HomeMy WebLinkAbout11 - Master CIPCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 11
February 12, 2008
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Stephen G. Badum
949 - 644 -3311 or sbadum @city.newport- beach.ca.us
SUBJECT: FY 2007 -08 MASTER CIP SCHEDULE UPDATE
RECOMMENDATION:
Receive and File.
DISCUSSION:
Attached is the 3rd Quarter Master Project Schedule update. For the most part, our
projects are proceeding on schedule and on budget. Projects that have specific funding
issues are noted below. In addition, those projects that are off schedule will probably
see. increased material costs when they get to construction. However, these increased
costs Will most likely be offset by a more competitive bidding environment. As private
sector work slows, we are seeing more contractors pursuing our projects. The
proposed streetlight project award, on this agenda, is evidence of this trend. Highlights
of progress made in the 2nd quarter and changes from the 2nd quarter schedule are
depicted as follows:
Projects completed in 2nd Quarter
1. FY06 /07 Sidewalk, Curb and Gutter Program, Contract No. 3908
2. Irvine Avenue and Dover Drive Water Transmission Main, Contract No. 3708
3. Coast Highway Medians Phase 1B, Contract No. 3867
4. Newport Shores Street End Improvements - Phase 2, Contract No. 3805
5. Newport Boulevard Right Turn Lane at Hospital Road, Contract No. 3655
Projects Schedule Modifications
1. 38th Street Tidal Structure /Motorized Tide Valve: This project is delayed by
three months. Design was originally planned to be completed in- house,. but due
to staffing demands on several other in -house designs, this project is being
reassigned to a consultant and is now scheduled for Council award around May.
FY 2007 -08 Master CIP Schedule Update
February 12, 2008
Page 2
2. Birch Street Pavement Rehabilitation, Bristol Street to MacArthur
Boulevard: This project involves grant funding under the Arterial Highway
Rehabilitation Program (AHRP). Due to residual state funding shortages in last
year's program, Caltrans did not approve this project in September. We have
been informed by Caltrans that the funding situation has been rectified, but
Caltrans has yet to provide formal approval so the project may proceed. The
revised schedule estimates construction of the project beginning around June
2008, a two month delay from our original estimate.
3. Balboa Island Bulk Head Repair: When the current CIP was developed, this
project was originally anticipated to be awarded in June. However, current
construction cost estimates indicate the project will cost approximately
$800,000. Only $160,000 was budgeted in the FY 07/08 CIP, indicating a
significant funding shortfall. Additional funds will be requested in the next fiscal
year, pending Council approval. A new project schedule will be developed as
part of the FY 08/09 workload projection.
4. Balboa Island Water Main Improvements: This project's schedule is
contingent.upon the approval of the Underground Utility District (District) for the
Island. Design is almost complete and construction will be in concert with the
District. Should the District fail, this project may be postponed. Approval of the
District is planned for late summer with construction starting in January 2009.
5. Balboa Village Alley Replacement: This project has been delayed by six
months as a result of utility company and resident/business related work issues.
The utility companies have not removed all the overhead facilities and six poles
remain in place. It is our understanding that in the next few months these
facilities will be removed as the companies work to resolve service issues to the
businesses around Main Street. Staff is now planning to start this work after
January 1, 2009 to avoid impacts with the summer and holiday seasons.
6. Bayside Drive (Jamboree Road to El Paseo Drive), CdM Area South of
Coast Highway and Dove Street Rehabilitation: The project is planned to be
designed in- house. The assigned Project Engineer has been heavily involved in
construction activities and working on Coastal Commission permitting for several
other projects. This project was selected to be delayed. Council award should
be around June with construction planned in August.
7. Bridge Seismic Retrofits — Jamboree Road and Goldenrod Foot Bridge:
This project has been delayed by four months due to funding approval by the
State. Approval is expected in the spring and project award is planned for July
with construction beginning late summer.
8. Buck Gully Arundo Removal: This project is not a high priority and is being
delayed in an effort to balance staff workload through the fiscal year. Original
award was planned in September 2007 and is now planned for this April.
FY 2007 -08 Master CIP Schedule Update
February 12, 2008
Page 3
9. Buck Gully Maintenance Road and Wetlands Project: The project has
suffered some significant delays due to weather damage. Due to Coastal
permitting restrictions, this work had to be scheduled during the rainy season.
Construction was scheduled for completion in early January and is now
estimated to be done in later spring.
10. Central Library Emergency Generator: This project is on hold pending the
outcome of the City Hall in the Park Intiative.
11. Coast Highway Sidewalk — Morning Canyon Road to Seaward Road: The
2nd Quarter Schedule Update reported this project was being accelerated to
coordinate with the planned River Avenue sidewalk project. The River Avenue
project has been postponed due to delays with the Utility Undergrounding
District in that area. The project is now on its original schedule estimating
Council award in April.
12.Corporation Yard Building G Roof Repair and Rehabilitation: This project
has been delayed by three months. Design was planned to be completed
in- house, but due to staffing issues on other in -house designs and construction
management, this project will now be completed later in the fiscal year. Council
award is anticipated forMay.
13. Dover Drivel, Sidewalk 1m provements: This project has been delayed due to a
lengthy and frustrating Coastal Commission perrnitting,process. The project has
now been approved and a Coastal Development Permit is pending the City's
final design submittals. Staff anticipates some additional negotiation with the
Coastal Commission staff, but anticipates construction beginning in fall 2008.
14.East Bay Avenue and A Street Rehabilitation and East Bay Storm Drain
Upgrade/Tidal Valve Installation: This project has been delayed by three
months. Design is planned to be completed in- house, but due to staffing
workload demand from other in -house designs and construction projects, this
project will now be completed later in the fiscal year. Council award is
anticipated in May.
15. Fire Facilities Assessment and Preliminary Design: This project has been
put on hold pending the direction of the Council Finance Committee regarding
the City Facilities Master Plan.
16. Flashing Crosswalk — Newport Boulevard at 23rd Street: This project was
planned for award in February. Due to high demand, the equipment for the
flashing crosswalk has a long lead time and construction would then be in the
summer months, which is not recommended on the Balboa Peninsula. For that
reason, staff is recommending delaying the project award until later in the fiscal
year with construction planned after the summer season.
FY 2007 -08 Master CIP Schedule Update
February 12, 2008
Page 4
17. Hoag Health Care Center — Traffic Signal and Median Improvements: This
project has been delayed by the developer who is still working through the
necessary design and permitting.
18. Irvine Terrace Landscape Improvements: This project is experiencing delays
due to scope creep. Only $150,000 was approved in the FY 07/08 CIP and the
design desired by the HOA is estimated at $450,000. Staff is working with the
various parties to try and formulate a project to fit available funding.
19. Little Corona Restroom Facility Remodel: This project was planned for
award in February with the hopes of construction being completed by summer.
The plans and specifications are complete and we are awaiting issuance of the
necessary Building Permits to complete the project. There is a concern that
completion may not happen before the summer season. In addition, only design
funding for the project was approved in this years CIP. Staff is recommending
awarding this project in the summer, assuming additional funding is approved for
the project in next years CIP ($400,000).
20. Newport Coast Drive at Pelican Hills Road North — Intersection
Improvements: The project plans and specifications are complete and are
ready to advertise for bid. The delay was caused by the HOA approval process
(approved on 1123/08), which was slowed due to the holiday season. The
Council award.is planned in April.
