Loading...
HomeMy WebLinkAbout09 - Police Department Generator ReplacementCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 9 March 23, 2010 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Tom Sandefur, Associate Civil Engineer 949 - 644 -3312 or tandefur@newportbeachca.gov SUBJECT: POLICE DEPARTMENT GENERATOR REPLACEMENT COMPLETION AND ACCEPTANCE OF CONTRACT NO. 4056 RECOMMENDATIONS: 1. Accept the completed work and authorize the City Clerk to file a Notice of Completion. 2. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 3. Release the Faithful Performance Bond one year after Council acceptance. Construction Contract Summary: Construction Contract Final Cost at Benchmark Contract Time Award Amount Completion Target Actual Time (days) Under or Over $245,958.00 $260,066.50 Contract Contract 60 (2) +10% +5.7% DISCUSSION: The existing emergency backup generator at the Police Facility is 75 kW and only backs up a limited number of key Police Department operations. A large number of items are not currently tied to the existing generator, including some lighting, air conditioning and computer terminals. The proposed 300 kW generator is sized to allow the Department to be fully operational during a power outage. There is sufficient excess capacity in the proposed generator to allow some additional connections to be made, should the Department require them. The work necessary for the completion of this contract consists of procuring and installing a new diesel powered emergency backup generator including removing Police Department Generator Replacement - Completion and Acceptance of Contract No. 4056 March 23, 2010 Page 2 existing generator, clearing, grubbing and pouring for a concrete foundation slab, running electrical conduit, procuring and installing new automatic transfer switch, providing temporary power to Police facility, and all testing and certification to make the generator operable. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $245,958.00 Actual cost of bid items constructed: 232,657.50 Total change orders: Final contract cost: 27,409.00 $260,066.50 There were five change orders totaling $27,409.00. The change orders were for the following: Item No. Description Amount 1 Upgrade Switchgear to 64 KAIC and add 400 Amp Main Circuit Breaker to Panel 100 $ 2,200.00 2 Abandon existing sump and fill with PCC 600.00 3 Install six crash posts in front of generator 3,600.00 4 Replacement of transformer, lid and additional temporary generator rental time 20,409.00 5 Install two crash posts in front of transformer 600.00 Total Project Change Orders $27,409.00 During construction coordination with Southern California Edison (SCE), SCE recommended that the old transformer and lid that feeds the Police facility be replaced to address corrosion and technological obsolescence issues. The City agreed to replace the customer -owned transformer and lid to ensure reliable power to the facility and issued Change Order No. 4. A summary of the project schedule is as follows: Estimated Completion Date per July 2009 Schedule February 26, 2010 Project Award for construction: June 23, 2009 Date of Notice To Proceed (NTP): October 19, 2009 Contract Completion Date per NTP & Approved Extensions: January 15, 2010 Actual Construction Completion Date: January 13, 2010 Police Department Generator Replacement - Completion and Acceptance of Contract No. 4056 March 23, 2010 Page 3 Environmental Review: This project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 Class 1 (c), of the CEQA Implementing Guidelines. This exemption covers the maintenance and alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. Public Notice: The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Funding Availability: In addition to the primary construction contract, this project involved other project expenses. Total project expenses are summarized as follows: Construction $260,066.50 Design 28,496.00 Preconstruction Testing 3,835.00 Electrical Setting 1,590.00 Meter Change 5,761.80 Incidentals 1,092.13 Total Project Cost $300,841.43 Funds for the construction project were expended from the following account: Account Description Account Number Amount Police Facility 7019- C1820918 $260,066.50 Generator Replacement Total: $260,066.50 Prepared by: Tom Sandefur Associate Civil ngineer Submitted by: I Stephen G. Badum Public Works Director