Loading...
HomeMy WebLinkAboutSS3 - Civic Center Project - Handout 1January 13, 2015 Agenda Item No. SS3 The Newport Beach Civic Center Close -Out Report and Lessons Learned January 13, 2015 Study Session of the Newport Beach City Council by Dave Kiff, City Manager, and Steve Badum, Assistant City Manager Dear City Council and Other Readers: As far back as April 1998, then -City Manager Kevin Murphy asked the community and City Council to begin planning for the long -term facilities needs of the city government (see Exhibit A). A case in point at that time was the City Hall building, constructed in 1947 and then 50 years old. Our report today attempts to summarize many — but not all — of the actions taken by public leaders since that time, actions that have resulted in the construction of the Civic Center at 100 Civic Center Drive, built at an "all - in" cost of about $140.2 million, if costs (hard construction costs, soft costs, planning costs, environmental review costs, insurance and inspections, and more) from mid -2008 through 2013 are taken into account. We both helped coordinate this project, and we are proud of how it came out. It was not a perfect process, from outreach to construction, but projects this large rarely are. When completed, it: • Was the result of over 100 public meetings and Council actions, as well as a public vote on Measure B, the action that in effect moved City Hall's operations from the Peninsula to the current site. • Was communicated to our residents via meetings with service clubs, HOAs, business associations, and mailed community newsletters 13 different times between 2008 and 2013, newsletters that went to every residence and business in the City (about 54,000 separate addresses). • Took advantage of a large downturn in the economy to build five needed different projects in one, saving millions had the five been built separately. These projects were: • An expansion of the Central Library • A City Hall, with a community room, Council chambers, a "one- stop" permit counter and disaster preparedness center. • A 15 -acre park, including a Civic Green, a dog park, and new landscaping around the Library. • A pedestrian bridge to easily link two sides of the park. • A 450 -space parking structure, 100 of which are for the Library. • Took over four years —from planning to completion —to build and occupy. • Was privately managed by a well -known construction manager (CW Driver), and had all elements of construction go out to public bid, where the lowest qualified bidder got the job. • Excavated 200,000 cubic yards of material, all to sink the buildings below a view plane, and comprising about $8 million of the cost. • Had over 700 change orders, most small in magnitude, but resulting in 6.1% of the total project cost (about in line with industry norms). • Caused significant debate in the community thanks to its cost, some of its design (like the wave roof and the sail), and aspects like the play elements for kids (the rabbits) and the cafe for Library users. • Was funded by a combination of debt (about $124M) and cash (the remaining $18.5M), which was the largest debt issuance by the City. Debt service is about 4.72% of General Fund revenues, and is declining slowly. SS34 • Has been used and enjoyed by residents, visitors, and the city employees who work here. We all feel very honored to work in such an impressive facility. After we describe the path to the Civic Center and its construction, we offer in this document our "lessons learned." We have tried to be critical of ourselves and our process, without casting blame beyond what we ourselves learned and accept. At the same time, we remain proud of the facility and the work done, and hope that others do as well. Constructing a public building in this era, when there is a general and strong concern about the scope and size of government expenditures (one we accept and often share), isn't easy and often isn't a popular action — but it was our assignment, and we took it on willingly. Sincerely, DAVE KIFF City Manager STEVE BADUM Assistant City Manager The Path to the Civic Center. In 2001, the Newport Beach City Council asked: "do we need to improve and or rebuild the City Hall ?" At that time, the City Hall complex consisted of four buildings of mixed age (the oldest building constructed in 1945) of approximately 44,000 square feet ( "SF "). Most of the circulation for the buildings was outside, in the nearly - always pleasant Newport Beach elements. At the time, City operations were a bit squeezed —we needed an additional 4300 SF and ultimately expanded into four additional trailers. Early Planning. At a July 24, 2001 Study Session, the City Council directed staff to pursue a long term strategic plan in the form of a City Hall Facilities Master Plan. At subsequent meetings, the City Council retained outside consultants to conduct a Space Needs Assessment (how much SF should be constructed) and to prepare conceptual and schematic plans to: • Replace the current City Hall at 3300 Newport Boulevard. • Replace Fire Station #2 (Lido); and • Construct a parking structure to accommodate City Hall needs. Several public workshops, study sessions, and regular Council meetings were held to develop the final concept. There was significant controversy over the cost of the consultants, and several residents spoke to the City Council about the roughly $560,000 cost for concept design efforts. As the wheels of this Project moved very slowly and deliberately, by now it's mid -2005. At the August 23, 2005 meeting, City Council approved a concept design that included: • A 72,000 SF City Hall with the ability to expand it 8,000 more SF if needed. • A 2,600 SF Community Room. • A replacement Fire Station; and • A roughly 35' tall parking structure with 350 spaces. SS3 -2 The City Hall office building was to utilize "tilt up" construction (similar to typical warehouse construction) and was estimated to cost $49,757,000 (in 2005 dollars). This cost was "all -in" — design, permitting, CEQA, soft costs, and hard costs. In 2006/07, the City Council membership evolved through an election and several appointments. At least three Council members had moved on to opportunities outside of the Newport Beach, resigning from their positions. New Council members were appointed, subject to election at the next general election. The new Council members wanted to take a fresh look at two things: (1) whether and how the City could afford a new City Hall; and, if so (2) where it should be located. On January 24, 2006, the City Council formed two committees — the Facilities Finance Review Committee and the City Hall Site Review Committee - to explore these issues. The appointed committee members were residents and /or business people that had extensive experience in financial and real estate matters, respectively. The Facilities Committee, working with staff, developed what is now the Facilities Financing Plan (FFP) to project the City's building facilities and other major infrastructure needs over the next 20 years. The committee held five public meetings to discuss issues and receive public comment. The committee's final report determined that the City could afford to construct a new City Hall along with a variety of other facilities' needs, but it also recommended issuing debt — specifically, Certificates of Participation (COPs). The COPS were to be paid back under a "level funding" concept, and funded by three "buckets" of revenues: 1. City reserves saved up for facilities purposes. 2. An annual contribution from the General Fund; and 3. Developer fees from large community projects, like the PIMCO Tower and more. The debt service would be low compared to City General Fund revenues — staying below 5% debt to General Fund Revenue. At that time, adjacent cities typically had debt ratios of as high as 17 %. The FFP is still in use today and continues as a tool for City Council to analyze and make financial decisions. Today, the City's debt to General Fund ratio is about 4.72% The second group, the City Hall Site Review Committee, conducted six public meetings, analyzed 22 sites throughout the city, and received over 70 public comments. Although there was a strong desire to centralize the location of City Hall in the Newport Center area, no sites near there were deemed appropriate, and this Committee recommended keeping the City Hall at the existing Peninsula location (3300 Newport Boulevard). One site that was very controversial was the site of the proposed "Newport Center Park" between Avocado and MacArthur (the location of the current Civic Center). The Site Review Committee didn't recommend it, and the Council itself was split on whether to use this location. This came on a 4 -3 vote, with current Council members Curry and Selich voting not to consider moving City Hall to the Newport Center Park site. By now it's 2007. A group of concerned citizens led by Bill Ficker, a renowned local architect and yachtsman, liked the idea of moving City Hall to the Newport Center Park site, and felt that the centralizing of the City Hall in Newport Center should be voted on by the people. The group gathered the necessary signatures to place the question on the February 2008 ballot, in the form of an amendment to the City Charter. This was Measure B. SS3 -3 Measure B, if passed, would say that City Hall must be located at the Newport Center Park site. The campaign was boisterous — "City Hall in the Park" versus something akin to "Save Newport Center Park. City officials — including staff — stayed out of the debate, as is the law. Nor did City staff comment on or have a role in developing what became campaign statements (including estimated costs of the project) on either side (see Exhibit B for an example of one campaign mailer). The February 2008 vote was 16,938 (52.9%) in favor to 15,092 (47.1 %) opposed. Measure B became the law of the land — and the placement of City Hall is in the City Charter (Section 425): Section 425 City Hall. City Hall, including most administrative offices of the City and related parking, shall be located on the City -owned parcel bounded by Avocado Ave. on the west, Son Miguel Dr. on the north, MacArthur Blvd. on the east and the Newport Beach Central Library on the south. In an effort to heal the community after a divisive vote, the City Council — led by then -Mayor Ed Selich — said words to the effect of "if we're going to do this, let's do it as a community and do it right." The Council initiated planning for the "City Hall in the Park" concept. Mayor Selich and the Council's unanimous goal was to provide a park for the park supporters while meeting the voter mandate to locate the City Hall in Newport Center at the Avocado site. At a meeting on February 26, 2008, the City Council confirmed that the City will be moving forward to build a new City Hall and large park at the vacant City -owned 12 -acre site north of the City's Central Library on Avocado Avenue. Included in the park's design and development would be the vacant 3.5 acre site north between San Miguel Road and the OCTA Transportation Center along Avocado Avenue. The next step in this effort was to select an architect. To ensure that the community's wishes were forefront in the effort, the City Council established the City Hall Design Committee, a group of five local resident architects. They were to meet in open, public sessions (in late afternoon and evening) at the Central Library to work with the community to develop "parameters" (later referred to as the General Design Parameters) for a design for the City Hall in the Park, and then to conduct an Architectural Design Competition. The Committee was formed on March 25, 2008, less than two months after the Measure B vote. The City Hall Design Committee held two public meeting to collect input and establish the design parameters for the City Hall in the Park. The parameters included considerations such as: • Access in and around the site and circulation • Building heights, and how that would impact public views • The approximate square footage for floor plans • Advice on costs per square foot for construction • A requirement that the City Hall and Park be connected to and with the Central Library. • A 450 -space parking structure • The style of the park (passive, not active —just as the Newport Center Park idea was more passive • Other park amenities, such as play areas. • And sustainability and LEED considerations. SS3-4 It was at this time that the Project grew most significantly in scope. The design parameters specifically recognized that this project would be more than a City Hall — it became a true "civic center" with parking, a park, and the library expansion in addition to the City Hall. The requirement that the Project stay below a "view plane" protecting public views from MacArthur was a significant statement — it also meant that the site would have to undergo massive (and costly) excavation. The City Council later discussed and amended the General Design Parameters, and adopted them at a public meeting on April 22. 