBURSEMENT AGREEMENT
BETWEEN THE ORANGE COUNTY SANITATION DISTRICT
AND THE CITY OF NEWPORT BEACH
This Cooperation and Reimbursement Agreement is made this day
of 2001, by and between:
:►o
ORANGE COUNTY SANITATION DISTRICT, a
political subdivision of the State of California,
(hereinafter referred to as "District')
CITY OF NEWPORT BEACH, California, a municipal
corporation of the State of California (herein referred
to as "City ")
RECITALS
WHEREAS, District currently owns and maintains a 24 -inch ductile iron
gravity trunk sewer in Back Bay Drive in City. (hereinafter referred to as 'Back
Bay Trunk Sewer"); and,
WHEREAS, District is planning to replace the Back Bay Trunk Sewer,
pursuant to Contract No. 5-46, commencing in September 2001 (hereinafter
referred to as "District Project'); and
WHEREAS, District has contracted for design and construction services
with Tran Consulting Engineers (hereinafter referred to as "Design Consultant')
for the District Project; and
1
WHEREAS, City is planning to reconstruct the pavement on Back Bay
Drive from Jamboree to Shellmaker Road (hereinafter referred to as "City Street
Improvements "); and
WHEREAS, City has completed plans and specifications for the City
Street Improvements; and
WHEREAS, City and District are desirous of combining each Party's
respective Projects in order to minimize costs and impacts to the public.
NOW, THEREFORE, in consideration of the mutual promises set forth
herein, the Parties hereto agree as follows:
Section 1: Elements of Agreement. City and District will work
cooperatively together so that City Street Improvements can be combined with
District Project to minimize costs and impacts to the public. The specific terms
and conditions governing the elements of this Agreement are set forth
hereinafter.
Section 2: District's Obligations. District shall:
A. Incorporate a design and pay for construction costs necessary for
the City Street Improvements.
B. Assume responsibility for letting and administering a construction
contract incorporating the District Project and City Street Improvements.
C. Include City approved bid items for the City Street Improvements in
the District Project Schedule of prices. Bid items are to be provided for each
project under separate headings.
7
D. Obtain all permits necessary for construction of the District Project
and City Street Improvements.
Section 3: City's Obligations. City shall:
A. Contract and pay a design consultant to provide design and
construction support services for the City Street Improvements.
B. Reimburse District for the actual cost of construction for the City
Street Improvements between Jamboree Road and the Northside of the Dunes
Main Entrance (Station 17 +00 on City Street Improvement plans, approximately
700 feet), as identified in the schedule of prices set forth in the District's bid
packet. In addition, reimburse District for change orders that are initiated by City
or due to unforeseen conditions in the field directly related to the City Street
Improvements, unless directly related to the District's construction activities and
as approved by the City and District.
C. Reimburse District for the reasonable administrative and
management costs associated with the construction of the City Street
Improvements, as specified in Section 3B above. The administration and
management costs shall be 5% of the total construction costs of the City's portion
of the Street Improvements, including change orders.
D. Provide finished plans and specifications for the City Street
Improvements to District for inclusion into the bid set of contract documents prior
to April 23, 2001, or as soon thereafter as possible.
E. Assume responsibility for inspection services on the City Street
Improvements.
Section 4: Change Orders and Design Addenda. City and District in
their respective obligations shall be given the opportunity to review and approve
all design addenda and construction change orders issued by either Party
pertaining to the work.
Section 5: Timing of Reimbursement. The City shall pay the District
10% of the total cost of the City Street Improvements based on the bid prices by
September 4, 2001. The City shall pay the District 40% of the total cost for the
City Street Improvements prior to the start of work on the City Street
Improvements. The District will notify the City, in writing, 30 days prior to the
start of work on the City Street Improvements. When all work associated with the
City Street Improvements is completed, an accounting shall be performed by
District to determine the remaining amount owed by City, in executing their
obligations under this Agreement. The City will be allowed to review the final
accounting. Upon completion of the accounting and acceptance by the City, an
invoice shall be submitted to City for the amount due, and shall be paid within
forty -five (45) days of billing.
Section 6: Environmental Documentation. District shall be responsible
for compliance with the California Environmental Quality Act ( "CEQA ") as to the
construction activity associated with District's project and City Street
Improvements described in this agreement.
