HomeMy WebLinkAbout12 - Wastewater Pump Station RehabilitationCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 12
February 9, 2010
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Andy Tran, P. E.
949- 644 -3315 or atran @newportbeachca.gov
SUBJECT: WASTEWATER PUMP STATION REHABILITATION - DIAMOND
AVENUE, BACK BAY DRIVE, BREN TRACT, POLARIS DRIVE, AND
HARBOR RIDGE - AWARD OF CONTRACT NO. 3804
Recommendations:
1. Approve the project plans and specifications.
2. Award Contract No. 3804 to Houalla Enterprises, Ltd. dba Metro Builders and
Engineers Group, Ltd. for the Total Bid Price of $1,994,112, and authorize the
Mayor and the City Clerk to execute the contract.
3. Establish an amount of $200,000 (approximately 10 %) to cover the cost of
unforeseen work.
4. Approve Amendment No. 2 to Professional Services Agreement with Stantec
Consulting California, Inc. for construction observation services for $35,618.
5. Approve a Budget Amendment appropriating $510,000 from the unappropriated
Wastewater Enterprise reserve fund balance to Account No. 7532- C5600100.
Discussion:
At 10:00 a.m. on December 22, 2009, the City Clerk opened and read the following bids
for this project:
Low Metro Builders and Engineers Group, Ltd.
2 MMC, Inc.
3 Orion Construction Corp.
4 GCI Construction, Inc.
5 SCW Contracting
6 Dawson - Mauldin Construction
TOTAL BID AMOUNT
$1,994,112.00
$2,052,000.00
$2,137,500.00
$2,261,900.00
$2,317,362.00
$2,545,800.00
Wastewater Pump Station Rehabilitation — Diamond Avenue, Back Bay Drive, eren Tract, Polaris Drive, and Harbor Ridge
Award of Contract No. 3804
February 9, 2010
Page: 2
7 Mike Bubalo Construction Company, Inc. $2,599,000.00
8 Pascal and Ludwig Contractors $2,922,000.00
9 Griffith Company $2,948,002.00
The low total bid amount is 3.4 percent below the Engineer's Estimate of $2,062,500.00.
The low bidder, Metro Builders and Engineers Group, Ltd., possesses a California State
Contractors License Classification "A" as required by the project specifications. A check of
the Contractors references indicates they have satisfactorily completed similar projects
for other municipalities.
This contract involves rehabilitating four wastewater pump stations and one new
replacement wastewater pump station as identified in the Wastewater Master Plan. The
proposed improvements include on -site redundant electrical power at four of the
stations. These improvements will help reduce the potential of sanitary sewer overflows
and are also needed to comply with the waste discharge requirements set forth by the
State Water Resource Control Board. The contract focuses on electrical improvements
at the Diamond Avenue, Back Bay Drive, Polaris Drive and Harbor Ridge pump
stations. The replacement station is for Bren Tract (Newport Hills Drive West at Ford
Road). Pursuant to the Contract Specifications, the Contractor will have 200
consecutive working days to complete the work. .
Environmental Review
The project was determined to be exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301 of the CEQA Implementing Guidelines. This
exemption covers the repair, maintenance and minor alteration of existing public
facilities with negligible expansion.
Public Notice:
The Notice Inviting Bids was advertised in the City's official publication and in
construction industry publications. Affected residents and businesses will be notified by
the Contractor prior to the start of the project.
Geotechnical and Material Testing Services
In addition to the contract costs, approximately $25,000 in geotechnical and material
testing services is projected to be needed for this project and will be performed under
the on -call professional services agreement with Harrington Geotechnicai Engineering.