2008 (see Exhibit Q. At the time, staff members and Council members spoke about the significant change in the Project scope. The architects' Design Committee continued with three public meetings to develop the design competition process over Spring and Summer 2008, generally at the Central Library. The Committee reviewed over 50 qualification proposals from various architectural firms, local, national, and international. After careful consideration, the Design Committee recommended five (5) design finalists to the City Council. City Council approved the top five finalists and awarded a $50,000 stipend to each firm to develop their design proposal based on the General Design Parameters. Later, each firm would make a presentation as to its proposal for the City Hall and Park. In late summer 2008, the finalists presented their design concepts over two public Design Committee meetings. There were also three additional meetings for public discussion of the presented design concepts. One was a 12- hour meeting on Saturday, September 27, 2008 at the City Council Chambers at 3300 Newport Boulevard — open to the public and with full presentations by the five design teams (see Exhibit D - agenda for this meeting). The Design Committee ranked the finalists and recommended Bohlin Cywinski Jackson (BCJ) of San Francisco as the top firm, with LPA second. BCJ's team included a number of subcontractors, including Peter Walker Partners (PWP) as landscape architect, and ARUP as civil engineers. After a detailed discussion, the City Council approved that recommendation and awarded a contract to BC1's team to further develop their conceptual plan on January 13, 2009. Concurrent with the design competition, the City Council stated that it wanted the private sector to manage this project, and that it should be done as "Construction Manager at Risk" (CM @R). Additionally, the Council wanted the construction manager to have a public low -bid process (with pre - qualification to ensure quality) for the various elements of the Project. These elements — like glass, steel, drywall, electrical, and more - ultimately became sixty (60) public bid packages, responses to which had to be opened in a local hotel's conference center to accommodate the crowds in November- December 2010. The City Council's three - member Building Committee (Council Members Selich, Rosansky, and Webb) with City staff conducted a selection process to hire the program manager to dig in early with the architect to help oversee Project design. This added to the planning costs, as the program manager was compensated for all of this time, but the goal was to ensure a project that was efficient and constructible. At the same time, the Building Committee was reorganized to include the same three Council members and three members of the Design Committee, whose work had ended. Following another request for qualifications process (RFQ versus an RFP) and interviews, seven firms were considered for selection as construction manager. The top firm was determined to be C.W. Driver. SS3 -5 At a public meeting on January 13, 2009, the City Council approved a contract with C.W. Driver to manage the design process. Starting soon after hiring, C.W. Driver, BCJ, and various City staff met on a regular basis to develop the final concept with periodic consultation with the Building Committee. At the same time, the City Council hired consultants to provide the detailed environmental analysis, documentation and technical support for the project. As an aside here, the major design phases of any large project are: • Concept Design (CD) • Schematic Design /Design Development (SD /DD) • Construction Documents (CD) Then the architect usually participates in "construction support" during the construction phase, responding to "requests for information" (RFIs) as the project is built. The Newport Beach Civic Center project actually had a pre- Concept Design phase in addition to the above, thanks to the design competition. At the conclusion of the Concept Design, staff and the architect presented a proposed concept to the City Council at a noticed public meeting for public discussion and approval. The concept included an: • An 85,000 square foot City Hall office building • A 5,250 SF Community Room • A 6,750 SF Council Chambers • A 450- space, four level parking structure • A 17,000 SF expansion to the Newport Beach Central Library, including an expanded Children's section, a cafe for Library patrons, a media lab, a sound lab, and a full second entrance connecting the Central Library with the Civic Center • A 14 -acre passive park utilizing a combination of native plants and low water or "California friendly" plantings with public walkways, a dog park, a pedestrian bridge over San Miguel, elements for kids to play on, and a restored wetlands. This is Where the Rabbits Come In. And there is a story behind the rabbits, which we relay in Exhibit D. More about the size of the Civic Center's office building. As a brief sidebar, we often hear about concerns over the size of the Civic Center as compared to the plan that was proposed at the old location. The plan at the old site including a Council Chambers and Community room proposed a floor plan of about 72,000 SF with consideration for future expansion to 80,000 SF. Our new site including the Council Chamber, Community room, an EOC is about 100,000 SF. Here are the reasons for the differences: • The design at the old site had all of the mechanical equipment (heating & AC) on the roof. A combination of the General Design Parameters height limitation and the chosen wave roof design, it was necessary to put an additional 6,000SF of mechanical space in the new building. • The former design envisioned more external circulation and less direct public access to the various City Departments (the plan called for walking through some departments to get to others). The current design has internal public walkways directly to each department and adds another 6000 SF. • Our new building has more vertical circulation or stairwells than what was proposed in the old plan ( +1000 SF) SS3 -6 • We also added a 3,000 SF EOC to our current facility. • The former plan had 10 conference rooms. Our design team did an assessment based upon the annual meetings scheduled (from our reservation system) and determined that we would need about 15 conference rooms and a hearing room. Although by personal observation we don't seem to have any scheduling problems, so we could have lived with a few less. This added approximately 5,000 SF more. • Another factor that added space was the narrowness of our site. Our new building is long and not deep, which helps at natural light, but is not the most efficient shape for office space. Square floor plans are generally the most efficient shape as it balances the circulation space required for a given work space. The former site was closer to that ideal. Adding the additional space from the above list the difference shrinks to approximately 7,000 SF and less depending on what value is assigned to the building shape inefficiency. The majority of this additional space is attributable to the public spaces which have generous waiting areas. The General Design Parameters set the employee space at 200 -250 SF per employee. The actual employee space is calculated at 187 SF per employee based upon the current employee count. Our Timeline — Mid -2009. The City Council approved the concept and authorized contracts with BCJ and C.W. Driver to continue with the schematic design and design development (SD /DD) phases of the project design on April 14, 2009. During the SD /DD process, groups associated with the Library and other community advocates from CERT asked the Council to consider a larger community room and a large Emergency Operations Center (EOC). There were several Council meetings and study sessions that: • Set the final size of the community room (at 5,250 SF including storage and a catering kitchen). • Added an EOC (of 3,000 SF) in the basement level. • Discussed "value engineering" of the facility's construction; and • Discussed potential phasing for the Project, including the proposed pedestrian More about Cost Estimating Before the start of the design process in March 2009, an independent construction estimator, C.P. O'Halloran Associates, prepared a Preliminary Concept Cost Estimate. The estimated cost of Project construction at that time was $107,633,286 without contingencies. With the addition of estimated design, project management, environmental documentation, ancillary costs including furniture, the preliminary budget was $140 million. During the subsequent design process, the design team, staff, and the Building Committee meet regularly to guide the project. A significant part of those meetings explored ways to reduce potential costs through value engineering and phasing. At the November 10, 2009 Council meeting, staff shared the current costs. At that meeting staff shared the possible scenarios from conservative to very optimistic. The very optimistic estimates envisioned: • Being able to sell or give away the dirt from the excavation at a savings of $4 million; • An additional 10% reduction for a better bid environment of $9 million; • Additional value engineering at $5 million; and • Phasing the bridge and North Park parcels for a later project at $7 million. Additional cost estimates were run at each stage of the project design. At the conclusion of the Design Development phase (April 2010) another estimate by the same firm showed the construction cost to be $102,779,710. An estimate in October 2010 by C. P. O'Halloran showed the cost to be $103,816,895. C.W. Driver also ran an independent estimate in October 2010 and their projected cost was $106,796,863. Despite our hopeful thinking, the final bid totaled $106,504,125 which was very close to the preliminary estimate in 2009. SS3 -7 bridge connecting the North Park and Dog Park to the central portion of the park. Importantly, the phasing discussions at the time looked through several scenarios that might reduce Project costs. At the Council meeting of November 10, 2009, we talked with the Council and community about the range of all -in costs, and suggested that these hard and soft costs (and contingencies) could be up to $140 million. In addition to the public meetings, the Building Committee continued its periodic meetings to guide the design process. On November 24, 2009, City Council certified the Environmental Impact Report (EIR) for the Project and, in a change of plans, authorized C.W. Driver to prepare a Design -Build request for proposals (RFP) to solicit bids to design and construct the 450 -space parking structure separate from other scopes of work. The thinking at the time was that it would be less costly to design -build the parking structure, given the large amount of local qualified firms who could do that kind of work. The SD /DD plans were completed in early April 2010. Along with the SD /DD plans, the grading plans were prepared as a separate project phase to enable the timely export of over 200,000 cubic yards of fill and the construction of a shoring wall to prepare the site — including the parking structure - for facility construction. During this same time, the national and local economy was suffering greatly from the recession — many firms doing large infrastructure work were hungry for projects. We had extensive discussions about this unique time to build, when labor and materials were relatively inexpensive. On April 27, 2010 the City Council approved the Civic Center's SD /DD plans along with a contract amendment with BCJ to proceed with the preparation of construction documents (CD). At the same meeting, Council continued program design management with C.W. Driver and executed the construction manager at risk contract with C.W. Driver. More about Construction Manager at Risk — CM @R. CM @R is an "alternative project delivery method" that has a proven track record with reducing costs and delays that many municipalities and state agencies have used with great success. The CM @R process allows a quality based selection (versus having to accept low bid) of the Construction Manager (CM), but it allows for competitive bidding by pre - qualified sub - contractors for the various components of the project. The CM @R process also provides a Guaranteed Maximum Price for the project. The CM @R process is as follows: • The City requests proposals from interested construction management firms, interviews the top firms, and selects the best qualified firm. • The City negotiates a contract with the firm that includes four components: ✓ Component #1: Basic Services or General Conditions. These include the fixed costs for the construction field office (including construction trailers, office equipment, portable restrooms, copiers, computers, telephone and equipment) and the necessary personnel to staff the project (including superintendent, inspection and support staff). These fixed costs are billed on a "time and materials" basis at a cost "not to exceed" a certain amount. Based upon our project concluding in January of 2013, our Basic Services were set at a cost not to exceed $7,169,255. ✓ Component #2: The actual cost of the construction work. The cost of the work will be set as a Guaranteed Maximum Price (GMP). The GMP will include the actual, opened bid prices of the competitive bid packages plus an internal contingency. Under the CM @R project delivery method, the construction manager bids out the various construction trade contracts in accordance with the Public Contract Code and oversight from the City Clerk. The City Council then approves the expenditure at a SS3 -8 public meeting and accepts the construction manager's GMP proposal for the work. The Construction Manager is then responsible for delivering all work and construction included in the approved work scope for the maximum cost stated in the GMP. Any costs exceeding the GMP will be borne by Construction Manager. Any savings under the GMP will be shared by the City and Construction Manager. The Civic Center & Park project was set up with the City receiving 75% of any savings and C.W. Driver receiving 25% of any savings as an incentive to reduce overall costs. However, additional work added to the project by the City or caused by unforeseen problems are generally except from the GMP. ✓ Component #3: Direct Expenses. These include the direct costs for bond premiums; general liability insurance; and additional services as requested by the City. Direct expenses include known costs and allowances for variable items, and are not marked up — they are passed along at the direct cost of the Construction Manager. ✓ Component #4: Project fees to manage the construction. These construction management fees represent the markup, overhead, and profit for the Construction Manager. The Basic Services, Direct Expenses, and GMP represent actual costs without any markups, overhead or profit. The rate for the Civic Center & Park construction management fee was set at 3.25% for the entire project, which is fairly typical —even on the low side —for a project of this scope. Parking Structure, Mass Excavation, and Shoring Wall. Also at the April 27, 2010 meeting, the City Council authorized the first phase of construction, and started to build the Project as well as the CM @R Contract with CW Driver —the CM @R contract gets built in phases, just like the Project. The first part of the CM @R Contract was the Mass Excavation and Shoring Wall Construction, at a guaranteed maximum price (GMP) of $ 7,336,439. Phase 1's work was completed by late August 2010. Concurrently, the City and C.W. Driver received bids from the three pre - qualified bidders to design -build the 450 -space parking structure. On September 14, 2010, the City Council approved Amendment #1 to C.W. Driver's contract to design -build the parking structure with Bomel Construction as a subcontractor. The amendment added $7,426,853 to the GMP. As that work proceeded, bid packages for the various trades started being released to pre - qualified bidders for the City Hall Office Building, the Central Library Expansion, and the park. This process continued in Fall 2010, and all bids we received and tallied by the end of January 2011. C.W. Driver packaged those bids for the second amendment to the GMP. More about COPS and Bonded Debt. In 2010, the City had about $80 million in reserves, some designated