Section 7: Hold Harmless. District shall defend and hold City, its
elected and appointed officials, and employees, harmless from any and all
rd
claims, damages or demands arising out of District's performance of its
obligations under this Agreement.
City shall defend, indemnify, and hold District, its Directors, Officers, and
employees, harmless from any and all claims, damages or demands arising out
of City's performance of its obligations under this Agreement.
Section 8: Insurance. District shall require the construction contractor
for its construction activity to maintain policies of Worker's Compensation
Insurance and General Liability Insurance for personal injury and property
damage, including motor vehicle operators, and products /completed operations
liability and blanket contractual liability during all times of the contract in the
amounts consistent with District's established policies for construction
agreements. Such policies shall name the District and City, its officers, agents,
and employees as additional insureds thereon.
Section 9: Term. The term of this Agreement shall be in full force and
effect until the specified obligations of both Parties have been fulfilled or
rescinded by both Parties.
Section 10: Agents. Any contractor or subcontractor performing work in
connection with the work described herein on behalf of either Party shall be
conclusively deemed to be the servant and agent of each respective Party
employing said contractor or subcontractors hereof, acting on behalf and within
the scope of such contractor and subcontractor employment for said Party.
5
Section 11: Notices. All notices shall be personally delivered or mailed
to the below listed addresses, or to such other addresses as may be designated
by written notice. These addresses shall be used for delivery of service of
process.
To District: Orange County Sanitation District
Attn: Penny Kyle
Board Secretary
10844 Ellis Avenue
Fountain Valley, CA 92708 -7018
To City: City of Newport Beach
Attn: Bill Patapoff
City Engineer
3300 Newport Blvd.
Newport Beach, CA 92663
Section 12: Breach. In the event suit is brought by either Party to
enforce the terms and provisions of this Agreement, or to secure the
performance hereof, each Party shall bear its own attorneys' fees.
Section 13: Force Majeure. Except for the payment of money, neither
Party shall be liable for any delays or other non - performance resulting from
circumstances or causes beyond its reasonable control, including, without
limitation, fire or other casualty, Act of God, strike or labor dispute, war or other
violence, acts of third parties not within City's or District's reasonable control or
any law, order or requirement of any governmental agency or authority.
Section 14: Governing Law. This Agreement shall be governed by the
laws of the State of California in effect at the time of signing this Agreement.
C
r
Section 15: Entire Agreement. This Agreement constitutes the entire
understanding and agreement between the Parties and supersedes all previous
negotiations between them pertaining to the subject matter thereof.
Section 16: Waiver. A waiver of a breach of the covenants, conditions or
obligations under this Agreement by either Party shall not be construed as a
waiver of any succeeding breach of the same or other covenants, conditions or
obligations of this Agreement.
Section 17: Modification. Alteration, change or modification of this
Agreement shall be in the form of a written amendment, which shall be signed by
each Party.
7
IN WITNESS WHEREOF, the parties hereto have executed this
Agreement on the day and year above first written.
Dated
ORANGE COUNTY SANITATION DISTRICT
0
Dated: By
APPROVED AS TO FORM:
THOMAS L. WOODRUFF
DISTRICT COUNSEL
In
Chair, Board of Directors
Secretary, Board of Directors
CITY OF NEWPORT BEACH, a municipal
corporation of the State of California
Dated: By
Dated:
ATTEST:
5Z
Garold B. Adams, Mayor
City Clerk
APPROVED AS TO FORM
Dated: By
City Attorney
F: \Users \PBW\SharedWgreements \Fy 01- 02\OCSD Co-Op Trunk Sewer.doc
8
a✓
_i , \ /
5 <) / ,
D
OZ
�J
OY
aj
a�
C �
m
(-1 ry in
3 m ti
U
Lu
Lu
cc
Z
IW-
W=
WX
W
L 1 ■
'^ L
W U
W
OC O
0 cc
CL
M�
W
U
MQ
�V
/
41VIIII�' � '
I /
C �
m
(-1 ry in
3 m ti
U
Lu
Lu
cc
Z
IW-
W=
WX
W
L 1 ■
'^ L
W U
W
OC O
0 cc
CL
M�
W
U
MQ
�V