Loading...
HomeMy WebLinkAbout07 - C-3322 Balboa Boulevard RehabilitationNovember 13, 2001 CITY COUNCIL AGENDA ITEM NO. 7 TO: Mayor and Members of the City Council FROM: Public Works Department SUBJECT: BALBOA BOULEVARD REHABILITATION FROM MEDINA WAY TO ADAMS STREET, CONTRACT NO 3322 — COMPLETION AND ACCEPTANCE RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond 1 year after Council acceptance. DISCUSSION: On December 12, 2000, the City Council authorized the award of the Balboa Boulevard Rehabilitation from Medina Way to Adams Street contract to All American Asphalt, Inc., of Corona, California. The contract included the construction of storm drains, curb inlets, water main and sewer main, and the repaving of approximately 57,000 square feet of roadway with rubberized asphalt. The construction also included the replacement of deteriorated and sub - standard sidewalk and curb access ramps. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $1,076,395.50 Actual amount of bid items constructed: 1,036,459.60 Total amount of change orders: 107,565.50 Final contract cost: $1,144,025.10 The decrease in the amount of actual bid items constructed under the original bid amount resulted from the substitution of a glass -grid interlayer to replace the asphalt hot -mix interlayer and crack seal. The final overall construction cost including change orders was 9.99 percent over the original bid amount. SUBJECT: Balboa Boulevard Rehabilitation from Median Way to Adams Street, Contract No. 3322 - Completion And Acceptance November 13, 2001 Page 2 A total of five change orders were issued to complete the project. They were as follows: 1. $46,950.00 provided for the construction of a parallel sewer in order to reconnect existing laterals on one side of Coronado Street. 2. $28,413.00 provided for the concrete paving of one -half of Coronado Street where the storm drain and sewer had been constructed. 3. $20,938.50 provided for the installation of 38,775 square feet of glass -grid interlayer beneath the asphalt surface. 4. $8,381.43 provided for additional water main installation work. 5. $2,882.57 provided for revisions to two street lighting poles and conduit in the island on Balboa Boulevard. Funds for the project were expended in the following accounts: Description Account No. Amount Gas Tax 7181- C5100399 $ 588,266.60 Water Distribution and Piping 7501- C5500386 290,475.00 Storm Drain Improvement 7012- C5100008 189,920.50 Sewer Main Inprovements 7531- C5600292 60,448.00 Sewer Pump Station Improvements 7532- C5600100 2,829.00 Sewer Manhole Lining 7533- C5600101 12,086.00 Total $1,144,025.10 The original scheduled completion date was May 8, 2001. Due to weather delays and underground utility conflicts, the work was extended to June 19, 2001. The work was substantially completed on that date. Minor miscellaneous punch list items were completed and final quantity measurements were agreed upon on October 19, 2001. Respectfully submitted PUBLIC WORKS DEPARTMENT Stephen G. Badum, Director By: /�• 4"il lj2A? R. Gunther, P.E. Construction Engineer