Funding Availability:
Funding for this project was originally budgeted at $2.2 million for design and
construction. During the course of design, other needed improvements were identified,
such as back -up emergency power at four of the stations. These additional
Wastewater Pump Station Rehabilitation — Diamond Avenue, Back Bay Drive, Bren Tract, Polaris Drive, and Harbor Ridge
Award of Contract No. 3804
February 9, 2010
Page: 3
improvements resulted in an increase in design and construction cost. In addition,
construction observation services were not included in the Professional Services
Agreement and Amendment No. 1. Therefore, staff is recommending the approval of
Amendment No. 2 with Stantec Consulting California, Inc. in the amount of $35,618 for
construction observation services. Upon approval of the recommended budget
amendment, sufficient funds will be available in the following account:
Account Description
Wastewater Enterprise
Proposed uses are as follows:
Vendor
Metro Builders and Engineers Group
Account Number
7532- C5600100
Total
Purpose
Construction Contract
Metro Builders and Engineers Group Construction Contingency
Harrington Geotechnical Engineering
Prepared by:
Andy T n
Senior Civil Engineer
Material Testing
Total:
Attachment: Project Location Map
Budget Amendment
Amendment No. 2 to PSA with Stantec
Submitted
Amount
$ 2,219,112.00
$ 2,219,112.00
Amount
$ 1,994,112.00
$ 200,000.00
$ 25,000.00
$ 2,219,112.00
Badum
s Director
AMENDMENT NO. TWO TO
PROFESSIONAL SERVICES AGREEMENT WITH
STANTEC CONSULTING CALIFORNIA, INC.
FOR SEWER PUMP STATION MASTER PLAN IMPROVEMENTS
THIS AMENDMENT NO. TWO TO PROFESSIONAL SERVICES AGREEMENT,
is entered into as of this _ day of ' 2010, by and between the CITY
OF NEWPORT BEACH, a Municipal Corporation ( "CITY "), and STANTEC
CONSULTING CALIFORNIA, INC. a California Corporation whose address is 19
Technology Drive, Irvine, California 92618 ( "CONSULTANT'), and is made with
reference to the following:
RECITALS:
A. On October 14, 2008, CITY and CONSULTANT entered into a Professional
Services Agreement, hereinafter referred to as "AGREEMENT," for professional
engineering services for the Sewer Pump Station Master Plan Improvements
Project, hereinafter referred to as "PROJECT."
B. CITY and CONSULTANT have entered into one separate AMENDMENT of the
AGREEMENT, the latest dated October 9, 2009.
C. CITY desires to enter into this AMENDMENT NO. TWO to reflect additional
services not included in the AGREEMENT or prior AMENDMENTS, to extend the
term of the AGREEMENT to December 31, 2011 and to increase the total
compensation.
D. CITY desires to compensate CONSULTANT for additional professional services
needed for PROJECT.
E. CITY and CONSULTANT mutually desire to amend AGREEMENT, hereinafter
referred to as "AMENDMENT NO. TWO," as provided here below.
NOW, THEREFORE, it is mutually agreed by and between the undersigned parties as
follows:
1. TERM
The term of the AGREEMENT shall be extended to December 31, 2011.
2. ADDITIONAL SERVICES TO BE PERFORMED
In addition to the services to be provided pursuant to the AGREEMENT and
AMENDMENT NO. ONE, CONSULTANT shall diligently perform all the services
described in AMENDMENT NO. TWO including, but not limited to, all work set
forth in the Scope of Services attached hereto as Exhibit A and incorporated
herein by reference. The City may elect to delete certain tasks of the Scope of
Services at its sole discretion.
3. COMPENSATION
City shall pay Consultant for the services on a time and expense not -to- exceed
basis in accordance with the provisions of this Section and the Schedule of
Billing Rates attached to the AGREEMENT. Consultant's total amended
compensation for all work performed in accordance with this Agreement,
including all reimbursable items and subconsultant fees, shall not exceed Three
Hundred Eighty -Four Thousand Eight Hundred and Fifty -Seven Dollars and
no /100 ($384,857.00) without prior written authorization from City,
3.1 The amended compensation reflects Consultant's additional
compensation for additional services to be performed in accordance with
this AMENDMENT NO. TWO, including all reimbursable items and
subconsultant fees, in an amount not to exceed Thirty -Five Thousand Six
Hundred and Eighteen Dollars and no /100 ($35,618.00), without prior
written authorization from City.
4. INTEGRATED CONTRACT
Except as expressly modified herein, all other provisions, terms, and covenants
set forth in AGREEMENT shall remain unchanged and shall be in full force and
effect.
2
IN WITNESS WHEREOF, the parties hereto have executed this AMENDMENT NO.
TWO on the date first above written.
