HomeMy WebLinkAbout12 - Balboa Village Improvement ProjectApril 9, 2002 CITY COUNCIL AGENDA ITEM NO. 12 TO: Mayor and Members of the City Council FROM: Public Works Department SUBJECT: PROJECT STATUS & APPROVAL OF AMENDMENT NO. 6 TO THE PROFESSIONAL SERVICES AGREEMENT WITH PSOMAS FOR THE BALBOA VILLAGE IMPROVEMENT PROJECT RECOMMENDATIONS: Approve Amendment No. 6 to the Professional Services Agreement with Psomas for the Balboa Village Improvement Project in the amount of $91,215. This Amendment supplements the Phase 1 construction services budget and provides a design budget to revise the construction and bid documents for Phase 2. The Amendment also provides for a time extension to the Agreement. 2. Authorize the Mayor and City Clerk to execute Amendment No. 6. 3. Approve a Budget Amendment approving the transfer of funds in the amount of $12,179 from Account No. 7181- C5100070 to Account No. 7181- C5100543. REVIEW OF THE PLANNING, DESIGN, AND CONSTRUCTION SERVICES BUDGET On May 23, 2000, Council authorized the City to execute an Agreement with Psomas to provide pre- design, design, and construction services for the Balboa Village Improvement Project for a fee of $493,131. Five amendments totaling $252,176 have been previously approved for planning, design, and design revision tasks. (Amendment No. 5 for $130,195 was approved by Council on May 8, 2001.) Tasks covered by the previous amendments included: • Participating in expanded planning activities and working on design development for the streetscapes, Peninsula Park refurbishment, pier plaza redesign, and the landmark tower concept and preliminary design. • Designing landscape areas for the pier plaza, Oceanfront median area, and Peninsula Park. • Researching options for replacement street trees. • Preparing parking design options for Bay Avenue. • Preparing design options for Balboa Boulevard. • Modifying the design for underground utilities. • Revising the storm drain alignment in Washington Street. • Planning and design for the storm drain outfall across Edgewater into Newport Harbor. • Designing a new storm drain tide gate and vault. SUBJECT: PROJECT STATUS & APPROVAL OF AMENDMENT No. 6 TO THE PROFESSIONAL SERVICES AGREEMENT WITH PSOMAS FOR THE BALBOA VILLAGE IMPROVEMENT PROJECT April 9, 2002 Page 2 • Design and revising parking, hardscape, trees, landscape, traffic, and utilities improvements throughout the Village. • Adjusting the drawings to accommodate a change in the limits of Phase 1 construction. • Providing supplemental survey. • Revising drawings to accommodate new construction phasing. • Providing enhanced project planning and coordination. AMENDMENT NO. 6 Amendment No. 6 totals $91,215. It provides $54,740 to supplement Phase 1 construction services and $36,475 for Psomas to revise the Phase 2 bid and construction documents. During the course of this complex revitalization project, several opportunities arose to improve and 'fine tune' the project design in an effort to improve the overall quality and aesthetics of the completed project. The construction services and design tasks to accommodate those revisions and improvements in Phase 1 include: • Extensive community coordination for the review of hardscape and landscape aesthetic treatments including investigating alternative colors, patterns, textures, and treatments. • Redesigning and coordinating the pier plaza seat walls, street furniture, planters, irrigation, concrete benches, and concrete trash receptacles to improve contructibility and durability of the completed product. • Preparing a palm tree relocation plan and hand selecting 60 King Palms. • Preparing a landscape plan for the area at the north end of Washington Street at Edgewater including special treatment to hide the tide gate vault. • Preparing as -built plans for the construction revisions. Phase 2 design tasks include: • Revising the Phase 2 drawing set to accommodate changed conditions discovered during Phase 1 construction and to ensure compatibility with completed Phase 1 improvements that were revised from the original plans. • Revising plans to accommodate future