HomeMy WebLinkAbout10 - C-3517 - Morning Canyon StabilizationCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 10 September 12, 2006 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Robert Stein, P.E. 949- 644 -3322 or rstein @city.newport- beach.ca.us SUBJECT: MORNING CANYON STABILIZATION —ADDITIONAL FUNDING REQUIRED FOR COMPLETION OF CONTRACT NO. 3517 RECOMMENDATIONS: Approve a Budget Amendment in the amount of $96,556 from the unappropriated General Fund Reserves for work completed to Account 7014- C5100805. DISCUSSION: On September 13, 2005, the City Council authorized the award of the Morning Canyon Stabilization contract to Sunquest General Engineering. The first phase of the project was the stabilization of the canyon slopes by constructing seven rock - filled gabion grade control structures, a rock - filled gabion bank protection structure, placing fill, grouted rock riprap, storm drain extensions, and fencing in order to bring the canyon into readiness to accept storm water flows. A portion of the Phase 1 improvements were funded by private contributions estimated at $271,265. The second phase of the work completed included slope backfill, planting of various California native shrubs and trees, and hydroseeding. At its June 27, 2006 meeting, the City Council accepted the work associated with Contract No. 3517 for the Morning Canyon Stabilization project. The contractor is due payment for work completed for plant maintenance and its retention and the Irvine Company is due reimbursement for costs related to the repair of a cart path that was damaged during construction. The fund is short by $96,556. At the time the notice of completion was prepared by staff, no allowance was made for surplus private contributions that needed to be returned, and therefore, it appeared that sufficient funds were available to make final payment to the contractor. Following the Council's action on June 27th, monies were returned to the private contributors for cost savings pertaining to specific tasks completed adjacent to two residences. Also, staff just approved a claim from the Irvine Company to repair a cart path, V -ditch and curbing that was impacted by the construction project. Since unencumbered CIP funds budgeted for this project were returned to the General Fund at the close of the fiscal year ending June 30, 2006, additional funding is now required to complete this contract. Morning Canyon Stabilization — Additional Funding Required for Completion of Contract No. 3517 September 12, 2006 Page 2 A summary of the contract cost is as follows: Environmental Review: This project is categorically exempt from the provisions of CEQA per Section 15333 pertaining to small habitat restoration projects. A Notice of Exemption was filed with the County Clerk on June 6, 2005. Funding Availability: Upon approval of the attached budget amendment, funds will be expended from the following accounts for the project: Account Description General Fund Private Contributions Prepared by: Robert Stein, P.E. Project Manager Account Number 7014- C5100805 7251- C5100805 Total: Submitted by: Amount $681,808.63 $188,573.00 $870,381.63 Works Director Private Contribution General Fund Total Original bid amount $271,265.00 $585,253.50 $856,518.50 Actual bid items constructed $188,573.00 $599,890.00 $788,463.00 Total change orders $ 41,543.63 $ 41,543.63 Final contract cost: $188,573.00 $641,433.63 $830,006.63 Damage repair costs: $ 40,375.00 $ 40,375.00 Total costs: $188,573.00 $681,808.63 $870,381.63 Environmental Review: This project is categorically exempt from the provisions of CEQA per Section 15333 pertaining to small habitat restoration projects. A Notice of Exemption was filed with the County Clerk on June 6, 2005. Funding Availability: Upon approval of the attached budget amendment, funds will be expended from the following accounts for the project: Account Description General Fund Private Contributions Prepared by: Robert Stein, P.E. Project Manager Account Number 7014- C5100805 7251- C5100805 Total: Submitted by: Amount $681,808.63 $188,573.00 $870,381.63 Works Director City of Newport Beach NO. BA- 07BA -015 BUDGET AMENDMENT 2006 -07 AMOUNT: $9s,sss.00 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates Increase in Budgetary Fund Balance X Increase Expenditure Appropriations AND X Decrease in Budgetary Fund Balance Transfer Budget Appropriations No effect on Budgetary Fund Balance SOURCE: from existing budget appropriations from additional estimated revenues PX from unappropriated fund balance EXPLANATION: This budget amendment is requested to provide for the following: To increase expenditure appropriations from unappropriated General Fund Balance for additional funding required to complete the contract for the Morning Canyon Stabilization. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account Description 010 3605 General Fund - Fund Balance REVENUE ESTIMATES (3601) Fund /Division Account EXPENDITURE APPROPRIATIONS (3603) Description Amount Debit Credit $96,556.00 " $96,556.00 Division Number Account Number �% • Automatic System Enfry. Signed: �O �/ l�—Jr =06 Signed: Financial Approval: Administrative Services Director Administrative Approval: City Manager Date Q� pate Signed: City Council Approval: City Clerk Date Description Division Number 7014 General Fund - Misc & Studies Account Number C5100805 Morning Canyon Stabilization Division Number Account Number Division Number Account Number Division Number Account Number Amount Debit Credit $96,556.00 " $96,556.00 Division Number Account Number �% • Automatic System Enfry. Signed: �O �/ l�—Jr =06 Signed: Financial Approval: Administrative Services Director Administrative Approval: City Manager Date Q� pate Signed: City Council Approval: City Clerk Date