RECOMMENDATIONS:
1. Accept the work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the Labor and Materials bond 35 days after
the Notice of Completion has been recorded in accordance with applicable
portions of the Civil Code.
4. Release the Faithful Performance Bond one year after Council acceptance.
DISCUSSION:
On June 24, 2003, the City Council authorized the award of the Jamboree Road -
MacArthur Boulevard Intersection Improvements contract to Hillcrest Contracting. The
contract provided for the widening of a portion of northbound MacArthur Boulevard
between Jamboree Road and Fairchild Road, adding a second left -turn lane on
MacArthur Boulevard at Jamboree Road for both directions, and a right -turn lane on
northbound MacArthur Boulevard.
To accommodate the roadway widening and traffic realignment, retaining walls, various
utility relocations, PCC sidewalks, asphalt concrete pavement, traffic signal and street
lighting, modifications were constructed. The southbound Jamboree Road right -turn
lane and the adjacent traffic island at MacArthur Blvd was reconstructed to improve
traffic flow. The existing curb -side bus stop along northbound MacArthur Boulevard in
front of the Koll Center Newport was replaced with a new mid -block bus "turn -out'
SUBJECT: Jamboree Road — MacArthur Boulevard Intersection Improvements - Completion And Acceptance of Contract
No-3369
May 10. 2005
Page 2
pocket. New landscaping, irrigation system, various drainage facilities, and pavement
striping and markings were constructed throughout the work limits.
This project was approved by the Orange County Transportation Authority for competitive
Intersection Improvement Program (IIP) funds under the Combined Transportation
Funding Program. The IIP is funding $657,740.40 for the completed construction work.
They will also be funding up to $87,600 for administrative, testing, and inspection
services. In addition, since the improvements are within both the City of Newport Beach
and the City of Irvine, the City of Irvine will reimburse the City of Newport Beach
$733,533.94 for their portion of the contractor costs ($713,544.51 as their share of costs
of the contract with Hillcrest, and $19,989.43 as part of Irvine's reimbursement to Newport
Beach for Newport Beach's payment to IRWD for relocating a watermain within the City of
Irvine. See attached letter from the City of Irvine). Irvine will also reimburse Newport
Beach for 2/3 of the costs for administrative and construction services provided by the
City of Newport Beach.
The contract has now been completed to the satisfaction of the Public Works
Department and the City of Irvine. A summary of the contract cost is as follows:
Original bid amount: $1,440,944.80
Actual amount of bid items constructed: 1,483,668.50
Total amount of change orders: 119,263.98
Final contract cost: $1,602,932.48
The increase in the amount of actual bid items constructed over the original bid amount
resulted from the need for additional deep lift asphalt concrete, 18 -inch diameter RCP
storm drain, and concrete for the retaining wall footing. The overall construction cost
including change orders was 11.2 percent over the original bid amount. The City
Manager has given his written authorization to exceed the original contract by over 10%
per the City Council Policy F -3.
Nine Change Orders in the amount of $119,263.98 were issued for the project. They
were numbered and described as follows:
1. In the amount of $9,010.53 providing for the removal of a tree at the retaining
wall and potholing for relocation of a watermain.
2. In the amount of $7,856.26 providing for the removal of conflicting utilities and
construction of a wall subdrain.
3. In the amount of $13,090.58 providing for additional concrete work for the
revised right turn island at the northwest corner of the intersection, storm drain
work, and traffic signal work.
4. In the amount of $7,519.31 providing for the addition of a new Myers cabinet and
electrical service to the irrigation controller.
5. In the amount of $7,288.49 providing for additional work at watermain
connections.
SUBJECT: Jamboree Road — MacArthur Boulevard Intersection Improvements - Completion And Acceptance of Contract
No.3369
May 10, 2005
Page 3
6. In the amount of $6,195.13 providing for storm drain modifications on
CNB Line A -1.
7. In the amount of $5,034.00 providing for replacement of pavement markers,
directional signs and additional groundcover required.
8. In the amount of $39,413.94 providing for additional over - excavation at the
retaining wall and irrigation and myroporum groundcover behind the retaining
wall.
8a. In the amount of $4,314.85 providing for a correction to CO8 for the additional
over - excavation behind the retaining wall.
9. In the amount of $19,540.89 providing for removal of extra thick asphalt at the
northwest corner of the intersection, additional electrical work, and other
miscellaneous items.
Environmental Review:
The City of Irvine prepared the Initial Study and the Negative Declaration (without
mitigation measures) document. No public comments were received.
Funding Availability:
Funds for the project were expended from the following accounts:
Account Description
Circulation and Transportation
Contribution from City of Irvine
Intersection Improvement Program
Account Number Amount
7261- C5100584 $211,658.14
7251- C5100584 $733,533.94
7284- C5100584 $657,740.40
Total: $1,602,932.48
The original completion date was June 4, 2004. The project completion was extended
to October 2004 due to change order work. The traffic signalization and traffic lanes
were substantially complete in October 2004. The landscape maintenance period
ended on January 15, 2005 when the City of Irvine accepted the landscaping on Irvine
right of way. All work was completed by March 1, 2005, when as -built documents,
CD's, and warranty and product brochures were delivered by the contractor. Since that
time, staff has worked with the contractor to finalize costs and with the City of Irvine to
finalize cost - sharing.
Prepared by: Submitted by:
Q 'Ole
R. Gunther, P. . S�pph G. Badum
Construction Engineer �PubJjWorks Director
Attachment: City of Irvine Letter Dated April 19, 2005
le �ie
\ 7a
pF
u � m
err{ of rvine, Ore Cmc Center Plaza. P.G. Box '9575 Irv,r.e, Caliiomr a 92623 -9575 (949) 721 -6000
April 19, 2005
R. Gunther
Construction Engineer
City of Newport Beach
P.O. Box 1768
Newport Beach, CA 9265 8 -89 1 5
SUBJECT: J.AvIBOREE ROAD / NIACARTHUR BOULEVARD INTERSECTION
IMPROVEMENT PROJECT — C-3365
Dear Gunther:
Thank you for your letter, dated April 7, 2005, explaining in detail, the additional excavation and
irrigation activities and costs associated with this complex joint project. The City of Irvine
appreciates the City of Newport Beach's efforts in leading .he final design and construction
phases of this project. After a careful review of the final cost sharing summary, dated March 16,
2005, as well as your recent letter and several telephone conversations explaining the additional
excavation and irrigation costs, the City agrees with and approves the final cost sharing
summary, as submitted on March 16, 2005.
Per the final cost share summary, the City of Irvine is responsible for its share of project costs in
the amount of $713,544.51, plus the reimbursement to Newport Beach for IRWD costs within
the City of Irvine, in the amount of $19,989.43.
If you have any questions, please feel free to call me at (949) 724 -6262.
Sincerely,
Sun -Sun T. Murillo, P.E.
Senior Transportation Analyst
C: Jon Toolson, Project Development Administrator
Tim Kirkham, Right -of -Way Administrator
Dave Mori, Project Development Administrator
Eric Gruber, Senior Construction Inspector
Bill Patapoff, City of Newport Beach
Fong Tse, City of Newport Beach