HomeMy WebLinkAbout10 - 05-06 Various Sewer ImprovementsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. io May 22, 2007 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Mike Sinacori 949 - 644 -3342 or msinacori @city.newport- beach.ca.us SUBJECT: 2005 -2006 VARIOUS CITY SEWER MAIN IMPROVEMENT AND BIG CANYON TRUNK SEWER REPLACEMENT — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3562 RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond 1 year after Council acceptance. 5. Approve a Budget Amendment appropriating $241,389.39 to Account No. 7251 - 05600292 for the completion of the Big Canyon Trunk Sewer Replacement and increase revenue estimates by $248,431.62 representing OCSD's final contribution for this work, including a 4% administrative fee on construction services provided by the City. DISCUSSION: On April 25, 2006 the City Council authorized the award of the subject project to Beador Construction. The contract provided a joint sewer project with the Orange County Sanitation District (OCSD). The contract has now been completed to the satisfaction of the Public Works Department and OCSD. A summary of the contract cost is as follows: Original bid amount: Actual amount of bid items constructed: Total amount of change orders: Final contract cost: $4,063,300.00 $3,975,739.30 $ 579.285.65 $4,555,024.95 2005 -2006 Various City Sewer Main Improvement and Big Canyon Trunk Replacement — Completion and Acceptance of Contract No. 3562 May 22, 2007 Page 2 The decrease in the amount of actual bid items constructed over the original bid amount resulted mostly from the deletion of City sewer lining efforts. Sewer mains that were inaccessible during the design phase were pre - televised by the contractor. Some reaches were shown to be in acceptable condition and those lines were deleted from the construction contract. The final overall construction cost including Change Orders was 12 percent over the original bid amount. Seven summary change orders in the amount of $579,285.65 were processed for the project and approximately $430,000 is the responsibility of OCSD. Attached is a summary of the Change Orders processed for the project. PROJECT BACKGROUND: A reimbursement agreement between the City and OCSD was approved by the City Council on June 14, 2005 which contained the following provisions: • OCSD will reimburse the City for costs to design and construct the OCSD sewer improvement project including a 4% administration fee ($150,567.23 based upon the final cost to OCSD). • City paid for the design and construction of the City sewer improvements not required by the OCSD improvements. • City was the lead on CEQA processing for the project with OCSD reimbursing the City for any costs related to their improvements. • OCSD had the authority to review and approve all plans, inspect the construction, and approve all Change Orders related to their new OCSD sewer. • Big Canyon Country Club (BCCC) provided new easements to the OCSD and City for the new aligned sewer locations. The joint construction project minimized impacts to the community by completing all the improvements in concert with the ongoing BCCC construction projects. This also minimized cost impacts for site and road restoration since the larger BCCC construction efforts will continue after the sewer improvements are completed. The joint project also allowed both OCSD and the City to take advantage of a larger sewer replacement and lining project that resulted in overall lower costs to both agencies. Environmental Review: City and OCSD staff reviewed the project and had determined the project was exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302 of the CEQA Implementing Guidelines when the project was authorized by the City Council. This exemption covers the maintenance and alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. A Notice of Exemption was filed with the County Recorder on May 2, 2006. 