for specific purposes and a minimal amount of outstanding debt. In accordance with the recommendations of the Facilities Finance Review Committee and the approved Facilities Financing Plan, it was determined that the City had sufficient debt capacity to finance the remaining portion of the Civic Center Project without effecting ongoing services or reserves. Following a vigorous review by all three bond rating agencies, Moody's, Standard and Poor's and Fitch, the city was awarded AAA underlying bond ratings by all three bond rating agencies. This is the highest rating achievable and Newport Beach become one of only five California cities to achieve this distinction. The bond ratings confirmed the ability of the City to undertake the financing without a tax increase. Because the Facilities Financing Plan confirmed that the financing could be accomplished without raising taxes, the City chose to use Certificates of Participation (COPS) as the financing vehicle for the Civic Center. General Obligation (GO) Bonds, the other alternative, requires voter approval because the issuance includes an authorization to add a levy on the property tax to pay for the debt. This was not necessary in the case of the SS3 -9 Civic Center. COPs utilize a lease structure, and have been the most commonly used technique in California to finance municipal improvements since 1978, following court validating decisions. During the two year period 2009 -2010, Congress had authorized Build America Bonds (BABs) as part of the American Recovery and Reinvestment Act (ARRA). Congress' goal was to Federally support local public works improvements and thus create jobs. The City took advantage of ARRA in other ways, too — for the remaining $18M to complete Upper Bay's dredging and for money to replace streetlights (and more). BABs are taxable bonds. However, the Federal Government agrees to pay 35% of the interest cost for the life of the bond issue. In our case, this amounts to a subsidy of $2.35 million annually. The City, like all municipal issuers at the time, conducted a cost - benefit analysis during the bond pricing process and determined that for the great majority of the debt issued, BABS would be less costly (by approximately $750,000 annually in debt service), than traditional tax exempt bonds. Also during the bond pricing, because of near record low interest rates, we determined that the outstanding debt related to the (1992) library COPS in the amount of ($10 million) could be refunded for savings of $120,000 annually. This component was added to the transaction. The total par size of the transaction was $127 million, of which $116,515,000 remains outstanding. The net debt service payment to the city is $8.32 million or 4.7% of general fund revenues. It's 2011 Now. On February 22, 2011, the City Council approved this Amendment #2 to the GMP to add the construction of the City Hall Office building, the library expansion, and the park to C.W. Driver's Construction Manager at Risk contract. At this time, Council decided to add the construction of the pedestrian bridge over San Miguel Drive back into the Project for an additional $2 million. However, one million of the additional cost was funded within C.W. Driver's internal construction contingency, so the net cost to the City was only $1 million (GMP Amendment #3). Plan Check and Inspection. Importantly, at the same time as the bids were awarded, the City made the decision to NOT use our qualified in -house staff to plan check and inspect the Civic Center project. This action added about $1.5M in defined cost to the Project, but to us it was worth it — it protected the rest of Newport Beach's residents and business owners from delays in reviewing plans for and inspecting their private home remodels and other construction projects. The City Council authorized outsourcing the building plan check and building official services for the Civic Center project to Anderson - Penna /Interwest at a cost of $1,426,285. On April 24, 2012, The City Council approved Amendment #4 to the CM @R contract with C.W. Driver for smaller items like project signage and dry utility connections (Gas, Electric, Data) in the amount of $476,281. This work was not included in the original contracts. The signage design work was delayed and could not be bid with the other bid packages, however, this late addition did not affect the construction schedule. The dry utility work, primarily SCE, was problematic in that SCE revised their design late in the schedule to reflect actual field conditions. This work did cause some delay in the overall schedule. SS3 -10 Amendment #5 to the CM @R contract was approved by City Council on October 23, 2012. During the construction demolition process on the north wall of the existing Central Library, it was discovered that the existing clerestory window system — built back in 1994 and at a location that had a persistent water leak - was failing. The failure (and possibly incorrect installation) was the cause of the ongoing storm water leakage problems. The original Project plans called for reuse of the clerestory windows, but it was quickly determined that a full replacement was needed. This cost another $720,913. This problem along with other miscellaneous existing problems with the structure eventually cost the Project another $1.5 million inclusive of design and related costs. About Furnishings. Near the end of the project, City staff and BCJ interior designers established selection criteria for the City Hall and Library s furniture, fixtures and equipment (FF &E). The criteria focused on balancing cost, quality, ergonomics, sustainability, and effectiveness in creating a professional and efficient workplace. Additionally, the City had stopped major purchases of furnishings in advance of the move to the Civic Center, assuming that we would save expense by not moving new furnishings from one location to another — we'd just wait until the new facility opened. After much research, the team selected four (4) furniture manufacturers /vendors on the basis of their experience, availability of local dealerships, references, and the ability to participate in government pricing programs. Each vendor representing a manufacturer was invited to bid on each piece of furniture. On June 26, 2012, city Council approved several FF &E bid packages totaling $2,755,000 for the Civic Center and $525,521 for the Central Library expansion. More about furnishings is Exhibit E. Move -In and Final Efforts. The City moved into the new facility in early April 2013. Work continued on minor items and the EOC with the completion of all work by June 2013. C.W. Driver requested that the City cover their extended Basic Service /General conditions costs beyond the original completion date of January 2013. Staff negotiated extended general conditions in the amount of $1,400,000 representing discounted fixed costs from January 2013 through May 2013. City Council approved those costs on October 8, 2013. ...and Finally. The final cost of the Civic Center & Park project less the Library repair costs was $140,214,967 including "all in" cost such as design, environmental, project management, construction support, inspection, change orders, and FF &E. SS3 -11 Civic Center Facilities Percentage of Overall cost Hard Construction Costs (including Change Orders) Share of Soft Costs including design & mngt FF &E OCIP Total cost by Facility Mass Excavation and Shoring Wall 7% $8,033,927 $ 1,555,788 $ 132,229 $ 9,721,945 Parking Structure 7% $7,549,072 $ 1,461,895 $ 124,249 $ 9,135,216 Park 13% $15,219,881 $ 2,947,365 $ 250,502 $ 18,417,748 Library addition and repair 11% $12,909,468 $ 2,499,948 $ 525,521 $ 212,475 $ 16,147,412 City Hall 51% $58,251,156 $ 11,280,470 $ 2,570,000 $ 958,747 $ 73,060,374 EOC 2% $2,055,923 $ 398,134 $ 85,000 $ 33,838 $ 2,572,895 Community Room 3% $3,597,866 $ 696,735 $ 50,000 $ 59,217 $ 4,403,818 Council Chambers 1 4% 1 $4,625,8271 $ 895,8021 $ 50,000 1 $ 76,1361 $ 5,647,765 San Miguel Bridge 1 2% 1 S2,158,6271 $ 418,023 1 1 $ 35,5291S 2,612,179 100% $114,401,747 $ 22,154,161 $ 3,280,521 1,882,922 $ 141,719,351 Library Repairs = $ 1,504,384 "Total Cost less Library Repairs = $ 140,214,967 ff # # In More Detail More about Schedule. The Timeline in Exhibit F shows the City Hall — Civic Center journey of over 12 years from start to finish. There were over 100 separate Council meetings & study sessions, public committee meetings or public workshops. In addition to the public meetings, countless presentations were made to community associations, service groups, and business associations. The original project schedule developed by C.W. Driver required a 6-8 month window of excavation and a 24- month window to construct the project. We were fortunate that nothing surprised us during the mass excavation of the site except a minor issue with drilling through rock. Our archaeological and environmental monitoring consultants found no issues. One issue that was significant was the tight window we had to get in the queue to fabricate the project's steel structure. Because of the complexity of the design, many questions were asked in the form of RFIs (Request for Information) by the steel fabricator. Unfortunately, the clarification and additional information needed to resolve these RFIs caused us to miss our fabrication window. C.W. Driver worked diligently to recover some of the time, but ultimately we lost about three months total time — and later the steel contractor filed a delay claim. Other minor delays also occurred such as the dry utilities issues discussed above and various weather delays. Overall with the exception of the steel fabrication issue, the project proceeded well. The construct and design teams worked hard to bring us back on track after each minor schedule issue. More about Change Orders and Contingency Amounts. If you spend any time with an architect, engineer, or builder and you'll hear them say "there's no such thing as a perfect set of plans." Change orders become a necessary (if unwelcome) part of any project. They certainly were part of this Project, although remarkably they stayed within industry averages. The Civic Center and Park project experienced contractual changes of about 6.1% of project cost. Change orders fell into these categories: SS3 -12 1. Building Code compliance 2. Unforeseen changes 3. Design enhancements 4. Items omitted from the original contract plans. Typically, a Project's contingency fund(s) would accommodate change orders. But with this Project, well before the City entered the project's construction phase, the project team and City Council deliberately set an ambitious goal of keeping contingencies very low - at 2.5% ($2,623,000) of the total construction cost. We optimistically (and maybe foolishly) thought we could beat the odds, and also didn't want to open the door to a free - spending contingency. The first big impact to the $2.6M Owner's Contingency came when the City reinforced the importance of the missing Pedestrian Bridge — it was in the initial plans but not part of the first phase of the Project. It would connect the two park parcels — it would help people use both parks, and would help to keep traffic moving along San Miguel by reducing street -level pedestrian crossings. Addition of the bridge to the Project reduced the contingency fund to $1.6 million. Despite considerable effort and oversight, the amount of contract change orders went from the initial goal of 2.5% of the total construction cost to about six percent (6 %). As noted, six percent is a typical contingency amount for a construction project of this magnitude. To help put the contingency amount in perspective, there were about 750 separate project change orders, and most of those were under $10,000 each. Change orders by dollar and category were: Newport Beach Civic Center Change Order Category Amount % of Total Building Code / City Requirements $730,000 11.2% Unforeseen Conditions $470,000 7.2% Design Enhancement $1,000,000 15.4% Design Omission $4,300,000 66.2% Total Change Orders $6,500,000 The largest percentage of change orders occurred in the design omission category. These were 4% of the overall construction cost. Here's where an important "lesson learned" comes in. The City team put the bid packages out to bid in November and December 2010 with some design work not fully complete. This was done to take advantage of what we assumed was a brief (and closing) window of lower labor and materials costs due to the significant downturn in the national economy. SS3 -13 We feel we rushed it. From a design perspective, the design team likely needed an additional three to six months to refine the construction documents, and they told us this. That action likely contributed the level of design omissions. But at the same time, we guessed correctly that the construction costs would rise. The Engineering News - Record's Cost Index ( "ENR Cost Index ") increased 3.6% from September 2010 (bidding period) to May 2011 — that translates into $3.8 million for this Projects cost elements. If we can assume that any plans would have had at least 2% of design omission issues, we probably came out ahead by $1.5 million. We understand that this action is worthy of discussion and a second review. More about Cost. Overall, we were fortunate to time the project during the economic downturn when costs were lower, work was slow, contractors were hungry, and the cost of financing was also low. According to the ENR Building Cost index, the project construction cost would have been 12% higher or $13 million more today. One negative with the slow economy was that our grading costs were higher than we thought. Few other projects were going on, so no one locally needed our excess dirt (we had hoped — optimistically — that we could find someone to "take our dirt for free "). The dirt is now in Irvine, but it went there at our cost. During good economic times there are usually construction projects that will take the dirt for free. The cost here was about $7 million (200,000 cubic yards or 15,000 truckloads). During the busiest trucking time, a huge dirt hauler was moving out of the site every 30 seconds. A more detailed cost spreadsheet is Exhibit G. We do think that the City and community got a well -made, well- designed, civic center project — a project that really was four or five major efforts wrapped into one big project. Doing them separately — at various times — would have been logistically challenging and significantly more costly. However, we recognize that many in the community may not have wanted the four or five major efforts at all, or didn't follow the major scope changes from 2008 and 2009. For those citizens, the project's scope and cost created anger and