HomeMy WebLinkAbout08 - Jamboree Road Rehabilitation - C-3785CITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 8 August 22, 2006 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Andy Tran, P.E. 949 - 644 -3315 or atran @city.newport- beach.ca.us SUBJECT: JAMBOREE ROAD REHABILITATION FROM UNIVERSITY DRIVE TO SOUTH BRISTOL STREET — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3785 RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond one (1) year after Council acceptance. DISCUSSION: On April 25, 2006, the City Council authorized the award of the Jamboree Road Rehabilitation from University Drive to South Bristol Street contract to R.J. Noble Company. The contract provided for asphalt pavement restoration, median concrete curb and access ramp replacement, traffic loops, striping, pavement markings and markers replacement, and utility adjustments. The contract has been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original Bid Amount: Actual amount of bid items constructed: Total amount of change orders: Final contract cost: $911,669.50 $846,183.36 $7,317.19 $853,500.55 Irvine Terrace Water Valve, Ocean Vista and Orange Street Water Main Replacement - completion And Acceptance of Contract No. 3643 August22,2006 Page 2 The decrease in the amount of actual bid items constructed primarily resulted from the reduction of rubberized asphalt surface course required. The final overall construction cost including one Change Order was 6.4 percent under the original bid amount. One Change Order in the amount of $7,317.19 provided for the repair of a streetlight conduit, replacement of advanced traffic detector loops, and the repair of the contractor's equipment due to damages from running into unmarked buried manholes. Environmental Review: The project was exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Implementing Guidelines when the project was authorized by the City Council. This exemption covers the repair, maintenance and minor alteration of existing public facilities with negligible expansion. Funds were expended from the following accounts for the project: Account Description Account Number Amount Gas Tax 7181- C5100831 $384,894.43 AH RP 7285- C5100831 $321,114.87 Measure M 7281- C5100831 $147,491.25 Total: $853,500.55 The original completion date was August 1, 2006. All work was substantially completed by July 26, 2006. Prepared by: Submitted by: Andy Tran, P.E. a adum Associate Civil Engineer ubli or Director