HomeMy WebLinkAbout08 - Industrial Way 36-inch Water Main ReplacementCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 8
October 14, 2008
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Tom Sandefur, Associate Civil Engineer
949 -644 -3312 or tandefur @city.newport- beach.ca.us
SUBJECT: INDUSTRIAL WAY 36 -INCH WATER MAIN REPLACEMENT —
COMPLETION AND ACCEPTANCE OF CONTRACT NO. C -3728
Recommendations:
1. Accept the completed work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the Labor and Materials bond 35 days after
the Notice of Completion has been recorded in accordance with applicable
portions of the Civil Code.
4. Release the Faithful Performance Bond 1 year after Council acceptance.
Discussion:
On May 8, 2007, the City Council authorized the award the Industrial Way 36 -Inch
Water Main Replacement Project to SJ &B Group, Inc. The contract provided for the
construction of a 36 -Inch water main to replace an ageing and undersized water main,
Water facilities within 16`" Street and Industrial Way were targeted to be replaced due
to their age and a need for increased capacity as part of the Water Master Plan. The
existing 14 -inch system was built in 1950 and has outlived its useful life. In addition,
there is an existing 30 -inch transmission main that was built in 1923 and traverses the
General Services yard parallel to Industrial Way. The project replaced the existing 14-
inch and 30 -inch mains with a single main located within the Industrial Way street right -
of -way between Superior Avenue and Old Newport Boulevard /15 "' Street.
During the construction of the project, the City was informed that the contractor, SJ &B
Group, Inc., filed a notice of default with its bonding company Safeco and would be
unable to independently complete the project. The City worked with the bonding
company to rebid the remaining portion of the work which included the installation of the
36 -inch pipe. The bids received by Safeco were significantly above the original bid
price of the remaining bid items. In an effort to expedite the project, the City worked
Industrial Way 36-Inch Water Main Replacement - Completion and Acceptance of Contract No. 3728
October 14. 2008
Page 2
with representatives from Safeco to fund SJ &B Group to finish the project. SJ &B
remobilized and finished the project.
The contract has now been completed to the satisfaction of the Public Works
Department. A summary of the contract cost is as follows:
Original bid amount: $990,285.00
Actual amount of bid items constructed: 869,447.07
Total amount of change orders: 122.096.57
Final contract cost: $991,543.64
The decrease in the amount of actual bid items constructed over the original bid
amount resulted from a reduced scope of paving operations and the removal of a
smaller amount of interfering water line pipe. The final overall construction cost
including Change Orders is .12 percent over the original bid amount.
10 Change Orders in the amount of $122,096.57 were approved on this project. The
Change Orders were as follows:
CO 1 — Additional paving on gate valve and new Air -Vac on Superior Avenue.
CO 2 — Dig out and replace 12 -Inch gate valve
CO 3 — Additional sidewalk, curb and gutter replacement due to realigning pipe. Cost
from pipe manufacturer for redesigning pipe.
CO 4 — Change order rescinded.
CO 5 — Remove, replace thrust block on 18 -inch water line to allow installation of pipe.
CO 6 — Realign sewer laterals around water line and replace damaged curb and gutter.
CO 7 — Removal of slurry surrounding the tie -in. Costs associated with improperly
closing valve requiring Contractor to shut down until City crews were able to get a
proper shut down of the water line.
CO 8 — CALTRANS permit fees and extra slurry around pipe.
CO 9 — Overtime charges to complete the tie -in work over the weekend so as to not
impact area residents and businesses during the week.
CO 10 —Additional traffic loops that were required to be cut in.
All work was substantially completed by August 29, 2008, approximately eight months
past the scheduled completion date of December 28, 2007. Extra time was needed to
complete the project due to a redesign required to avoid unmarked utilities and to
accommodate working with the bonding company as outlined above. The following is a
summary of the project schedule:
Schedule Summary
Estimated Completion date per June "07 Schedule:
Project award for construction: May 8, 2007
Estimated completion date at award: December 28, 2007
Actual completion date: August 29, 2008
Industrial Way 36 -Inch Water Main Replacement - Completion and Acceptance of Contract No. 3728
October 14, 2008
Page 3
Environmental Review:
The project was determined to be exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301 of the CEQA Implementing Guidelines at the time
the project was authorized by the City Council. This exemption covers the repair,
maintenance and minor alteration of existing public facilities with negligible expansion.
Geotechnical /Survey Services:
Geotechnical services were provided by Arroyo Geotechnical pursuant to the City's on-
call agreement. Surveying Services were provided by Bush and Associates, Inc.
pursuant to the City's on -call agreement.
Funding Availability:
In addition to the primary construction contract, this project involved other project
expenses for material testing. Total project expenses are summarized as follows:
Construction
$991,543.64
Design
147,274.91
Materials Testing
27,921.45
Survey
12,647.00
AT &T
2,949.97
Construction Inspection*
4,552.65
Traffic Signal Repair
5,027.18
Incidentals
2,864.50
Total Project Cost
$1,194,781.30
*In addition to the above costs, overttime expenses for city inspection of work performed
outside normal working hours will be charged against this project.
Funds for the construction contract were expended from the following accounts:
Account Description
Water Transmission Main
Master Plan Improvements
Programmed Pipeline
Master Plan Replacement
Prepared by:
Tom Sandefur, P.E.
Associate Civil Engineer
Account Number Amount
7501- C5500386 $847,043.64
7501- C5500578 144,500.00
Total: $991,543.64