HomeMy WebLinkAbout16 - Hyatt Regency Environmental Impact ReportCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 16
October 14. 2008
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Planning Department
Jaime Murillo, Associate Planner
(949) 644 -3209, 0 m u rillo(cD city. newport-beach. ca. us
SUBJECT: Contract for Environmental Consulting Services
Hyatt Regency Environmental Impact Report (EIR)
APPLICANT: Sunstone Hotel Investors, Inc.
ISSUE
In accordance with Council Policy F -14 (Authority to Contract for Services), the City
Manager shall provide notice of a permit application and a brief description of the
proposed project to the City Council when a contract for professional services is paid for
by funds in an applicant deposit account and the total cost for services exceeds
$100,000.
RECOMMENDATION
Receive and File.
This report is intended to provide notice to the City Council of a contract for professional
services between the City of Newport Beach and The Planning Center for the
preparation of an Environmental Impact Report (EIR) associated with a project to
expand the existing Hyatt Regency Hotel at 1107 Jamboree Road. The current contract
is in the amount of $190,070.00, which was paid for by the project applicant ( Sunstone
Hotel Investors, Inc.); however, the scope of work has been expanded to include
additional analysis required for additional work beyond the approved scope of work to
complete the Final EIR. The approved scope of work assumed a minimal level of
response to comments on the Draft EIR and two weeks preparation for the Final EIR;
however, numerous lengthy comment letters were received on the Draft EIR, including
substantive comments that required additional research, and substantial discussion and
coordination with the project team to develop responses. Preparation of the Final EIR
October 14, 2008
Page 2
will also require revisions to the Draft EIR and preparation of additional exhibits. The
estimated budget to Complete this additional analysis is $46,520.00, resulting in a total
contract amount of $236,590.00. The applicant has been notified of the amended
contract amount and has agreed to fund the amount.
The project includes the addition of 88 timeshare units, an expanded 11,032 square -foot
ballroom, a 10,072 square -foot spa and new pool, and a new two -level parking garage.
Implementation will require demolition of 12 existing hotel rooms and the Terrace
Ballroom and removal of a nine -hole golf course. The expansion will require the
following approvals from the City:
• A parcel map to reconfigure two existing lots, allowing the timeshares to remain
on one parcel and the hotel on the other, and to establish finished grades for the
purposes of measuring height.
• A use permit to allow the expansion of the existing hotel and establishment of a
timeshare development. A use permit is also required to allow the proposed
timeshare buildings and ballroom to exceed the 26 -foot base height limit.
• A modification permit to allow commercial tandem parking and to allow the
architectural tower and finial element of the proposed ballroom to exceed the 35-
foot maximum height limit.
• A development agreement between the City and the operator of the timeshare
development relating to the amount of tax payable to the City for the right of
occupancy of the timeshare units.
• Certification of an Environmental Impact Report
The Final EIR is currently under preparation and will consist of the circulated Draft EIR,
the response to comments on the Draft EIR, and revisions to the Draft EIR. An October
23, 2008 Planning Commission hearing is tentatively scheduled for review of the project
and EIR.
Prepared by: Submitted by:
V_e�z. Z44_�
daime Murillo, Associate Planner omer Bludau ity anager
F :IUSERSIPLN\Shared\Professional Services Agreements & Contracts*iyaR - Planning CenterUiyatt Council Report 3.doC
THE
PLANNING
CENTER
August 18, 2008
Governmental Services
Planning & Urban Design
Environmental Studies
School Facilities Planning
1580 Metro Drive
Costa Mesa, CA 92626
Mr. Jaime Murillo, Associate Planner Plrone: 714.966.9220
City of Newport Beach
3300 Newport Boulevard Fav 714.966.9221
Newport Beach, CA 92658
�^1P cosmmesa@pJanningcenter.com
Subject: Request for Contract Amendment No. 3 for Environmental Services for
the Hyatt Regency Newport Beach Project (CNB -09.OE) (As updated September 24, 2008)
Dear Mr. Murillo:
This letter is to request Contract Amendment No. 3 for The Planning Center's environmental services for
the Hyatt Regency Newport Beach Project. Our last contract amendment (December 2007) addressed
additional work required to revised the Screencheck EIR prior to its release as a Draft EIR. This
amendment is required for additional effort beyond the approved scope of work to complete the Final
EIR, including extended meeting attendance to coordinate that effort. This amendment also includes
additional effort for IBI to respond to operations and construction- related traffic comments received on
the Draft EIR.