electrical service the proposed Balboa Theatre. • Adding low- voltage uplighting on palm trees along Palm Street both north and South of Balboa Boulevard. • Adding irrigation and street light conduit to accommodate changes in the construction phasing to add Main Street North of Balboa Boulevard into Phase 2 and Balboa Boulevard East of Main Street into Phase 3. Designing a Fire Department connection near the Balboa Pavilion. • Completing the Palm Street seashell pattern plan and specification. • Preparing a striping delineation plan for Oceanfront sidewalk/bikeway. • Preparing Phase 2 bid specifications and special provisions. • Assisting in the preparation of a staged construction plan. • Preparing a circulation and parking plan (to be evaluated in conjunction with the construction staging approach and shall include OCTA bus circulation, tourist bus circulation, pedestrian access requirements & signage, City parking permits, and City parking policies for metered areas). SUBJECT: PROJECT STATUS & APPROVAL OF AMENDMENT NO. 6 TO THE PROFESSIONAL SERVICES AGREEMENT WITH PSOMAS FOR THE BALBOA VILLAGE IMPROVEMENT PROJECT April 9, 2002 Page 3 Funding for this work is available in the following accounts: Description Balboa Peninsula Improvement Balboa Village Plan EIR/Preliminary Plans Account No. Amount 7161- C5100361 $ 4,456.00 7181- C5100543 $74,580.00 7181- C5100070 $12,179.00 Total $91,215.00 Staff is requesting a Budget Amendment to transfer $12,179 from Account No. 7181 - 05100070 to Account No. 7181- C5100543. This transfer of funds will ease the trace ability of the expenses with the Balboa Village project. If approved, the term of Psomas' agreement will be extended to December 31, 2003. REVIEW OF PROJECT PHASING The Village Project has three construction phases. Phase 1, with a construction budget of approximately $3.5 million, will complete by June 2002. The major components of Phase 1 include: • Reconfiguring and resurfacing the pier parking lot including adding new bus bays. • Reconstructing the street and sidewalks on Balboa Boulevard (Adams Street/Main Street) • Installing a new storm drain system with new outfall to the Bay. • Installing a new water main in Balboa Boulevard. • Installing new street lights along Balboa Boulevard and in the pier parking lot. • Reconstructing the pier plaza. • Constructing an egress road from the A Street Parking Lot. • Installing new trees on Balboa Boulevard and in the pier parking lot. • Installing new street furniture. Phase 2 is scheduled to begin on September 9, 2002. The Phase 2 construction budget is estimated at $2.0 million. The recently approved $2.4 million CDBG loan will fund the Phase 2 improvements. In this phase, the construction tasks include: ■ Reconstructing the Oceanfront boardwalk and median area, ■ Reconstructing Main Street for the pier parking lot to the Pavilion. • Reconstructing Washington Street and Palm Street from Oceanfront to Balboa Boulevard. • Adding new trees on these streets. • Installing new streetlights and street furniture on these streets. Phase 3, scheduled to begin in September 2003 has an estimated cost of $1.5 million. The following project elements are slated for construction in Phase 3: • Reconstructing Washington Street and Palm Street from Balboa Boulevard to Edgewater. SUBJECT: PROJECT STATUS & APPROVAL OF AMENDMENT NO. 6 TO THE PROFESSIONAL SERVICES AGREEMENT WITH PSOMAS FOR THE BALBOA VILLAGE IMPROVEMENT PROJECT April 9, 2002 Page 4 • Reconstructing Bay Avenue from Palm Street to Main Street. • Installing an odor control system in the vicinity of Bay Avenue and Washington Street. • Widening the sidewalk on Balboa Boulevard from Main Street to A Street. • Adding new trees on these streets. • Installing new streetlights and street furniture on these streets. • Installing a new irrigation system and new turf in Peninsula Park. CONCURRENT PROJECTS In the Balboa Village area, there are also several other projects that are anticipated to be in construction sometime during the implementation of Phase 2 and 3 of the Village Project including: • The Balboa Inn expansion could be