CITY COUNCIL STAFF REPORT
Agenda Item No. 15
June 8, 2004
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
R.Gunther, P.E.
949 - 644 -3311
rgunther@city.newport-beach.ca.us
SUBJECT: OCEAN FRONT WALKWAYS — MCFADDEN SQUARE — COMPLETION
AND ACCEPTANCE OF CONTRACT NO. 3660
RECOMMENDATIONS:
1. Accept the work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the Labor and Materials bond 35 days after
the Notice of Completion has been recorded in accordance with applicable
portions of the Civil Code.
4. Release the Faithful Performance Bond 1 year after Council acceptance.
DISCUSSION:
On March 23, 2004, the City Council authorized the award of Oceanfront Walkways -
McFadden Square contract to Trademark Concrete Systems, Inc. The contract
provided the removal of the majority of the tiled areas within the McFadden Plaza.
These tiled areas were replaced with stamped concrete that matched the current tiles in
color and texture.
The contract has now been completed to the satisfaction of the Public Works
Department. A summary of the contract cost is as follows:
Original bid amount: $104,331.00
Actual amount of bid items constructed: 109,166.73
Total amount of change orders: 0.00
Final contract cost: $109,166.73
SUBJECT: Ocean Front Walkways —McFadden Square -Completion and Acceptance of Contract No. 3660
June 8, 2004
Page 2
The increase in the amount of actual bid items constructed over the original bid amount
resulted from the need for additional 359 square feet of removal of tiles and
construction of stamped concrete. The final overall construction cost was 4.64 percent
over the original bid amount. No Change Orders were issued for the project.
Environmental Review:
The project was determined to be exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301 of the CEQA Implementing Guidelines. This
exemption covers the maintenance of existing public facilities, involving negligible
expansion of the facilities in areas that are not environmentally sensitive. This project
involved removing and replacing selected failed areas of tiled sidewalk.
Fundinq Availability:
Funds for the project were expended from the following account:
Account Description Account Number Amount
Balboa Peninsula Beach Walkway 7295 C5100570 $109,166.73
All work was completed by the scheduled completion date of May 21, 2004.
Prepared by: Submitted by:
R. un fher, P.E. Step G t um
Construction Engineer Py Ic Vy rks Director