21. Oceanfront Water Main Improvements — 141th Street to 201h Street:
Construction of this project is contingent upon the approval of the pending
Underground Utility District. Construction for this project will move forward in
concert with the District. If the District fails, this project would most likely be
postponed. Approval of the District is planned for late summer with construction
starting in fall 2008.
22. Pedestrian Coastal Access and Circulation Improvements — River Avenue
Sidewalk: Community members recommended the project be expanded to
include City maintained landscaped parkways. In addition, the road widths
might be reduced to improve pedestrian circulation and safety. Staff is
preparing a concept plan that will assist in further community outreach and
preparation of final contract documents. Additional CIP funding will be
requested in FY 08/09 and, if approved, the project will be awarded in the
summer. Construction is planned for the fall 2008.
23. Public Docks Access Improvements: This project was planned for award in
the spring. It was originally anticipated that the work could be permitted under
the City's Regional General Permit with Coastal. After closer review, it appears
a CDP is required and will delay the project by six months. In addition, Building
Codes require some accessibility improvements which prompted the need for
more funding. An additional $35,000 in CIP funding may be requested in FY
08/09.
24. SAH Joint Use Channel Maintenance and Equestrian Facility: Additional
community outreach has caused a significant delay in this project.
FY 2007 -08 Master CIP Schedule Update
February 12, 2008
Page 5
25. Tennis Court Fencing Replacement — West Newport Park: This project was
originally planned for award in November 2007. Unfortunately, no bids were
received and the project was successfully re -bid. The project has now been
awarded and construction will commence shortly.
26.West Coast Highway Vision Plan: This project was delayed by two months
due to the recently completed Superior Avenue Median Improvements. Based
on the community response to that project, staff will incorporate comments and
concerns as they approach the West Coast Highway area improvements.
27. Westcliff Street Light Improvements: This project was bid in the fall, however,
the bids were three times what was budgeted and staff recommended Council
reject the bids. Additional funding will be sought in the FY 08/09 CIP and, if
approved, the construction is estimated in the fall.
Proiects Advanced
1. Buffalo Hills Park Lighting Improvements with San Miguel and Bonita
Creek Park Lighting Replacements: This project is being advanced so that it
can be combined with the San Miguel and Bonita Creek park lighting
replacement efforts. The San Miguel and Bonita. Creek lighting efforts were bid
with the larger Westcliff Street Light Replacement Project and bids were rejected
in November due.to the unexpected cost. Bonita Creek park lights have been
planned for replacement for the past year and, due to safety concerns, were
removed this past fall. The parking lot has been without lighting since that time.
Council also expressed a desire to have the Buffalo Hills project completed
sooner than later.
2. West Newport Park at Orange Street and Newport Island Park Playground
Replacement: This project was originally scheduled for construction in fall 2008.
Recreation staff requested that the playground equipment be purchased
independently of the construction contract to expedite the project. Since Council
approved this action in December, the construction of the playgrounds can be
completed prior to summer.
3. Police Lobby Modifications: This project is being advanced by one month to
begin in May rather than June.
New projects
1. Central Library Book Store Remodel: The Friends of the Library have
requested that a concept plan be prepared for the remodel of the Friends Book
Store. The project is being funded by the Friends of the Library.
The Master Project Schedule is posted on the City's web page under the Public Works
Department at hftp: / /www. city. newport- beach.ca.us /Pubworks /CIP.html and is updated
quarterly. As presented at the January 8th Study Session, staff is developing a web
based reporting system that is planned to be on line in July. The reporting system will
FY 2007 -08 Master CIP Schedule Update
February 12, 2008
Page 6
be updated in real time to provide the schedule and cost information for our capital
improvement program.
Prepared by:
David Webb
Deputy Public Works Director /City Engineer
Attachment: CIP Master Schedule - 3`d Quarter
Submitted by:
Ste�pp en G. Badum
blic Works Director
FY 2007 -08 MASTER PROJ6
SCHEDULE - 3rd Quarter
ID
Task Name
j Start
L
Finish
2008
J J
I A I S 1 O 1 N I D
J F M A M I J I J A I S 1 O 1 N I D
234
38th Street Tidal Structure/Motorized Tide Valve
(1) Design - In House/Nolan Consulting - (p. 23)
(2) Award
(3) Construction ($135,000)
Arroyo Park, Avon Street at Tustin Avenue. Corona del Mar Area Parking
Lots, Irvine Terrace, Newport Heights and West Balboa Slurry Seal
(1) Design - In House - (p. 24, 25, 33, 45, 49 & 61)
(2) Award ($48,000, 69,000, 120,000, 395,000, 580,000 & 89,000)
(3) Construction ($1,301,000) -
ASBS Assessment Program
(1) Prop 40/50 Grant contract ($397,500) - (p. 90)
(2) Public Use and WO Assessments (Weston)
(3) Cross contamination impact study (Everest)
(4) Pilot Renovation Program (Cal. State Fullerton)
(5) Bioassay Study (Weston)
(6) Final Integrated Coastal Watershed Management Plan
Assessment District 19 - Santa Ana Heights
(1) Utility Company Design Efforts & Assessment Engineering (p. 139)
(2) Underground and Transmission Construction ($7,411,200)
(3) Street Improvements
(4) Utility Systems Installation and Wiring
(5) Resident Conversion
Assessment District 69 - West Newport
(6) Resident Conversion
Assessment District 87 - Balboa Island
(1) Utility Company Design Efforts & Assessment Engineering
(2) Public Hearing - District Approved
(3) City Water System Improvements
(4) Underground Construction
(5) Utility Systems Installation and Wiring
(6) Resident Conversion
(7) City Street Improvements
(8) City Alley Improvements
Assessment District 92 - Mariners Mile
(1) Utility Company Design Efforts & Assessment Engineering
(2) Public Hearng - District Approved
(3) Underground Construction
(5) Street Improvements
(6) Utility Systems Installation and Wiring
(7) Resident Conversion
Tue 01/01/08
Tue 01101/08
Tue 05/27/08
Mon 09/08/08
Mon 12103107
Mon 12/03/07
Tue 04122/08
Mon 05/12/08
Thu 01/05/16
Thu 01/05/06
Mon 04/30/07
Wed 11/01 /06
Mon 01/15/07
Fri 12/01106
Mon 06/02/06
Fri 01/23104
Fri 01/23/04
Mon 01/05/09
Mon 05/10/10
Mon 05110/10
Mon 01/10/11
Tue 08109105
Tue DB/09 /05
Tue 01/28103
Tue 01/28/03
Tue D9 /09108
Mon 11/03/08
Mon 01/05/09
Mon 07/04/11
Tue 09/07/10
Mon 08/29/11
Mon 01/07/13
Tue 11/09/04
Tue 11/09/04
Tue 01/22/08
Tue 04/01/08
Tue 09/23108
Wed 10/01/08
Wed 10/01/08
Fri 12019/08
Tue 04/01/08
Tue 05/27/08
Fri 12/19/08
Fri 08/22108
Fri 02/29/08
Tue 04/22/08
Fri 08/22/08
Mon 06102/06
Wed 06/21/06
Mon 03131/08
Mon 03/31/08
Mon 03/31/08
Mon D3 131108
Mon 06102108
Fri 05127/11
Tue 11/04/08
Fri 05/07/10
Fri 09/24/10
Fri 01/07/11
Fri 05/27/11
Thu 06119/08',
Thu 06/19/08
Fri 06102/13
Wed 06104/08
Tue 09109/08
Fri 10/16/09
Fri 07/01/11
Fri 08124112
Mon 12/24/12
Fri 06101/12
Fri 06702/13
Tue 11/2409
Fri 09/21/07
Tue 01/22/08
Mon 09122108
Mon 03/16/09
Tue 0428109
Tue 11124/09
:.