starting construction in Fall 2002. • The Orange County Sanitation District is anticipating construction of a replacement pump station at Balboa Boulevard and A Street in January 2003 with a 14 -month construction schedule. • The formation of an Underground Utilities Assessment District for the Village is underway. Construction is anticipated for the spring of 2003. CONSTRUCTION MANAGEMENT Harris & Associates is providing the day -to -day construction management of the Phase 1 Village improvements. Staff anticipates the City will need to hire a construction manager for the remaining two phases to inspect the proposed improvements, as well as to help coordinate the Village construction with the other proposed project in the area. Respectfully sub aged, _ PUBLI ORKS DEPARTMENT Stephen G. Badum, Director By: Robert Stein, P.E. Project Manager Attachment: Amendment No. 6 BALBOA VILLAGE IMPROVEMENT PROJECT AMENDMENT NO.6 TO PROFESSIONAL SERVICES AGREEMENT WITH PSOMAS THIS AMENDMENT NO. 6 TO PROFESSIONAL SERVICES AGREEMENT, entered into this day of , 2002, by and between the CITY OF NEWPORT BEACH, a municipal corporation, (hereinafter referred to as "CITY ") and Psomas, whose address is 3187 Red Hill Avenue, Suite 250, Costa Mesa, California, 92626, (hereinafter referred to as "Consultant'), is made with reference to the following: RECITALS: A. On May 23, 2000, CITY and CONSULTANT entered into a Professional Services Agreement, hereinafter referred to as "AGREEMENT', for final design and construction support services for the Balboa Village Improevement Project, hereinafter referred to as "PROJECT ". B. CITY and CONSULTANT have entered into five separate AMENDMENTS of the AGREEMENT, the latest dated May 8, 2001. C. CITY desires to enter into this AMENDMENT NO. 6 to reflect additional services not included in the AGREEMENT or prior AMENDMENTS and to extend the term of the AGREEMENT to December 31, 2003. D. CITY desires to compensate CONSULTANT for additional professional services needed for PROJECT. E. CITY and CONSULTANT mutually desire to amend AGREEMENT, hereinafter referred to as "AMENDMENT NO. 6 ", as provided here below. NOW, THEREFORE, the parties hereto agree as follows: 1. CONSULTANT shall be compensated for services performed pursuant to this AMENDMENT NO. 6 according to Exhibts "A, A -1, B, B -1 and B -2" attached and dated March 26, 2002, attached hereto. 2. Total additional compensation to CONSULTANT for services performed pursuant to this AMENDMENT NO. 6 shall not exceed ninety -one thousand, two hundred fifteen and 00/100 Dollars ($91,215.00). 2003. 3. The term of the AGREEMENT shall be extended to December 31, 4. Except as expressly modified herein, all other provisions, terms, and covenants set forth in AGREEMENT shall remain unchanged and shall be in full force and effect. IN WITNESS WHEREOF, the parties hereto have executed this AMENDMENT NO.6 on the date first above written. CITY OF NEWPORT BEACH, A municipal corporation L3' APPROVED AS TO FORM: Mayor City of Newport Beach City Attorney ATTEST: LaVonne Harkless City Clerk Psomas M f:WSers \pbw\shared\agreements \fy 0"2\psomas - amendment no. 6.doc BALBOA VILLAGE IMPROVEMENT PROJECT AMENDMENT NO. 6 TO PROFESSIONAL SERVICES AGREEMENT WITH PSOMAS THIS AMENDMENT NO. 6 TO PROFESSIONAL SERVICES AGREEMENT, entered into this day of , 2002, by and between the CITY OF NEWPORT BEACH, a municipal corporation, (hereinafter referred to as "CITY ") and Psomas, whose address is 3187 Red Hill Avenue, Suite 250, Costa Mesa, California, 92626, (hereinafter referred to as "Consultant'), is made with reference to the following: RECITALS: A. On May 23, 2000, CITY and CONSULTANT entered into a Professional Services Agreement, hereinafter referred to as "AGREEMENT', for final design and construction support services for the Balboa Village Improevement Project, hereinafter referred to as 'PROJECT ". B. CITY and CONSULTANT have entered into five separate AMENDMENTS of the AGREEMENT, the latest dated May 8, 2001. C. CITY desires to enter into this AMENDMENT NO. 6 to reflect additional services not included in the AGREEMENT or prior AMENDMENTS and to extend the term of the AGREEMENT to December 31, 2003. D. CITY desires to compensate CONSULTANT for additional professional services needed for PROJECT. E. CITY and CONSULTANT mutually desire to amend AGREEMENT, hereinafter referred to as "AMENDMENT NO. 611, as provided here below. NOW, THEREFORE, the parties hereto agree as follows: 1. CONSULTANT shall be compensated for services performed pursuant to this AMENDMENT NO. 6 according to Exhibts "A, A -1, B, B -1 and B -2" attached and dated March 26, 2002, attached hereto. 