HomeMy WebLinkAbout14 - Ocean Pier Repairs - C-3798CITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 14
October 24, 2006
TO: HONORABLE MAYORAND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Stephen Luy
949 -644 -3330
sluy@city.newport-beach.ca.us
SUBJECT: OCEAN PIER REPAIRS -AWARD OF CONTRACT NO. 3798
RECOMMENDATIONS:
Approve the plans and specifications.
2. Defer Additive Bid work.
Award Contract No., 3798 to John S. Meek Company, Inc. for the Total Base Bid
Price of $687,550, and authorize the Mayor and the City Clerk to execute the
contract.
4. Establish an amount of $68,000 (10 %) to cover the cost of unforeseen work.
5: Approve a Budget Amendment in the amount of $271,550 from Unappropriated
Tide and Submerged Lands Fund Balance to Account No. 7231- C5100836.
DISCUSSION:
At 11:00 a.m. on October 11, 2006 the City Clerk opened and read the following bids for
this project:
Low John S. Meek Company Inc.
2 MINCO Construction
TOTAL BASE BID
AMOUNT
$687,550
796,000
TOTAL ADDITIVE BID
AMOUNT
$210,600
394,000
The low base bid amount is 55 percent above the Engineer's Estimate of $443,000. The
disparity between the estimate and the actual bid price reflects the specialized work
involved for this type of project, the limited number of contractors available to perform the
work, and the current high demand for similar work by other agencies. Staff contacted the
plan holders who ordered plans and specs for the project that did not bid to determine why
Ocean Pier Repairs —Award of Contract No. 3798
October 24, 2006
Page: 2
they did not submit a bid. Two of the plan holders determined that the project was outside
the scope of their construction abilities, one was a materials supplier, one thought the
project was too small to bid, and three indicated their current work load precluded them
from bidding.
Because of the unanticipated high Total Base Bid amounts compared to available
funding for this project, staff is recommending that the Additive Bid work, clearing
marine growth from piles on both piers, be deferred.
The low bidder, John S. Meek, possesses a California State Contractors License
Classification "A" as required by the project specifications. The Contractor has
satisfactorily completed many similar projects for the City of Newport Beach.
The scope of work for the completion of this contract consists of replacing deteriorated
and or missing cross bracing, stringers, cross bridging, hardware, etc; and installing
fiberglass jackets, reinforcement and epoxy grout to stabilize /repair pier pilings; and
installing trowelable epoxy to fill voids and fix cracks in existing structural members of
the pier; and performing all related work as required to complete the contract work in
accordance with the drawings and specifications. The last such pier repair contract was
performed in fiscal year 2001 -2002.
Per the Contract Specifications the Contractor will have 60 consecutive working days to
Complete the work. Liquidated damages are $1,000 per day.
Environmental Review:
City staff has reviewed the project and has determined the project is exempt from the
California Environmental Quality Act (CEQA) pursuant to Section 15302 of the CEQA
Implementing Guidelines when the project is authorized by the .City Council. This
exemption covers the maintenance and alteration of existing public facilities with negligible
expansion of the facilities in areas that are not environmentally sensitive.
Public Notice:
The Notice Inviting Bids was advertised in the City's official publication and in
construction industry publications.
Geotechnical. Material Testing, and Survey Services:
In addition to the contract costs, approximately $2,000 in material testing is estimated
for this project and $2,000 for printing and other incidentals.
Ocean Pier Repairs —Award of contract No. 3798
October 24, 2008
Page: 3
Funding Availability:
The amount currently available for this project is $488,000. With approval of the
recommended Budget Amendment the remaining $269,550 would become appropriated
and sufficient funds will be available in the following accounts for the project.
Account Description
Tide and Submerged Lands
Budget Amendment
Proposed uses are as follows:
Vendor
John S. Meek Company, Inc.
John S. MeekCompany, Inc.
