HomeMy WebLinkAbout07 - Corporation Yard Building G RepairsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 7 May 27, 2008 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Tom Sandefur 949 -644 -3312 or tandefur @city.newport- beach.ca.us SUBJECT: Corporation Yard Building G Roof Repairs —Award of Contract No. 3966 Recommendations: 1. Approve the project plans and specifications. 2. Award Contract No. 3966 to Pre -Fab Builders, Inc. for the Total Bid Price of $118,592 and authorize the Mayor and the City Clerk to execute the contract. 3. Establish an amount of $11,850 to cover the cost of unforeseen work. 4. Approve a Budget Amendment transferring $30,000 from Account No. 7013 - 051000019 (Streets, Bikeways and Parking Lot Improvements) to Account No. 7011- C1002002 (Corporation Yard Building G Repair and Rehabilitation). Discussion: At 10:00 a.m. on April 30, 2008 the City Clerk opened and read the following bids for this project: BIDDER TOTAL BID AMOUNT Low Pre -Fab Builders, Inc. $118,592.00 2 Copper To Enterprises $123,623.40 " Corrected Bid Amount The low total bid amount is 7.8 percent above the Engineers Estimate of $110,000. The higher bids were the result of a larger than expected cost to clean and paint the existing metal members. The low bidder, Pre -Fab Builders, possesses a California State Contractors License Classification C -51 as required by the project specifications. A check of the Contractors references indicates they have satisfactorily completed similar projects for other municipalities. The project will replace existing roof members that, due to the exposure to the harsh marine air, have become severely corroded. The project will also remove deteriorated gutter and flashing, paint all exposed roof members and install bird netting under roof. Corporation Yard Building G Roof Repair — Award of Contract No. 3966 May 27, 2008 Page: 2 Pursuant to the Contract Specifications, the Contractor will have 45 consecutive working days to complete the work. Environmental Review: The project was determined to. be exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Implementing Guidelines at the time the project was authorized by the City Council. This exemption covers the repair, maintenance and minor alteration of existing public facilities with negligible expansion. Public Notice: The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Geotechnical, Material Testing, and Survey Services: Geotechnical, material testing, and survey services are not anticipated for this project. Funding Availability: The transfer detailed in the attached Budget Amendment is from a cost savings on a project completed earlier in this year. Upon approval of the recommended Budget Amendment, sufficient funds will be available in the following accounts for the project: Account Description General Fund Proposed uses are as follows: Vendor Pre -Fab Builders, Inc. Pre -Fab Builders, Inc. Prepared by: Tom Sandefur Associate Civil Engineer Attachments: Project Location Map Budget Amendment Account Number 7011- C1002002 Total: Purpose Construction Contract Construction Contingency Total: Submitted by: Amount $ 130,442 $ 130,442 Amount $ 118,592 $ 11,850 $ 130,442 um Works Director LOCATION MAP CORPORATION YARD BUILDING "G" ROOF REHABILITATION CONTRACT NO. 3966 City of Newport Beach NO. BA- 08BA -071 BUDGET AMENDMENT 2007 -08 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates Increase Expenditure Appropriations AND fJ Transfer Budget Appropriations SOURCE: from existing budget appropriations from additional estimated revenues from unappropriated fund balance EXPLANATION: This budget amendment is requested to provide for the following: AMOUNT: 830,000.00 Increase in Budgetary Fund Balance Decrease in Budgetary Fund Balance qX No effect on Budgetary Fund Balance To transfer expenditure appropriations from the Street Bikeways, and Parking Lot Improvement project to the Corporation Yard Building G Repair and Rehab project for roof repairs. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account Description REVENUE ESTIMATES (3609) Fund /Division Account Description EXPENDITURE APPROPRIATIONS (3603) Amount Debit Credit $30,000.00 $30,000.00 S— /3 - U Date Da Date Description Division Number 7013 General Fund - Capital Street Projects Account Number C5100019 Streets, Bikeways, & Parking Lot Imprvmts Division Number 7011 General Fund - Capital Facilities Projects Account Number C1002002 Corp Yard Bldg G Repair & Rehab Division Number Account Number Division Number Account Number p C.-- Signed: 4C fir Financial Approval: Administ ive Services Director Signed: . Administrative Ap val: City Manager Signed: City Council Approval: City Clerk Amount Debit Credit $30,000.00 $30,000.00 S— /3 - U Date Da Date