CITY COUNCIL AGENDA
ITEM NO. 9
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: COOPERATIVE AGREEMENT BETWEEN THE CITY OF IRVINE AND
THE CITY OF NEWPORT BEACH FOR THE INSTALLATION OF
MEDIAN LANDSCAPING ON JAMBOREE ROAD BETWEEN CAMPUS
DRIVE AND BRISTOL STREET
RECOMMENDATION:
Approve the Cooperative Agreement between the City of Newport Beach (Newport
Beach) and the City of Irvine (Irvine) for the installation of median landscaping on
Jamboree Road between Campus Drive and Bristol Street, and authorize the Mayor
and the City Clerk to execute the Agreement.
DISCUSSION:
Staff is requesting that the City Council approve a cooperative agreement for the
installation of median landscaping along Jamboree Road between Campus Drive and
Bristol Street. Because the City boundary line generally exists along the centerline of
Jamboree Road this project involves the cities of Newport Beach and Irvine. Prior to
construction of these improvements, a cooperative agreement must be executed by
both City Councils. Irvine's City Council will be meeting on April 9, 2002, to authorize
its Mayor to sign the agreement.
The cooperative agreement outlines the total installation costs and administrative roles
and responsibilities for construction and maintenance of the project. The proposed
improvements include the removal of existing median pavement and the installation of
stamped colored concrete, shrubs, ground cover, and irrigation control systems.
As outlined in the Agreement, Newport Beach will supervise the construction of this
project within established budgets and time frames and will complete the project using
guidelines established by both the cities of Newport Beach and Irvine. The final design
drawings and cost estimates have been reviewed and approved by both cities.
Construction is anticipated to start in May of 2002.
The total cost for the project is estimated at $264,000, which includes a 10 percent
contingency. Irvine will reimburse Newport Beach for Irvine's share of construction costs
estimated at $72,700. The total cost for construction administration, survey, testing, and
inspection is estimated at $36,000 of which Irvine would be responsible for $9,900.
SUBJECT: COOPERATIVE AGREEMENT BETWEEN THE CITY OF IRVINE AND THE CITY OF NEWPORT BEACH
FOR THE INSTALLATION OF MEDIAN LANDSCAPING ON JAMBOREE ROAD BETWEEN CAMPUS DRIVE
AND BRISTOL STREET
March 21, 2002
Page 2
The total landscaped area is approximately 23,380 square feet and 5,920 square feet are
within Irvine's city limits. Total annual irrigation and maintenance costs for the median
planters are estimated at $2,700 and Newport Beach will pay these costs. Irvine will
reimburse Newport for 25 percent of that total annual cost.
The Project will be awarded this fiscal year and the budget provides a total of $200,000.
$100,000 for the City's share of this project is available in Account No. 7261- C5100580
and $100,000 for Irvine's share is available in Account No. 7251- C5100580.
Respectfully submitted,
PUBLIC WORKS DEPARTMENT
Stephen G. Badum, Director
By: �&/
Stephen J. Luy, P. L.
Project Manager
Attachments: Agreement
Project Location Map
ru
COOPERATIVE AGREEMENT
For
Jamboree Road Median Improvements from Bristol Street to Campus Drive
This Agreement is made and entered into this day of , 2002, by and
between the CITY OF NEWPORT BEACH ( "Newport Beach') and the CITY OF IRVINE
( "Irvine "):
RECITALS
WHEREAS, the median reconstruction of Jamboree Road between Bristol Street and Campus
Drive, is a project that involves Irvine and Newport Beach because the city boundary line exists
along the centerline of the Project.
CONTRACT TERMS AND CONDITIONS
Newport Beach will supervise the construction of the Project to the best of its ability within the
established budget and time frame, and shall implement and complete the Project under
guidelines established by the Cities of Newport Beach and Irvine, and will follow all public bid
and contract procedures.
2. The terms of this Agreement cover the administrative responsibilities of the parties with regard
to the Project, but not the actual construction of the Project itself, although Newport Beach will
cause the construction to be completed.
3. Irvine has reviewed and signed the final design drawings and reviewed the engineer's
construction cost estimate (Attachment "A "). Irvine shall receive a complete breakdown of the
actual construction costs prior to invoicing, and shall be invoiced for its portion of the cost
incurred by Newport Beach upon completion of the construction phase.
4. The total cost for the project is estimated at $264,000, which includes a 10% contingency.
Subject to prior approval by Irvine of the award for the construction contract, Irvine will
reimburse Newport Beach for Irvine's share of construction costs estimated at $72,700. The
total cost for construction administration, survey, testing, and inspection is estimated at $36,000
of which Irvine would be responsible for $9,900. Newport Beach will invoice Irvine when the
project is complete and Irvine shall make payment to Newport Beach within 30 days of the
invoice.
