HomeMy WebLinkAbout13 - Mariners Park Restroom ConstructionCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 13
May 13, 2008
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Frank Tran
949 - 644 -3340 or ftran @ city.newport- beach.ca.us
SUBJECT: Mariners Park Restroom Construction - Award of Contract No. 3992
Recommendations:
1. Approve the project plans and specifications.
2. Award Contract No. 3992 to Nile Advanced Construction, Inc., for the Total Bid
Price of $543,000, and authorize the Mayor and the City Clerk to execute the
contract.
3. Establish $54,300 to cover the cost of unforeseen construction work.
4. Establish an amount of $42,500 for supplemental expenses including $15,000 to
cover an early completion incentive, $22,500 for geotechnical and material
testing services, and $5,000 for building inspection and miscellaneous expenses.
5. Approve a budget amendment transferring $639,800 from unappropriated
General Fund balance into Account Number 7015- C5100909.
Discussion:
At 11:00 a.m. on April 22, 2008, the City Clerk opened and read the following bids:
BIDDER
Low Nile Advanced Construction, Inc.
2 Hondo Engineering Contractors
3 Delt Builders
4 Tei -Tech Construction, Inc.
5 Hanan Construction Company, Inc.
6 General Consolidated Contractors
7 MJ Contractors, Inc.
8 Horizons Construction Co. International, Inc.
9 Coppertop Enterprises, Inc.
10 Burge Corporation
11 Metro Builders
12 Newman Midland Corp.
13 Omari Construction Co.
TOTAL BID AMOUNT
$543,000.00
$596,610.00
$602,500.00
$618,926.00
$646,000.00
$647,000.00
$655,000.00
$657,662.00
$679,612.58
$685,000.00
$689,524.00
$695,890.00
$834,260.00
*
**
* Corrected Bid Amount is $695,898
** Corrected Bid Amount is $721,500
Mariners Park Restroom Construction —Award of Contract No. 3992
May 13, 2008
Page: 2
The low total bid amount is approximately 22 percent below the Engineer's Estimate of
$700,000. The low bidder, Nile Advanced Construction, Inc. (Nile), possesses a California
State Classification "B" Contractors License as required by the project specifications. A
check of the Contractor's references indicates Nile has satisfactorily completed building
projects for other agencies.
The project specifications provide sixty consecutive working days for Nile to complete
the work. In an effort to minimize construction noise and impacts to Mariners
Elementary School while school is in session, contract provisions allow for extended
work hours (5:00 pm to 6:00 pm.weekdays and 8:00 am to 6:00 pm Saturdays) if special
permission from the Engineer is first obtained. The specifications also provide for an
early completion incentive of $1,000 for each working day that Nile finishes the project
ahead of the August 29, 2008 project completion date. The maximum early completion
incentive amount that could be earned is $15,000. If work continues beyond the
allowed sixty working days, Nile will be assessed liquidated damages in the amount of
$1,000 for each calendar day of late completion.
During the Mariners Park Improvement project, the outdated restroom building was
removed. Since that time, the park has been served by rented portable sanitary
facilities. Funding for constructing this new restroom building was not included in the
Fiscal Year 2007 -2008 Capital Improvement Program budget. The new replacement
restroom building will have the same floor plan and appearance as those constructed
for the Bonita Sports Park. It measures approximately 1,1.00 square feet and is sized
for the expected number of visitors at the park.
Environmental Review:
The project was determined to be exempt from the California Environmental Quality Act
(CEQA) pursuant to. Section 15302 (Replacement or Reconstruction) of the CEQA
Implementation Guidelines. This Exemption Covers the replacement or reconstruction
of existing structures and facilities where the new structure will be located on the same
site as the structure replaced and will have substantially the same purpose and capacity
as the structure replaced,
A Notice of Exemption has been filed with the County of Orange and the State
Clearinghouse.
Public Notice:
The Notice Inviting Bids was advertised in the City's official publication and in
construction industry publications. Prior to starting work, two City prepared notices will
be distributed by the Contractor to both residents and businesses. The first notice will
be distributed ten days before work in the area and the second notice 48 hours prior to
starting work in the area.
Mariners Park Restroom Construction —Award of Contract No. 3992
May 13, 2008
Page: 3
Geotechnical and Material Testing Services:
An estimated $22,500 in geotechnical and material testing services will be needed for
this project. These tasks will be performed under an on -call professional services
agreement with Leighton Geotechnical.
Building Inspection and Miscellaneous Expenses:
An estimated $5,000 for building inspection and miscellaneous expenses will be needed
for this project. Building Inspection will be provided using on -call inspections services
agreement. Architectural construction services will be provided by Ron Yeo for this
project per a previously executed contract.
Funding Availability:
Upon approval of the recommended budget amendment, sufficient funds will be
available in the following account for the project:
Account Description
Account Number
Amount
Mariners Park Improvements - Restrooms 7015- C5100909 $
639,800
Total: $
639,800
Proposed uses are as follows:
Vendor
Purpose
Amount
Nile Advanced Construction, Inc.
Construction Contract
$
543,000
Nile Advanced Construction, Inc.
Construction Contingency
$
54,300
Nile Advance Construction, Inc.
Early Completion Incentive
$
15,000
Leighton Geotechnical
Materials Testing
$
22,500
Various
Building Inspection / Misc.
$
5,000
Expenses
Total:
$
639,800
Prepared by: Submitted by:
7� r T. Tran e . Badum
A ciate Civil Engineer P li orks Director
Attachments: Project Location Map
Budget Amendment
City of Newport Beach NO. BA- 08BA -068
BUDGET AMENDMENT
2007 -08
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates
X Increase Expenditure Appropriations AND
Transfer Budget Appropriations
SOURCE:
from existing budget appropriations
from additional estimated revenues
PX from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
AMOUNT: 8639,800.00
Increase in Budgetary Fund Balance
X Decrease in Budgetary Fund Balance
No effect on Budgetary Fund Balance
To increase expenditure appropriations from unappropriated General Fund fund balance for the Mariners Park Restroom
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Account
Description
010 3605
General Fund - Fund Balance
REVENUE ESTIMATES (3601)
7015 General Fund Capital - Parks
Fund /Division Account
Description
EXPENDITURE APPROPRIATIONS (3603)
Signed
Signed:
r
Approval: Administro} a Services Director
Manager
Amount
Debit Credit
$639,800.00
Automatic
$639,800.00
3-- 6 --GB
Date
_ to o
Signed:
City Council Approval: City Clerk Date
Description
Division
Number
7015 General Fund Capital - Parks
Account
Number
C5100909 Mariners Park Restrooms
Division
Number
Account
Number
Division
Number
Account
Number
Division
Number
Account
Number
Signed
Signed:
r
Approval: Administro} a Services Director
Manager
Amount
Debit Credit
$639,800.00
Automatic
$639,800.00
3-- 6 --GB