-.
-
is
,06102
235
236
237
206
207
208
209
7
8
9
10
11
12
13
418
419
420
421
422
423
3B8
387
401
-
'.
402
403
404
405
406
407
408
409
388
-i -
389
390
391
392
393
394
— _ —
Tue 02/05/08
Page 1
FY 2007 -08 MASTER PROJO SCHEDULE - 3rd Quarter
ID
Task Name Start Finish
Assessment District 99 - Balboa Peninsula Tue 10109/07 Tue 05126/10
(1) Utility Company Re- Design Efforts 8 Assessment Engineering Tue 10/09/07 Fit 06/06108
(2) Public Hearing - District Approved Tue 08/12/08 Tue 08/12108
(3) City Water System Improvements Wed 10/01108 Tue 12/23108
(4) Underground Construction Mon 11/03/08 Fri 07103/09
(5) Utility Systems Installation and Wiring Mon 07/06/09 Fri 12/25/09
(6) Resident Conversion Wed 04/01/09 Tue 01/05110
(7) Street and Alley Improvements Wed 01/06/10 Tue 05/25/10
Assessment District 100 - Central Balboa Ocean Front Tue 06/22/04 Fri 06115112
(1) Utility Company Design Efforts 8 Assessment Engineering Tue 06/22/04 Thu 04/02/09
(2) Public Heanng - District Approved Tue 05/12/09 Tue 05/12109
(3) City Water System Improvements Mon 09/07/09 Fn 01/08/10
(4) Underground Construction Mon 09107109 Fri 05/07/10
(5) Utility Systems Installation and Wiring Man 05110/10 Fri 12/03/10
(6) Resident Conversion Mon 05/10/10 Fri 07/01/11
(7) Alley Improvements Mon 07/04111 Fri 06/15/121
Assessment District 101 - Central Balboa Tue 05125104 Fri 05174110
(1) Utility Company Design Efforts 8 Assessment Engineering Tue 05/25/04 Fri 05/02/08
(2) Public Hearing - District Approved Tue 05/20/08 Tue W20 108
(3) Underground Construction Mon 09/081015 Fn 05/08/09
(4) Utllity Systems Installation and Wring Mon 06/01/09 Fri 12/25/09
(5) Resident Conversion Mon 36 /01 /09 Fn 05/14110
Assessment District 103 - Peninsula Point Tue 11/09/04 Fri 05118/12
(1) Utility Company Design Efforts 8 Assessment Engineering Tue 11/09/04 Thu 04/02/09
(2) Public Hearing - District Approved Tue 06/09/09 Tue 06/09/09
(3) City Water System Improvements Man 09107/09 Fri 04102110
(4) Underground Construction Mon 09107109 Fri 06/11110
(5) Utility Systems Installation and Wiring Mon 06/14/10 Fri 01/07111
(6) Resident Conversion Mon 06/14/10 Thu 12/29/11
(7) Alley Improvements Mon 01/02/12 Fill 05/18/12
Back Bay View Park Replenishment 8 Enhancement Tue 10/23/07 Fri 09/05/08
(1) Design - SWA - (p. 7B) - ($32,000) Tue 10/23/07 Fri 05/16/08
(2) Construction/Installation ($318,000) Mon 12/03/07 Fri 09105108
Balboa Island Bulkhead Repairs Tue 04/01108 Fri /16/19/09
(1) Design - In House - (p- 26) Tue 04101/08 Mon 10/27/08
(2) Award Tue 12/09/08 Tue 12/09/08
(3) Construction ($160.700) Mon 01105/09 Fn 06119109
Balboa Island Water Main Replacement Mon 10101/07 Fri 10/16/09
(1) Design - In House Mon 10/01/07 Thu 08151/08
(2) Award Tue 10114/08 Tue 10/14108
(3) Construction ($1,000,000 - FY08/09) Mon 11103/08 Fri 10/16109
2008 _
410
-
411
412
413
414
415
416
417
424
425
426
-
_
-
427
428
429
430
431
395
396
397
398
399
400
432
433
434
-
-.
-
-
b
5114
.
435
436
437
438
439
167
168
169
122
123
124
125
218
219
220
221
Tue 02/05/08 Page 2
FY 2007 -08 MASTER PRO
SCHEDULE - 3rd Quarter
ID
Task ame
Start
Finish
2008
J J A S O N D
J F M A M J J A B N D
226
Balboa Peninsula Walkway, Flat Coast Highway Curb and Gutter, Park
Asphalt Walkway Replacement with Annual Sidewalk, Curb and Gutter
Replacement Program (along with ADA Improvements)
(1) Design - In House (p. 59, 88. 141, 38. & 21 - FY 06107)
(2) Award - ($541,006) - Nobest
(3) Construction - ($100.000. 86.000, 115,000 & 301,216)
Balboa Village Alley Replacement
(1) Design - In House (p. 27)
(2) Award
(3) Construction ($177.390 & $200,000)
Bay Crossing Water Transmission Main Replacement
(1) Design ($300.000) - Consultant - (p. 118)
(2) Permitting
(3) Award
(4) Construction (not funded)
Bayslde Drive (Jamboree to El Pas ,o), CDM Area South of Coast Highway
and Dove Street Rehabilitation
(1) Design - In House - (p. 28, 34 & 35)
(2) Award
(3) Construction ($211,000, $1,000,000 & $97.000)
Bayside Waterfront Walkway to Balboa 191. Bridge
(1) Design - URS (Cash) - ($44000) - (p. 63)
(2) Coastal Permitting
(3) Award
(4) Construction (FY 08109 Development Funding)
Beach Sand Study & Monitoring Program
Design & Coastal Permitting - Moffatt & Nichol - $200,000 - (p. 83)
Big Canyon Creek Restoration
(1) Design - VA/Mark Reader - (p. 106)
(2) Coastal Permitting
(3) Award
(4) Construction (not funded)
Birch Street Pavement Rehab. - Bristol to MacArthur
(1) Design - In House/Emmet Berkery - (p. 29)
(2) Caltrans Processing
(3) Award
(4) Construction ($293,000, $176,000 & $263.000)
Bridge Seismic Retrofits - Jamboree and Goldenrod Foot
(1) Design - Dokken ($278,000) - (p. 30)
(2) Caltrans Processing/Coastal Permitting
(3) Award
(4) Construction ($312,400 & $1,270,700)
_
Mon 01/09/07
Mon 01/08/07
Tue D6 /26107
Mon 09/17/07
Mon 07/02107
Mon 07/02/07
Tue 10/28/08
Mon 01/05/09
Thu 11/07/07
Thu 11/01/07
Wed 10/15/08
Tue 07/14/09
Tue 09108109
Mon 07/02/07
Mon 07/02/07
Tue 06/10 /08
Mon 08/04/08
Tue 08/14/07
7ue 08/14/07
I'd 12128107
Tue 07/29/08
Mon 09/08/011
Mon 10/10/05
Mon 10/10/05
Fri 09101106
Fri 09 /01 /06
Thu 10125/07
Tue 09/09/08
Mon 11103108
Mon 01101107
Mon 01/01/07
Mon 06/18/07
Tue 04/22/08
Mon 06102/08
Mon 08/01105
Mon 08/01/05
Mon 06/05/06
7ue 06124/08
Tue 09/09/08
Tue 02126/06
Fri 04/06/07
Tue 06/26/07
Tue 02/26/08
Fri 04117109
Wed 08/20/08
Tue 10128108
Fri 04117/09
Mon 01/05110
Tue 10/14/08
Tue 05112109
Tue 07/14/09
Mon 04/05/10
Fri 11114108
Wed 04 /02/08
Tue 06/14108
Fri 11114108
Fri 02120/09
Thu 12/27/07
Thu 06119/08!
