HomeMy WebLinkAbout05 - C-3718 - 2004-2005 Sidewalk Curb & Gutter Replacement ProgramCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 5 April 12, 2005 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department R.Gunther, P.E. 949 - 644 -3311 rgunther @city.newport- beach.ca.us SUBJECT: 2004 -2005 SIDEWALK, CURB AND GUTTER REPLACEMENT PROGRAM — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3718 RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond one year after Council acceptance. DISCUSSION: On October 12, 2004 the City Council authorized the award of the 2004 -2005 Sidewalk, Curb and Gutter Replacement Program contract to Damon Construction Company. The contract provided for the removal of old curb, gutter, sidewalk, driveway approaches, curb access ramps, root pruning trees and construction of new PCC curb, gutter, sidewalk, driveway approaches, curb access ramps, and installation of new tree root barriers in the Westcliff area. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $304,525.00 Actual amount of bid items constructed: 316,274.50 Total amount of change orders: 0.00 Final contract cost: $316,274.50 SUBJECT: Sidewalk, Curb and Gutter Replacement Program - Completion And Acceptance of Contract No. 3718 April 12, 2005 Page 2 The increase in the amount of actual bid items constructed over the original bid amount resulted from the need for additional concrete curb and gutter. The final overall construction cost was 3.9 percent over the original bid amount. No Change Orders were issued for the project. Funding Availability: Funds for the project were expended from the following accounts: Account Description General Fund Gas Tax CDBG Concrete Maintenance Account Number 7013- C5100020 7181- C5100302 7161- C5100549 3130 -8239 Amount $156,249.50 21,300.00 50,000.00 88,725.00 Total: $316,274.50 The original completion date was January 28, 2005. Due to rain and additional curb and gutter construction the work was completed on March 28, 2005, the revised completion date. Prepared by: —&' R. Gunther, P.E. Construction Engineer Submitted by: Stephen G. B d n% Public Works Director