HomeMy WebLinkAboutManager's_Report (16)Manager's Re
ort
October 20, 2010
Harbor Resources
C4 �:
Dredging —Upper Bay
Ribbon Cutting Ceremony for elected officials, dignitaries and
sponsors. City Council and Harbor Commission will be invited.
Saturday, November 6, 2010
10:00 AM
Peter and Mary Muth Interpretive Center
Dredging — Lower Bay
Corps Colonel Mark Toy Visit to Newport Beach
With Corps staff, Council Members, Commissioner Rhyne and senior
staff to discuss:
• Lower Bay
• Santa Ana Marsh (Newport Slough area)
• Upper Bay completion
Lower Bay funding has about $2.5 M in federal funds
Waiting for President's budget in January for possible increase
• This amount is enough to start a dredging project for minimal quantities
• Possible that the Corps could start dredging in 2011
1► Ib: V:ul Oj
LONG BEACH
r raearcm"M
October 18, 2010
Mr. Chris Muter
City of Newport Beach
Harbor Resources Division
829 Harbor Island Drive
Newport Beach, CA 92660
Subject: Application for Placement of Dredged Material in the Pon of Long Beach Middle
Harbor Fill Site - Lower Newport Bay Maintenance Dredging Project
Dear Mr. Miller.
The City of Newport Beach (City) recently submitted an application to the Port of Long Beach
(Port) to place approximately 700,000 cubic yards (cy) of dredged material from the City of
Newport Beach/U.S. Army Corps of Engineers Lower Newport Bay Project, into the Middle
Harbor Slip 1. The Port has now completed the review of third party applications and, based on
our review of your application submittal, your material appears to be suitable for placement
within certain areas of the fill. However, at this time it does not appear that there is capacity for
your material in the fill project. IFcapacity should become available, additional geotechnical
data —as requested in the Port's Inter to the City dated August 26, 2010 —will need to be
provided for further evaluation before the materials will be considered for future placement.
Although this project was not selected for placement in the first phase of Fill, there may be
additional opportunities in the future, including the second phase of the slip fill (anticipated to
begin in 2014). The City is encouraged to stay in contact with the Pon regarding future
opportunities and is welcome to submit an application for this material when the solicitation is
released for third party material for the second fill phase.
Attached is the preliminary list of projects tentatively accepted for the fill, with corresponding
placement location and schedule information. The Port will be presenting the results of the
application process and tentative fill plan to the Contaminated Sediment Task Force (CSTF) for
comment and discussion. The Port will then consider CSTF's input and finalize the fill plan in
consultation with individual applicants. The City will be notified of the date and location of the
CSTF meeting once it has been scheduled.
Thank you for your participation in the application process. If you have any questions, please
con art Annsprunna Watanabe at (562) 5904160.
i ly,
/ Itiehard D. Cameron
Director of Environmental Planning
JW:s
Dredging — Rhine Channel
Port of Long Beach Accepted the Rhine Material
❑ 150,000 cubic yards
❑ Layer 1
❑ Window is open between May 2011 to August 2011
Very big milestone!
Permits
Air Quality Management District approved our mitigation credits
Regional Water Board issued a 401 Certification
Waiting on Coastal then Corps permits
LONG BEACH
:racmr:: rx-
Way October 18, 2010
Mr. Chris Miller
City of Newport Beach
Harbor Resources Division
829 Harbor Island Drive
Newport Beach, CA 92660
Subject: Application for Placement of Dredged Material in the Pon of Long Beach
Middle Harbor Fill Site — Rhine Channel Contaminated Sediment Cleanup
Project
Dear Mr. Millar:
The City of Newport Beach (City) recently submitted an application to the Port of Long
Beach (Port) to place approximately 150,000 cubic yards Icy) of dredged material from
the Rhine Chanel Sediment Cleanup Project into the Middle Harbor Slip 1. The Port
has completed the review of third party applications and, based on our review of your
application submittal, we are pleased to inform you that your project qualifies for
placement in the fill site and is conditionally approved for placement in Layer I of the
fill.
Attached is the preliminary list of projects tentatively accepted for the fill, with
corresponding placement locations and schedule information. The Port will be presenting
the results of the application process and the tentative fill plan to the Contaminated
Sediment Task Force (CSTF) for comment and discussion. The Port will then consider
CSTF's input and finalize the fill plan in consultation with the individual applicants. The
City will be notified of the date and location of the CSTF meeting once it has been
scheduled.
This conditional approval for Rhine Channel Sediment Cleanup Project material is based
in part upon the City of Newport Beach fulfilling the following requirements:
Obtain all required entitlements.
Meet the established placement schedule for this project.
Ensure that project funding, insurance requirements, Memorandum of Agreement,
and other related documents have been satisfied.
Develop a project- specific fill plan with Port engineers.
Mr. Chris Miller
October 18, 2010
Paee 2
As stated in the City's letter to the Port dated September 10, 2010, submit a final
dredge design and disposal plan that isolates an approximately
10- foot -by -10 -foot area (bounded by the most recent core samples) that may
contain hazardous material, and dispose of that material elsewhere.