2. Total additional compensation to CONSULTANT for services performed pursuant to this AMENDMENT NO. 6 shall not exceed ninety -one thousand, two hundred fifteen and 00/100 Dollars ($91,215.00). 2003. 3. The term of the AGREEMENT shall be extended to December 31, 4. Except as expressly modified herein, all other provisions, terms, and covenants set forth in AGREEMENT shall remain unchanged and shall be in full force and effect. IN WITNESS WHEREOF, the parties hereto have executed this AMENDMENT NO. 6 on the date first above written. CITY OF NEWPORT BEACH, A municipal corporation L]' APPROVED AS TO FORM: Mayor City of Newport Beach By: City Attorney ATTEST: LaVonne Harkless City Clerk Psomas F-.W f :\users\pbw\shared\agreements \fy 01- 02\psomas - amendment no. 6.doc P S O M A S Memorandum Exhibit A Additional Service Authorization Date: March 26, 2002 Client: City of Newport Beach Project: Balboa Village Psomas Project No. 2NEW060300; City of Newport Beach Project No.: 3333 Psomas Project Manager Reference Change Order — Phase I I am forwarding a change order prepared by Psomas, Austin -Foust and Nuvis for extra work solicited by the City on the Phase I Construction. The support requested by the City has been substantially beyond that anticipated by the original contract, and a number of design tasks, not anticipated by the original contract, have been added to our scope during the construction phase. I. Construction Support — The number of construction and coordination meetings held on the project have been higher than budgeted; extensive coordination has been needed to properly control issues related to the hardscape aesthetic treatments; and the number of RFI's being generated by GCI to the Psomas team are more than budgeted in the original scope of work. At the City's request Psomas is estimating about 6 hours of coordination effort per week for an anticipated period of 15 weeks to complete the project. A description of Nuvis' tasks and manhours is attached. 2. The City has asked that the Pier Plaza be redesigned at the request of GCI so that the project can be completed on schedule. Psomas activities include revising the base geometry, revising the horizontal control plan, revising tree well locations, eliminating and adding lights to the plaza, revising the plaza grading, and revising all top -of -wall and top -of- footing callouts along the seat wall. A description of Nuvis' tasks and manhours is attached. 3. The Psomas team must prepare as -built drawings for the Phase I construction. In Psomas' case, the anticipated amount of work required to prepare the as -built drawings is anticipated to be higher than the original budget prepared for this task. This assessment is based upon discussions with Omar Dandashi and Emmet Berkery. Austin- Foust's construction support budget included a dollar and manhour amount intended to cover both support and as- building the drawings. The amount of support requested of Austin - Foust has been higher than budgeted and they no longer have any budget remaining to prepare the as -built plans. A description of AFA's manhour estimate to prepare the as -built plans is attached. 4. Nuvis has been asked to prepare a Palm Tree Relocation Plan. A description of their scope and manhour estimate is attached. Psomas has provided some coordination manhours for this effort. 