Tue 07/29108
Fri 02/20/09
Wed 06125108
Wed 06/25/08
Fri 05129109
Tue 01 129/08
Tue 07101108
Tue 09109100
Fri 05/29/09
Fri 08122108
Fri 05/18107
Wed 02/131081
Tue 04/22/08
Fri D8122/08
Mon 04106/09
Wed 02/27/08
Wed 04/30/08
Tue 06/24/08
Mon 04/06/09
i
227
228
229
214
—'
215
216
217
179
180
181
182
183
94
NOW I
-�
9
95
98
97
48
49
50
51
52
141
142
43
'.
—_
44
45
46
47
336
J
2
337
338
339
340
246
-
-
.
247
248
249
250
Tue 02/05/08
Page 3
FY 2007 -06 MASTER PROje
SCHEDULE - 3rd Quarter
ID
Task am
Bristol Street Sign Bridge Improvements
(1) Design - Consultant - (p. 64)
(2) Award
(3) Construction ($100,000)
Buck Gully Arondo Removal Project
(1) Design - In House (p. 114)
(2) Award
(3) Construction ($45,000)
Buck Gully Erosion Control Project
(1) Concept Plan - RBF /Emmet Berkery ($418,000) - (p. 145 FY 06107)
(2) Council Concept Plan Review
(3) Final Construction Docuements (Not Funded)
(4) Coastal Permitting
(5) Award
(6) Construction (Not Funded)
Buck Gully Force Main Replacement - Poppy Ave. from Hazel Dr. to ECH
(1) Design - ($22,000) - Nolan Consulting (p. 122)
(2) Award
(3) Construction ($274,633) - Mike Pdich & Sons
Buck Gully Maintenance Road & Wetlands Project
(1) Design, Permits and Easement (Dudek) - $125,000 (p. 107)
(2) Award - ($386,323.60)
(3) Construction ($115,823, $67,500 & $203,000) - McKenna General Eng.
Buck Gully Resource Management Plan
Consultant/Dave Kill - ($170,000)
Buffalo Hills. Bonita Creek & San Miguel Park Lighting Improvements
(1) Design - JMDiaz - (p. 85)
(2) Award
(3) Construction ($215,000 8 $125.000)
Central Library Bookstore Remodel
(1) Concept Design - Landwurks Development Services/Mark Reader ($9,000
(2) Design 8 Building Permits
(3) Award
(4) Construction (Not Funded - Friends of the Libratary Funding)
Central Library Emergency Generator (On Hold)
(1) Design - In House - (p. 1)
(2) Award
(3) Construction ($40,000 - Need Additional Funding)
Wed 01102108
Wad 01/02108
Tue 05/27108
Mon 07/14108
Wed 08/01/07
Wed 08101/07
Tue 04/22108
Mon 06/02/08
Mon 07103/06
Mon 07/03106
Tue 02/12/08
Tue 02/12108
Tue 03!10/09
Tue 02123/10
Mon 04/05/10
Mon 01/02/08
Mon 01102/06
Tue 08114/07
Wed 01/02/08
Fri 07101105
Fri 07101/05
Tue 07/24/07
Wed 08115/07
Mon 10/01107
Mon 10/01/07
Mon 10115107
Mon 10/15/07
Tue 02/12/08
Tue 04 /01 /08
Mon 01114108
Mon 01/14/08
Mon 04 )07/08
Tue 10/28/08
Mon 12/01/08
Mon 03/03/08
Mon 03/03108
Tue 09/09/08
Mon 10/13/08
Finish
Fri 1112808
Tue 04 /15/08
Tue 05127/08.
Fri 11128/08
Mon 09101108
Fri 02/29/08
Tue 04122108
Mon 09/01108
Fri 01/07/11
Fri 01/18!08
Tue 02/12/08
Mon 03/09/09
Mon 12/28/09
Tue 02/23/10
Fri 01/07111
Tue 03125108
Fri 06/29/07
Tue 08/14/07
Tue 03/25108
Wed 04/30/08
Thu 05/31/07
Tue 07/24/07
Wed 04/30/08_
Tus 07101108
Tue 07 101 /08
Mon 08/18108
Thu 01103108
Tue 021121083
Mon 08/18108
Fri 02/20/09
Fri 04/04!08
Fri 09/19/08
Tue 10/28/08',
Fri 02/20/09
Fri 02/27/09
Fri 07118/08
Tue 09/09/08
Fri 02/27109
2008__
J
J A S 1 O rM _ A M T J I J I A 1 5 O N I D
298
_
299
300
301
62
83
84
85
126
02112
-
..-0
-�
-
7124
_
_
'.
.
