HomeMy WebLinkAbout07 - 2013 -2014 Streetlight Improvement Project - NOC and Acceptance of Contract No. 5495 (CAP14-0016)CITY OF
NEWPORT BEACH
City Council Staff Report
January 27, 2015
Agenda Item No. 7
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director- (949) 644 -3330,
dawebb @newportbeachca.gov
PREPARED BY: Peter Tauscher, Civil Engineer
PHONE: (949) 644 -3316
TITLE: 2013 -2014 Streetlight Improvement Project - Notice of Completion and Acceptance
of Contract No. 5495 (CAP14 -0016)
ABSTRACT:
On March 25, 2014, City Council awarded Contract No. 5495, 2013 -2014 Streetlight Improvement Project
to California Professional Engineering, Inc. (CPE), for a total contract cost of $468,700.00 with a
$47,300.00 (10 percent) allowance for contingencies. The required work is now complete and staff
requests City Council acceptance and close out of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of
Completion has been recorded in accordance with applicable portions of the Civil Code; and
c) Release the Faithful Performance Bond one year after acceptance by the City Council.
FUNDING REQUIREMENTS:
Funds for the construction contract were expended from the following account:
Account Description Account Number Amount
General Fund 7013- C2201000 $521,452.16
Total: $521,452.16
7 -1
DISCUSSION:
Overall Contract Cost /Time Summary
Awarded
Contract
Amount
Final Cost at Contingency
Completion Allowance
or
Allowed Contract Time (days) 1 105
Actual
% Due to
:,ontract
Directed
Change
Change
11.3%
-4.4%
Actual
Time
Under f-1
or Over N
% Due to
Unforeseen
Change
30
The contract replaced 129 existing streetlight fixtures with new energy efficient LED streetlight fixtures and
upgraded the existing streetlight circuit per the City's Streetlight Replacement Master Plan. The project
area included Irvine Avenue from north of Santiago Road to Tustin Avenue, and a portion of the Westcliff
neighborhood. The contract was completed to the satisfaction of the Public Works Department. A
summary of the contract cost is as follows:
Original bid amount: $ 468,700.00
Actual cost of bid items constructed:$ 542,198.50
Total change orders: $ - 8,246.34
Liquidated damages: $ - 12,500.00
Final contract cost: $ 521,452.34
The final construction contract cost was approximately 11.3 percent over the original contract amount,
which is slightly more than the allotted 10- percent contingency. The bulk of the cost increase was caused
by the unforeseen need to replace a large portion of existing deteriorated electrical conduit. Two change
orders were executed; the first change order was a reimbursement to the City for making emergency
repairs caused by CPE. The second change order was providing the contractor extra days needed for the
installing the additional conduit.
CPE exceeded the allotted contract working period by 30 days often times not appearing for work;
supplying the project with unacceptable materials that were subsequently rejected; and providing
insufficient staffing. CPE also repeatedly failed to meet construction milestones established for the
project. On October 13, 2014, CPE was notified that they would be subject to the agreed liquidated
damages in the amount of $500.00 per day following the contract completion date of October 17, 2014.
Subsequently, CPE did increase its staffing and was able to complete the contract 30 days after the
contract completion date. Given CPE's renewed demonstration to work with City staff, liquidated damages
were limited to 25 days. CPE was given every opportunity to complete the work on time. Staff feels it is
appropriate to assess 25 days of liquidated damages at $500.00 per calendar day for late completion as
specified in the Contract Specifications.
A summary of the project schedule is as follows:
Estimated Completion Date per 2014 Baseline Schedule September 19, 2014
Project Awarded for Construction March 25, 2014
Contract Completion Date with Approved Extensions October 28, 2014
Actual Substantial Construction Completion Date December 12, 2014
ENVIRONMENTAL REVIEW:
City Council found this project exempt from the California Environmental Quality Act ( "CEQA ") pursuant to
Section 15302 (replacement of existing facilities involving negligible expansion of capacity) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a
significant effect on the environment.
7 -2
NOTICING:
This agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at
which the City Council considers the item). In addition, the City Clerk will be filing a Notice of Completion
for the project as a result of this action.
The Notice Inviting Bids was advertised in the City's official publication and in construction industry
publications.
ATTACHMENTS:
Description
Attachment A - Location Map
Attachment B - Letter to California Professional Engineering dated October 13, 2014
7 -3
JP
Q� P�
�s "areiHC 5�P
NF P
LS, 5P
NTS v V vvvvvvvvvv r.A,
HEATHER SANE
I FGFND
CONSTFUCTION ��������������
IMITS
NEWPORT BACK
BAY
STREETLIGHT CIRCUIT SLD0079
BACK
BAY
STREETLIGHT CIRCUIT SLD0075
2013 -2014 STREETLIGHT CITY OF NEWPORT BEACH
IMPROVEMENT PROJECT PUBLIC WORKS DEPARTMENT
LOCATION MAP C -5495 1/27/15
7 -4
ATTACHMENT B
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
David A. Webb, Public Works Director
October 13, 2014
Van Nguyen
California Professional Engineering, Inc.
929 Otterbein Avenue, Unit E
Rowland Heights, CA 91748
Subject: 2013 -2014 Streetlight Improvement Project (C -5495)
Liquidated Damages Assessment
Dear Mr. Nguyen,
This is to advise you that as specified in the contract documents for the 2013 -2014 Streetlight
Improvement Project, Contract (C- 5495), California Professional Engineering, Inc. (CPE) had seventy -
five (75) consecutive working days to complete all work under this contract. The 'Notice to Proceed'
(NTP) was issued on May 23, 2014 for work to begin on June 2, 2014.
Per the NTP and approved additional working days added for unplanned work, the contract
completion date is Friday, October 17, 2014. In the field meeting, an updated schedule was
requested by the City on Tuesday, October 6, 2014 and still has yet to be provided to the City for
review. CPE shall be subject to liquidated damages per Section 6 -9 Liquidated Damages of the
contract at $500.00 per calendar day for failure to complete the work within the allotted time.
Upon multiple occasions Project Inspector, Frank Martin, and me observed CPE failing to show up for
work or with limited crews adding to the delayed completion. Regular project meetings were
conducted and during those meetings CPE was notified to work with SCE and subcontractor to
complete the project. You are hereby notified that CPE has until October 17, 2014 to respond in
writing to this letter with an action plan to complete this project in a suitable manner. In case of non -
response, the City will consider CPE has agreed to the above liquidated damages amount and that
such damages will be deducted from future progress and retention release payments due CPE.
Sincerely,
/ Cif -w� v
Peter Tauscher, P.E.
Civil Engineer
Cc Mark Vukojevic, City Engineer
Frank. Martin, Senior PW Inspector
Leonie Mulvihill, Asst. City Attorney
100 Civic Center Drive • Post Office Box 1768 a Newport Beach, California 92660 (P.O. Box 92658 -8915)
Telephone: (949) 644 -3330 • Fax: (949) 644 -3308 • www.newportbeachca.gov
I: 1Usem1PBW1Shamd \Cont,acts\FY14 -15 CURRENT PROJECTS@00- STREETS AND DRAINAGBC -5495 -FY 13-14 Ste tfight Improvement CAP14- MMotloe of Uquideted
Damages- 101014.docx . 1 -
7 -5