APPROVED AS TO FORM:
OFFICE OF THE CITY ATTORNEY
Mynette D. Beauchamp
Assistant City Attorney
A
Leilani I. Brown,
City Clerk
CITY OF NEWPORT BEACH,
A Municipal Corporation
ffin
Keith D. Curry
Mayor
STANTEC CONSULTING
CALIFORNIA, INC.:
(Corporate Officer)
Title:
Print Name:
M
(Financial Officer)
Title:.
Print Name:
Attachments: Exhibit A — Additional Services to be Performed
141
r�
stantec Consulting Inc.
?9 Technology Drive
Irvine CA 92618 -2334
Tel: (949) 923.6000
,�
Fax 1949) 923 -6121
---...._ --
stantec
.....__ .. ....... ......... . __ ....... . ... _ ..—.
January 6, 2010 J.N.2040467900
Mr. Andy Tran, P.E.
Senior Civil Engineer
City of Newport Beach Public Works Department
3300 Newport Blvd
Newport Beach, CA 92663 -3884
Reference: Request for Authorization for Additional Construction Support Services for the (5)
Wastewater Pump Stations Modifications Project- Change Order Request No. 2
Dear Andy,
Stantec is pleased to present the following change order request No. 2 letter proposal for additional construction
support services for the subject wastewater pump stations modifications project.
The City of Newport Beach has requested that Stantec (with support from Dudek) provide the following additional
support services at the direction and request of the City:
• Attend weekly construction meetings (in lieu of bi- weekly meetings) for the first 4 months of the project.
• Provide review and feedback on contractor's 2 -week look -ahead schedule.
• Conduct additional field visits as necessary, and where appropriate, and make field recommendations.
• Provide on -site construction guidance, observation and consultation as needed and requested by the
City.
To perform the above scope of services an additional 200 hours of construction support services time for the (5)
Wastewater Pump Stations for the City of Newport Beach is proposed. These hours are proposed to be split up
accordingly: 160 hours of Neil Harper's (Dudek) time and 40 hours of Bob Seeman's (Stantec) time.
Therefore, we are requesting that our existing contract be increased by $35,618. See attached breakdown. If you
should have any questions, please do not hesitate to call the undersigned directly.
Sincerely,
STANTEC CONSULTING INC,
�R /be. Seeman, P.E.
Senior Project Manager
Tel: (949) 923 -6266
Fax: (949) 923 -6121
bob. seeman @sta n tec. com
c: Mike Sinacori, Newport Beach
V ROJECr 0404B XOW0 300 mnfiCO ReQVeal t consetu'oyort 2DfWf06.COc
City of Newport Beach
Estimated Cost Breakdown of Change Order Request Fee
for
Additional Construction Support Services for the Wastewater Pump Stations Rehabilitation 4JIVtK
V'WRUIU' T'L MWOJMMMrc \Nq �mNxaµLlU_muuupp�L2UlUUlUfi �IaNCVpn� M- W WPS h8
Page 1 of 1
City of Newport Beach
BUDGET AMENDMENT
2009 -10
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates
Increase Expenditure Appropriations AND
Transfer Budget Appropriations
SOURCE:
from existing budget appropriations
from additional estimated revenues
PX from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
NO. BA- 10BA -031
AMOUNT: $510,000.00
Increase in Budgetary Fund Balance
X Decrease in Budgetary Fund Balance
No effect on Budgetary Fund Balance
To increase expenditure appropriations from unappropriated Wastewater Enterprise Fund fund balance due to the award of the
contract with Metro Builders and Engineers Group, Ltd. for wastewater pump station rehabilitation.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Account
530 3605
REVENUE ESTIMATES (3601)
Fund /Division Account
EXPENDITUREAPPROPRIATIONS (3603)
Description
Wastewater Fund - Fund Balance
Description
Signed:
Signed:
Signed:
Administrative Services Director
Approval: City
City Council Approval: City Clerk
Amount
Debit Credit
$510,000.00 `
Automatic
$510,000.00
7-11 12676
Z imo
Date
Date
Description
Division
Number
7532 Sewer Pump Station Improvement Program
Account
Number
C5600100 Sewer Pump Station Master Plan Improvement
Division
Number
Account
Number
Division
Number
Account
Number
Signed:
Signed:
Signed:
Administrative Services Director
Approval: City
City Council Approval: City Clerk
Amount
Debit Credit
$510,000.00 `
Automatic
$510,000.00
7-11 12676
Z imo
Date
Date