5. Additional consulting services affecting Irvine shall be reviewed and approved by Irvine.
6. Change orders affecting Irvine shall be reviewed and approved by Irvine prior to granting
approval with the Contractor.
The total landscaped area is approximately 23,380 square feet of which 5,920 square feet is
within Irvine City limits. The total annual irrigation and maintenance costs are estimated at
$2,700. Newport Beach will pay for irrigation and maintenance for the median planters. Irvine
will reimburse 25% of that total cost to the City of Newport Beach, estimated at $675. Irvine
will be invoiced annually and payment is due within 30 days of the invoice.
8. Inspectors and/or engineers from both Cities will coordinate for spot construction inspections
and a site walk prior to completion of the project.
9. As referenced in the Drawings, Special Provisions, Proposal and Contract for the Project, the
"Owner" shall refer to Newport Beach and the contract responsibilities held by Newport Beach.
10. Newport Beach shall require that the independent contractor provide the necessary insurance
coverage for construction work, as specified in Section 6 -1 of the Special Provisions and
Section G of the Contract for the Project. Newport Beach and Irvine shall be named as
additionally insured parties in the Special Provisions and Contract for the Project, and shall be
insured for the amounts specified in Section 6 -1 of the Special Provisions and Section G of the
Contract.
11. The following staff members, or as otherwise designated in writing by the City Manager of
Irvine or the City Manager of Newport Beach, shall be the selected representatives of each City
to act in each respective City's behalf with respect to this Agreement. Any notices, requests,
approvals, or communications shall be given to each representative noted below:
To Newport Beach:
Bill Patapoff
Public Works Department
P.O. Box 1768
Newport Beach, CA 92658 -8915
(949) 644 -3321
To Irvine:
James H. Eldridge
Public Works Department
P.O. Box 19575
Irvine, California 92623 -9575
(949) 724 -7556
12. Each of the parties agrees to do all things in a timely manner reasonably necessary or
convenient to carry out the spirit, intentions and objectives described in this Agreement whether
or not expressly prescribed herein and no consent, agreement, approval, concurrence, decision,
determination or action shall be unreasonably withheld by either party.
13. Any controversy or claim arising out of this Agreement or alleged breach thereof shall first be
resolved through voluntary mediation or as otherwise designated in writing by the City Manager
of Newport Beach or the City Manager of Irvine. Said City Managers shall be the selected
representatives of each City to act in each respective City's behalf with respect to this
Agreement.
14. Newport Beach shall indemnify, defend, save and hold harmless Irvine, its City Council,
officers, and employees from and against any and all loss, damages, liability, claims, allegations
of liability, suits, costs and expenses for damages of any nature whatsoever, including, but not
limited to, bodily injury, death, personal injury, property damages, or any other claims caused
by the willful actions or active negligence of Newport Beach, its employees, or agents in the
performance of its obligations pursuant to this Agreement, and shall include attorneys' fees and
other reasonable costs incurred in defending any such claim.
2
15. Irvine shall indemnify, defend, save and hold harmless Newport Beach, its City Council,
officers, and employees from and against any and all loss, damages, liability, claims, allegations
of liability, suits, costs and expenses for damages of any nature whatsoever, including, but not
limited to, bodily injury, death, personal injury, property damages, or any other claims caused
by the willful actions or active negligence of Irvine, its employees, or agents in the performance
of its obligations pursuant to this Agreement, and shall include attorneys' fees and other
reasonable costs incurred in defending any such claim.
16. This Agreement represents the entire understanding of the parties as to those matters contained
herein, and no prior oral or written understanding shall be of any force or effect with respect to
those matters covered in this Agreement. This Agreement shall be governed by and construed
in accordance with the laws of the State of California, and construed as if drafted jointly by
Irvine and Newport Beach. This Agreement may be amended at any time by the mutual consent
of the parties by an instrument in writing.
17. The persons executing this Agreement on behalf of the parties hereto warrant that they are duly
authorized to execute this Agreement on behalf of said parties and that by so executing this
Agreement the parties hereto are formally bound to the provisions of this Agreement.
This Agreement shall be made effective upon execution by both parties and shall remain in effect
until project reimbursement is complete or both parties agree to amend or terminate it.
IN WITNESS WHEREOF, Newport Beach and Irvine have caused this Agreement to be executed
by its duly authorized officers and representatives, respectfully, on this day of
, 2002.
CITY OF NEWPORT BEACH
By: Tod W. Ridgeway, Mayor
By: City Clerk
APPROVED AS TO FORM:
By: City Attorney
CITY OF IRVINE
By: Larry Agran, Mayor
By: City Clerk
10]]18
i
r
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
ABOREE ROAD MEDIAN IMPROVEMENTS
BRISTOL STREET TO CAMPUS DRIVE
I,
CONTRACT NO. 3459
DATE
DRAWING N0. EXHIBIT A