5. Nuvis has been asked to provide a detail and color palette of the circular pattern at the northeast comer of Balboa and Palm. Psomas has helped coordinate this effort and hours have been included to add the detail to the as -built plans after completion of the work. Assumptions: • Our work needs to be done by June so that the bidding and award of the work will occur during the summer and work can actually begin just after Labor Day. • As- builts won't be fully available until May, Psomas may need to revise this estimate based upon the amount of as -built information received at that time. Project Manager $140/hr 120 Ins CAD Tech $85/hr 30 hrs Nuvis $32,390 Austin -Foust $2,500 Reproducibles $500 C:\WINDO WS\Temporary Internet Files \OLKCI81 \020226 Ph 1 Const Changes.doc P S O M A S Additional Services Fee: $ 54,740 Type of Fee: (check one) _ Lump Sum _ Time & Materials X Time & Materials, not to exceed: $ 54,740 Psomas Manager: (signature required) Neil Gillis, Project Manager (Date) Client Authorization: (signature required) (Name) (Title) C: \WINDOWS \Temporary Intemet Files \OLKCl81 \020226 Ph 1 Const Changes.doc (Date) P S O M A S Exhibit B Project Manager $140/hr 120 hrs CAD Tech $85/hr 30 his Nuvis $32,390 Austin -Foust $2,500 Reproducibles $500 MAR.27.2002 5:59PM MIS N0. 113 P. 1 FAX /TRANSMITTAL. To: Bob Stein Dates 3/27/03 City of Newport Beach Project Balboa Village Project #t 00- 210,01 ❑ By Delivery ❑ For Approval �- ❑ By Mail ❑ Review and Comment ❑ Overnight Information W U V I S Fox ❑ Distribution of pages is inclusive of cover sheet. Please Coll (71:41754-7311 ex 230 if all pages are not transmitted. LANOSCAPI ARCNITECTURE A N D ► L A N N r N e Bob: As requested, please fined o copy of the task and hourly breakdown for Phase One INNOVATIVE AND Change Orderitem #1. RESPONSIBLE DESI6N SOLUTIONS FOR OUR ENVIRONMENT Irrigation Valve Plan: (One Auto Cad Drawing @ 1 " =20' on a 30 "x40° sheet) Meetings- Project Principal had a total of two on site meetings of the request of City Staff to review Irrigation Volvo relocation olternofives. (The total meeting time was three and a half hours) Revised Irrigation Plan- Nuvis under direction of City Staff and General Contractor developed a Auto Cod Drawing showing all irrigation revisions along Balboa Avenue. See attached reduced pion for additional information. (The total number of hours to develop this drawing was twenty two plus on odditionol two hours on site to verify existing conditions in addition to two and a half hours of Principal review.1 Site Furniture Relocation Plan: 3151 AIRWAY AVENUE, SURE 1-3 (Three Auto Cad Drawings @7' =20' on 30'x40" sheets) COSTA MESA, CALIFORNIA Meetings- Project Principal had a total of five meetings at the request of City Staff and U.S.A. 97626 -4640 Construction Management to review and select alternative 40 gal. trash cons, add TX: 714.754.7346 additional 32 gal. bosh cons @ Balboa Avenue, coordinate replacing metal benches with PH: 714.754.7311 E-MAIL- NUV15 {M4i+RUYIS.NET concrete benches and coordinate revised drawings City Staff. he total meeting time g tY (The 9 was seven hours) Revised Site Furniture Poo- Nuvis under direction of City Stoff developed Auto Cod Drawings showing locations of revised Site Furniture, quantities and locations. (The total COSTA MESA, CALIFORNIA number of hours to develop this drawing package was twenty plus one hour of Principal SAN RAMON, CALIFORNIA review) LAS VEGAS, NEVADA Signed: CALIFORNIA 1246 NEVADA 396 cc: MAR.27.2002 5:59PM NUVIS N0. 113 P. 2 FAX /'TRANSMITTAL To: Bob Stein Dote: 3/27103 City of Newport Beach Project: Balboa Village Project #: 00.210.01 ❑ By Delivery ❑ For Approval �� ❑ By Mail ❑ Review and Comment i7 V I S ❑ Overnight Information N Fax ❑ Distribution _# of pages is inclusive of cover sheet, Please call if all pages ore not transmitted. LANDSCAPE ARCNITECtURE A N P P L A N N I IN G Palm Tree Relocation Plan: (Two Auto Cad Drawings @ 11 =201 on 30 °xA011 sheets) A PREMIER RESOURCE FOR Meetings- Project Principal Under direction from City Stoff was asked to develop a strategy INNONATIVEANDCOMPR9eUMe and plan that would best cotegorize the existing palm trees at the pier parking lot. Nuvis DESIGN SOLUTIONS FOR OUR ENVIRONMENT attended a total of five meetings during this period several to "cifically identify and verify over one