frustration with us and the project. What are our Lessons Learned? Public Process • While we met a lot and talked a lot and wrote a lot, a portion of the population never got the message that this was no longer just a city hall. Additionally, the attendance at the various public meetings and workshops never exceeded 100 people. And often the same people. Lesson: You can never give out too much good information. We need to continue exploring new ways to get information to the public and generate interest in participating. • Because of the tight contingency amounts, the impression at the end was that the change orders were unreasonably high for a project of this scope (only 6%). Yet at the same time, we wanted folks not to think that a fat contingency was there for the using /asking. However, if the contingency was a more typical amount, the change orders would have been accommodated just like in any other project. Lesson: Stick with industry standards on contingency percentages. • We could have briefed the Council and community more frequently on construction updates, including change orders and hurdles crossed — this could have added to the public's understanding of Project Scope. Lesson: You can never give out too much good information. • While we attended and made presentations at many HOAs, service groups, and business association gatherings, we could have had a more active Speaker's Bureau about the design parameters, the project and its scope change, and expected expense. Lesson: You can never give out too much good information. • The campaign in support of Measure B (Feb 2008) — done without City input or support — left the project with an unrealistic and ill- defined cost perception in the community — were the dollars quoted by the SS3 -14 proponents at the time the "all in" cost? Was it just construction? Did it take into account really costly things like California's water quality protection standards for new construction (these alone added about $2M to the project). Did they realize that excavating the dirt to protect views and grade the site would cost $7 million? No one knows today. No matter what it included, was the cost even based on construction reality? The City itself was not behind Measure B, but we're not sure how many people know that. Lesson: We should have spoken up sooner to question the costs used in that campaign, and you can never give out too much good information. Public Impressions • We did not have a message that explained how the scope of the project changed after the Design Parameters were adopted in mid -2008. Lesson: Communicate more frequently with the media and public about the project. • We were tone -deaf about aspects of the project that would become lightning rods — the kids' elements, the cafe. Lesson: Giant white rabbits might possibly too much for Newport Beach. • We should have strategized these issues more as a project team — what are we doing that could become a lightning rod issue? Does it matter to us that it could? Lesson: Spend part of every project team meeting with the public information folks asking how elements will appear to our residents. Early Design Period • Robert Schafer of CW Driver always was accurate and cautious with us about what the rolling cost estimate was. He ended up being among the smartest guys in the room, and was right in the end. I (Dave K) often pushed us to be aggressively low with the use of contingencies, to market fast given the state of the labor /materials market, and overly optimistic as to whether the dirt would be trucked away to a needy residential project for free. That optimism assumed this project could beat the odds and come in under Robert's realistic /conservative projections. Lesson: Use the conservative, not the optimistic, cost projection. • The design competition set up expectations for an amazing project, and we got one. But much of the public was not as engaged in the competition as it could have been, and never followed with the project scope changes following the Measure B election. That noted, it is understandable and appropriate that the public could have stepped back from following this project, trusting that their city staff would apply reason and efficiency to the effort. While it may surprise some for us to say this, we think we did. We can, however, understand and respect how residents might feel otherwise. Lesson: You can never give out too much good information. • While the design competition gave us an iconic facility, it was also problematic as it set the look and associated construction type without a clear, fixed eye to the potential costs. Once the Design Committee, Council and those community members following the Project embraced the proposed concept, it was difficult to predict the "All -In" cost until we were much further into the project design. Going from a relatively modest to conservative "tilt up" box construction in 2001 at the old City Hall site to a modern, glassy, tiered structure with a wave roof was a bold change — but it was also an expressed desire with those following the project. Lesson: Be aware that starting with visual concept makes it difficult to change course at later stages of a project. • To say it another way, the project itself grew significantly between the Measure B election and the adoption of the Design Parameters. The approach for the project was "this is the one time in multiple generations that several needed concerns (larger library, an EOC, more parking, etc) can be addressed at once, in a down economy when labor and materials are cheap" versus "this is how much money we have for this project and that's all we'll spend." (ENR Building Cost Index: April 2010. 5068.58; Today, 5688.50; 12.2% increase) There could have been more of a balance between these two approaches. Lesson: this is o community that probably embraces the latter approach versus the former. SS3 -15 • Size of the City Hall. The City Hall was designed in 2008 -09 for a number of employees that is higher than we have today, though not much higher (there are about 5-8 unused workstations). There was a sea change in our approach to the size of our local government in the middle of the Project's phasing. As the design was completed, it was quite late to trim things back without significant expense to reflect this new smaller government. Additionally, we needed space for outsourced staff to work in a central location to serve the customers. We also suffered in the old City Hall from an embarrassing lack of conference and meeting space for the public as well as staff. Space per employee is in line with or less than industry standards, but that doesn't mean it's not worth reviewing in future buildings. Lesson: While I'm not sure we could have predicted the future for the drop in employees from 833 FTE to 729 FTE, this all could have been communicated a lot better. However, the up side is that additional space can be repurposed, possibly to be a potential revenue generator. Construction Process • Did the CM at Risk method with a separate contract with the architect (8CJ ) as well as with the construction company (CW Driver) result in no one entity (except the City) "owning' the product, the schedule, and budget? Would "design- build" have been better? In hindsight Probably not. Our research, which was presented to Council in 2005, showed that CM @Risk project delivery method was superior in holding costs down and keeping schedule over design build and traditional design- bid - build. One variation of the "at Risk" method called Program Manager at Risk might have helped. This variation is similar to CM @R but with the architect contract assigned to the Program Manager. Contractually, the architect would have more responsibility to hold their design to the project budget. However, many architects will not agree to the assignment of their contract to a program manager. • Timing of the bid preparation, bid award —was this part of the schedule rushed? • In order to take advantage of what we thought was a bottom of the construction trades market as well as a very low interest rate environment for the COPS, we went out to bid with construction specifications not yet in final form. This was an accurate assumption as to the market, but it had a cost as well as a benefit. The ENR Cost index increased 3.6% from September 2010 (bidding period) to May 2011, or approx. $3.8 million savings. Our Change orders were 6% or $6.5 million. While our change orders were within industry standard, 5 -10 %, its doubtful that we would have exceeded $3.8 million savings by not waiting an additional six months to refine the plans Lesson: We don't really know whether this action saved as much as it cost and hindsight remains 20120. However, I would not go to market again without finalized contract documents based on approved bids in the current cost environment. • We shot for a December 2012 first meeting date in the new CC chambers, and that impacted the project schedule and project costs adversely. Construction management costs were higher (about six months at $250,000 /month) in part because of it — especially managing staff, officials, and visitors on a regular basis in an active construction site. The rush to be present at the facility in December '12 may have caused CW Driver to re -order some processes that were not as cost - effective as following a less rushed plan. Lesson: Don't stubbornly adhere to o schedule unless common sense dictates it. • Requests for Information (RFIs - these are clarifications of design questions that the contractor has of the architect). The architect's contract did not specify a turnaround time for RFIs. While most RFIs were processed in accordance with industry standards, a defined turnaround time may have led to better communication and expectations on that time. Lesson: Have an agreed -upon turnaround time for RFIs and how to deal with exceptions. • Insurance. We provided insurance at both the contractor's level and the project owner's level. This added to the cost, and while it was very conservative in protecting us against claims (they were minimal), it was probably too conservative and costly. Lesson: Stick with one or the other — on OCIP or o CCIP. SS3 -16 • Change Orders • Were we able to minimize the change orders that would have occurred because of incomplete designs? 66% or approx. $4.3 million of the change orders were attributable to errors and missing information in the plans. Most changes were minor but many in number. In the construction industry "there's no such thing as a perfect set of plans." Even if we could have reduced that number by half, we were still ahead due to construction cost inflation. • Did the City itself contribute to the problem by making changes /improvements mid - stream, such as design enhancements? Yes, the design enhancements represented 15.4% or $1 million. However, many of the changes were smarter long -term moves such as revising the roof edge paint finish to minimize glare to the adjacent neighbors or upgrading materials to increase the life cycle and lower maintenance costs. The remaining $1.2 million was attributable to Building code requirements and unforeseen problems. Sometimes these changes are inevitable, and it can be foolhardy to ignore good improvements with a flat rule against change orders. • Lesson: Assign an appropriate contingency amount plus a more regular and transparent update to the public and decision- makers. • Furnishings. Even as the City stopped making major investments in purchasing chairs, desks, tables, and related furnishings about five years before the move to the new facility, we didn't estimate these savings as an offset to new purchases for the new City Hall. We also would have had to pay the expense of moving the old furniture over — this was avoided, too. And while quality furnishings pay for themselves in avoided repair costs for equipment with poorer warrantees, the chair pricing was viewed as an example of government excess, and we don't blame people for thinking that. Lesson: Be more analytical in comparing lifecycle costs in our purchasing, acknowledge that there are both costs and benefits in doing so and communicate those options to the decision makers. Project Completion • At the end of the project, a number of contractors were in the wings complaining about delay costs they had allegedly incurred because of the project's carefully orchestrated schedule. We thought most — if not all —of these delay claims were not supported by the record, especially given the recession (i.e., even if there were delays, there was no other work out there for these contractors to pursue). We could have litigated and fought back. While we fought the claims hard administratively, and the work done to minimize end -of- project claims was admirable, how could that process have been improved? We could have aggressively entertained a legal strategy on the claims, but sometimes the risk of losing the judgment outweighs the defense costs. o Lesson: We should have briefed the public and Council earlier on the possibility of delay claims. We should have involved the City Attorney's office earlier in the process about possible non - litigation strategies in dealing with the claimants. Overall Analysis • The Good: • This project accomplished five separate projects (City Hall, 15 -acre Park, Library Expansion, Parking Structure, Pedestrian Bridge) which, if constructed separately at separate times, are likely to have cost significantly more as stand -alone projects. Some of them, such as the library expansion, may have been physically impossible at another time because of the site constraints. • There was a cost savings in going to the bond market when we did, as well as being able to take advantage of the BABs subsidy. • There was a cost savings in constructing (labor and materials) the project during the downturn in the economy, although one aspect (the dirt removal — at about $7 million in cost) was not any cheaper because no one else was out there building things and needing the dirt "for free." SS3 -17 • The CM @R delivery method created a strong and open partnership that worked together with a common goal. The design group — architect, construction manager, and City — worked together well and did not have any disputes at the end of the Project. Had we utilized traditional design bid build approach we would have potentially had an adversarial relationship between the contractor, City and architect that could have resulted in substantial costs, overruns, delays, and claims. • There appears to be great use by the Newport Beach community and satisfaction of the five Project elements following completion of the Project. • The Not -So -Good: • The "lessons learned" as previously listed. • The Measure