',,� - -� --
t27
128
129
130
131
132
147
148
149
160
78
79
8o
81
18
19
202
203
204
205
349
350
351
362
353
251
252
253
254
Tue 02/05/08
Page 4
FY 2007 -08 MASTER PRO
SCHEDULE - 3rd Quarter
Task-game
CIMf Drive Park Sta irway and Handrail Replacements
(1) Design - In House (p. 86)
(2) Coast
(3) Construction ($147,426.60) - G2 Construction
Coast Highway Sidewalk - Morning Canyon to Seaward
(1) Design - In House/CNllwarks ($44.000) - (p. 32)
(2) Award
(3) Construction ($205,000)
Corporation Yard Building Fleet Maintenance Locker Room
(1) Design - In House - (p.5)
(2) Building Permits
(3) Construction ($65,000)
Corporation Yard Building G Roof Repair and Rehabilitation
(1) Design- In house/Consultant- (p.4)
(2) Award
(3) Construction ($120,000)
CYC Rehabilitation
(1) Master Planning - Dougherty - Dougherty /Mark Reader - (p. 6)
Directional and Wayfinding Signage - Citywide
(1) Design - In Housellris Lee - (p. 65)
(2) Award
(3) Construction ($225,000 & $102,000)
Dover Drive & Westcliff Drive Medians Renovation (On Hold)
(1) Design - In House /Consultant - (p. 36 & 62)
(2) Award
(3) Construction ($125,000 & $80,000)
Dover Drive Sidewalk Improvements
(1) Design - ($69,838) Van Dell (p. 37)
(2) Permitting
(3) Award
(4) Construction ($64,000, $102,645 & $278,500)
East Bay Avenue and A street Rehabilitation and East Bay Storm Drain
Upgraderridal Valve Install
(1) Design - In House - (p. 38 & 39)
(2) Award
(3) Construction ($113,000 & $30,000)
EastbluN Drive Street Rehabilitation
(1) Design - DMS - (p. 40 & 56)
(2) Award
(3) Construction ($1,180.000 & $200,000)
Start
Tue 05101/07
Tue 05/01/07
Tue 09/11/07
Thu 11!01107
Wed 08/01107
Wed 08/01107
Tue 04122/08
Mon 05/12/08
Wed 08/01107
Wed 08/01/07
Thu 11101107
Mon 02/04/08
Thu 11 /01 /07
Thu 11/01/07
Tue 05/27/08
Tue 07!01 /08
Wed 08/01 /07
Wed 08/01/07
Thu 02/01/07
Thu 02101/07
Tue 06/12/07
Mon 07/16/07
Tue 07/01/08
Tue 07101/08
Tue 07/01108
Wed 07 /02!08
Mon 10104/04
Mon 10104/04
Mon 06/26/06
Tue 08/12/08
Mon 09115108
Wed 08101 /07
Wed 08/01/07
Tue 06110108
Mon 08/11/08
Sat 09 /01107
Sat 09/01 /07
Tue 04/22/08
Mon 06/09108
Finish
Tue 03/25/08
Mon 07/02/07
Tue 09/11/07
Tue 03/25!08
Fri 09126/08
Fri 02/22/08
Tue 04/22/08
Fri 09/26/08
Fri 05/1 W08
Wed 10/31/07
Fn 02/01!08
Fit 05116/00
Mon 10113108
Tue 04101/08—
Tue 05/27108
Mon 10 /13108
Fri 06/27/08
Fri 06/27/00
Tue 02/26108
Wed 0511&07
Tue 06/12107
Tue 02/26108
Wed 07/02106
Tue 07/01/08
Tue 07101/08
Wed 07/02/08
Fri 12126/06
Fri 06/23/06
Wed 06/25/08
Tue 06/12/08
Fn 12126108
Tue 11125/08
Fri 04118108
Tue 06/10/08
Tue 11/25/08
Fri 10124/08
Wed 02/27/08
Tue 04122108
Fn 10124100
2008
J J A S O
N D
J F M A M J J A S 0 N D
-`_ —
12
}--�
4122
-
-�i',.
-t>W27
-
.
7101
[2�67
269
270
382
383
384
385
238
239
240
241
33
34
107
108
109
110
222
223
224
225
102
;
103
104
106
708
242
_
-��
.- 08110.7
r
�---i
243
244
245
210
211
212
213
Tue 02/05/08
Page 5
FY 2007.08 MASTER PRO
SCHEDULE - 3rd Quarter
ID
Task Name
Start
Finish
2008
J J
A S O N D J T F I M A I M I J I J I A I S O N D
370
Fire Facilities Assessment and Preliminary Design
Study - Consultant - (p. 7) - ($280,000)
Fire Station 1 Gender Modifications
(1) Design and Building Permits - Consultant - (p.8)
(2) Award
(3) Construction ($160,000 & $74,600)
Fire Station 3 Water Pipe Replacement
(1) Design - Consultant - (p. 9)
(2) Award
(3) Construction ($30,000 & $65,000)
Flashing Crosswalk - Newport Boulevard at 23rd Street
(1) Design - KOA -lip. 66)
(2) Award
(3) Construction ($110,000)
Harbor Area Management Plan ($345,800)
(1) Consultant Award - WestorVFong Tea - (p. 76 FY 06107)
(2) Prepare assessment, studies and recommentations
(3) Prepare Final Plan
Hoag Health Care Center - Traffic Signal Improvements
(1) Design - Consultant/Emmet Berkery
(2) Right -of -Way Acquisition
(3) Award
(4) Construction ($330,000, $800.000, & $130,000)
HR Recruitment Trailer Project
(1) Design - In House - (p. 21)
(2) Award
(3) Construction ($43.000 & 15,000)
Indian Spring Lane, Polaris, Santiago & Spyglass Hills Subdrains
(1) Design - In House (p. 42, 51 & 55)
(2) Award - with FY D &09 Street Projects
(3) Construction ($50,000, $270.000 & $75.000)
Industrial Way -36 -inch Water Transmission Main Replacement - Superior
Avenue to Old Newport Road
(1) Design ($122,000) - HDR - (p. 102 - FY 08/07)
(2) Award - ($990,285) - &JB Group
(3) Construction ($144,500 & $919,785)
Interpretive Resources and Facility
(1) DesigniBulld - (p. 114)
(2) Construction ($26,700)
Mon 10/01/07
Mon 10/01/07
Tue 01/01/08
Tue 01/01/08
Tue 05/13108
Mon D6/02J08
Thu 11101107
Thu 11/01/07
Tua 01/08/08
Tue 01/08/08
Wed 08/01107
Wed 08 /01107
Tue 05/27/08
Mon 09115108
Tue 05/08/07
Tue 05/0 8/07
Tue 05/0 8107
Fri 05/16/08
Mon 07102107
Wed 0 &01107
Mon 07102/07
Tue 10114/08
Mon 01105/09
Mon 08M3107
Mon 0 8113107
Tue 11/13/07
Tue 11/13107
Tue 01108/08
Tue 01/0 8108
Tue 12/09/08
Mon 02/02/09
Wed 05/11/05
Wed 0 &11/05
Tue 0 5/0 &07
Mon 07/1 6/07
Mon 07102/07
Mon 07/02/07
Mon 10/01/07
Mon 12131/07
Mon 12/31/07
Fri 07/18/08
Fri 03/14/08
Tue 05/13/08
Fri 07/18/08
Thu 02/07/08
Tue 12/18/07
Tue 01/08/08
Thu 02/07/08
Fri 12/05/08
Fri 0312 &08
Tue 05/27/08
Fn 12105108
Tue 07/22/06
Tue 0 510 8107
Thu 05/15/08
Tue 07/22/08
Fri 05/22/09
Fri 0029/08
Wed 07/30/08
Tue 10/14!08
Fri 0 5/22/09
Tue 02/26108
Thu 09/27/07
Tue 11/13/07
Tue 0212 6/08
Fri 05/15109
Mon 10/13/08
Tue 12/09/08
Fri 05/15/09
Tue 04/22106
Tue 03/13/07
Tue 05108)07
Tue 04122108
Thu 02/28/08
Thu 09 /20/07
Thu 02/2&08
-.
Now
13
106'
371
35
36
37
38
372
373
374
375
286
♦05
287
288
209
20
21
22
23
318
�J
- 11/13
-
_
-.
