Loading...
HomeMy WebLinkAbout06 - Ocean Pier RepairsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 6 August 12, 2008 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Stephen Luy, Associate Civil Engineer 949 - 644 -3330 or sluy @city.newport - beach.ca.us SUBJECT: OCEAN PIER REPAIRS - Award of Contract No. 3973 Recommendations: 1. Approve the project drawings and specifications. 2. Award Contract No. 3973 to AIS Construction Co. for the Total Bid Price of $659,445.02, and authorize the Mayor and the City Clerk to execute the contract. 3. Establish an amount of $66,000 (10 %) to cover the cost of unforeseen work. 4. Approve a budget amendment transferring $47,500 from unappropriated Tidelands Fund balance to 7231- C4801001 (Ocean Pier Repairs) Discussion: At 11:00 a.m. on July 23, 2008 the City Clerk opened and read the following three bids for this project: BIDDER TOTAL BID AMOUNT Low AIS Construction Co. $659,445.02 2 John S. Meek Company, Inc. 679,790.00 3 American Marine Corp. 1,310,035.00 The low total bid amount is 20 percent above the Engineer's Estimate of $528,000.00 The disparity between the estimate and the actual bid prices may reflect the current volitility in the oil industry since many of the products used in the pier repair are petroleum based, as well as the special nature of the work and the limited availablity of skilled contractors qualified in this type of work. The low bidder, AIS Construction Co. (AIS), possesses a California State Contractors License Classification "A" as required by the project specifications. As part of staff's reference check, staff has had phone conversations with the president of AIS and the Ocean Pier repairs — Award of Contract No. 3973 August 12, 2008 Page: 2 company's listed references. All references (Vandenberg Air Force Base Boat Harbor, Presido Land Trust, Army Corp of Engineers, and Long Beach Unified School District) indicated the Contractor has satisfactorily completed marine -type projects for them. Over its twelve year history, AIS has limited direct ocean pier rehabilitation work experience. However, AIS has done substantial marine related work including dolphin repair and rehabilitation, structural steel repair at or below water level, recoating of dolphins, repair and fabrication of a new fendering system, pile repair and replacement, dredging projects, and gabion construction projects. Additionally, the contractor and his employees proposed for this project have direct pier and related rehabilitation work experience under past employers. The Ocean Pier Repair project has a budget of $680,000. Bids for the project came in higher than budgeted funds. To cover the shortfall, staff recommends transferring $47,500 from the unappropriated Tidelands Fund balance. The proposed work consists of replacing deteriorated and or missing cross bracing, stringers, cross bridging, hardware, etc; removing and replacing damaged /deteriorated portions of piles, wrapping existing piles and repairing previous pile wraps; installing fiberglass jackets, reinforcement and epoxy grout to stabilize /repair pier pilings; installing trowelable epoxy to fill voids and fix cracks in existing structural members of the pier; and performing all related work as required to complete the contract. Pursuant to the Contract Specifications, the Contractor will have 60 consecutive working days to complete the work. Environmental Review: This project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Guidelines. This exemption covers the repair of existing facilities involving negligible or no expansion of existing use. Public Notice: The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Funding Availability: Sufficient funds will be available in the following accounts for the project. Account Description Account Number Amount Tide and Submerged Lands 7231- C4801001 $ 680,000.00 Budget Amendment 7231- C4801001 47,500.00 Total: $ 727,500.00 Proposed uses are as follows: Vendor AIS Construction Co. AIS Construction Co. Various Prepared by: -/?�7 -�/ 4 Stephe Luy Associate Civil Engineer Attachments: Project Location Map Ocean Pier repairs — Award of Contract No. 3973 August 12, 2008 Page: 3 Purpose Construction Contract Construction Contingency Printing and Incidentals Total: Submitted by: Amount $ 659,445.02 $ 66,000.00 $ 2,054.98 $ 727,500.00 KG. Badum Works Director I �1 NEWPORT PIER BALBOA PIER C-3973 OCEAN PIER REPAIRS 08 -09 e'�df City of Newport Beach NO. BA- 09BA -006 BUDGET AMENDMENT 2008 -09 AMOUNT: $a7,soo.00 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates Increase in Budgetary Fund Balance X Increase Expenditure Appropriations AND Decrease in Budgetary Fund Balance Transfer Budget Appropriations. No effect on Budgetary Fund Balance SOURCE: from existing budget appropriations from additional estimated revenues PX from unappropriated fund balance EXPLANATION: This budget amendment is requested to provide for the following: To increase expenditure appropriations from Tidelands Fund unappropriated fund balance to the Ocean Pier Repairs account to enter into an agreement with AIS Construction. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account Description 230 3605 General Fund - Fund Balance REVENUE ESTIMATES (3601) Fund /Division Account Description EXPENDITURE APPROPRIATIONS (3603) Description Division Number 7231 Tidelands - Capital Account Number C4801001 Ocean Pier Repair /Inspection Signed: Signed: Signed Approval: Administrative $(pproval: City Manager Director Amount Debit Credit $47.500.00 " Automatic $47.500.00 Date b� v5 e D City Council Approval: City Clerk Date