TITLE: Sunset Ridge Park — Notice of Completion and Acceptance of Contract No. 3449
(CAP09 -0076)
ABSTRACT:
On December 10, 2013, City Council awarded Contract No. 3449 for the construction of Sunset Ridge
Park, to Environmental Construction, Inc. for a total contract cost of $5,214,820.00 plus a contingency
allowance of approximately 10 percent. The required work is now complete and staff requests City Council
acceptance and close out of the construction contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of
Completion has been recorded in accordance with applicable portions of the Civil Code; and
c) Release the Faithful Performance Bond one year after City Council acceptance.
FUNDING REQUIREMENTS:
Funds for the construction contract were expended from the following account:
Account Description Account Number Amount
Major Facilities Master Plan 7412- C5100515 $ 5,387,986.02
Total Construction Cost: $ 5,387,986.02
7 -1
DISCUSSION:
Overall Contract Cost/Time Summary
This contract involved the construction of a 13.7 acre park situated on the northwest corner of West Coast
Highway and Superior Avenue in the West Newport community. Active amenities include a PONY league
baseball field, two soccer fields, warm -up field, and a children's play area. Sunset Ridge Park also provides
passive amenities such as a picnic area with restrooms, a memorial butterfly garden, a shaded overlook
area with views of the Pacific Ocean, and meandering walkways throughout the park. This contract has
now been completed to the satisfaction of the Public Works Department. A summary of the contract costs
are as follows:
Original bid amount: $ 5,214,820.00
Actual cost of bid items constructed: $ 5,214,820.00
Contract change order: $ 173,166.02
Final contract cost: $ 5,387,986.02
The final overall construction cost was approximately 3.3% over the original bid amount but well within the
overall budget including the contingency amount. The 3.3% difference was partly attributed to unstable
existing soil conditions that were unforeseen and encountered in the park grading process, which resulted
in a 1.1 percent increase to the overall project cost. Staff also directed the contractor to implement several
park features to improve the functionality of the park. The two most notable features include automatic
programmable locks for the restroom gates and anti - graffiti coating for all exposed structures. In addition,
staff made modifications to the steel overlook trellis structure due to the lack of availability of material.
These added features and modifications, along with other minor changes, resulted in a 2.2 percent
increase to the overall project cost.
The original contract allowed for 180 consecutive working days to complete the original scope of work. The
contractor was allowed 52 additional working days due to inclement weather and additional time needed to
complete extra work associated with change orders. The project was substantially completed on December
5, 2014.
A summary of the project schedule is as follows:
Estimated Completion Date per July 2014 Schedule: December 12, 2014
Project Awarded for Construction: December 10, 2013
Completion Date per Contract and Approved Extensions: December 10, 2014
Actual Substantial Construction Completion Date: December 5, 2014
7 -2
Actual
Awarded Contract
Final Cost at
Contingency
% Due to
% Due to
Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$5,214,820.00
$5,387,986.02
Approx. 10%
+3.3%
2.2%
1.1%
Actual Time
Allowed Contract Time (days)
232
-3
Under - or Over +)
This contract involved the construction of a 13.7 acre park situated on the northwest corner of West Coast
Highway and Superior Avenue in the West Newport community. Active amenities include a PONY league
baseball field, two soccer fields, warm -up field, and a children's play area. Sunset Ridge Park also provides
passive amenities such as a picnic area with restrooms, a memorial butterfly garden, a shaded overlook
area with views of the Pacific Ocean, and meandering walkways throughout the park. This contract has
now been completed to the satisfaction of the Public Works Department. A summary of the contract costs
are as follows:
Original bid amount: $ 5,214,820.00
Actual cost of bid items constructed: $ 5,214,820.00
Contract change order: $ 173,166.02
Final contract cost: $ 5,387,986.02
The final overall construction cost was approximately 3.3% over the original bid amount but well within the
overall budget including the contingency amount. The 3.3% difference was partly attributed to unstable
existing soil conditions that were unforeseen and encountered in the park grading process, which resulted
in a 1.1 percent increase to the overall project cost. Staff also directed the contractor to implement several
park features to improve the functionality of the park. The two most notable features include automatic
programmable locks for the restroom gates and anti - graffiti coating for all exposed structures. In addition,
staff made modifications to the steel overlook trellis structure due to the lack of availability of material.
These added features and modifications, along with other minor changes, resulted in a 2.2 percent
increase to the overall project cost.
The original contract allowed for 180 consecutive working days to complete the original scope of work. The
contractor was allowed 52 additional working days due to inclement weather and additional time needed to
complete extra work associated with change orders. The project was substantially completed on December
5, 2014.
A summary of the project schedule is as follows:
Estimated Completion Date per July 2014 Schedule: December 12, 2014
Project Awarded for Construction: December 10, 2013
Completion Date per Contract and Approved Extensions: December 10, 2014
Actual Substantial Construction Completion Date: December 5, 2014
7 -2
ENVIRONMENTAL REVIEW:
The Final Environmental Impact Report for the Sunset Ridge Park project was certified by City Council on
March 10, 2010.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at
which the City Council considers the item).
ATTACHMENTS:
Description
Attachment A - Location Mao
7 -3
m rr Fr r7
iii
T
` \
1-,-74( 410-
Attachment A
PROJECT LOCATION
m TTI� TTM TT TTT7 /77 i-m F�
SUNSET RIDGE PARK
LOCATION MAP
�i
I L.
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C -3449 1 04/14/2015