B Feb 2008 campaign may not have had strong cost analyses — especially for the soft costs, the EIR, the Park, and more. As a result, it offered an undefinable cost for a vague project. The public understandably expected this cost at the end. • The public was not brought along with the changes in the Project scope as it grew and changed from the "just a City Hall" at 3300 Newport Boulevard, from as early as 2008. • We should have revised the design competition to include a very preliminary cost estimate from the designers - even if it would have increased the stipends. The design completion led many to want to achieve the Project's look before firmly knowing the cost. When the cost became more finalized, we were well down the road to undo things without considerable redesign cost. • The architect was creative and innovative, but designed a project plan that some in our community see as overly grand. We acknowledge that many Newport Beach residents enjoy seeing grand buildings, but might wish something more austere for their public halls of government. • The rabbits were included in the landscape package and we were not aware of the line item cost. Looking back, we should have requested a more detailed breakdown. If we had known the line item cost, we probably would have deleted or replaced them with something more modest. However, in the project team's defense, there were literally thousands of moving parts to this project and it was moving very quickly. More of our focus was on the bigger ticket items that could prove disastrous if mishandled. • We should have spent more time providing Council and the public with the Iifecycle costs for furnishings. Perhaps there was a better balance between short term and long term costs, but the decision should have been more transparent. • The contingency percentage amounts were too tight for a project of this complexity. We should have been more realistic and set the overall contingency between 5 and 10 %, probably 8 %. However, we didn't want to encourage the contractor and sub - contractors that there was more money to be made. Summary of Exhibits: A —Memo from Mr. Murphy B— Measure B Mailer C— Design Parameters D —Civic Center Rabbits E— More about Furnishings F —Civic Center Expenditure Detail SS3 -18 EXHIBIT A �,ewPO� MEMORANDUM TO: MAYOR AND CITY COUNCILMEMBERS FROM: Kevin J. Murphy, City Manager DATE: April 24, 1998 RE: CITY HALL NEEDS ASSESSMENT BACKGROUND: On March 23rd the City Council referred the discussion of the preparation of a comprehensive City Hall Needs Assessment to a future Study Session. This action followed a recommendation by the City Council Finance Committee to prepare a comprehensive study of the City Hall complex and defer the Fire and Marine /City Attorney Office Remodeling project, which was approved in the 1997 -98 Budget. In conversation with several City Councilmembers following the action on March 23rd it is apparent that a major reason for the request for a Study Session is to allow time to discuss several aspects of the recommendation including: (1) a concern regarding the projected costs of a comprehensive study; (2) a concern regarding the scope of the study; (3) a concern that judgments have already been made regarding the future of City Hall (e.g. remodel /rehabilitate/ or move off site). DISCUSSION: The City Hall complex was originally constructed in 1948 and has been modified and altered substantially since its original construction. Additional buildings in the complex have been constructed to house the Planning, Building and portions of the Public Works Department. The complex originally housed the Police Department until the construction of the new Police Facility in 1974. The area which housed the Police Department now houses a portion of the Community Services Department and the MIS and Telecommunications Division of the Administrative Services Department. The Building now occupied by the City SS3 -19 Attorney, Fire Administrative offices, the MIS Division of Administrative Services and the City's print shop operation has been added onto many times over the years. Operations within the Main Building have been moved to accommodate the space needs of various operations including Personnel and the Revenue Division of Administrative Services. 1998 marks the 50th anniversary of the City Hall complex and as we look forward to the next century and beyond at all areas of our City infrastructure it is also important that we review the current and future needs of the City Hall facility to serve the residents of the City. The City has changed dramatically since 1948, and the one constant in life is change. The City of Newport Beach will continue to evolve and change in the future. In 1948 the City's land area was only 4.23 square miles with a population of 12,120. Today, the City is a major corporation with a $120 million operating budget and 670 employees. We will be in operation serving the community forever and it is essential that we, not unlike our counterparts in the private sector, take stock of our facilities in a comprehensive fashion and determine how best to serve our customer from our corporate headquarters. Efforts to remodel or rehabilitate City Hall should be undertaken in a planned and coordinated fashion, rather than in a piecemeal and disjointed manner. Currently, the City isn't staffed with professional space or facilities planners. Since this isn't a regular part of our business it doesn't make sense to retain employees to handle this type of work. In contrast, Rockwell International, located on Jamboree Road, has a staff that handles all space planning needs and building maintenance activities, supplemented by professional architects and engineers who prepare plans and specifications when specific projects are identified. For a corporation holding 1 million square feet of space that is constantly changing and evolving this makes sense. In 1990 the City completed a renovation plan for the City Hall complex which examined the needs in 1990 and in the year 2000. The study, prepared by The Blurock Partnership produced a draft renovation /site plan which would have demolished older parts of the complex, including the Fire and Marine /City Attorney wing and added a net 5,510 square feet. The City Council took no action on this plan when it was delivered in December 1990. Today, I'm suggesting that the City Council consider the undertaking of a comprehensive and careful process to look at our space and facility needs well beyond the year 2000. Our business of providing local government services isn't going to go away. We're here to stay and we should be planning our needs flexibly well into the next century, not unlike our efforts at master plans for water, sewer, storm drains, roads and parks. SS3 -20 When the City Council Finance Committee suggested a long range comprehensive plan the City staff contacted two architectural firms which undertake these types of studies to seek their methodology and gauge their cost. Since the City Council meeting on March 25d City staff has received an expression of interest from eight firms to undertake this work for the City. If the City Council proceeds on this work program staff suggests that we develop an RFP and solicit competitive proposals. One of the eight submittals was from a Newport Beach firm nearby City Hall, Newport Resource Management, Inc. It's Chairman is Rush Hill II, and he has offered at no cost to brief the City Council at our study session on how these studies are undertaken, why, and what results we can expect. I've asked Mr. Hill to make a presentation and keep it to no more than 20 -30 minutes. RECOMMENDATION: The City Council receive the presentation by City staff and Newport Resource Management and give appropriate direction to City staff on the next steps in the comprehensive review of the City Hall complex. SS3 -21 4 -24 -1998 1:29PM APRIL 24, 1998 FROM GENERAL SERVICES 714 660 0747 TO: GENERAL SERVICES DIRECTOR P. 1 Post -its Fax Note 7671 3 To Co. �Dept� MAt�igL7; =�. l Co. 6r S O� sl Ph one Phone Far. R Fax N FROM: BUILDING MAINTENANCE SUPERVISOR OPERATION SUPPORT SUPERVISOR SUBJECT: CITY HALL ASSESSMENT 1990 - COUNCIL CHAMBERS REMODEL; TRAVIS ASKEY: $75,000.00 1991 -CITY HALL MAIN COMPLEX COPPER RE -PIPE: 19.00 1992 -ALL AREA BUILDING FUMIGATION: $17,725.0 0 (SERVICE CONTRACT $2,000.00 PER YEAR) 1993- COMMUNITY SERVICES ANNEX BUILDING COPPER RE -PIPE: 10$ ,400.00 1993- ELECTRICAL RETROFIT - CONSERVATION -LIGHT FIXTURES; HERB WOLLERMAN: $12,500.00 1993 -CITY HALL MAIN COMPLEX ZONE DAMPER INSTALLATION: $10,800.00 1993 THROUGH 1997 -HVAC REPLACEMENTS(3), PROF. & TECH. BLDG.: $12,000.00 1993 THROUGH 1996 - EXTERIOR AND INTERIOR CITY HALL SURFACE PAINTING: $33,872.QQ 1995- RESTROOM PARTITION REPLACEMENT -MAIN COMPLEX: $1,80S.00 1995- REMODEL OLD PERSONNEL OFFICES TO ACCOMMODATE REVENUE, ACCOUNTING, & PAYROLL. WORK INCLUDED CONSTRUCTING NEW SERVICE COUNTER AND 12 NEW WORK STATIONS: 58$ ,000.00 1995 -ADA RESTROOM REMODEL: 11$ ,400.00 1995- DEPUTY CITY MANAGER'S OFFICE & COMMUNITY SERVICES DIRECTOR'S OFFICE RECARPETING: $2.200.00 APR -24 -1999 14:43 714 650 0 ?47 96% SS3 -22 P.01 4 -24 -1998 1:30PM FROM GENERAL SERVICES 714 650 0747 P.2 1995- REMODEL OLD JAIL FACILITY TO ACCOMMODATE TELECOMMUNICATIONS & OPERATIONS. JOB INCLUDED AIR CONDITIONING, 6 NEW WORK STATIONS AND GARAGE FACILITY: $10,50Q.00 1996 -HVAC REPLACEMENT; CITY MANAGER'S OFFICE AREA: $4.500.00 1996- REMODEL OLD REVENUE OFFICES TO ACCOMMODATE HUMAN RESOURCES. WORK INCLUDED 5 NEW WORK STATIONS, AIR CONDITIONING AND CARPET: $17,400.00 1996- REMODEL CITY CLERK'S OFFICES, INCLUDING NEW DOORS, SERVICE COUNTER, 4 NEW WORK STATIONS, AIR CONDITIONING, AND CARPET: $17,000.00 1996 THROUGH 1997- REMODEL OLD FACILITY TO ACCOMMODATE GIS. INCLUDED 12 NEW WORK STATIONS, AIR CONDITIONING, NEW WINDOWS, AND CARPET: $18,900.0 0 1997- REMODEL ADMINISTRATIVE SERVICES OFFICES AND WORK AREAS. INCLUDING SERVICE COUNTER, 4 NEW WORK STATIONS: $8,600.00 1997 - REMODEL PROF./TECH BLDG. TO ACCOMMODATE TRANSPORTATION AND DEVELOPMENT. WORK INCLUDED 7 NEW WORK STATIONS: 8 7$ , 00.00 1997- REMODEL OLD FACILITY TO ACCOMMODATE ENGINEERING DIVISION. WORK INCLUDED 7 NEW WORK STATIONS, AIR CONDITIONING, AND CARPET: 1$ 4,900.00 1995 THROUGH 1997- WINDOW REPLACEMENT THROUGHOUT CITY HALL: $48,000.0 0 1997 -NEW CARPET CITY MANAGER'S OFFICE, HALLWAYS, AND LOBBY: $13,200.00 1997- REPAINTING OF CITY HALL INTERIOR: $7,500.00 1997- REMODEL ASSISTANT CITY MANAGER'S OFFICE, WORK STATION, CARPET, WINDOW, AND PAINTING: $4.1.00.00 1997- REMODEL COMMUNITY SERVICES AREA INCLUDING 4 WORK STATIONS. PAINTING, AND CARPET: $7,200,00 1997 - REMODEL PRINT SHOP & MAIL ROOM: $4,500.00 APR -24 -1998 14:44 714 650 0747 981/ P.02 SS3 -23 r 4 -24 -1998 1:30PM FROM GENERAL SERVICES 714 650 07d7 1998 -NEW WORK STATION CITY HALL TABBY; $2,3_()0.00 1998(ONGOING)- REMODEL CITY ATTORNEY'S OFFICE AREA AND WORK STATIONS: $13,000. 0 1998 -NEW DOORS IN ADMINISTRATIVE SERVICES, PROF/TECH., HUMAN RESOURCES: 2$ ,400.00 1998- DRAINAGE SYSTEM BACK OF CITY HALL: 44.600.00 FUTURE CONSIDERATIONS: 1)ELECTRICAL UPGRADES; 64 0.000.00, 2)HVAC SYSTEM REPLACEMENT REVENUE; 22 000.00 3)HVAC SYSTEM REP.LACEMENT(5 TO 10 YEARS), COUNCIL CHAMBERS; $28.000.00: 4)CARPET REPLACEMENT PROF./TECH. BLDG.; 1$ 7,000.00. RESPECTFULLY SUBMITTED, CHARLES M.COAKLEY GEORGE MILLIKYN APR -24 -1998 14:44 714 650 0747 98/. P. 3 P.03 SS3 -24 Paid for by Newport Beach City Hall in the Park Committee, Yes on Measure B ID# 1297811 537 Newport Center Drive #604 Newport Beach, CA 92660 PflESOflT STO U.S. POSTAGE PAID BC sz�oa SS3 -25 J e V1111 law- w ar �c mo Sr; 41'ji �ark_cem Don Adkinson Joan Allen Russell Allen William Allen, Jr. Charlotte Allison Gerald Allison Judith Altshuler J. Pete Anderson Virginia Anderson Douglas Ayres Pam Bacich Jim Bailey Josephine C. Baldwin Barbara Barnard Steve Barnard Barton Beek Linda Beek Pat Beek Seymour Beek Lyn Belasco Wendy Bell Ben Benjamin Honorable Marian Bergeson Triona Bergin Debi Bibb Helga Birmingham James Birmingham Barbara Birney Susan K Bise George Bissell Dr. Melinda Blackman Mary Blake John Clark Booth Deane Bottorf Don Bowers Joe Bradford Judy Bradford Steve Brahs Wendy Brooks Ruth Budlong Joyce Cain Christina Calacd Jane Calder Scott Calder Nancy Caldwell Diane Cannon Richard Cannon Thomas C. Casey Paul Christ Peter Churm Tim Collins Judy Colver Juli S. Cook Jack Croul Kingsley Croul Peggy Crull Timm Crull John Curd Samuel Davidson Kirk Dawson Peter Desforges Suzanne Desforges Grace Deutsch Roger DeYoung, Jr. Tom Doan Dorothy Doan Heidi Dom Larry Dom Richard Dorsey Andrew Dossett Corinne Dossett Marcia Dossey Jim Dow Susan Dow George Drayton Phyl Drayton Pete Duca Susan Duley Joyce Dungan Cathy Dunlap James Dunlap Sara Dunlap Dennis Durgan Jake Easton III Laurie Easton Gale Edelberg Drew Elisius Nina Elisius Kirk S. Elliott Pat Ella Mary Anne Emett Robert Emett Janet Eversmeyer Allan Fainbarg Barbara poker Bill Ficker Fran Fleischman Douglas Fletcher Salty Fletcher Russ Fluter Herbert Foss Orlene Foss Eve Foussard David Fraser Barbara Freeman Roy Freeman Vern Frost Joe Garrett John Garrison Jack Geerlings Nancy Geerlings Dennis Gitschier Rita Goldberg Rl Greenwood Sheryl Griffith Daniel M. Guggenheim Sue Guggenheim Iris Gunning -Wyatt Bruce Harrington Mickey Harding John Heffernan Novell Hendrickson Ron Hendrickson Barry L Hoeven Bob Hoffman Ilene Hoffman Carol Hudson Dwight Hudson Bob Huntsberger Penny Huntsberger Frances Hylton Dolores Johnson Karen Johnson Mike C. Johnson Todd Johnson George Jones H. Gilbert Jones Nancy Jones Sharon Jurgensen Bill Kelly Gay Wassail Kelly Teri Kennady Dolores Keman Gene Keman James Kerrigan Tricia Kerrigan Patricia Kingsley David Klages H. Taylor Knight Ken Knight Paula Knight Don Krotee John Kruse Paula Kruse Lucille Kuehn Gale Layman Will Layman James K. Leason Judy Leeper Ann Lehman John Lehman Richard Lewis Jerry Lezama Judah Lezama Karen Linden Thomas Linden John Lipyanik Mary Lipyanik Kent Lucas Richard Luehrs Susan Luehrs Gil Lukosky Bill Lusk Val Lyon Stuart MacFarland Henry Mackel Edith Marowitz Richard Marowitz Verna Mattox Bob McCaffrey Laura McCant Martha McClarty Rollo McClellan, Jr. Dorothy McDonald James M. McFadden Don McHone Stuart McKenzie Carol McKibbin Jack McManus Shirley McManus Louise McNeil James Mears Barbara Meserve Steve Morton Lonnie Nadal Alexandra Nichols Dick Nichols Sandy Nichols Audrey Nye Wallace Olson Alan Oleson Loraine O'Neil Eugene O 'Rourke Marilyn O'Rourke Dolores Otting Tony Otting Basil Pafe Eva Parsons JoAnne Potts Robert Primmer Rally Pulaski Char Raffetto Tom Raffetto Janet Ray Walkie Ray Don Regan Carol Reinhold Terry Reinhold Ross Ribaudo Linda Richley Mel Richley, Jr. Paul Richley Bernice Riley William Ring Jim Robertson Stephanie Robertson