HomeMy WebLinkAbout14 - Wide Area Network UpgradesCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 14
May 23, 2006
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Administrative Services Department
Dennis C. Danner, Administrative Services Director 949 - 644 -3123
ddanner@city.newport-beach.ca.us
SUBJECT: Wide Area Network Upgrades
RECOMMENDATION:
Approve an agreement with Embee Technologies for hardware and services to provide
100 MB wireless radio Wide Area Network (WAN) connections between the City Hall
and Utilities sites and between the Utilities and Corporation Yard sites. Total cost of the
project is $69,882.20.
DISCUSSION:
Background:
Over the past decade, the City's dependence on access to electronically stored
information and electronic communications has increased by orders of magnitude. To
keep up with this ever increasing demand, the MIS Division has continually upgraded
capacity by replacing user workstations, servers that process and store information, and
the local area networks (LANs) that connect components at the same location together.
In contrast, the wide area network (WAN), which connects various City locations
together, has not significantly changed in over a decade.
Currently the connection between City Hall and the Utilities Department (949 W 16th
Street) and City Hall and the Corporation Yard (592 Superior Avenue) consists of T -1
circuits provided by AT &T. These leased T -1 circuits provide 1.5 Mb /sec connectivity
from City Hall to each respective location. In contrast, the City LANs provide
connectivity to resources at either 100 Mb /sec or 1000 Mb /sec depending upon the
equipment and location. Lower bandwidths (speed) provided by the existing T -1 circuits
has begun to adversely impact these locations as the volume of network traffic has
dramatically increased due to more computer users located at these two sites and
increased reliance on shared network applications such as file sharing, e-mail, voice
mail. Specialized applications such as GIS have been under utilized by the Utilities and
Wide Area Network Upgrade Project
05/23/2006
Page 2
General Services Departments because the existing WAN response is too slow. The
network is also used on a daily basis to transfer water meter readings to the City's
billing system during meter reading periods. Additionally, on several occasions, the poor
performance of the WAN has led to the loss of some data. Changes in WAN
technologies have made higher bandwidth solutions to remote sites more cost effective.
T -1 circuits, once considered to be "high bandwidth" solutions are being replaced by
newer technologies designed to provide much faster connectivity.
Staff examined several alternative solutions to increase bandwidth between sites
including solutions from SBC and Cox Communications but the Total Cost of Ownership
(TCO) for a licensed microwave is lower than all other comparable solutions both in the
short and long terms.
Staff has determined that the most appropriate solution with regards to cost, reliability,
and performance is to purchase an FCC licensed microwave system manufactured by
DragonWave of Canada. Their system provides scalable full duplex (bidirectional)
bandwidth from 50Mb /sec to 200 Mb /sec through simple software upgrades, and can be
upgraded to as much as 400 Mb /sec with additional components. Staff recommends
implementing a 100 Mb /:sec system initially since it provides sufficient bandwidth for our
present needs and anticipated growth.
The existing T -1 circuits would continue to be maintained for backup purposes. In the
event of a partial or complete failure of the proposed microwave system, the network
will automatically revert to the T -1 circuits with no or minor disruption in service for
users.
In addition to solving the problem of insufficient bandwidth necessary for daily use of the
enhanced data services, the proposed WAN upgrade project will allow the MIS Division
to implement critical projects related to information disaster recovery. A critical
component of the MIS Division's information disaster recovery plan is to store copies of
the City's information resources at a location that is protected from all likely disaster
scenarios. The implementation of this project will allow MIS staff members to fully
develop a disaster recovery plan designed to use this faster connection to send copies
of all critical data and information to components located at the Utilities Department site.
These components will allow staff to quickly recover any information that could be lost in
a disaster related event.
Environmental Review: 'The City Council's consideration of this item does not require
environmental review.
Funding Availability: Funding for the project is available and included in the current FY
2005 -06 budget and no budget amendment is required.
Alternatives: None
Prepared by:
Paul Malkemus
MIS Manager
Attachments: Embee Technologies Proposal
Wide Area Network Upgrade Project
05/23/2006
Page 3
Submitted by:
Dbnnis Danner `
Administrative Services Director
16592 Millikan Ave.
Irvine, CA 92606
PHONE: 949266.1700
FAX: 949.435.1595
Web Site: www.embeetech.com
PREPARED FOR
The City of Newport Beach
Attn:Jonothon Cone
PO Box 1768
Newport Beach Ca. 92658 -8915
Estimate
DATE
ESTIMATE NO.
412012006
3672
SALES PERSON
Dragonwave Air Pair 50
AA7 7�TYYN 7f71rNPl
rJ 1.31x09.1.1
QTY
DESCRIPTION
UNIT PRICE
TOTAL
2
Dragonwave Air Pair 50
19.800.00
39,600.00T
18 Ghz standard power, 2ft dish
FCC Band
4
ODU Bundle Cable 1000 BT /10 BT and DC Power 30m
360.00
1,440.00T
2
ODU Install Kit (N America)
1,632.00
3,264.00T
2
FCC license of 18 Hz frequency - 10 year license
2,400.00
4,800.00T
2
Shipping charges
660.00
1,320.00
City Hall installation:
Embee will use existing antenna mast system that is already
in place to save money on this project.
24 Labor: to install Radio, conduit system, power, data and
grounding.
1 Product: conduit, data and grounding.
1 Labor: Setup and alignment of Radio /System
Utilities Yard installation (Tower):
24 Labor to install Radio, conduit system, power, data and
grounding.
TOTAL
The acceptance of this estimate is a binding purchase contract between the
undersigned and Embee Technologies, and is subject to Embee CLIENT SIGNATURE
Technologies terms and conditions which appear on the reverse.
Client warrants that the signature below is that of an authorized agent.
Page 1
65.00
255.00
1,200.00
1,560.00
255.00T
1,200.00
1,560.00
I�
i�
16592 Milliken Ave.
Irvine, CA 92606
PHONE: 949.266.1700
FAX: 949.435.1595
Web Site: www.embeetech.com
PREPARED FOR
The City of Newport Beach
Attn:Jonothon Cone
PO Box 1768
Newport Beach Ca. 92658 -8915
Estimate
DATE
ESTIMATE NO.
4/20/2006
3672
SALES PERSON
QTY
TOTAL
The acceptance of this estimate is a binding purchase contract between the
undersigned and Embee Technologies, and is subject to Embee
Technologies terns and conditions which appear on the reverse. CLIENT SIGNATURE
Client warrants that the signature below is that of an authorized agent.
Page 2
$69,882.20
JOB DESCRIPTION
PROJECT NO.
QTY
DESCRIPTION
UNIT PRICE
TOTAL
1
Product: Mast support system for tower, bracketing and
1,325.00
1,325.00T
bracing supplies,data and grounding.
32
Tower Labor to install (2) radio heads on tower 100 above
150.00
4,800.00
ground.
1
Labor: Setup and alignment of Radio /System.
1,200.00
1,200.00
General Services installation:
32
Labor: to install Radio, conduit system, power, data and
65.00
2.080.00
grounding.
1
Product: Mast support system, conduit, bracing supplies,data
325.00
325.00T
and grounding cable
1
Labor: Setup and alignment of Radio /System
1,200.00
1,200.00
Sales Tax Rate for Orange County
7.75%
3,953.20
TOTAL
The acceptance of this estimate is a binding purchase contract between the
undersigned and Embee Technologies, and is subject to Embee
Technologies terns and conditions which appear on the reverse. CLIENT SIGNATURE
Client warrants that the signature below is that of an authorized agent.
Page 2
$69,882.20