As summarized in Table 1, Cost Estimate, our existing contract as previously amended for this project is
for a total of $190,070, including subconsultants and reimbursables. To complete the processing of this
project, we are requesting $42,820 in additional labor fees for The Planning Center and $3,700 in fees for
IBI. No additional reimbursable costs are requested. Total contract amount upon approval of this
amendment will be $236,590, including subconsultants and reimbursables.
THE PLANNING CENTER
SCOPE OF WORK
Task 1: Initial Study/Notice of Preparation
This task has been completed and there are no changes.
Task 2: Public Scoping Meeting
Subsequent to contract execution, the City decided that a public scoping meeting would not be
necessary for the project. The budget for this task was subtracted in Contract Amendment No. 1.
Task 3: Screencheck Draft EIR
This task has been completed and there are no changes.
3
Mr. Jaime Murlllo, City of Newport Beach
August 18, 2008
Page 2 of 5
Task 4: Draft EIR
This task has been completed and there are no changes.
Task 5: Final EIR /Response to Comments
The original contract assumed a minimal level of comment on the Draft EIR and two weeks preparation
time for the Final EIR. Numerous lengthy comment letters were received on the Draft EIR, including
substantive comments that required additional research, and substantial discussion and coordination
with the project team to develop responses. Preparation of the Screencheck Final EIR has also required
revisions to the Draft EIR and preparation of additional EIR exhibits. Incoordination with the City and
applicant project team, the preparation of the Final EIR (to date) has taken approximately 20 weeks to
complete and review per team review comments. Preparation also includes incorporating revisions to
the project description relative to landscaping and fuel- modification plans to address fire department
requirements. Supplemental detail has been provided by the team and incorporated into the Final EIR,
including lighting plans, updated BMPs, fuel modification, visual simulations, grading plan detail, and
hydrology/ loodplain information.
Additional work required for IBI to assist The Planning Center in preparing Response to Comments for
the Final EIR is detailed below under Subconsultants.
Task 6: Mitigation Monitoring Program
This task has not been initiated and we are not recommending any changes.
Task 7: Findings of Fact and Statement of Overriding Considerations
This task has not been initiated and we are not recommending any changes.
Task 8: Public Hearings /Meetings
As included in our Contract Amendment No. 2 scope of work (November 8, 2007), our remaining scope
included attendance at up to one additional meeting and up to four public hearings by our project
manager. We have attended the following meetings subsequent to the last contract amendment:
Date Meeting Purpose
12/21/07 Meeting at City to review SCEIR team comments (3.5 hours.
TPC attendees: JoAnn Hadfield and Jorge Estrada)
4/7/08 Meeting at City to review DEIR comments (5 hours. TPC
attendee: JoAnn Hadfield)
7/22/08 Meeting at City to review Screencheck Final EIR (3 hours. TPC
attendees: JoAnn Hadfield and Azurde Harris)
In addition to the additional time required for these meetings, the cost estimate for this contract
amendment assumes that Nicole Vermillion from our staff will attend the public hearings with JoAnn
Hadfield to address potential air quality, noise, and /or climate change questions on the project.
Mr. Jaime Murlllo, City of Newport Beach
August 18, 2008
Page 3 of 5
Task 9: Notice of Determination
This task has not been initiated and we are not recommending any changes.
Task 10: Project Management and Coordination
As noted above, the schedule for preparation of the Final EIR was extended substantially beyond the
schedule assumed in our scope of work, as amended through Contract Amendment No. 2. Our cost
estimate for this task was based on the submittal of the SCEIR by the end of November 2007 and the
assumed timeframes in the original proposal for Draft EIR public circulation and preparation of the Final
EIR. Based on these assumptions, the Final EIR would be completed 13 weeks from the start of the
public review period. Assuming completion of the Final EIR by the end of August, this task will have
taken 22 weeks since the close of the public review period. Additional fees for project management and
coordination have been based on an estimated 2 hours/week for the additional 9 weeks, in comparison
to the contract as approved to date.