Lorraine Robinson Mickey Rowe Robert Rosenast J. Edgar Rutter Ned Rutter Susan Ruzbasan Gregory V. Ruzicka Paul Salata Mrs. W.D. Schack Dennis Scholz Bob Shelton Nancy Skinner Jean Slack Marilyn Slaughter Gated Smith Larry Smith Natalie Smith Walker Smith, Jr. Jim Somers Larry Somers Dick Stevens Joan Stevens John Store Byron Tarnutzer Shannon Tarnutzer Wanda Taylor James Thompson Linda Thompson Cecelia Tobin Tom Tobin Ralph Tomlinson Jim Tracy Judy Tracy Buzz Tupman Irene Tupman Tom Tupman Clarence Turner James Turner Charles Vandervort Jo Vandervort Gene Verge John Virtue Bill Voit Margie von KleinSmid William von KleinSmid John Vultee Polly Wall Barbara Wallace David Wallace Linda Webb Kevin Weeda Chris Welsh Sally Welsh Terry Welsh Bill Wenke Jean Wenke Linda West Denny E. Whelan Bill Wilkinson Bob Williamson Julie Wilson Justin Wilson Norm Witt Mary Wolff Tom Wolff Dougtas M. Wood George Woodford Ben Wright Sandy Wright Bonnie Zillgitt Preston Zillgitt Partial list Senator Marian Bergeson and Ron Hendrickson. SS3 -28 EXHIBIT C rEW �R> City Hall and Park Master Plan Design Competition vt/COM1N General Design Parameters (adopted by the City Council on April 22, 2008, posted April 24, 2008 and amended on May 13, 2008) The following General Design Parameters are for the firms /teams selected to participate in the Newport Beach City Hall and Park Master Plan Design Competition. a. Access to Site and Circulation — Vehicular access to the City Hall and Park site shall be off of Avocado Avenue. Farrallon shall not be extended through to MacArthur from its current eastern terminus at Avocado. Farrallon may be considered as an entrance point to the City Hall and Park provided that no direct connection to MacArthur Boulevard exists from Farrallon. There shall be no "right -turn in" vehicular entrance to the City Hall and Park site from MacArthur within the Central Parcel. Exhibit A shows surrounding streets, today's access points to the Library, and identifies the three key parcels (North Parcel, Central Parcel, Library Parcel) subject to the master plan. b. City Hall location on the site — The City Hall and its parking shall generally be located in the Central Parcel south of the projection of Farrallon Drive, as shown on Exhibit B. c. Building Height — The height of the City Hall building (and parking facility) shall be no higher than the height limits imposed by the Newport Village PC Text View Plane limitation as depicted on Exhibit C except that architectural design features, appropriate to the scale of the primary structure, may penetrate the view plane created by the aforementioned height limits. Height limits in the Newport Village PC Text are generally 45 feet above grade OR the View Plane limitation (expressed in feet above mean sea level), whichever is lower. All landscaping and park improvements, at maturity, shall be lower than the View Plane limitation. d. Geotechnical Considerations — Geotechnical considerations will be set forth in a soils investigation performed by Leighton Associates in April 2008 which is to be attached as Exhibit D when completed. The current expected date for the final report is the end of April. Preliminary results show no unique soils or water table issues. e. Library Access and Orientation to City Hall — The Newport Beach Central Library currently faces away from the Central Parcel and the site of City Hall, towards the ocean. The Design should, to the greatest extent practicable, maximize the Library's relationship to the City Hall structure through consideration of a second entry, plaza, shared parking, landscaping or any other appropriate means within the context of the proposed design. f. Natural Park Considerations — The northerly 5 -6 acre portion of the Central Parcel ( "Newport Center Park ") has been proposed as a natural park (i.e. one that is reflective of the region's natural habitats and not overly manicured nor oriented towards turfgrass). Of particular importance is preserving the view from the southernmost meadow area and creating a landscaped border around the natural park area as a transition from the more manicured streetscape to the natural park. g. Other Park Requirements — The southernmost meadow area of the Central Parcel and the 3 -acre North Parcel shall have park amenities such as restrooms, a tot lot, picnic and SS3 -29 General Design Parameters Posted April 24, 2008 Page 2 of 9 seating areas (including a softscape ampitheater, if appropriate), drinking fountains, and an ADA- accessible path (the latter being around all or part of the 20 -acre master plan area). Both parcels shall be integrated as portions of the same Newport Center Park. They shall have activity- oriented facilities but not any organized sports fields. h. Lighting — Exterior lighting throughout the Project (City Hall, Parking, and Park) should be designed in such a fashion as to be the minimal intensity necessary to meet safety needs. Landscaping Considerations — The landscaping of the Park and City Hall area shall use water conserving plant material to the greatest extent possible. The intent is to not create a desert or dry landscape palette but a palette that is "California- friendly" and blends into the landscape palette of Newport Center and Newport Beach. Best Management Practices in water conservation, irrigation and drainage shall be employed in the design. j. Parking — 350 spaces shall be provided for City Hall with an additional 100 spaces for the Central Library (the Library has a shortage of spaces currently). Parking for the general public should be convenient to the City Hall and Library buildings. The parking structure should be a separate structure from the City Hall building. The additional 100 library spaces need not be in the City Hall parking structure. k. Space Allocation and Needs Assessment Criteria — The 2002 Needs Assessment prepared by LPA (a link to this document, and any updates to the document, on the City's website is Exhibit F) will be the basis for the primary program requirements for the City Hall Structure with the following adjustments: • The City desires an open floor plan concept with maximum flexibility for future needs; • The building shall be designed for 270 full time employees at 200 -250 square feet per employee, not including public areas; and • The building's overall size shall be approximately 72- 79,000 total square feet including public areas. Please note that the 2002 Needs Assessment includes these two program requirements, both of which remain desirable: • A "one -stop shop" permit counter (for permits relating to Building, Planning, Public Works, and Fire Prevention along with a cashier); and • A 150 -seat Council Chambers. I. LEED Criteria - The City Hall Structure(s) shall be designed to at least a Leadership in Energy and Environmental Design ( "LEED ") standard of silver, with a goal to go higher, if feasible within budgetary limitations. m. Corona del Mar Plaza Considerations — The City will develop a direct entrance to the Central Library's existing parking lot, as shown (generally) in Exhibit E. This entrance may or may not be signalized. No further improvements to CdM Plaza's access are envisioned at this time. n. View Considerations — Views are a sensitive issue in Newport Beach. In addition to the criteria in "c" above, the design should protect the public views westward over the property from MacArthur Boulevard. The design should also be sensitive to the westward views SS3 -30 General Design Parameters Posted April 24, 2008 Page 3 of 9 from homes east of MacArthur Boulevard over the property. Any penetrations above the view plane as permitted in "c° above should only serve to enhance the architectural appearance of the City Hall structure or frame or enhance the private or public views across the property. Usable landscaped roof treatments or roof terraces are acceptable — these are neither encouraged nor discouraged. Also, the building and parking facility's lighting design shall take into consideration nighttime views from the residences east of MacArthur Boulevard. All landscaping and park improvements, at maturity, shall be within the view plane on Exhibit C. o. Building Design — The city is not setting any design theme for the City Hall building other than seeking a timeless design that will wear well over the years and not be dated in a few years. The design should reflect the character of Newport Beach. It should be harmonious with the adjacent Library and the eclectic architectural styles of Newport Center. The building should be recognized as a significant public building. p. Budgetary Constraints – The budgetary goal of the Project is as follows: • Approximately $400 -450 per square foot for the City Hall structure (not including FF &E); • Approximately $20- 25,000 per space for the parking structure; and • Approximately $15 -20 per square foot for landscaping, irrigation, access, site work (grading and drainage) and site improvements. The above amounts are exclusive of soft costs. The City Hall is not at this time planned to be an "essential services building." The budget parameters expressed here are not absolute amounts but are intended to indicate the price range the City expects the project to cost. Designers should use these numbers as a guide in preparing their submittals. Design economy will be an important consideration. Exhibits Exhibit A – Diagram showing 20 -acre Master Plan area showing North Parcel, Central Parcel, and Library Parcel along with surrounding streets and current site access points to the Library (attached). Exhibit B – Diagram showing the area of the Central Parcel where City Hall and Parking are to be located (attached). Exhibit C – Diagram of the 20 -acre master planning area showing View Plane restrictions over the property (attached). Exhibit D – Soils Report (link attached). Exhibit E – Diagram showing any potential or revised access, parking or circulation considerations for Library area and CdM Plaza (attached). Exhibit F – 2002 LPA Needs Assessment with updates (link attached). SS3 -31 General Design Parameters Posted April 24, 2008 Page 4 of 9 Exhibit A The Master Plan Area Legend: • BLUE arrow is the delivery access point to Library. • arrrows show the public access point to the Library. SS3 -32 General Design Parameters Posted April 24, 2008 Page 5 of 9 Exhibit B City Hall and Parking Facility Location within Central Parcel The area southerly of the red line in the direction of arrow is the area where City Hall and Parking are to be located. The City does not anticipate using the entire portion of the parcel southerly of the red line for the City Hall and parking structure — this diagram is provided merely to advise where on the parcel both should go. SS3 -33 • I m m J � I I a .1 Exhibit C View Plane Limitations � u I I i I �I a � r � I I I I I I I I I I I I I I I I I I I I =1 •I �I J i SS3 -34 Exhibit D Soils Report Use the following link: http://www.city.newport- beach. ca. us/CityHallDesignCommittee /2008 Geotechnical Study.pdf SS3 -35 General Design Parameters Posted April 24, 2008 Page 8 of 9 Exhibit E Potential locations for increased access to CDM Plaza _ CITY HALL ACCESS OPPORTUNITIES Library Access Opportunity �..�.......... -� .. wummT� \�+Nrmnnrr. ms.e.s u a+N •e. 4aY 9.:0:2. SS3 -36 General Design Parameters Posted April 24, 2008 Page 9 of 9 Exhibit F 2002 LPA Needs Assessment with any updates (a website link) http: / /www.city. newport- beach .ca.us /cmo /CityHall /cityhal Idesignparkmasterplan.asp SS3 -37 EXHIBIT D Exhibit D: The Civic Center Rabbits a The 16 rabbit sculptures in the Civic Center Park are nearing their 2 -year birthdays and we still get a lot of questions about them. The most frequently asked questions include: • Why are they there? • Why rabbits? • What did they cost? • Are they art? The Civic Center Rabbit Story is this. They are not intended to be art. They are a feature for kids. The landscape architect for the Civic Center Park, Peter Walker Partners (PWP - the same firm doing the 9/11 Memorial Park in Lower Manhattan) wanted to place unique children's elements in the park. �r To PWP, a traditional tot lot with manufactured play equipment just wasn't the right fit for this site. There's room to roam here and the landscape architects didn't see a need for a specific play area. They wanted visitors of all ages to explore the different features throughout the park's approximately 14 acres. The project budget included $225,000 for adding fun, play elements that would appeal to children. (A standard tot lot costs about $250,000 and up.) PWP looked at various climb -able sculpture concepts based on wildlife (giant sea turtles, spider webs and more) and even one of Patrick Dougherty's willow sculptures (his sculptures are alive after planting and stay alive for some time). The costs ran too high for some of these ideas, while durability and lifespan were in question for others. So how did we end up with rabbits? As the project team considered the wildlife sculptures, all agreed that the design should be based on something actually found in Newport Beach (unlike giant sea turtles). Desert Cotton Tails are the real, live bunnies that are native to this area and a number of them consider the park site home. So, rabbits became a sculpture option. About that same time, PWP held an office reception and someone brought in real rabbits to help entertain the young children. As Peter Walker tells the story, the bunnies were a hit not just with the young kids, but with the older kids and the adults all evening. People were just drawn to them. Soon after, PWP decided rabbit sculptures could be the right fit for the Civic Center Park. SS3 -38 So why are they gigantic? While the rabbits have an element of reality (going back to the idea that Desert Cotton Tails are native to this area), PWP also wanted them to be whimsical and to have an element of surprise and encourage imagination. They wanted something that would draw kids and grownups into the park and then from one area of the park to another. They even thought — and it's turned out to be true — that drivers might pull off of MacArthur or Avocado to see what those gigantic rabbits are all about. The rabbits do command attention and their large size also makes them fun for kids. They are practically indestructible (the rabbits) and it seems that children can't help but climb on them and they often pose with them for pictures (we've noticed quite a few adults having their pictures taken with the rabbits too). So what did the rabbits cost? The final price for grading, placement, manufacturing, design, painting, and graffiti - protection was just over $221,000, or about $13,800 per rabbit. After watching a steady stream of kids (and parents) interact with