Background
Water Master Plan identified the need to replace existing
cast iron water mains.
The existing 20 -inch cast iron transmission water main in
Newport Boulevard was installed in the 1920's
New 24 -inch steel transmission water main will:
Z. Improve operation and service reliability
2. Increase fire flow
3. Reduce potential of major water pipeline breaks associated
with old cast iron mains.
Proposed 24 -inch Pipeline Alignment
Via Oporto to 28th Street
1_ '':& a a W; W'19=1 . -P
Nli ,
Proposed 16 -inch Pipeline Alignment
A
4
a r�
26th Street to 19th Street
4 4 +
4 _
! V
f f •
Ak
Project Schedule
Award Contract
Contractor Preparation/ Pipe Order
Construction Start
Construction Complete
May 12, 2015
May - Sept.
Sept. 2015
May 2016
2015
Recommendations
Approve the project plans and specifications
Award contract No. 5481 to low bidder T.E. Roberts, Inc.
for total bid price of $3,511,515
Establish contingency amount of $350,000 (10 %)
Approve Budget Amendment appropriating $260,000
from Water Enterprise Fund
0