319
320
321
322
151
152
153
154
255
256
257
258
143
144
145
148
119
120
121
Tue 02/05/08
Page 6
ILl
1 296 1
1 140 1
1 356 1
FY 2007 -08 MASTER PRO SCHEDULE - 3rd Quarter
Ids Avenue and Coast Highway Traffic Signal
(1) Design - Reds - (p. 67)
(2) Award
(3) Construction ($100,000 & $180,000)
Irrigation - Citywide Central Computer Program
(1) Ongoing Irrigation management program (p. 94) ($90,000)
Irrigation - Newport Coast Central Computer System
(1) Newport Coast Central Computer System Program (p.95) ($100,000)
Irvine Avenue and Dover Drive 24 -inch Water Transmission Main
Replacement - Santiago to Westcliff
(1) Design - ($140,000) Stantec - (p. 92 & 90 FY 05/06)
(2) Award
(3) Construction ($2,827,049) - Vadnais
Irvine Avenue Drainage Improvements (Beacon to Clay)
Design - In House (Design Only)
Irvine Avenue Realignment- University to Bristol (County Lead)
(1) Design - County /Emmet Berkery (p. 43)
(2) Right -of -Way Acquisition
(3) Award (County Administration)
(4) Construction ($330,200 & $800,000)
Irvine Terrace Landscape Improvements - Phase I (On Hold)
(1) Design - Pendian - (p. 44)
(2) Award
(3) Construction ($130,000 & $20,000 - Need Additional Funding)
Jamboree Road Widening over SR -73 (ON HOLD)
(1) Design - ($923,483) - RBF /Emmet Berkery (p. 46)
(2) Right -of -Way Acquisition ($299,100 & $115,000)
Little Corona Restroom Facility Remodel
(1) Design - In- House /Mark Reader - (p. 12)
(2) Award
(3) Construction ($350.000 - Not Funded)
Marina Park Improvements
(1) Conceptual Design - Robber Herman Design/Mark Reader
(2) Preliminary Engineering, Design and CEQA Documents
(3) Final Design (not funded)
Mariners Mile Waterfront Walkway- Prel. Plane/Permits
Pierhead Line Extension - Cash & Assoc. ($175,760)
Mariners Park Restroom
(1) Design - Ron Yao - $26,000 - (p. 91)
(2) Award
(3) Construction ($750,000 - FY 08/09)
Mon 10101/07
Fri 03107/08
�-
Tue 04/29/08
Tue 04/29/08
Mon 06 /02/08
Fri 10/17/08
Mon 07/02/07
Mon 06I30/0e
Mon 07/02/07
Mon 06/30 /08
Mon Crirf 07
Mon 06/30/08
Mon 07102/07
Mon 06/30108
�-
Mon 08107 104
Tue 0122/08
I
Mon 06/07/04
Fn 05/05106
Tue 06113/06
Tue 06/13/06
Fn 01/19/07
Tue 01/22/08
Tue 04101/08
Mon 08/18/08
Tue 04/01/08
Mon 08/18/08
Thu 1228100
Fri 10103108
Thu 1228100
Fit 06/29/07
Fri 12101/06
Fri 06129107
-
Tue 09/11107
Tue 09 111107
owl
Mon 02104/08
Fd 10/03108
Mon 07/02107
Fri 12105/08
MEN om
Mon 07/02/07
Wed O6 /11/08
Tue 08 /12/08
Tue 08 /12/08
Mon 09/15/08
Fn 12/05/08
Tue 02108105
Tue 06105/07
PP
Tue 02/08/05
Mon 01108/07
Wed 02/01/06
Tue 06105 /07
1 '..
Tue 05/01107
Fri 12/19108
Tue 05/01107
Thu 06115108
Tue 0722108
Tue 0722108
Mon 09108108
Fri 12/19/08
Wed 08/01107
Tue 06101/10
Wed 08/01 /07
Fri 12/14/07
Mon 02/04108
Fri 05/01/09
Mon 05/04/09
Tue 06/01/10
Tue 06/01104
Thu 12131/09
Tue 06/01/04
Thu 12/31/09
Tue 01/01 /08
Fri 04/03!09
Tue 01/01/08
Mon 06/23/08
C
Tue 08/12/08
Tue 08/12/08.
Mon 09/08!08
Fn 04 /03/09
Tue 02/05/08 Page 7
12
FY 2007 -081 MASTER PRO
SCHEDULE - 3rd Quarter
Task Name
Start
Finish
2008
J J A S O N
D J I F M A _M._
J J A_ S O N D
Mariners Park Spo rts. Field Improvements
(2) Award
(3) Construction ($792,587 & $68,629) - Environmental Construction
Marines 111 Castaways Park Monument
(1) Design - In House
(2) Award
(3) Construction
McFadden Square Centennial Monument
(1) Design Perddiari/Emmet Berkery ($45,000)
(2) Coastal Permitting
(3) Award
(4) Construction ($369,582.75) - Hillcrest
Mess -Birch Park
(3) Construction ($357,000) - Belaire -West Landscape
(4) Plan Establishement and Maintenance (150 days)
Neighborhood Traffic Management Improvements - Phase 2
(1) Design - In House - (p. 68)
(2) Award
(3) Construction ($150,000 & $49,200)
Newport Bay Watershed Management Program ($850,000)
(1) Phase 1 Watershed Management Plan collaboration with IRW D
(2) Prop 50 grant applications [$5 million]
(3) Final Watershed Management Plan including RAMP
(4) Prop 84 grant applications ($10 million]
(5) Web portal and website maintenance
Newport Center Park (On Hold)
(1) Design - Hall & Foremanl Mark Reader - (p. 93)
(2) Award
(3) Construction ($200.000 & $61)(0,000)
Newport Coast Dr. at Pelican Hills Rd. North - Intersection Improvements
(1) Design - RSF - $100,000
(2) Award
(3) Construction (not funded)
Newport Coast Rain Gauges
(1) Design (1 location) - Geomatdz ($24,000)
(2) Permits and easements (City /County Staff)
(3) Installation ($15,000)
Newport Coast Runoff Reduction Program
On Going Program - Shane Burkle(Tom Ash
Tue 09/11107
Tue 09/11/07
Mon 10/08/07
Mon 12/03/07
Mon 12/03/07
Tue 02126/08
Mon 03/10/08
Tue 01/02!07
Tue 01/02/07
Mon 08/13/07
Tue 11/27/07
Mon 02104/08
Mon 12110107
Mon 12/10/07
Man 05/05/08
Mon 10/01/07
Mon 10/01/07
Tue 04/22/08
Mon 06/02108
Mon 01108/07
Mon 01/08/07
Mon 01/08/07
Mon 05/07/07
Mon 09/01/08
Mon 08/06/07