2005 -2006 various City Sewer Main Improvement and Big Canyon Trunk Replacement— Completion and Acceptance of Contract No. 3562 May 22, 2007 Page 3 Project Costs and Fundina Availability: In addition to the primary construction contract, this project involved other project expenses for construction support, geotechnical, and incidental items. Total project expenses are summarized as follows: Vendor Purpose Amount Beador Construction Contractor $4,555,024.95 Walden & Associates(') Design and CM Support 269,650.00 Leighton Geotechnical OCSD Design Geotechnical 25,170.03 Clarke Construction OCSD Pre- Construction Cost 28,948.00 AESCO Geotechnical OCSD Construction Geotechnical 29,050.00 Big Canyon Country Club OCSD Liquidated Damages (2) 75,000.00 Project Partners City Contract Inspection Support 25,922.92 Various Printing and Incidental Expenses 2,103.56 City of Newport Beach Administration Charge to OCSD 147,567.23 Total: $5,158,436.69 (t) Pending final billing. (2) Per the Construction Access Agreement, BCCC was due $2,000 per calendar day in liquidated damages (LDs) for everyday past the initial 150 days allowed in the agreement. OCSD negotiated LDs with BCCC for the late completion of its portion of the work amounting to $75,000 and has agreed to pay that amount to BCCC. More than three - quarters of the funding for this project is provided by OCSD. A Budget Amendment is required to recognize the increase in anticipated revenue contributions from OCSD and to appropriate additional funds into the contribution account. Upon approval of the Budget Amendment, funds for the project will be expended from the following accounts: Account Description OCSD Big Canyon Trunk Sewer Sewer Main Master Plan Improvement Superior Avenue Trunk Sewer Improvement Storm Drain Improvement Program Account Number 7251- C5600292 7531- C5600292 7531- C5600863 7012- C5100008 Total Amount $3,912,081.62 $ 936,986.96 $ 290,368.11 $ 19,000.00 $5,158,436.69 The Contractor was allowed 100 working days to complete the OCSD Big Canyon Trunk Sewer and 200 working days to complete the entire project. All work was completed on April 20, 2006, 21 working days ahead of the original scheduled completion date of May 21, 2007. With approved time extension, the contractor was allowed until July 17, 2007 for completion. 2005 -2006 various City Sewer Main Improvement and Big Canyon Trunk Replacement — Completion and Acceptance of Contract No. 3562 May 22, 2007 Page 4 Prepared by: Submitted b Mlehael J. Sinacori, P.E. St . Badum Principal Civil Engineer u orks Director Attachments: Summary of Change Orders — Dated May 11, 2007 Budget Amendment References: June 14, 2005 Council Report — Reimbursement Agreement with OCSD for Big Canyon Trunk Sewer Replacement April 25, 2006 Council Report — 2005 -2006 Various City Sewer Main Improvement and Big Canyon Trunk Sewer —Award of Contract No. 3562 City of Newport Beach PUBLIC WORKS DEPARTMENT VFW PART o m U S CgZ1F00.N`P TYPE A - Added Scope C - Change in Scope RD - Rain Day TBD - To Be Determined OCSD -BIG CANYON TRUCK SEWER REPLACEMENT PROJECT No 5 -62 CITY WIDE SEWER IMPROVEMENTS CONTRACT No C -3562 PCO & Estimates Log May 11, 2007 PCD C.O. C.D. Previously Pending Total No. TYPE ORIGIN DATE DESCRIPTION APPRVL NO. Approved CDR approve, Days REMARKS STATUS DATE Costs Costs and pending Pending & Approved Estimates 1 A Beador 0820/06 Delay - Tie -in Location Elevation Revision at Ste 54 +07 09/0512006 1 $12,654.93 $12,654.93 2 Resubmitted 9/1/06 A 2 A Beador 08/20/06 Delay due to existing utilities conflicts. 8" Water main was 09/05/2006 1 $26,846.07 $26,846.07 2 Resubmitted 9/1/07 A running parallel to 15" sewer main (MH # 12 to MH # 13) 3 A Beador 08/20/06 Additional Work due to Dewatering and Utility Interference on 09/05/2006 1 $4,521.77 $4,521.77 0 Resubmitted 9/1/08 A the Driving Range 4 A Beador 08/20/06 Delay due to Dewatering Operation 09/052006 1 $8,202.34 $8,202.34 1 Resubmitted 9/1109 A 5 A Beador 09/29/06 Delay due to Dewatering Operation - MH # 14 at Parking lot - TBD 2 $13,342.80 $13,342.80 2 A Excessive water due to existing utility trenches 6R A Beador 12/29/06 Delay due to working under 4" and 8" water lines at Ste 50+ 79 TBD 4 $21,807.03 $21,807.03 2 Revised from $25,807.03 A near MH # 12 7 A Beador 09/029/06 Delay due to 8 "sewer line at Sta 42 +08 not shown on plans. 