IBI
The following additional scope of work for IBI is based on revisions to their original scope of work as
presented in Appendix B of our February 2006 proposal and amended under Contract No. 1.
TASK 1: Project Definition
No additional work efforts are assumed under Task 1.
TASK 2: Existing Conditions
No additional work efforts are assumed under Task 2.
TASK 3: Future Traffic Conditions • TPO Analysis
No additional work efforts are assumed under Task 3.
TASK 4: Future Traffic Conditions - CEQA Analysis
No additional work efforts are assumed under Task 4.
TASK 5: Review of Applicant Parking Study
IBI groups was requested to pdate the project parking demand analysis to include a revised size for the
existing banquest/meeting facilities. The parking demand update will also include the incorporation of a
non-captive user ratio into the parking demand analysis and updates to the traffic study report.
TASK 6: Response to Environmental Impact Report Comments
Comments received from Caltrans District 12 on the Draft Environmental Impact Report request the
analysis of the Pacific Coast Highway /Dover Drive and Pacific Coast Highway/Bayside Drive intersections
using the Highway Capacity Methodology (HCM). The City of Newport Beach authorized this analysis in
May 2008. The completion of new analysis goes beyond the anticipated scope and budget for this task,
which had assumed only the preparation of responses to comments, not new traffic analysis. The budget
augment is request to cover the work efforts necessary to complete this analysis.
0
S
Mr. Jaime Murlllo, City of Newport Beach
August 18, 2008
Page 4 of 5
TASK 7: Meetings
No additional work efforts are assumed under Task 7 beyond what current remains in our approved
budget.
TASK B: Future Traffic Conditions - Construction Analysis
The traffic analysis for this task will be revised to assume that all construction trips take access to the site
from Back Bay Drive. These revisions will require changes to the construction traffic analysis report,
figures, and intersection level of service worksheets.
SUMMARY COST ESTIMATEAND SCHEDULE
Attached Table 1 summarizes the previously approved contract and requested Contract Amendment No.
3 by task and consultant. This contract amendment request is for a total of $42,820 for The Planning
Center labor and $3,700 for IBI labor. No additional reimbursable costs are requested. Approval of this
3rd Contract Amendment would bring the total contract amount to $236,590 for the Hyatt Regency
Newport EIR. For purposes of planning and budgeting, it is assumed that the final landscaping plans
and view simulations due from the project applicant will be available to The Planning Center August
2008, and that the revised Final EIR will be submitted to the City prior to the end of the month (August
2008). Public hearing attendance is assumed to be completed prior to November 2008.
We look forward to working with the City and the Hyatt consultant team to successfully complete this
project. Please contact me with any questions you may have regarding this contract amendment �-
request. 4
Sincerely,
THE PLANNING CENTER
JoAnn Hadfield
Director, Environmental Services
Attachment
3
Mr. Jaime Murlllo, City of Newport Beach
August 18, 2008
Page 5 of 5
Table 1
The Planning Center
COST SUMMARY
Requested
Total Approved Contract
Original Contract Contract Contract through Amendment
Task Contract Amendment # 1 Amendment # 2 12/2007 # 3 Total
Task 1. Initial Stud /NOP
$4,250
$0
$0
1 $4,250
$0
$4,250
Task 2. Public Scoping Meeting
2,640
-2,640
0
0
0
0
Task 3. Screencheck Draft EIR
46,020
16,800
17,020
79,840
0
79,840
Task 4. Draft EIR
6,450
0
0
6,450
0
6,450
Task 5. Final EIR/Response to Comments
9,200
0
0
9,200
33,775
42,975
Task 6. Mitigation Monitoring Program
750
0
0
750
0
750
Task 7. Statement of Findings /Statement of Overriding
Considerations
1,400
0
0
1,400
0
1,400
Task 8. Hearings/Meetings
3,960
4,200
0
8,160 1
2,925
1 11,085
Task 9. Notice of Determination
200 1
0
1 0
1 200 1
0
1 200
01 0