hundred palm trees. (The total meeting time was fifteen hours) Revised Palm Tree Relocation Plan- Nuvis under direction of City Staff Developed Auto Cod Drawings illustrating exact locations of all palm trees to be relocated of the new pier parking lot. ( The total number of hours to develop this package was eight plus one hour of Principal review.) Palm Tree Selection: As requested by City Staff Nuvis spent eight hours hand selecting over 60 King Palms In Son Diego for Phase 1 and spent four hours reviewing photographs of alternate palm trees and reviewing planting revisions due to the lack of King Palm ovoilability, S CROW CANYON COURT. #110 Tide Gate Vault: SAN RAMON, CALIFORNIA See attached hourly breakdown for estimated hours. U.S.A. 9,1583.1621 .F%: S 1 0 . 6 2 0 2 7 1 1 Estimated Construction Support5ervlces: PH; 5 1 0. R 2 0.2 7 7 2 The estimated nine hours a week is based on the overage of on site meetings that are requested from City Staff and Construction Management for o number of tasks due to design modifications and documentation, COSTA MESA, CALIFORNIA Please feel free to contact me if you additional information, SAN RAMON. CALIFORNIA 105 ANGELES, CALIFORNIA Sincerely, LAS VEGAS, NEVADA MESQUITE. NEVADA CALIFORNIA 1226 Signed: Perry A. Cordozo cc: Neil Gillis MAR. 27. 2002 9:11AM NUVIS N0. 093 N. 2 3127/03 Phase I Support Services hourly breakdown for item #1 Change Order dated 3125102 Irrigation Valve Plan 24Yus @ $70 ($1,680) 6brs @ $110 ($660) Total $2,340 Site Furniture Relocation Plan 20 hrs @ $70 (1,400) Shrs @ $110($880) Total $2,280 Palm Tree Relocation Plan , 16hrs @ $70($1,120) Stirs @ $110 ($880) Total $2,000 Palm Tree Selection - 12hrs @ $110 ($1,200) Total $ 1,200 Tide Gate Vault Preliminary Design 10hrs @ $110 ($1,100) Working Drawings Construction Details, Planting & Irrigation 25hrs @ $70 ($1,750) 8hrs @ $110 ($880) Total 2,630 Estimated Construction Support Services: 15 weeks @ 9hrs a week @ $110 ($14,850) (Starting Feb -18 -May 27) Subtotal Request for Change Order Item $25.300 IF L_ R.27.2002_ 6:OOPM -NUVIS NO. 113: waeE,eteo�awe�n t4114- lip r k f m g B�i L 15i: 8 oil u;F a � 9 3 Ni B€ Y V 4: .r r I � S I ___I P. 3 �Q rip 4: .r r I � S I ___I P. 3 iw " 9 4f 27.2002— 6:OOPM —NUVIS N0. 11 1 1F �a�A NO vi• 0n i I P. 4 ptltl 111,00060 06 qp fa 1p 4 egga�o $��# iii Rob � ®00 0000 O 00 �'viq � � r $ Ell o�q "f3�R6 llp 1110. Is gy �rvg a € gg aa § p a ® lot P. 4 a 2 1� 27.2002— 6:O1PM-- -NUV1S N0. 11 e � 'R A F if 9 na a °ges iy i$ 4g; a tl� w� 1 1-9 F;WI 1 I "'TVV a nom law-BOA am ME BELOW le wo 01 . I°Mc"- m0-r >- $ra �ldflq®oo� ®m# Ze. if P. 6 I m e6 . 1 = a 5 9Y9 2 YI a AR. 21.2002_ 6:03PN -NUVIS N0. 113, 4 � �°q°ca m 0 -i a� $ r p a E j y o 0ti y¢F AAA i it it I * 9 Q¢ y M11 ® 4 am L C � P. B P S O M A S Exhibit A - I Memorandum Additional Service Authorization Date: March 26, 2002 Client: City of Newport Beach Project: Balboa Village Psomas Project No. 2NEW060300; City of Newport Beach Project No.: 3333 Psomas Project Manager Reference Change Order— Phase 2 1. Provide recommendations to the Phase 2 drawing set and revise accordingly. Emmet Berkery will redline plans for CAD drafting by Psomas. Psomas estimates that revisions to each of 3 intersections will require about 2 hours of minor CAD drafting for each. The revisions for the frontage road revisions will be more extensive and an allowance of 6 hours has been provided for drafting revisions to that area. 6 hours of coordination time has been provided for the Project Manager (and I hour for participation of Project Principal in the Phase 2 design activities) has been included in this task. Descriptions and manhours estimates for both Nuvis and Austin -Foust tasks are attached. 2. Contact Edison and show the proposed theatre vault in Main St at Alley 256U. Confirm with SCE that the 2 vents near BJ's must remain in place. Emmet Berkery will contact SCE and coordinate the placement of the SCE Vault for electric service to the theater. Actual design work will be performed by SCE; Emmet will provide Psomas with a redlined plan which will define the location of the theater vault. Psomas will provide CAD drafting to include the vault on our improvement plans. 