Wed 07/05/06
Wed 07 /05/06
Tue 08/11/09
Thu 10/01/09
Tue 04110107
Tue 04/10/07
Tue 04/22100
Mon 06/02/08
Mon 07/02/07
Mon 07/02/07
Mon 08/13/07
Thu 04/10106
Mon 07/02/07
Mon 07102/07
Thu 03127/09
Tue 09111/07
Thu 03!27108
Tue 06/27108
Fd 01/1 8/08
Tue 02/26/08
Tue 05/27/08
Fri 06108109
Fri 10/05/07
Wed 12'26/071
Tue 11/27107
Fri 06/06/08
Fri 10131/08
Fri 05/02108
Fri 10/31108
Fri 08/08/08
Thu 03/13/08
Tue 04/22/08
Fri 08/08/08
Tue 03/31/09
Wed 12/05/07
Thu 01/31/08
Wed 02/06108
Tue 03/31/09
Wed 07/30/08
Wed 04/28/10
Fri 06/19/09
Tue 08111/09
Wed 04/28/10
Fri 10117MO
Thu 02/21/08
Tue 04122/08
Fri 10/17/08
Wed 05/21/08
Fri 08/10 /07
Wed 04/09/08
Wed 05/21108
Mon OWl30/09
Mon 06/30/08
-
-
02128
r_
—
-
k1D
114
323
324
325
326
327
26
27
28
290
291
292
293
1
2
3
4
5
6
341
342
�L
`-04
343
344
115
116
117
118
86
87
Be
89
14
15
Tue 02/05108
Page 8
FY 2007 -08 MASTER PRO
SCHEDULE - 3rd Ouarter
ID
Task me
Start
Finish
2008
J 7 J I A I S 1 O 1 N I
D
J F M A I M I J I J I A I S O N D
362
Newport Terrace Landfill Gas Remedistion
(2) Award
(3) Construction ($018.800) - ICS /Gail Pickart
Newport Theatre Arts Center Entry Improvements, Utilities Yard Building 3
Remodel & Radio Tower Facilities Building
(1) Design - Jorgensen/Ruffing (p. 5,133, 1 DO 8 105 - FY 06107)
(2) Award - Big West Construction
(3) Construction ($300266, 25,000, 125.000, 50,000 & 240,000)
Oasis Center Concept Study
(1) Pre - Design Study - Coffee/Wes Morgan - (p. 14) - $52,100
(2) Design - Coffee /Steve Badum - ($1,496.600)
(3) Award
(4) Construction
Ocean Pier FY 07/08 Repairs and Inspection
(1) Design - In House (p. 96)
(2) Award
(3) Construction ($500,000)
Oceanfront Alley Water Main Repl. Btw. 14th and 20th
(1) Design - In -House (p. 119, 120 & 123)
(2) Award
(3) Construction ($750,000 & $100,000)
011field Improvement Program
(1) Ongoing oilfield management program (p. 133) ($453,400)
Pedestrian Coastal Access & Circulation Improvements - River Ave. Sldewall
(1) Design - In House/Civilworks (p. 69)
(2) Award
(3) Construction ($399,100)
Police Department Lobby Remodel
(1) Building Permits - In House - (p. 19)
(2) Award
(3) Construction ($249,900 & $43,700)
Police Facility Generator Replacement
(1) Design - Consultant - (p. 16)
(2) Building Permits
(3) Award
(4) Construction ($190,000)
Public Docks Access Improvements
(1) Design - Consultant - (p. 97)
(2) Permits
(3) Award
(4) Construction ($140,000 - Need 535,000 Additional Funding)
Tue 07124/07
Tue 07/24107
Mon 09103107
Mon 10/03/05
Mon 10/03/05
Tue 05/22107
Mon 07/02!07
Fri 06/01/07
Fri 06/01/07
Tue 10123/07
Tue 11/25/08
Mon 01105/09
Tue 01101/08
Tue 01/01/06
Tue 07/08/08
Mon 09/15/08
Wed 01/02108
Wed 01/02/08
Tue 09/09108
Wed 10101108
Mon 07102107
Mon 07/02107
Mon 00113/07
Mon 08/13/07
Tue 07 /DB/08
Mon 09/08108
Mon 12/03107
Mon 12/03/07
Tue 04/08/08
Mon 05 /05/08
Mon 10/01107
Mon 10/01/07
Fri 03/28/08
Tue 08/12/08
Wed 10101108
Tue 01101/08
Tue 01 /01/08
Mon 03/03108
Tue 11/11/08
Mon 0t/D5/09
Thu 09737108..
Tue 07/24/07 4
Thu 03/27/08
Wed 04!02/08
Fri 03/09/07
Tue 05/22/07
Wed 04/07/08
Fri 07/31/09
Wed 09/12/07 _ �1
Wed 10 /01/08 j--
Tue 11/25108
Fri 07/31/09
Fri 12126/08
Mon 05/19/08
Tue 07/08/08
Fri 12126/0B
Tue 12123/08
Tue 07/29/08
Tue 09/09/08
Tue 12/23/08
Mon 06/30/08
Mon 06/30/08
Fri 07/23109
Wed 05114/08
Tue 07/08/08
Fri 01123109
Tue 08/12/08
Fri 02129108.
Tue 04/08/08
Tue 08/12/08
Tue 12123MO
Thu 03/27/08
Thu 06/19/08
7ue D8112/08
Tue 12/23/08
Fri 04/17109
Mon 06 123/08
Fri 09/28/08
Tue 11/11/08
Fri 04117/09
,
C j
C;
—8'.
f
1�- 07108 -�
- TI-
I- --
8
-
lilt
363
364
29
30
31
32
365
366
367
368
369
98
99
100
101
275
276
277
278
279
280
271
272
273
274
39
40
41
42
184
185
186
187
108
281
282
283
284
285
Tue 02/05/08
Page 9
FY 2007 -05 MASTER PRO
SCHEDULE - 3rd Quarter
ID
Task Name
Start
Finish
12008
J J A B O N D
J F M A M J J A S O N I D
73
Rhine Wharf Repairs & Rhine Channel Visitors Ship Dock & Ramp
(1) Design/Build - (p. 99)
(2) Coastal Permitting
(3) Award
(4) Construction ($330,000 & $240.000)
SAH Joint Use Channel Maintenance & Equestrian Facility
(1) Design - Keeton Kreitzer ($60,233) - (p. 20)
(2) Community Outreach /Coastal Permitting/Final Design
(3) Award
(4) Construction ($81,650)
San Joquin Hills Road Median Trees
(1) Design In House - (p. 53)
(2) Award
(3) Construction ($50,000) -
Semeniuk Slough Dredging Project
(1) Engineering, Permit and USACE Coordination - (S1 05K) - Noble
(2) Award - (p. 115) - Any Corps Administered
(3) Construction ($360,000 & S300,000)
Sewer Master Plan Update
Study - AKM Consulting - (p. 109) - $632.776 - FY06/07
Sewer Pump Station Improvements - Back Bay, Bran Tract, Diamond,
Harbor Ridge and Polaris
(1) Pre - Design ($34,000) - Civiltec - (p. 124)
(2) Final Design ($200,000) - Consultant
(3) Award
(4) Construction ($1,500,000 - FY 08109).
