HomeMy WebLinkAbout12 - C-3646 - Cameo Shores Sewer Force MainCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 12 June 22, 2004 TO. HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department R.Gunther, P.E. 949 - 644 -3311 rgunther@city.newport-beach.ca.us SUBJECT: CAMEO SHORES SEWER FORCE MAIN — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3646 RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond 1 year after Council acceptance. DISCUSSION: On January 13, 2004, the City Council authorized the award of the Cameo Shores Sewer Force Main contract to GCI Construction, Inc. The contract provided the upsizing of an existing 4 -inch diameter sanitary sewer force main to 6- inches to allow for better hydraulic capacity for the pump station. The force main handles flow for Cameo Shores and Pelican Point and extends on Milford Drive between Camden Drive and Hampden Road. During peak flows the existing 4 -inch force main impacted the capacity of the pump station. In addition, access road modifications were made to allow the City's larger equipment to access the pump station and a new discharge manhole was installed at the terminus of the new force main. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $177,905.00 Actual amount of bid items constructed: 181,361.50 Total amount of change orders: 28,381.92 Final contract cost: $209,743.42 SUBJECT: Cameo Shores Sewer Force Main - Completion and Acceptance of Contract No. 3646 June 22, 2004 Page 2 The final overall construction cost including Change Orders was 17.9 percent over the original bid amount. Per City Council Policy, the City Manager has given his written authorization to exceed the original contract by over 10 %. Three Change Orders in the amount of $28,381.92 were issued for the project. Change Order No. 1 in the amount of $11,908.69 provided for reconstruction and replacement of asphalt pavement adjacent to the sewer trench. Change Order No. 2 in the amount of $12,653.10 provided for the removal of the existing sewer pipe and for a drop manhole connection. Change Order No. 3 in the amount of $3,820.13 provided for asphalt reconstruction and replacement based on as built measurements in addition to the amount in Change Order No. 1. Environmental Review: The project was determined to be exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302 of the CEQA Implementing Guidelines at the time the project was authorized by the City Council. This exemption covers the maintenance and alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. Funding Availabilit : Funds for the project were expended from the following account(s): Account Description Account Number Amount Sewer Main Replacement 7531- C5600728 $194,905.00 Wastewater Enterprise 7531- C5600292 14,838.42 TOTAL: $209,743.42 The original contract completion date was May 7, 2004. Due to the added Change Order work the completion date was extended to May 27, 2004. All work was completed by the revised completion date. Prepared by: 'e, "Y"kL� R. Gunther, P.E. Construction Engineer Submitted by: Stephen G. ._ Public -OoL CITY OF NEWPORT BEACH OFFICE OF THE CITY CLERK LaVonne M. Harkless. CMC June 23, 2004 Orange County Recorder P. O. Box 238 Santa Ana, CA 92702 RE: Notices of Completion (C -3646, C -3654, C -3649 and C -3447) Please record the enclosed documents (4) and return to the City Clerk's Office. Thank you. Sincerely, LaVonne M. Harkless, CMC City Clerk Enclosures 3300 Newport Boulevard - Post Office Box 1768 - Newport Beach. California 92658 -8915 Telephone: (949) 644 -3005 - Fax: (949) 644 -3039 - wwv,.city.newport- beach.ca.us RECORDING REQUESTED BY AND WHEN RECORDED RETURN TO: City Clerk City of Newport Beach 3300 Newport Boulevard Newport Beach, CA 92663 NOTICE OF COMPLETION 6103" NOTICE IS HEREBY GIVEN that the City of Newport Beach, 3300 Newport Boulevard, Newport Beach, California, 92663, as Owner, and GCI Construction, Inc., of Costa Mesa, California, as Contractor, entered into a Contract on February 9 2004. Said Contract set forth certain improvements, as follows: Cameo Shores Sewer Force Main (C -3646 Work on said Contract was completed on May 27. 2004 and was found to be acceptable on June 22 2004, by the City Council. Title to said property is vested in the Owner, and the Surety for said Contract is Fidelity and Deposit Company of Maryland fll-ublic s Director City ewport Beach VERIFICATION certify, under penalty of perjury, that the foregoing is true and correct to the best of my knowledge. Executed on Lrt aL;o at Newport Beach, California. BY City Clerk