3. Add low- voltage uplighting on palm trees along Pahn Street both north and south of Balboa Blvd. Psomas has prepared a budget of hours to coordinate this work by Emmet Berkery and City Staff, with support from Nuvis. Nuvis will prepare a total of two lighting alternatives for the Fan Palms at Palm Street and submit to the City for approval. The two alternatives will consist of a providing cut sheets showing a low voltage light fixture alternative as well as a 120 volt light fixture as the second alternative. Emmet and City staff will prepare construction drawings for transformer locations, service connections and conduit runs. The estimate assumes that Psomas will not have to make extensive plan sheet modifications to Sheets 13 and 14, "Main Street Improvement Plans," which should be the only Psomas plans impacted by the proposed revisions. 4. As needed, modify irrigation drawings to provide irrigation to Main Street N/o Balboa Boulevard and on Balboa Boulevard E/o Main Street No conduit may run in the street through the Main Street intersection pavers. If needed, consider if conduit can be in the sidewalk area of the Main Street Intersection. Modify the street light drawings to provide power to Balboa Boulevard street lights E/o Main Street, Eliminate any conduit crossing within the street at the Main Street intersection. Consider if conduit can be run in the sidewalk area of the Main Street Intersection. Psomas has prepared a budget to coordinate this work by Nuvis and Austin- Foust. Descriptions and manhours estimates for both Nuvis and Austin -Foust tasks are attached. Nuvis will review the irrigation drawings for Main Street north of Balboa Boulevard and consider if the system will be battery or electric powered for phases 2 and 3. The irrigation system will be resized C:IWINDOWSUemuorary tntemetRes\OLKC181 \032602 Pb 2 Revisions sldoc : P S O M A S accordingly and the drawings modified.. On Balboa Boulevard east of Main Street, Nuvis will consider if the irrigation system will be battery or electric powered and they will resize the system accordingly. Austin- Foust will redesign the existing lighting system to provide power to streetlights on Balboa east of Main Street. AFA proposed to do the following: a) Recalculate existing system voltage drops to see if it can accommodate the streetlights. b) Redesign existing system to add these street lights or design new system with new power source to provide power to these lights. c) Modify all plans to reflect this new design. 5. Design FDC (Fire Department Connection) at Pavillion. Emmet Berkery will coordinate and prepare redlines for a FDC in the vicinity of the Pavillion at the north end of Main Street Psomas will prepare a design sheet for the work defined by Emmet. 6. Complete the Palm Street seashell pattern plan spec. Psomas has prepared a budget of 1 hour to coordinate a specification section modified by Nuvis. The City will coordinate the incorporation of Nuvis' modification into the specification. Nuvis' task description and budget is attached. 7. Need striping delineation for Oceanfront. Coordinate with Paul Taylor. Psomas has prepared a budget of 2 hours to coordinate this work by Austin- Foust. Austin - Foust's task description and budget is attached. 8. Revise specs and estimate as needed. Emmet Berkery will perform this task. Psomas will provide up to 6 hours of support for this task, helping Emmet identify new specification requirements and also help him prepare the bid item list. 9. Stage Construction and Schedule based on funding. (Support for Omar and Emmet) Psomas and Austin -Foust will provide support for this activity, which will be performed by the City and other support staff. Psomas will provide up to 4 hours of support. A description of Austin - Foust's scope and manhour estimate is attached. 