HomeMy WebLinkAboutSS2 - Status Report on Top 10 Staff Priorities for 2001-2002CITY OF NEWPORT BEACH
AGENDA ITEM NO. SS2
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Homer L. Bludau, City Manager
DATE: July 23, 2002
SUBJECT: Status Report on Top 10 Staff Priorities for 2001 -2002
As the City Council is aware, last year for the first time the City Management
Team went through a process to determine its highest priorities for
accomplishment for the 2001 -02 fiscal year. That year is now completed, and
the City Manager wants to review the status of those priority accomplishments for
you. They are as follows:
SIGN A JWA SETTLEMENT AGREEMENT WITH THE COUNTY
Completed. The Settlement Agreement Extension was signed by all 4
parties by June 25, 2002. Of course, this accomplishment was not within
the complete control of City staff; however, the City Attorney and City
Manger both contributed to the meeting of deadlines, cooperative working
relationships established with the corridor cities, and preparation of
documents needed to achieve this highest Council and staff priority.
2. BEGIN AND COMPLETE THE PUBLIC OUTREACH PORTION OF THE
GENERAL PLAN UPDATE PROCESS
Started and well underway. The GP public outreach process began in
January, 2002, with a kick -off event at Hoag Hospital and continued with
neighborhood meetings held in each Council district. Kits were made
available for the input process to any individuals and groups that desired
such participation. The General Plan Advisory Committee (GPAC) was
appointed by Council, which consists of residents from various
geographical and interests areas of the community. The public outreach
has not yet concluded. It will further consist of a statistically accurate
telephone survey with 1200 residents and a concluding "Community
Congress ", to inform the community of the outreach results. After the
City Hall • 3300 Newport Boulevard • Post Office Box 1768 • Newport Beach, California 92659 -1768
Status Report on Top 10 Priorities for 2001 -2002
Page 2
visioning process is completed and the Council has determined the scope
of the update, the GPAC will continue to provide input into the
development of General Plan policy statements, based on the community
input information.
3. COMPLETE THE ANNEXATION OF THE NEWPORT COAST AND
BEGIN PROVIDING CITY SERVICES TO THE POPULATION
Completed. LAFCO certified the annexation in December, 2001, and the
City began providing our new residents City services on January 1, 2002.
4. HAVE THE CITY COUNCIL ADOPT NEW PERSONNEL POLICIES
Completed. The City Council adopted the new personnel policies at its
meeting of December 11, 2001, after an extensive review /dialogue
process with employee associations and the Civil Service Commission.
5. ATTAIN FULL COMPLIANCE WITH THE NEW NPDES PERMIT
REQUIREMENTS AND COMPLETE THE THREE WATER QUALITY
TESTS REQUIRED BY THE REGIONAL QUALITY CONTROL BOARD
Full compliance has been attained; testing is underway. City staff
(including Building, Planning, Public Works, General Services, and the
City Manager's Office) actively participated in the review and development
of the new 5 -year Municipal Separate Storm Sewer System ( "MS4 ")
Permit required of every public agency in central and north Orange County
that operates a storm drain system. The Permit, adopted by the California
Regional Water Quality Control Board, Santa Ana Region ( "Regional
Board ") in January 2002, contains significant new requirements of
residents, visitors, businesses, developers, and especially city
government.
The City partnered with the Santa Ana Regional Water Quality Control
Board in 2001 -02 to conduct two of the three studies contemplated in this
Priority. We submitted all materials and results to the Regional Board.
Additional phases of all three studies will continue in FY 2002 -03 using
State resources.
6. COMPLETE THE MOST TIME - SENSITIVE CAPITAL IMPROVEMENT
PROJECTS
a) The Newport Pier was completed and re- opened in May 2002; the
Balboa Pier was completed and re- opened in June, 2002.
b) Balboa Village Phase 1 was effectively completed in June, 2001. The
contractor is performing minor revisions and corrections (punch list
2
Status Report on Top 10 Priorities for 2001 -2002
Page 3
items) in order to fulfill his contractual obligations and achieve formal
completion.
c) The original scope of work for Bonita Canyon Sports Park is currently
complete, with the exception of some minor corrections and the plant
establishment period, which will conclude in November, 2002. The
West Park portion (along MacArthur Blvd.) was added to the project by
the City Council on August 14, 2001; this landscaping portion will be
completed in October, 2002, with the plant establishment period
concluding in March, 2003. The bankruptcy of the original contractor,
Costello Construction, caused a delay of 6 months in project
completion.
7. IMPROVE THE PLAN CHECK AND PERMIT ISSUANCE PROCESS
A new plan check process was implemented July 1, 2002 to meet the
standard of 90% of initial plan checks made and returned to applicants
within a 4 week time period. This process will also speed up time frames
for additional checks of plans required after the first return. This effort
involved major procedural changes on the part of Building, Planning, and
Public Works staffs. It is too soon to measure the success of the new
processing changes, but the time frames will be monitored closely and
that information will be provided to Council as time goes on.
8. REDUCE THE CITY'S ELECTRICITY CONSUMPTION (MEASURED IN
KILOWATT HOURS) BY 10% FROM JANUARY 2001 TO JUNE 2002
Goal was revised. Based on more study, it was decided to concentrate on
two energy saving measures. Measure 1 was to utilize $120,000 to
change out our overhead office lighting with energy efficient electronic
ballasts and lighting. This project was completed in April, 2002. While
the project was under way, a change order was issued to add additional
change outs not included in the original contract; this work will be
completed in 4 weeks. Measure 2 was to change out a high energy -
utilization water pump station at the Big Canyon Reservoir to a more
energy efficient motor control system, which included a standby
emergency generator. Due to cost considerations, work began later than
originally planned, but the change -out will be completed by July 19, 2002.
9. DEVELOP AND IMPLEMENT A TRAINING PROGRAM FOR FIRST LINE
AND MID -LEVEL MANAGERS WITHIN THE ORGANIZATION
Completed. The first two training classes for first -line and mid -level
managers started on April 8"' and were completed on June 19, 2002.
Three additional classes will start this fall. By the end of this calendar
year, 120 first line and mid -level managers within the organization will
Status Report on Top 10 Priorities for 2001 -2002
Page 4
have graduated from this training. The training is getting high marks for
subject content and relevancy from its participants.
10. BEGIN THE LOCAL COASTAL PROGRAM CERTIFICATION PROCESS
Begun and well underway. SB 516 requires the City to submit a complete
LCP application to the Coastal Commission before June 30, 2003.
Council has appointed the LCP Certification Committee, and a timetable
and outline has been approved. Technical consultants have been
retained and the preparation of needed studies is underway. The Planning
Department has drafted the first two chapters of the LCP Land Use Plan.
A preliminary draft of the LCP should be ready for submittal to the Coastal
Commission staff in November, 2002.
I