11/14/06 2 $15,222.04 $15,222.04 1 A Dewatering and repairs between MH # 9 and #10 8R A Beador 12/29/06 Delay due to working under 3 water mains at Ste 43 +40 TBD 4 $6,944.93 $6,944 -93 1 Revised from $11,944.93 A between MH # 10 and #11 9 A Beador 0929/06 Delay due to ground water and Installation of 8" drain line at 11114/06 2 $28,656.47 $28,656.47 3 A Ste 60 +40 on the Driving Range 10 A Beador 0929/06 Delay due to multiple leak repairs due to unstable grade at Ste 11/14/06 2 $36,251.67 $36,251.67 4 A 56 +90 by MH # 14 at the Pond Fill area 11 A Beador 09129106 Delay due to leak repair, testing and encasement of 15' main 11/14/06 2 $23,489.89 $23,489.89 3 A on Line A near MH # 14 12 A Beador 10/12/06 Additional Landscaping work and irrigation work at #9 Green 11/14/06 2 $5,287.44 $5,287.44 A and #1 Tee area - not part of original restoration 13 A City NB 11/09106 Tree removal at existing sewer manhole and concrete pad 11/14/06 2 $3,333.00 $3,333.00 A installed by Southwest US OCSD PCO Log 5.11,07,xls/PCO and Estimates List 1 ot3 PCO C.O. C.O. Previously Pending Total No. TYPE ORIGIN DATE DESCRIPTION APPRVL NO. Approved CDR approved Days REMARKS STATUS DATE Costs Costs and pending 14 A Beador 10/31/06 Invoice from Christensen Irrigation Co for main line relocation 11/14/06 2 $17,962.85 $17,962.85 Cost for work was pre- approved A for 8" water line conflict at bore pit at MH # 4 by OCSD 15 A Beador 11/10/06 Generator Rental and support equipment to dewater installed 12/14/06 3 $5,614.79 $5,614.79 A sewer mainline during manhole installation 16R A Beador 1229/06 Grade and remove excess dirt in the construction areas to 01/05/07 4 $6,226.08 $6,226.08 Revised from $11,226.08 A assist Southwest US in their restoration of the golf course Extra work required to install 8" VCP (Lateral D near MH # 9) 17R A Beador 11/15106 under 6" water lines that were required to remain online and 01/05/07 4 $16,769.44 $16,769.44 2 Revised from $20,669.44 A not cut and capped Extra work required during the Direct Boring Operation due to 18 A Beador 1129/06 buried concrete drain structure and rip rap encountered at the 12/14/06 3 $21,084.31 $21,084.31 3 A 250 foot point of the 400 If bore. Relocation of 10" Suction Line for the waterfall fed from Lake 19R A Beador 1229/06 5 by MH # 5 due to interference with 48" bore casing at Sta 01/05/07 4 $4,162.45 $4,162.45 2 Revised from $8,324.89 A 24 +50. 20 A Beador 12/13/06 Rain Day for 12/11/06 due to heavy rain over the weekend of 01/05/07 4 1 A 12/9/06 21 A Beador 12/10/06 Generator Rental and support equipment to dewater installed 01/05/07 4 $2,406.34 $2,406.34 A sewer mainline during manhole installation R1- Revised from Extra work due to Differing Site Conditions during the s$41,066.11 Added curb and sidewalk 22R2 A Beador 12/10/06 installation of Mainline and Line "B" (MH 3 and 3A) along Big 02/02/07 5 $69,045.71 $69,045.71 6 reparis on Big Canyon West A Canyon Drive (west). R2 -added asphalt Rain Day for 1227/06 due to wash out of work area at 1 A 23 A Beador 12/29/06 Fairway # 17 and Fairway # 3. 01/05/07 4 Extra work due to unmarked 6" ACP water main during the Revised from $25,807.03. 24R A Beador 1229/06 installation of Line "B" (MH 3 and 3A) along Big Canyon Drive 01/05/07 4 $27,222.53 $27,222.53 3 Added Christensen Irrigation A (west). Repairs of 6" water line 25 A Beador 09/08/06 Credit for Surveying deleted from contract 01/05/07 4 $'6,067.2 .) ;$16,387.25; A 26 A Beador 01/02/07 Kilbrides 8" sewer Repair at #66 Royal St George 01/05/07 4 $4,887.50 $4,887.50 A 27 A Beador 0124/07 Remove concrete encasement at Sta 77 +25 to 77 +46 on 02/02/07 5 $8,545.44 $8,545.44 1 A existing sewer line at tie point at MH #20 (Frairway 17) 28 A Beador 0124/07 Generator Rental and support equipment to dewater installed 02/02/07 5 $2,406.34 $2,406.34 A sewer mainline during manhole installation 29 A Beador 0124/07 Extra work due to unmarked 8" ACP water main during the 02/02/07 5 $8,628.65 $8,628.65 1 A installation of sewer at Sta 75 +77. Tunnel under 36" CMP 30 A Beador 02/02/07 Extra work for landscape sub - contractor to repair irrigation 02/02/07 5 $5,479.45 $5,479.45 A electrical lines on Hole 3 near bore pit. 31 A Beador 02/22/07 Extra work due to ground water issues at MH #5. The ground 02/22/07 6 $5,838.75 $5,838.75 A water daylighted at edge of stream. 