10. Circulation and Parking Plan (to be evaluated in conjunction with the construction staging approach and should include OCTA bus circulation, tourist bus circulation, pedestrian access requirements & signage, City parking permits, City parking policies for metered areas) Psomas will provide input and minimal coordination to this task, which will be primarily performed by Austin -Foust and Emmet Berkery. City staff will provide limits of work and design criteria to Austin - Foust. Austin -Foust will revise traffic and pedestrian control plans to accommodate the staging plan defined by the City. Assumptions: • Our work needs to be done by June so that the bidding and award of the work will occur during the summer and work can actually begin just after Labor Day. • As- builts won't be fully available until May, Psomas may need to revise this estimate based upon the as -built information that is not yet available. • Survey activities are not included. If survey is deemed necessary a supplemental budget will be prepared or City staff will provide the requested data. • Billing rates have been adjusted to reflect rates currently used on other Psomas Public Works projects. C:\ WINDOWS \Te orary Internet Files\ OLKC181W32602 Ph 2 Revisions rasl.dx^: "'° te• et dae P S O M A S • 4 hours of coordination time for Gary Dysart has been spread throughout the various tasks. Project Director $150/hr 4 hrs Project Manager $140/hr 36 bra Design Engr $95/hr 8 bra CAD Tech $85/hr 29 hrs Project Asst $60/hr hrs Nuvis & A -F $24,010 Reimbursables $3,600 Additional Services Fee: $ 36,475 Type of Fee: Time & Materials, not to exceed: $ 36,475 Psomas Manager: (signature required) Gary Dysart, Project Principal (Date) Client Authorization: (signature required) (Name) (Title) C:\ WINDOWS \TenIDorary Internet Files \OLKC181 \032602 Pb 2 Revisions rasl.doc . (Date) NUVIS Exhibit B 1- BiMbg Rates Name Title Billing Rate Robert R.Cardoza SeniorPrinci al $110.00 Leslee A. Temple SeniorPrinci al $110.00 Robert W. Stone Senior Principal $110.00 Perry Cardoza Principal $110.00 TomMttnoz Piinci al $110.00 Jaime Rios Desikner $ 85.00 Linda Forde CADD Tech I $ 70.00 Lamont Mecker CARD Tech 1 $ 70.00 Chris Atencio CADD Tech II $ 55.00 Robert Ftisbie Draftsperson I $ 45.00 Scott Downey Drafts erson II $ 35.00 May 11, 2000 ziZ'd 69G, OW WdE0:0T 0002'TT',kdW ®Ar�AUST /N FOUST ASSOCIATES, INC, TRAFFIC ENGINEERING AND TRANSPORTATION PLANNING 2020 NORTH TUSTIN AVENUE • SANTA ANA, CALIFORNIA 92705.7827 Effective January 1, 2000 AUSTIN -FOUST ASSOCIATES, INC. INDIVIDUAL RATE SCHEDULE Exhibit B —Z TELEPHONE (714) 667 -0496 FAX (714) 667 -7952 E-mail: mail @austinfoust.com CATEGORY HOURLY RATE Principal Terry Austin $135 Joe Foust $135 Design Engineer Rick Chavez $105 Transportation Engineer Cathy Lawrence $95 Jamie Anderson $90 Pat Kelley $80 Design Drafter Rob Steaffens $70 Technical /Clerical Connie Woodward $55 Joanne Herbel $50 Direct expenses billed as actual costs of City of Newport Beach BUDGET AMENDMENT 2001 -02 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates Increase Expenditure Appropriations PX Transfer Budget Appropriations SOURCE: from existing budget appropriations rq from additional estimated revenues from unappropriated fund balance EXPLANATION: NO. BA- 038 AMOUNT: $12,179.00 Increase in Budgetary Fund Balance AND Decrease in Budgetary Fund Balance X No effect on Budgetary Fund Balance This budget amendment is requested to provide for the following: To transfer funds provide for Amendment No. 6 to the professional services agreeemnt related to the Balboa Village Improvement Project. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account REVENUE ESTIMATES (3601) Fund /Division Account EXPENDITURE APPROPRIATIONS (3603) Description Description Signed: Signed: Signed: Financial Administrative City Manager City Council Approval: City Clerk Amount Debit Credit $12,179.00 $12,179.00 Z Date Date Description Division Number 7181 Gas Tax Account Number C5100070 EIR/Preliminary Plans Division Number 7181 Gas Tax Account Number C5100543 Balboa Village Plan Division Number Account Number Division Number Account Number Division Number Account Number Signed: Signed: Signed: Financial Administrative City Manager City Council Approval: City Clerk Amount Debit Credit $12,179.00 $12,179.00 Z Date Date