Sidewalk, Curb and Gutter Replacement and ADA and Median Maintenance
Strips - City -Wide Improvements
(1) Design - In House - (p, 54 & 47)
(2) Award
(3) Construction ($695,600, $101,733 & $200,000)
Slope Repairs
Design - In- House/Leighton - (p. 140) - $100,000
Streetlight Replacement Program
(1) Ongoing slreetlighl replacement program P. 57) ($240,000)
Sunset Ridge Park
Concept Design - EPT Design/Wes Morgan (p. 101) - $150,000
Superior Avenue Median Improvements
(1) Design - ($30,000) - In- houserrCiLA - (p. 58 & 56)
(2) Award
(3) Construction ($376,600, $200.000, $50.000 & $176,000)
Fri 12fol/06
Fri 12/01/06
Mon 10/01/07
Tue 05/13108
Mon 07/07/06
Thu 02/01/07
Thu 02/01/07
Thu 04/26/07
Tue 09122/09
Mon 11/02/09
Mon 09/03/07
Mon 09/03107
Tue 02/26/08
Tue 04 /01!08
Tue 07104/06
Tue 07/04/06
Tue 06/10/08
Wed 10101/08
Thu 06/01!06
Thu 06/01/06
Mon 10/01107
Mon 10101/07
Tue 04/08 /08
Tue 12109/08
Mon 02/02/09
Sat 09101/07
Sat 09/01/07
Tue 02112108
Mon 03110/08
Thu 11101/07
Thu 11/01/07
Mon 07102107
Mon 07/02/07
Wed OOM1107
Wed D8/01/07
Mon 03/12/07
Mon 03/12107
Tue D9/25/07
Mon 10/08/07
Fri 11121=
Thu 05/24/07
Thu 03/13/08
Tue 05/13/08
Fn 11121/08
Fri 03/19110
Wed D4/25/07
Mon D6 /01109
Tue 09/22/09
Fit 03/19/10
Mon 08/04106
Thu 12/13/07
Tue 02/26108
Mon 06/04/08
Tue 03/17/09
Thu 05/29108
Tue 0 6/10 1D8
Tue 03/17/09
Mon 06/02/08
Mon 06/02/08
Fri 08/28/09
Thu 02/28/06
Mon 11/03/08
Tue 12/09/06
Fit 08/2a(09
Fri 08/29105
Fri 01/11/08
Tue 02/12/08
Fri 08/29/08
Tue 01027108
Tue 05/27/08
Mon 06/30106
Mon 06/30108
Fri 05102101)
Fri 05/02/08
Thu 03/06108
Fri 07/06/07
Tue 09/25/07
Thu 03/06/08
Militia
-
♦-.05 -
74
76
78
77
53
54
65
56
j
57
159
160
12
1862
133
j Own
- -
-
-
12
L—
- .09/25
134
135
136
163
164
174
175
176
177
178
90
91
92
93
89
70
350
381
165
188
199
194
195
198
Tue 02/05/08
Page 10
FY 2007 -08 MASTER PRO
SCHEDULE - 3rd Quarter
ID
Task Name
Superior Avenue Street Rehabilitation
(1) Design - In House - (p. 59)
(2) Caltrans Processing
(3) Award
(4) Construction ($641,000 & $400,000)
Tennis Court Fencing Replacement - West Newport Park
(1) Design - Recreation Dept./in House - (p. 102)
(2) Award
(3) Construction ($130,000)
Traffic Signal Modernization Ph. 1 - Newport Center
(1) Design - Iteris - (p. 70)
(2) Award - ($1,071,685)
(3) Construction ($335.000, $59,400, $200,000 & $477,285)
Traffic Signal Modernization Ph. 2 - Jamboree Road
(1)Design- Consultant -(p. 71)
(2) Award
(3) Construction ($750,000 8 $300,000)
Traffic Signal Modernization Ph. 3 - Airport Area
(1) Design - Consultant - (p. 72) - ($150,000 & $100.000)
(2) Award
(3) Construction (Not Funded - FY 08/09)
Traffic Signal Replacement Program
(1) Design - Consultant - (p. 74)
(2) Award
(3) Construction ($251,800 & $240,000)
Upper Bay Comprehensive Resource Management Plan
Roger Mallett/Dave Klff - ($120,000)
Via Lido Crib Wall Replacement, 36th Street at Finley Bulkhead Repairs,
Rivo Alto Coping Repairs & 26th Street Tidal Structure and Bulkhead
(1) Design - In House - (P. 60 and P. 22, 52. & 21)
(2) Award - ($79200, $280000) John. S. Q, Meek Co 0 & $389.000)
(3) Construction - ($836,000) -John. S. Meek Company
Water Master Plan Update
Study - In- House/Consultant - (Not Funded)
Water Well Rehabilitation - Dolphin Deep
(1) Design - Richard Slade and Associates - (p. 121)
(2) Award
(3) Construction ($150,000)
Weal Coast Highway Vision Plan
Study - Consultant - (p. 76) - $80,000
Start
Fri 12101/06
Fri 12101106
Mon 05/04107
Tue 01/06/08
Mon 02/04108
Tue 05/01 /07
Tue 05/01/07
Tue 01/08/08
Mon 02104/08
Thu 02101107
Thu 02/01/07
Tue 02/26/08
Tue 04101108
Thu 11 /01/07
Thu 11101/07
Tue 07108/08
Mon 09/08/08
Mon 03103/00
Mon 03/03/08
Tue 01/27109
Mon 03/02109
Tue 01/01/08
Tue 01101 108
Tue 06110/08
Mon 08/04/08
Mon 10/01 /07
Mon 10/01/07
Mon 05102/05
Mon 05102105
Tue 09/11/07
Thu 11/01107
Mon 12/03/07
Mon 12103107
Wed 08/01 /07
Wed 08101107
Tue 12/11/07
Mon 12/17/07
Tue 01 /01/06
Tue 01/01108
Finish
Fri 06/20108
Mon 05121/07
Thu 10/18/07
Tue 01/06/08
Fri 06/20/08
Tue 04/O M
Fd 11/23/07
Tue 01/08/08
Tue 04/08/08
Mon 09/15/08
Mon 12131/07
Tue 02/26108
Mon 09/15/08,
Fri 02/20/09
Tue 05127108
Tue 07100/08
Fri 02/2DO9
Fri 07017109
Fri 12/05/08
Tue 01/27/09
Fri 07/17/09
Fri 12/19106
Mon 04/14/08
Tue 06/10/08
Fri 12/19/08
Tue 07 /01/08
Tue 07/01/08
Tue 07101/08
Fn 08103 107
Tue 09/11/07
Tue 07/01108
Fri 10/10/09
Fri 10/10/08
Tue 02/26,106
Mon 11/12/07
Tue 12/11/07
Tue 02/26/08
Mon 06119/08
Mon 05/19/08
2008
J J A S 1 O 1 N D
J F M A M J J A S O N D
197
_
,10
-
-
_ - " "-
i
- -�
_
12/11 [
198
199
200
201
259
260
261
262
306
307
306
309
310
311
312
313
314
315
316
317
302
303
304
306
16
17
61
62
63
84
172
173
165
156
157
168
170
171
Tue 02/05/08
Page 11
FY 2007 -08 MASTER PRO
SCHEDULE - 3rd Quarter
ID
Task a
Start
Finish
i zoos
-J J A S O N D J F M A M J J A S O N D
283
West Newport Park ® Orange Street and Newport Island Playground
Thu 11/01/07
Tue 06!24108
Equipment
264
(1) Design - In House/Sew Levin- (p. 103)
Thu 11/01/07
Tue 02/12/08
265
(2) Award
Tue 04 /08/08
Tue 04/08/08 8:
288
(3) Construction ($32,000, $80,000 & $80,000)
Mon 05/05/08
Tue 08/24108 -
189
WeatcliH Street Light Improvements (ON -HOLD)
Mon 06/02/08
Fri 03/20109
190
(1) Design JMDtaz - (30,000) - (p. 84 & 57)
Mon 06/02/08
Fri 07/11/08
191
(2) Award
Tue 09/09/08
Tue 09/09/08
192
(3) Construction ($353,500 - Additional Funding Required) -
Mon 11103/08
Fri 03/20/09
Tue 02/05/08
Page 12