On —call Consultant
Various
Prepared by:
Stephen Luy
Associate Civil Engineer
Attachments: Project Location Map
Bid Summary
Budget Amendment
Account Number
7231- C5100836
7231- C5100836
Total
Purpose
Construction Contract
Construction Contingency
Materials Testing
Amount
$488,000
$271,550
$759,550
Amount
$687,550
$ 68,000
$ 2,000
Printing and Incidentals $ 2,000
Total: $759,550
Submitted by:
ht4T�
LCQ4<t
F pf ,_
BALBOA
PIER
ILL '-
NE WORT
PIER
T
N.T.S.
O h~
4� N
pqQyt
&q
CITY OF NEWPORT BEACV
Luc WOMS. DIPARTMEW
OCEAN PIER REPAIRS
N.T.S. I a'i
C
OMM
Lm
C -3798
Dm G- d-
Duo#" NO. EXHIBIT A
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
TITLE: OCEAN PIER REPAIRS BID LOCATION: City Clerk's Office- City Hall
CONTRACT NO.: C3798 DATE: 10/11/2006 TIME: 11:00A.M.
ENGINEER'S ESTIMATE: $443,000.00 BY: Stephen Luy CHECKED: Shari Rooks DATE: 10111/2006
PROJECT MANAGER: Stephen Luy
f:Wwm"w !shared \cwtmct100- 011161D SUMMARY Page 1
En ineer's Estimate
John S. Meek Co.
Minako America Corp.
ITEM
DESCRIPTION
QUANTITY
UNIT
AMOUNT
UNIT
AMOUNT
UNIT
AMOUNT
1
IMobilization
1
1 LS
24,000.001
24,000.00
65,800.00
65,800001
10,000.00
10,000.00
2
lNewport Pier Rehabilitation
1
1 LS
220,000.00
220,000.00
217,920.00
217,920.00
397,000.00
397,000.00
3
Balboa Pier Re air
1
LS
199,000.00
199,000.00
403,830.00
403,830.00
389,000.00
389,000.00
Total Base Bid EE 443 000.00 LOW 687 550.00 2ND 1 796,0 0.00
Additive Bid Items QUANTITY UNIT AMOUNT UNIT AMOUNT UNIT AMOUNT
FAA—E12 Clean Marine Growth from Newport Pier
1 LS -
100000.00
100000.00
117,000.00
117000.00
197 000.00 197,000.00
AB2 Clean Marine Growth from Balboa Pier
1 LS
100000.00
100,000.00.
93600.00
93600.00
197 000.00 197000.00
Total Additive Bid
Total Bid
EE
200 000.00
LOW
210 600.00
2N2 394 000.00
EE
643 000.00
LOW
898 150.00
2ND 1,190,000.001
f:Wwm"w !shared \cwtmct100- 011161D SUMMARY Page 1
City of Newport Beach NO. BA- 07BA -020
BUDGET AMENDMENT
2006 -07 AMOUNT: $271,550.00
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates Increase in Budgetary Fund Balance
�X Increase Expenditure Appropriations AND X Decrease in Budgetary Fund Balance
Transfer Budget Appropriations No effect on Budgetary Fund Balance
SOURCE:
from existing budget appropriations
from additional estimated revenues
NX from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
To increase expenditure appropriations to enter into a contract for ocean pier repairs.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Account
230 3605
REVENUE ESTIMATES (3601)
Fund /Division Account
EXPENDITURE APPROPRIATIONS (3603)
Description
Tide & Submerged Land - Fund Balance
Description
Amount
Debit Credit
$271,550.00 '
Description
Division Number 7231 Tidelands - Capital
Account Number C5100836 Ocean Pier Repairs $271,550.00
Division Number
Account Number
Division Number
Account Number
Division Number
Account Number
Division Number
Account Number
Automatic System Entry.
Signed: p
Finance I proval: Administrativ ervices Director D e
Signed:
A inistrative Appro I: City anager D e
Signed:
City Council Approval: City Clerk Date