the rabbits over the last six months, we know PWP's thinking was probably correct. The quirky, huge bunnies have drawn more people to the park and been at the center of more fun and imagination than a solitary tot lot ever could. Another question we were recently asked, "Can someone buy one for their own yard ?" And we're not sure about this one. SS3 -39 EXHIBIT E "Columns about lower back work comp claims avoided, flimsy chairs not purchased then repurchased, or tables that didn't wobble and break are notoriously boring." — Frustrated city managers everywhere Exhibit E — More about the Civic Center Furniture The new Civic Center City Hall and Library Expansion are designed to last for the next 100 years. So what about the furniture? Unfortunately, not many furniture companies make furniture to last 100 years, but it's amazing how long well -made pieces do last. Many folks own furniture that has been passed down through several generations. The City has a history of making smart purchases in the furniture department. Just two short years ago, anyone visiting the old City Hall would have stumbled upon many desks, chairs, filing cabinets, and bookcases that have been in use for decades. Our City Manager, Dave Kiff, used the same desk that was used by Bob Wynn, City Manager from 1971 to 1991. That desk was over 40 years old, his chair was over 17 years old. The Public Works Director's desk was also over 40 years old. There were filing cabinets that were older than those desks. Much of the furniture was made by Steelcase and Kimball, two well known makers of quality office furniture at that time. So fast forward to today. The City recently purchased new furniture for the new Civic Center. In planning for that event, the City held back any new furniture purchases (and many facility repairs) for several years. You may remember that discussions to replace City Hall started in 2002, so we limped along without investing in new furniture or capital repairs to the old City Hall buildings for about 10 years. That action allowed the City to bank repair and replacement funds — into the hundreds of thousands of dollars - to be used in the new Civic center. The Civic Center design team reviewed several manufacturers and lines of furniture and established specifications based upon a balance of cost and quality. Cost and quality vary greatly in today's market from the mass produced, overseas -made furniture that is available at the big box stores to fine furniture that is made of exotic woods and premium fabrics. Furniture in the public areas of the city hall and library needs to be durable and have some modest level of aesthetics. Furniture in public areas tends to be treated similar to the way folks treat rental cars, "Don't worry about that spill, it's a rental ". It was into these public areas — public meeting rooms and waiting areas as well as the new children's room and study areas at the Central Library — that the most expensive furniture went. Furniture in the employee areas needs to last long and be functional. Additionally, furniture in work areas need to be ergonomically correct to prevent workplace injuries and associated costs under workers compensation and loss of productivity. A cheap "Under $100" desk chair can quickly become very expensive due to workplace medical claims, time off, and a loss of productivity. SS3 -40 Systems Furniture (cabinets, files, desks, study carrels) With the open floor plan design of the City Hall office building, our first thought was to explore the various versions of pre- manufactured partitions. These partitions are designed to have furniture attached to them and have built in electrical and data. Many businesses use partition systems as they are portable when a business moves and easily reconfigured for changing needs. However, these partition systems are very expensive. In our situation, it's unlikely that we'd be moving City Hall, but we do need flexibility to meet the changing community services and needs. Our design team came up with an inexpensive but effective solution. In place of expensive manufactured partitions, they designed a simple partition made of "Apple Ply ", multilayered plywood (yes, plywood) with veneer surfaces. The City's partition system is designed to accept various components of standard system furniture (cabinet, file, desk, and credenza units). The design is easily reconfigured and costs much less than manufactured partition systems. The purchasing process for the standard systems furniture was by competitive bid. Furniture lines from Haworth, Teknion, Herman Miller, Steelcase, and Allsteel were considered. Furniture distributors representing the various product lines submitted competitive bids to the City. ICS, representing the Haworth product line was selected as the lowest responsible bid for the systems furniture. Another innovation at the Civic Center is the unique study carrels at the Central Library's expansion. These individual study stations provide privacy, electricity, and comfort in addition to good aesthetics. These durable carrels are among the most well -used and popular aspects of the Civic Center project, which added additional study room and a new children's room to the already widely - popular Newport Beach Public Library. Chairs & Tables The criteria for the selection of chairs and tables were based upon the various uses. Chairs and tables in the public areas needed to be durable and of quality construction. The waiting areas have commercial grade seating with strong metal frames and stain - resistant surfaces. The new furniture in the kids' room at the Central Library needed to be miniaturized but still durable, fun, and comfortable. All of the pieces are designed to last a long time and maintain appearance through thousands of users. Many of the furniture pieces purchased have a 10- to 12 -year full warranty. They are also renewable in that they can be reupholstered. The Library recently reupholstered several chairs in the Central Library that were over 13 years old. This action potentially doubles the service life of our furniture at a lower cost than replacing the furniture. The cost of the chairs and tables ranged from $180 for guest chairs in offices to $4,000 for the larger commercial couches in the public waiting areas, like the permit counter. When spread over the life of the chair or table, the cost of the selected furniture is very competitive with alternative products that do not have longevity, quality, or warrantees built into them. Similar to the system furniture purchase, furniture distributors representing the various product lines submitted competitive bids to the City. SS3 -41 Pivot Interiors representing Herman Miller and other furniture lines was selected as the lowest responsible bid for the chairs and tables. Critics of these purchases point out that the City could have bought cheap desk chairs for under $100. That's completely true. But cheap isn't always economical. Checking the Office Max website, you can buy desk chairs for under $100 up to premium chairs at $850. However, the cheap chairs usually have a use recommendation listed for casual use, "0 to 3 hours per day." Additionally, those chairs only carry no warranty or a short three year limited warranty (limited usually means foam and upholstery for one year, metal parts for three). The employee desk chairs that were purchased for the Civic Center are Herman Miller Aeron chairs for about $560 each (retail $680). They come with a 12 -year full warranty that covers everything. They are ergonomically superior to the cheaper chairs. This is especially important when you have employees working in these chairs for 8 or more hours each day to prevent expensive medical claims, workers compensation, and loss of production issues. In theory, you could buy four cheap chairs that would last as long as one of our current desk chairs with a savings of $160 (if you can believe the warranties, 4@ 3yr vs. 1 @ 12yr). If you factor in the overhead cost for city staff to purchase and re- purchase this chair four times along with the potential medical claims and loss of production from a chair that is only recommended for use between 0 and 3 hours per day, the $160 savings likely evaporates (and more). We think we've made some very smart purchases for furniture and equipment, as the furniture purchased for our new Civic Center will service us for many years to come. Our history of balancing cost and quality has served us well. SS3 -42 EXHIBIT F CIVIC CENTER PUBLIC MEETING TIMELINE January 13,2015 Meeting Meeting Date Type Subject Action Summary Contract Cost Notes Former Site at 3300 Newport Boulevard City Hall Space Options Staff directed to bring back options of a more permanent nature with architectural guidance 07/10/2001 CCSS 07/24/2001 CCSS Review of City Hall Space Options Staff directed to pursue retaining an architectural consultant early 2002 01/08/2002 CCRM City Hall Needs Assessment Approved PSA with Griffin Advisors $ 154,780 04/08/2003 CCSS City Hall Needs Assessment Public Comment & Discussion 06/10/2003 CCRM City Hall Facilities Schematic Design Approved PSA with Griffin Holdings $ 578,185 06/24/2003 CCRM Resolution to create Building Ad Hoc committee Approved with Bromberg /Heffernan /Ridgeway as appointees 08/01/2003 BC Council sub committee discussion Schematic Design put on hold 02/08/2005 CCRM City Hall Facilities Schematic Design Reaffirmed Approval of PSA with Griffin Holdings 02/08/2005 CCRM Resolution to extend Building Ad Hoc Committee Approved with extension to project completion 03/05/2005 PW City Hall Conceptual Design Workshop #1 Public Comment & Discussion continued to next workshop 04/02/2005 PW City Hall Conceptual Design Workshop #2 Public Comment & Discussion continued to next workshop 04/23/2005 PW City Hall Conceptual Design Workshop #3 Public Comment & Discussion continued to next workshop 04/25/2005 PW City Hall Conceptual Design Workshop #4 Public Comment & Discussion concludes with recommendations forwarded to Council 05/10/2005 CCRM Review of Site Plan Alternatives & Site Selection Approved the Building Committee recommendation to proceed with schmatic design Directed staff to include a 2600 SF Community room Directed staff to include a 350 space parking structure Approved recommendation to procceed with LEED Certification Approved MOU with Lido Partners for a conditional lot line adjustment Directed staff develop potential financing options for the project 08/09/2005 CCRM Review and Direction on planning status Reviewed conceptual plans, received public comment, no action City Hall (68,000 SF), 350 space structure, Fire Station 08/23/2005 CCRM Review and Direction on planning status Directed architect to increase building program to 72,000 SF City Hall (72,000 SF), 350 space structure, Fire Station Adopt the site plan configuaration Adopt OCFA building standards increasing cost by approx. $360,000 Approve Council Chambers layout including glass wall provide structural improvements to accommodate future 8000 SF expansion City Hall (80,000 SF), 350 Space Structure, Fire Station 09/13/2005 CCRM Status Report from Civic Center Financing Team Receive presentation regarding financing options and sale of COPS 09/13/2005 CCRM Civic Center Financing Report Receive presentation on COPs 09/27/2005 CCRM City Hall - Alternative Delivery Options Discussion of Traditional Design- Bid -Built vs. Design -Build vs Construction Manager at Risk 11/22/2005 CCRM Civc Center Building Committee Recommendations Accept Griffin Structures Design Development Contract as fulfilled Form a City Hall Site Review Committee (7 -10 residents + 2 City Council ad hoc members) Form a Facilities Finance Review Committee (7 -10 residents+ 2 City Council ad hoc members) Committee appointments to be made Jan. 10 2006 and conclude May 1, 2006 Total Cost approved by Council action for 3300 Newport Boulevard Site *_ $ 732,965 Current site at 100 Civic Center Drive Site & Financial Review Committee Selection Process City Council to review all applications with selection set for Jan 24, 2006 meeting 01/10/2006 CCRM 01/24/2006 CCRM Site & Financial Review Committee Selection Site Review Committee - Larry Tucker, Chair Facilities Finance Review Committee - Keith Curry, Chair Steve Frates became Chair after Keith Curry's appt. 02/13/2006 SRC Site Review Committee #1 Discussion and public input 02/17/2006 FFRC Facilities Finance Review Committee #1 Discussion and public input 03/06/2006 SRC Site Review Committee #2 Discussion and public input 03/13/2006 FFRC Facilities Finance Review Committee #2 Discussion and public input 03/20/2006 SRC Site Review Committee #3 Discussion and public input Legend! CCRM - City Council Regular Meeting CCSS - City Council Study Session BC- Building Committee DC- Design Committee SRC - Site Review Committee FFRC - Facilities Finance Review Committee PW - Public Workshop SS3 -43 CIVIC CENTER PUBLIC MEETING TIMELINE January 13,2015 Meeting Meeting Date Type Subject Action Summary Contract Cost Notes 03/27/2006 FFRC Facilities Finance Review Committee #3 Discussion and public input 04/03/2006 SRC Site Review Committee #4 Discussion and public input 04/10/2006 FFRC Facilities Finance Review Committee #4 Discussion and public input 04/17/2006 SRC Site Review Committee #5 Discussion and public input 04/24/2006 FFRC Facilities Finance Review Committee #5 Discussion, public input, & Committee Recommendation 05/01/2006 SRC Site Review Committee #6 Discussion, public input, & Committee Recommendation 05/23/2006 CCRM Site & Facilities Finance Review Committee Reports Corporate Plaza West & existing location were recommended by the Site Revew Comm. Finance Committee confirmed that the new City hall along with the 20 year plan can be afforded. 