32 A Beador 0222/07 Extra work repairing the concrete and landscape at Big Canyon 02/22/07 6 $13,300.00 $13,300.00 A Park due to work on 2 sewer manholes. 33 A Beador 03105/07 T &M efforts to install City sewer main at Orchid Ave. - Sht. 2 03/05/07 6 $17,396.49 $17,396.49 A of 24. Existing Water Main not shown on plans correctly. OCSD PCO Log 5.11.07.4 PCO and Estimates List 2 of,? POO C.O. C.D. Previously Pending Total No. TYPE ORIGIN DATE DESCRIPTION APPRVL NO. Approved COR approved Days REMARKS STATUS DATE Costs Costs and pending 34 A Beador 03/05/07 T &M efforts to adjust OCSD Manhole in center of Canyon Hills 03/05/07 6 $3,694.04 $3,694.04 A Park as directed by the HOA and OCSD Staff. 35 A Beador 03/05/07 Additional cost for manhole lining efforts requested by the City 03/05/07 6 $10,135.00 $10,135.00 A Additional landscape restoration related to abandoment efforts 36 A Beador 03/05/07 and installation of manhole at Station 65 +07 at back of driving 03/05/07 6 $23,694.95 $23,694.95 A range. Cost were not included in original bid. Additional Cost for City /OCSD sharing of BCCC Parking Lot 37 A Beador 03/05/07 Restoration ($2,250) and Diver at Lake No. 5 ($1,250) cost 03/05/07 6 $3,500.00 $3,500.00 A billed by BCCC - November 20, 2006 Letter to Beador. Additional Cost for Point Repairs requested by City, Extra Cost 38 A Beador 04/17/07 from Insituform, repair cost to Newport Harbor Yacht Club for /11/07 7 $71,033.64 $71,033.64 Revised May 3, 2007 - $67,096 A resurfacing and repainting and Additional Paving Cost required Original Submitted. by BCCC. Additional Point Repair at 8th Street/Balboa, extra work at 707 39 A Beador 04/20/07 & 709 Bay Street, Additional Repairs at 6th and Balboa, 59th 05/11/07 7 $27,870.54 $27,870.54 A Street and extra work on Acacia alley. Potholing Efforts at Orange Street to investlgate plpebursting 40 A Beador 03/05/07 versus lining of existing 8 -inch City Sewer ($4,641.94) and 05/11/07 7 $11,907.23 $11,907.23 A Abandonment of OCSD Manhole in between Holes 13 and 17. Totals $579,285.65 $0.00 $579,285.65 41 Total Pending, Approved & Estimated Costs $579,285.65 OCSD PCO Log 5.11.07.xWPC0 and Es6'mafes List 3 of 3 City of Newport Beach BUDGET AMENDMENT 2006 -07 EFFECT ON BUDGETARY FUND BALANCE: X Increase Revenue Estimates X Increase Expenditure Appropriation! AND Transfer Budget Appropriations X SOURCE: from existing budget appropriations X from additional estimated revenues from unappropriated fund balance EXPLANATION: This budget amendment is requested to provide for the following: NO. BA- 07BA -075 AMOUNT: $248431.62 Increase in Budgetary Fund Balance Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance To increase expenditure appropriations for the completion of the Big Canyon Trunk Sewer Replacement and to increase revenue estimates to recognize the contribution from the Orange County Sanitation District. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Amount Fund Acco n Description Debit Credit 010 3605 General Fund - Fund Balance $7,042.23 REVENUE ESTIMATES (3601) Fund /Division Account Description 250 4839 Contributions - OC Sanitation District Contribution $241,389.39 5100 5132 Public Works: Engineering - City Staff Service Fee $7,042.23 EXPENDITURE APPROPRIATIONS (3603) Signed: Signed: Signed: Financial Approval: Administrative Services Director Administrative Approval: City Manager City Council Approval: City Clerk $241,389.39 Date Date Date Description Division Number 7251 Contributions Account Number C5600292 Sewer Main Master Plan Improvement Division Number Account Number Division Number Account Number Division Number Account Number Division Number Account Number Signed: Signed: Signed: Financial Approval: Administrative Services Director Administrative Approval: City Manager City Council Approval: City Clerk $241,389.39 Date Date Date