Thank you for your participation in the application process. If you have any questions,
pleassee /mac /pmatt Matt s or Jana Watanabe at (562) 5904160.
SinayTery,
i
Richard D. Cameron
Director of Environmental Planing
JW:s
Attachment
Approximate
Elevation (ft)
+15 to +45
+8 to +15
-5 to +8
-15 to -5
20 to 1- 5
Granular Layer
« < -20
Q- Berm
p� --------- --
< -20
Middle Harbor Fill Site: Tentative Fill Plan
Off -Site Material — Phase 1
Fill Layer
Tentative Projects for Each Layer
Estimated
Source
Volume (cy)
Estimated
Total
Volume (cy)
Tentative Timing
of Fill Availability
7
Borrow Site
500,000
700,000
After Dec 2012
Western Anchorage Storage Site
200,000
6
Western Anchorage Storage Site
300,000
300,000
Sept to Dec 2012
5
LA County, Marina del Rey, Areas 1 -6
116,000
531,000
May to Aug 2012
LA County, Marina del Rey, Areas 7 -9
108,000
Port of Los Angeles, China Shipping Surcharge
307,000
4
Eagle Rock Aggregate, Port of Long Beach D44
6,000
300,000
Jan to Apr 2012
Miscellaneous Port of Long Beach Projects
100,000
City of Long Beach Colorado Lagoon
70,000
City of Long Beach Alamitos Bay
41,000
LA County, Marina del Rey, Areas 7 -9
83,000
3
LA County, Marina del Rey, Areas 1 -6
164,000
164,000
June to Dec 2011
2
LA County, Marina del Rey, Areas 7 -9
100,000
100,000
June to Dec 2011
1
City of Newport Beach, Rhine Channel
150,000
325,000
May to Aug 2011
USACE LARE and City of Long Beach Rainbow
Harbor
175,000
Sept to Dec 2010
Rhine Wharf Public Dock
Dock construction currently underway
Anticipated completion date early November
Ribbon Cutting ceremony with Council, Harbor
Commission and others:
Tuesday, November 23
@ 3:30 PM
Refreshments provided by the Cannery Restaurant
Sea Lions
Most have left the Harbor for "bluer pastures"
Few sea lions have remained as they do every year
Big thanks to Chuck South for herding them on his
nightly patrols for the past 3 months
This
year was lighter than
before
with fewer problems
and
a severe reduction
in
phone
calls
Other Issues
The RFP for Balboa Yacht Basin marina management
is still under review. We expect a decision next week.
The RFP for the RGP -54 Permit has ended. Proposals
will be reviewed by the committee next week.
Harbor Resources cost of service fees will be
discussed at the Council Study Session on October 26.
Harbor Area Management Plan (HAMP) will be
considered by Council on November 9.
Other Issues
Joint Harbor Commission / Planning Commission
October 21St meeting postponed
Possible dates to consider:
Thursday, November 18
Thursday, December 9
Or sometime in 2011
Current City Hall Redevelopment
Goal: Develop a land use strategy for the area
Cooperative agreement between City and Fritz Duda
Co. (Pavilions area)
T.C. Collins & Associates, Inc. is assisting with this
plan
Calendar Subscribe to News & Alerts FAQs Contact Us
*Newport CITY OF Beach HOM%d ABOUT CITY GOVERNMENT RESIDENTS VISITORS BUSINESS ONLINE SERVICES
ir
NEWS 8. EVENTS AGENDAS& MINUTES
ANewport Beach Receives AAA : Committee Meeting BUDGET 6 SALARY INFORMATION
Ratings from Big Three Rating AM
Agencies JOBS
have assigned the CM the highest DosstllI
underlying agency rating of AAA. This makes - - - - r .. MAPS
Newport Beach only the filth city n Carfome, and r!� the only Orange County city, to receive the AAA NBTV
rating from a0 three agencies. r _
r ONLINE PAYMENTS
Back Bay Road Closure
The road between San Miguel and
-- PROJECTS 8 ISSUES
EasMluff 6 dosed due to the heavy
'�
rain conditions.
r.�. ..� RECREATION CLASSES
Calendar •
F9F9',yy.,.,, Joel Fick loins City as Interim Meeting Agendas & 1I..
�q Community Development Director - - SERVICE REQUESTS
"��1 The City of NewDDrt Beach has
retained Joel Fick, a former deputy STAFF DIRECTORY
city manager for the City of Anaheim, to help
Next Meeting
Wednesday, November 10, 2010
6:00 pm
Council Chambers
For More Information
http://www.newportbeachca.gov/HarborResources
Chris Miller, Harbor Resources Manager
❑ cmiller @newportbeachca.gov
❑ (949) 644 -3043
Shannon Levin, Harbor Resources Supervisor
❑ shannon @newportbeachca.gov
❑ (949) 644 -3041