06/27/2006 CCRM City Council Building Committee Recommendations Confirm that the City Hall stay at current location & authorize $25,000 for alternative ext. design $ 25,000 07/11/2006 CCSS Ficker Plan for City Hall Plan presented by Bill Ficker to locate City Hall on Avocado 07/25/2006 CCRM Staff Assessment of the Avocado Site for City Hall Referred to Building AdHoc Committee 04/10/2007 CCRM Proposed City Hall at Transportation Center Site PSA With DMJM $ 42,000 10/09/2007 CCRM Initiative Measure amending Charter to locate City Hall Certified petition and placed upon the Feb. 5, 2008 ballot $ 42,000 02/26/2008 CCRM Certification of Special Municipal Election Results Measure B, Charter Amendment passes 16,938 yes ; 15,092 no 02/26/2008 CCSS Building Comm. Recommendations for Location and Process Approved recommendations on location, process, & established City Hall Design Committee Res 2008 -14 03/25/2008 CCRM Confirmation of Appointments to the City Hall Design Committee Rush Hill, Walt Richardson, Steve Sandland, Linda Taylor, Andrew Bowden„ Larry Tucker, Chair Chair non - voting 04/07/2008 DC #1, Organizatiuonal Meeting; set calendar, draft RFQ Staff directed to distribute RFQ to architectural community 04/21/2008 DC #2, Finalize procedures for design competition Draft design parameters developed 04/22/2008 CCRM General Design Parameters for City Hall, Park, & Parking Structure Approved the General Design Parameters 05/05/2008 DC #3, Design competition discussion Refined Design competition process & referred various issues to the Building Ad Hoc Committee 05/13/2008 CCRM Preliminary Traffic analysis, Farallon Ext v. Improv at San Miguel Supported intersection improvements in lieu of Farallon Extension Preclude "right turn in" from MacArthur Boulevard 05/19/2008 DC #4, Continued Design and selection Discussion Public Comment & Discussion 06/02/2008 DC #5, Continued Design and selection Discussion Public Comment & Discussion 06/16/2008 DC #6, Recommendation of Design firm finalists Forward recommendations to City Council 06/24/2008 CCRM Selection of Five finalists for City Hall & Park Design Competition Selected BCJ,Gonzales Goodale,Johnson Fain, LPA, & Rosetti Architecture ($50,000 each stipend) $ 250,000 09/22/2008 DC Public Presentations of Design Concepts by Finalists Presentations broadcasted on NBTV and videos posted on City Web page 09/29/2008 DC Public Discussion of the Five Design Concepts Public Comment & Discussion 10/13/2008 DC Continued Public Discussion of the Five Design Concepts Functionality and operational needs report presented by staff 10/27/2008 DC Continued Public Discussion of the Five Design Concepts Committee members presented their top three 11/10/2008 DC Continued Public Discussion of the Five Design Concepts Forward final report to City Council 11/12/2008 CCRM City Hall Design Committee - Draft final Report Receive and File 11/25/2008 CORM City Hall & Park Design Issues Accept final Report of the City Hall Design Committee Adopt Res. 2008 -98 modifying the membership of the Design committee's subcommittee on SD /DD Approve Hill, Sandland, & Bowden on SD /DD subcommittee Adopt Res 2008 -99 modifying Building Ad Hoc Committee Approve the Building committee's recommendation to direct staff to negotiate a PSA with BCJ 11/25/2008 CCRM City Hall Site General Plan Amendment 2008 -009 Approved GPA changing land use from Open Space (OS) to Public Facilities (PF) 01/10/2009 CCRM City Council Goal Setting 2009 Discussed various design issues, Park, Sail feature, Library linkage, Community Rm & Council Cham. Original direction to not include EOC 01/13/2009 CCRM Professional Services Agreement with Bohlin Cywinski Jackson Approved PSA with BCJ for Conceptual Development $ 647,675 01/13/2009 CCRM Professional Services Agreement with CW Driver Approved PSA with CW Driver for Program Management Services $ 233,660 01/27/2009 CCRM Professional Services Agreement with LSA Associates Approved PSA with LSA Associates for Environmental Services $ 180,000 02/24/2009 CCRM Professional Services Agreement with Leighton Consulting Approved PSA with Leighton Consulting for Geotechnical Services $ 62,674 02/25/2009 DC Joint meeting with PB &R and Arts Comissions BCJ presented concept plan from competition 03/23/2009 DC Continued discussion of BCJ concept BCJ presented concept plan from competition 04/14/2009 CCRM Consideration of Concept Design & Schematic Design Phase Approved conceptual plan and directed staff to negotiate with BCJ for Schematic Design phase Legend: CCRM - City Council Regular Meeting CCSS - City Council Study Session BC- Building Committee DC- Design Committee SRC - Site Review Committee FFRC - Facilities Finance Review Committee PW - Public Workshop SS3 -44 CIVIC CENTER PUBLIC MEETING TIMELINE January 13,2015 Meeting Meeting Date Type Subject Action Summary Contract Cost Notes 04/14/2009 CCRM Amendment #1 & #2 to PSA with LSA Associates Approved Amendment #1 to PSA with LSA Associates for technical studies and reports $ 34,584 Approved Amendment #2 to PSA with LSA Associates for phase 2 Environmental services $ 250,505 04/28/2009 CCRM Amendment #1 to PSA with BCJ Approved Amendment #1 to PSA with BCJ for Schematic Design and Design Development Phases $ 4,689,775 05/26/2009 CCRM Amendment #1 to PSA with CW Driver & Amend #1/ #2 with Leighton Approved Amendment #1 to PSA with CW Driver for Program Management for SD &DD $ 647,018 Approved Amendment #1 to PSA with Leighton for supplemental geotechnical (concept phase) $ 18,555 Approved Amendment #2 to PSA with Leighton for design level geotechnical report fo SD /DD phase $ 33,574 07/14/2009 CCRM Professional Services Agreement with RBF consulting Approved PSA with RBF Consulting for Traffic Engineering Services $ 99,500 08/11/2009 CCRM Civic Center Update - Size /Scope /Square Footages Presentation by staff on current space configuaration and comparisons to existing City Hall Revised direction to include EOC 08/11/2009 CCRM Amendment #2 to PSA with BCJ Approved Amendment #2 to PSA with BCJ to add SD /DD for an Emergency Operations Center (EOC) $ 169,222 08/11/2009 CCRM Professional Services Agreement with Hall & Foreman Approved Amendment to Newport Center Park Survey services to add Civic Center Survey Services $ 46,150 09/08/2009 CCRM Amendment #3 to PSA with Leighton Consulting Approved Amendment #3 to PSA with Leighton for supplemental geotechnical $ 99,640 09/22/2009 CCRM Amendment # 3 to PSA with BCJ Approved Amendment #3 to PSA with BCJ for IT selection services $ 5,780 10/13/2009 CCRM Amendment #3 to PSA with LSA Associates Approved Amendment #3 to PSA with LSA Associates for supplemental services $ 37,790 10/27/2009 CCSS Civic Center Update - Cost, VE, Phasing Staff presented update on costs, value engineering, and potential phasing 11/10/2009 CCRM Civic Center Update Staff presented update 11/24/2009 CCRM Certification of EIR & Authorization of Parking Structure Design /Build Certified EIR & authorized CW Driver to prepare Design /Build RFP for a 450 space parking structure 02/23/2010 CCRM Bond Reimbursement Authorization for Civic Center Expenditures Adopted Res 2010 -18 to allow Civic Center expenditures to be eligible for bond reimbursement 04/27/2010 CCRM Professional Services Agreement with LSA Associates Approved a PSA with LSA Associates for biological, cultural,& paleontological monitoring services $ 108,160 04/27/2010 CCRM Approve DD Phase plans & PSA with BCJ for Construction Documents Approved Design Development phase plans Approved Professional Services Agreement with BCJ for construction documents $ 4,949,214 04/27/2010 CCRM PSA with CW Driver for Project Management & CM @Risk contract Approved PSA with CW Driver for Project Management during Construction Document preparation $ 2,305,933 Approved Construction Manager at Risk Contract with CW Driver $ 14,617,374 Established contingency for the Mass excavation and shoring construction $ 673,000 06/22/2010 CCRM Professional Services Agreement with Leighton Consulting Approved PSA with Leighton Consulting for Construction observation and material testing (Geotech) $ 326,563 09/14/2010 CCRM Professional Services Agreement with Kroury Approved PSA with Kroury for material testing $ 865,498 09/14/2010 CCRM Amendment #1 to CM @R Contract with CW Driver, GMP Phase 2 Approved Amendment #1 to CM @R contract with CW Driver for Parking Structure $ 7,426,853 Established contingency for Parking Structure $ 350,000 11/09/2010 CCRM Authorization for 2010 Civic Center Financing documents Adopted Res 2010- authorizing financial documents for Certificates of Participation (COPS) 11/09/2010 CCRM Professional Services Agreement with BCJ for Construction Support Approved Professional Services Agreement with BCJ for construction support $ 3,935,112 02/22/2011 CCRM Amendment #2 to CM @R Contract with CW Driver, GMP Phase 3 Approved Amendment #2 to CM @R contract with CW Driver for City Hall, Library Expansion & Park $ 82,374,384 Established contingency for City Hall, Library Exp. & park $ 1,600,000 Approved a PSA with Anderson Penna for Building Inspection /plan review /Building Official Services $ 1,090,840 Authorized the addition of the San Miguel Pedestrian Bridge $ (1,000,000) $1 million Contractor, $1 million City Contingencies 07/26/2011 CCRM Amendment to PSA with BCJ for project signage /Const. support Approved amendment to PSA with BCJ for additional construction support and project signage $ 165,780 08/09/2011 CCSS Civic Center Project update Staff presented current status including schedule cost, VE, and contingencies 11/22/2011 CCRM Amendment #4 to PSA with BCJ for FF &E Approved Amendment #4 to PSA with BCJ for the addition of services in selecting FF &E $ 220,310 02/28/2012 CCRM Amendment #1 to PSA with Allana Buick & Bers Approved Amendment #1 to PSA with Allana, Buick, & Bers for waterproofing monitoring services $ 243,052 04/10/2012 CCRM Amendment # 3 to PSA with LSA Consulting Approved Amendment #3 to PSA with LSA Consulting for additional environmental monitoring $ 35,800 04/24/2012 CCRM Amendment #4 to CM @R Contract with CW Driver Approved Amendment #4 to CM @R Contract with CW Driver for Signage and Dry Utilities $ 476,281 06/26/2012 CCRM Purchase of City Hall Furniture, fixtures & Equipment (FF &E) Approved the purchase of Millwork with Montbleau and Associates $ 642,590 Approved the purchase of ancillary furniture with Pivot Interiors $ 1,083,491 Approved the purchase of systems furniture with 105 Interiors $ 898,500 Established a contingency of 5% $ 130,418 Legend: CCRM - City Council Regular Meeting CCSS - City Council Study Session BC- Building Committee DC- Design Committee SRC - Site Review Committee FFRC - Facilities Finance Review Committee PW - Public Workshop SS3 -45 CIVIC CENTER PUBLIC MEETING TIMELINE January 13,2015 Meeting Meeting Date Type Subject Action Summary Contract Cost Notes 10/09/2012 CCRM Purchase of Library Expansion Furniture, fixtures & Equipment (FF &E) Approved the purchase millwork with Montbleau Associates $ 210,916 Approved the purchase of ancillary furniture with Pivot Interiors $ 223,190 Approved the purchase of fabric ceilings with Preferred Ceilings $ 15,890 Approved lighting and electrical with Rosedin Electric $ 50,525 Established a contingency (5 %) $ 25,000 10/23/2012 CCRM Central Library Clerestory Repair Approved Amendment #5 to CM @R Contract with CW Driver for Library Clerestory Repair $ 720,913 Existing clerestory window system replacement 11/27/2012 CCRM Amendment to PSA with Anderson -Perna Approved Amendment to PSA with Anderson -Perna for additional inspection services $ 205,805 02/26/2013 CCRM Amendment #2 to PSA with Kroury Approved Amendment #2 to PSA with Koury for additional materials testing $ 273,268 06/11/2013 CCRM Civic Center & Park Closeout Accounting Approved the increase of the project contingency to $6.5 million (6 %) $ 4,877,000 Approved final Amendment to PSA with BCJ for additional services $ 579,670 10/08/2013 CCRM Final Amendment to the CM @R Contract with CW Driver Approved Final Amendment to CM @R contract with CW Driver for final costs $ 1,400,000 Extended Basic Services Jan thru May 2013 02/25/2014 CCRM Claims Settlement -CW Driver, BCJ, and City Approved Final claims settlement and executed agreement $ 2,399,430 Legal Settlement - Not considered a project cost Total Cost approved by Council action for 100 Civic Center Drive Site *_ $ 142,115,862 * does not include expeditures authorized by the City Manager or Department heads per their authority under Council Policy F -5. for detailed costs see Project cost summary Legend: CCRM - City Council Regular Meeting CCSS - City Council Study Session BC- Building Committee DC- Design Committee SRC - Site Review Committee FFRC - Facilities Finance Review Committee PW - Public Workshop SS3 -46 CIVIC CENTER & PARK 01- Aug -14 Expenditure Breakdown EXHIBIT G Description Amount SOFT COSTS ARCHITECTURAL DESIGN Concept Design Refinement 647,675 Schematic Design & Design Development, SD & DD 4,998,677 Construction Documents (CD) 5,588,154 Construction Support (CS) 4,514,782 Total Design= 15,749,288 ENVIRONMENTAL DOCUMENTATION & MONITORING Environmental Impact Report 618,049 Geotechnical 253,421 Environmental Mitigation Monitoring 68,186 Total Environmental = 686,235 TOTAL DESIGN 16,435,523 PROJECT MANAGEMENT /CONSTRUCTION SUPPORT Project Management: SD & DD 647,018 Project Management: CD & CS 2,305,933 Leadership in Energy and Environmental Design (LEED) 170,250 TOTAL PROJECT MANAGEMENT 3,243,895 SCE - SAVINGS BY DESIGN - 261,150 TOTAL SOFT COSTS 19,418,268 HARD CONSTRUCTION COSTS CONSTRUCTION Basic Services /General conditions 7,169,255 • GMP Phase 1- Mass Excavation & Shoring Wall 7,336,439 • GMP Phase 2 - Design Assist /Build Parking Structure 7,426,853 * GMP Phase 3 - City Hall, Library & Park 82,374,384 * GMP Phase 4- San Miguel Pedestrian Bridge 1,000,000 * GMP Phase 5 - Signage & deferred Electrical Utilities 476,281 * GMP Phase 6 - Library Clererstory Window Replacement 720,913 106,504,125 CONSTRUCTION CHANGE ORDERS CCO #1 -ADA Ramp Modifications 12,269 CCO #2 - Revised DG surface for Dog Park 10,964 CCO #3 - AV Modifications & shelving 35,001 CCO #4 - Window Shade and Lighting Controls 134,618 CCO #5 -Storm Damage,( Reimbursed by FEMA, $65,005) 0 CCO #6- Structural elements, electrical & Lighting 250,493 CCO #7 - Landscaping and Site modifications 271,666 CCO #8 - Architectural and Structural revisions 611,842 CCO #9 - Various 561,912 CCO #10 - Various 367,835 CCO #11- Various 215,376 CCO #12 - Various 394,627 CCO #13 - Various 475,665 CCO #14 - Various 586,085 CCO #15 - Various 348,538 CCO #16 - Various 1,412,717 CCO #17 - Various 808,014 6,497,622 EXTENDED GENERAL CONDITIONS (Jan -May) 1,400,000 TOTAL HARD CONSTRUCTION = 114,401,747 SS3 -47 CONTRACT BUILDING OFFICIAL - PLAN CHECK & INSPECTION MATERIAL TESTING & SPECIAL INSPECTION FIXTURES, FURNITURE AND EQUIPMENT CityHall FF &E Library FFE OCIP INSURANCE PROJECT COSTS SUBTOTAL Clerestory Window Repair Floor leveling Additional Carpeting due to floor leveling Existing Library Foundation Waterproofing Refurbishment of existing roller shades Additional power and data at self checkout Upgrade existing Electrical Remove and replace 48 diseased Olive Trees Upgrade Library book Security System to RFID Existing Stairway rebuild due to alignment problem TOTAL LIBRARY REPAIR Share of Soft costs Share of insurance Share of General conditions TOTAL LIBRARY REPAIR 1,426,285 1,309,608 2,755,000 525,521 TOTAL FF &E = 3,280,521 1,882,922 TOTAL ANCILLARY COST= 7 141,719,351 720,913 50,514 13,773 47,799 5,000 7,499 22,983 52,500 33,621 250,000 1,204,602 204,466 19,826 75,489 PROJECT COSTS TOTAL (Less Dedicated Library repair costs) = 140,214,967 SS3 -48